HomeMy WebLinkAbout13-02-CIAC RESOLUTION 13-02-CIAC
A RESOLUTION CONVEYING THE SEMI-ANNUAL REPORTS OF THE
CAPITAL IMPROVEMENTS ADVISORY COMMITTEE, RELATIVE TO
THE PROGRESS OF THE CAPITAL IMPROVEMENTS PLAN AND THE
IMPOSITION OF IMPACT FEES FOR THE PERIOD OF OCTOBER 1,
2012 THROUGH MARCH 31, 2013.
WHEREAS, the City council of the City of Euless, Texas, has adopted Water and
Wastewater Impact Fees and is operating under a Capital Improvements Plan as
required by Chapter 395 of the Texas Local Government Code for the imposition of
impact fees for water and sanitary sewer improvements; and
WHEREAS, the City Council, in compliance with Chapter 395, has appointed a Capital
Improvements Advisory Committee to monitor and evaluate implementation of the
Capital Improvements Plan; and
WHEREAS, Chapter 395 requires the Capital Improvements Advisory Committee to file
semi-annual reports to the City Council with respect to the progress of the Capital
Improvements Plan and any perceived inequities in implementing the Plan or imposing
the impact fees; and
WHEREAS, the Capital Improvements Advisory Committee has monitored and
:r.
evaluated the implementation of the Capital Improvements Plan and imposition of
impact fees;
NOW THEREFORE BE IT RESOLVED BY THE CAPITAL IMPROVEMENTS
ADVISORY COMMITTEE OF THE CITY OF EULESS, TEXAS:
SECTION 1. That adequate progress is being made to implement the Capital
Improvements Plan for providing facilities necessitated by and attributable to new
development.
SECTION 2. That the Capital Improvements Advisory Committee finds no inequities in
implementing the Capital Improvements Plan or imposing the impact fees.
SECTION 3. That the Capital Improvements Advisory Committee finds that the impact
fees are being collected and that all funds collected are maintained in accordance with
the law.
SECTION 4. That since the City Council adopted Resolution No. 07-1263 affirming the
Water and Wastewater Impact Fees in September, 2007, based on public input, the City
of Euless was tasked to update the Land Use Assumptions, Capital Improvements
Program and Impact Fee Program. The updated Land Use Assumptions, Capital
Improvements Program and Impact Fee Program was approved by the City Council
through Ordinance No. 1992 on April 9, 2013.
SECTION 5. That the semi-annual reports, attached hereto as Exhibit A and
`'" accompanying Tables and staff memos, are hereby conveyed to the City Council of the
City of Euless, Texas, for its information.
PASSED AND ADOPTED THIS 18th DAY OF JUNE 2013.
1
Ric and Mc eese, Chairman
Resolution 13-02-CIAC, Page 2 of 2
EXHIBIT A
SEMI-ANNUAL REPORT
OCTOBER 1, 2012 THROUGH MARCH 31, 2013
BY THE
CAPITAL IMPROVEMENTS ADVISORY COMMITTEE
June 18, 2013
PURPOSE
This semi-annual report was prepared by the Capital Improvements Advisory
Committee to advise the City Council of the progress of Water and Wastewater Impact
Fees and the Capital Improvements Plan, as well as, any perceived inequities found in
implementing the Plan or imposing the impact fees. It is intended to satisfy the
requirements of Chapter 395 of the Local Government Code.
LAND USE ASSUMPTIONS
The Land Use Assumptions, adopted by City Ordinance No. 1992 on April 9, 2013
provides a description of the City’s water and wastewater service area, as well as,
projections of changes in land use densities and intensities, and projections of
population changes in the service area. The Land Use Assumptions have been
deemed appropriate for use as the basis for the Capital Improvements Plan (CIP).
CAPITAL IMPROVEMENTS PLAN:
WATER AND WASTEWATER
Appendices A and B of the 2013 Water and Wastewater Impact Fee Review and update
show eligible existing facility costs and eligible proposed facility costs identified in the
CIP adopted for water and wastewater. Pages 10-13 of the same report describe the
Living Unit Equivalency and Maximum Impact Fee calculations. The CIP is progressing
at a pace that meets the demands of the City of Euless. Additions to the water and
wastewater systems will be implemented as development occurs within those areas of
the City needing additional capacity.
IMPACT FEE CHARGES
The impact fee calculations show the actual cost of providing capital improvements
needed to maintain the current level of service were $2,955.80 per service unit for water
facilities and $1,049.40 per service unit for wastewater facilities. These figures
represent the maximum impact fee per service unit that could be charged by the City.
Impact fees set by the City Council in April of 2013 were 50% of the maximum impact
fee amount allowed. City Council Ordinance No. 1992 established impact fees per
service unit of $1,477.90 for water facilities and $524.70 for wastewater facilities. The
Fees charged for both water and wastewater facilities are based on water meter size,
with a 5/8” water meter considered one service unit. Wastewater impact fees are not
charged when water meters are installed for water that will not enter the wastewater
system, such as landscape irrigation. The Ordinance established the following impact
fees:
Meter Size
(inches) Water Sewer Total
5/8” or 3/4” $1477.90 $524.70 $2,002.60
1” $3,694.75 $1,311.75 $5,006.50
1.5” $7,389.50 $2,623.50 $10,013.00
2” $11,823.20 $4,197.60 $16,020.80
3” $35,469.60 $12,592.80 $48,062.40
4” $62,071.80 $22,037.40 $84,109.20
6” $135,966.80 $48,272.40 $184,239.20
8” $236,464.00 $83,952.00 $320,416.00
IMPACT FEE ASSESSMENT, COLLECTION, AND DISBURSEMENT
From October 1, 2012 through March 31, 2013 impact fees collected were $113,312.25
for water and $5,353.92 for wastewater. Impact fee funds disbursed from the accounts
during this time period totaled $142,988.40. The projects funded included: Water Tower
Debt Payment (Project WT0101) for $130,170.00; and Engineering Services from
Birkhoff, Hendricks & Carter (Project WT1203) for $12,818.40.
CONCLUSION
The Capital Improvements Advisory Committee finds that for the time period included in
this report, no inequities were created in imposing the impact fees and the fees were
properly extended in effect as a result of the Council Resolution No. 07-1263 as allowed
by Chapter 395 of the Texas Local Government Code. The assessment and collection
of water and wastewater impact fees was in accordance with the guidelines of
Ordinance No. 111, Ordinance No. 1364, and Chapter 395 of the Texas Local
Government Code. All money collected was deposited into separate interest bearing
accounts reserved for impact fees. For future impact fee assessments, the collections
will be made utilizing the fees associated with Ordinance No. 1992.
Date: 6/10/13
To: Mike Collins, Director of Planning and Economic Development
From: Alice Norwood, Accountant
RE: Impact Fee Funds
The Impact Fees Fund is divided into separate funds. The amount of funds available in the
Water Impact Fees Fund as of March 31, 2013 is $1,838,692.69. A portion of this amount
totaling $1,837,815.69 is invested in interest bearing accounts all available immediately.
The amount of funds available in the Wastewater Impact Fees Fund as of March 31, 2013
is $526,999.19. A portion of this totaling $510,851.49 is invested in interest bearing
accounts all available immediately.
AN
Mike Collins, Director of Planning and Economic Development
Chrls Barker′Asslstant City Manag錫FROM:
DATE:June 12′2013
RE: Capitallmprovement Pian―Water and Wastewater
Funds distributed from the VVater and VVastewaterlnnpact Fee accounts forthe period of October l,
2012 through March 31,2013 were S142′988 40 A breakdown ofthe disbursed fundsis as fo∥ows:
Waterlmpact Fees
Proj WT0101(Water TOWer Debt Paymeno
Proj WT1203(lmpaCt Fee Study)
Wastewaterlmpact Fees
There were no disbursements during this time period
Tota∥mpact Fees{10/2012-03/2013)
S130,17000
S12′81840
S142,98840
The Capital lmprovement Plan is progressing at a pace that meets the demands of the City of Euless.
Additions to the water and wastewater systems will be implementei as development occurs within
those areas of the City needing additional capacity. lmpact Fees established by the City of Euless are
being collected in accordance with applicable State Law.
WATER IMPACT FEE EXPENSES OCTOBER 12 THROUGH MARCH 13
Project WT0101
10/20/2012 Transfer for Debt $21,695.00
11/20/2012 Transfer for Debt $21,695.00
12/20/2012 Transfer for Debt $21,695.00
1/20/2013 Transfer for Debt $21,695.00
2/20/2013 Transfer for Debt $21,695.00
3/20/2013 Transfer for Debt $21,695.00
TOTAL $130,170.00
Project WT1203
11/7/2012 Birkhoff, Hendricks & Carter $3,190.96
2/13/2013 Birkhoff, Hendricks & Carter $3,063.50
3/12/2013 Birkhoff, Hendricks & Carter $6,563.94
TOTAL $12,818.40
WASTEWATER IMPACT FEE EXPENSES OCTOBER 12 THROUGH MARCH 13
$0.00
TOTAL REVENUE COLLECTED OCTOBER 12 THRU MARCH 13
Fund 505 WATER Fund 508 Wastewater
Fees $111,636.63 Fees $4,994.42
Interest $1,675.62 Interest $359.50
TOTAL $113,312.25 TOTAL $5,353.92