HomeMy WebLinkAboutPreliminary Capital Improvements Program FY09-10CITY OF EULE$
0
PRELIMINARY CAPITAL
IMPROVEMENTS PROGRAM
FY2009-201-0
201 N. ECTOR DRIVE
EULESS, TEXAS 76039
PHONE (817) 685-1626
— FAX (817) 685-1459
www.euless.org
CITY OFFICIALS
FY2009-2010
MARY LIB SALEH, MAYOR
Tim Stinneford, Council Member — Place One, Mayor Pro Tem
Leon Hogg, Council Member — Place Two
Linda Martin, Council Member — Place Three
Donna Mickan, Council Member — Place Four
Glenn Porterfield, Council Member — Place Five
Perry Bynum, Council Member — Place Six
Gary McKamie, City Manager
Loretta Getchell, Deputy City Manager
TABLE OF CONTENTS
PRELIMINARY CAPITAL IMPROVEMENTS PROGRAM
City Officials
Table of Contents
FUNDED PROJECTS
Summary of Funded Projects ....................................
FY09 Amendments....................................................
Drainage Proiects
Summary of Funded Drainage Projects ....................................................
DR9903 Misc. Drainage Improvements Program .............................
DR0701 Eastcliff Drive/Greenbriar Drive Improvements ..................
DR0801 Rockwall Drive/Lamar Drive Improvements .......................
DR0802 Hurricane Creek & Bridge at Marlene Drive Design...........
DR0901 Bear Creek Parkway Erosion Repair ..................................
Street Proiects
Summary of Funded Street Projects......................................................................
PS9901 North Main Street.............................................................................
PS9904 Harwood Road.................................................................................
PS9909 FM157 North — SH183 to SH121.....................................................
PS0304Glade Road......................................................................................
PS0605 South Pipeline Road Bridge Replacement ......................................
PS0802 Fuller -Wiser Road Connector..........................................................
PS0901 Ash Lane/Denton Drive/Fair Oaks Boulevard Overlay ....................
PS0902 Vine Street Design...........................................................................
PS0903 Traffic Signals Mid Cities Boulevard @ Gateway Boulevard and
Mid Cities Boulevard @ Baze Road ..................................................
Wastewater Proiects
Summary of Funded Wastewater Projects .....................................
WW0002 Misc. Wastewater Rehabilitation ............................
M0605 TRA Wastewater Payments — Impact ....................
WW0702 Line Replacement — Arnett Addition ......................
WW0801 Line Replacement — Fayette Drive ........................
M0802 Line Replacement — South Mills CDBG-R.............
M0901 Line Replacement — Woodridge Circle/Koen Lane
WW0902 Line Replacement — West Mills Drive-341h CDBG..
Water Proiects
i-v
01-02
03
05
06-07
08-09
10-11
12-13
14-15
17
18-19
20-21
22-23
24-25
26-27
28-29
30-31
32-33
34-35
37
38-39
40-41
42-43
44-45
46-47
48-49
50-51
Summary of Funded Water Projects................................................................................ 53
WT0001 Misc. Water Utility Rehabilitation.............................................................. 54-55
WT0101 Water Tank Debt Payment........................................................................ 56-57
WT0104Well Repairs.............................................................................................. 58-59
WT0201 Well Rehabilitation/Disinfection................................................................ 60-61
WT0202 Effluent Water Main.................................................................................. 62-63
WT0803 Transponders/Meters................................................................................ 64-65
WT0901 TRA Water Payments—Impact.................................................................. 66-67
0
Other Proiects
Summary of Other Funded Projects...............................................................................
69
AC0901 Texas Star Sports Complex Study/Fencing..............................................
70-71
CM0304 Entry Monument Sign Program...............................................................
72-73
CM0804Redevelopment.......................................................................................
74-75
DV9901 EDC Incentive Funds..............................................................................
76-77
ED0101 Planning Consultants..............................................................................
78-79
ED0801 Redi-Mix Regional Headquarters.............................................................
80-81
PD9901 Police and Municipal Court Facility..........................................................
82-83
PR0601 Park Amenities Upgrade..........................................................................
84-85
PR0720 Misc. Park Structures...............................................................................
86-87
PR0804Park Irrigation..........................................................................................
88-89
PR0901 Trail Enhancement — Bob Eden Park .......................................................
90-91
PR0902 Senior Citizen Center at Midway Park ......................................................
92-93
PR0907 Midway Park Family Life Center Phase I ..................................................
94-95
PROPOSED & UNFUNDED PROJECTS
Summary of FY10 Proposed & Unfunded Projects — Sorted by Type ................................ 97-100
Drainaae Proiects
Summary of FY10 Proposed & Unfunded Drainage Projects .......................................... 101
Hurricane Creek & Bridge at Marlene Drive — ROW .............................................. 102-103
Boyd Branch Improvements................................................................................... 106-107
Hurricane Creek & Bridge at Marlene Drive — Construction ................................... 104-105
HollowOak Drive Erosion...................................................................................... 108-109
Marlene Drive Culvert Replacement...................................................................... 110-111
FloodingMitigation............................................................................................... 112-113
Kynette Drive Culvert Modifications....................................................................... 114-115
BellHi Addition...................................................................................................... 116-117
Blessing Branch — Main Street to SH 360.............................................................. 118-119
Little Bear Creek Land Acquisition......................................................................... 120-121
Little Bear Creek Improvements............................................................................ 122-123
Simmons Culvert Improvements............................................................................ 124-125
Street Proiects
Summary of FY10 Proposed & Unfunded Street Projects .............................................. 127
Baze Road — Glade Road to Mid Cities Design/ROW............................................ 128-129
Wilshire Drive/Marlene Drive Overlay.................................................................... 130-131
Ash Lane — Aransas Drive to N Main Street Design/ROW..................................... 132-133
Baze Road — Glade Road to Mid Cities Construction ............................................. 134-135
Ash Lane — Aransas Drive to N Main Street.......................................................... 136-137
Vine Street — SH 183 to SH 10.............................................................................. 138-139
Traffic Signal — Harwood Road at Bear Creek Parkway ......................................... 140-141
Cullum Drive/Alexander Lane................................................................................ 142-143
BearCreek Parkway.............................................................................................. 144-145
RossAvenue......................................................................................................... 146-147
CresthavenDrive................................................................................................... 148-149
11
HighlandDrive......................................................................................................... 150-151
South Pipeline Road................................................................................................ 152-153
�.. Fuller -Wiser Road — SH 183 to Harwood Road ....................................................... 154-155
Fuller -Wiser Road — Harwood Road to Mid Cities Boulevard .................................. 156-157
Wastewater Projects
Summary of FY10 Proposed & Unfunded Wastewater Projects ......................................
159
Line Replacement — West Alexander Lane/Franklin Drive/Norman Drive ...............
160-161
Line Replacement — Arnett Drive.............................................................................
162-163
Line Replacement — Pauline Street.........................................................................
164-165
Line Replacement — Alexander Lane/Ascot Outfall.................................................
166-167
Line Replacement — Whitener Road/Ascot Outfall..................................................
168-169
Line Replacement — Collin Drive.............................................................................
170-171
Line Replacement — Blanco Drive/Aransas Drive/Crane Drive ...............................
172-173
Line Replacement — Slaughter Lane/E Huitt Lane ..................................................
174-175
Line Replacement — Ross Avenue..........................................................................
176-177
Line Replacement — Oakwood Terrace Phase I ......................................................
178-179
Line Replacement — Oakwood Terrace Phase 11.....................................................
180-181
SH 183 Utility Relocation.........................................................................................
182-183
Line Replacement — N Midway Park.......................................................................
184-185
Line Replacement — S Main Street..........................................................................
186-187
Line Replacement — Aransas Drive.........................................................................
188-189
Line Replacement — Glenn Drive/Crane Drive ........................................................
190-191
Line Replacement — Boyd Branch...........................................................................
192-193
Line Replacement — Cedar Hills Estates/Hollywood Boulevard ..............................
194-195
Line Replacement — Cedar Hills Estates/Sunset Drive ...........................................
196-197
Line Replacement — Eastcfliff Drive/Windlea/Signet...............................................
198-199
Line Replacement — Huntington/Koen/Atkerson/E Huitt/Slaughter/Martin ..............
200-201
Line Replacement — Ector Drive/Fayette Drive .......................................................
202-203
Line Replacement — Donley Drive/Shelmar Drive ...................................................
204-205
Line Replacement — Denton Drive...........................................................................
206-207
Line Replacement — Collin Drive/Harris Drive/Trion Drive ........................................
208-209
Line Replacement — Ector Drive/Donley Drive/Crane Drive ....................................
210-211
Line Replacement — Evans Drive/Canyon Ridge/N Kynette Drive ..........................
212-213
Line Replacement — Janann Street/Brownstone Drive/Shelmar Drive ....................
214-215
Line Replacement — Kynette Drive/ Wilshire Drive/Sierra Drive ..............................
216-217
Line Replacement — Lakewood Boulevard/ Dogwood Circle ...................................
218-219
Line Replacement — Mary Drive/Marlene Drive/Commerce Street ..........................
220-221
Line Replacement — NW Midway/Rusk/Parker........................................................
222-223
Line Replacement — Northcliff/Toplea/Winlea .........................................................
224-225
Line Replacement — Sagebrush/Toplea/Wilshire....................................................
226-227
Line Replacement — W Midway DriveNictoria Drive/Delta Drive ............................
228-229
Line Replacement — W Donley Drive/ Private Drive/Mimosa Lane .........................
230-231
Water Projects
Summary of FY10 Proposed & Unfunded Water Projects ...............................................
233
Line Replacement — Live Oak Ct/Live Oak Drive/Marlene Drive .............................
234-235
Line Replacement — S Pipeline Road West.............................................................
236-237
Water & Wastewater Impact Fee Update................................................................
238-239
Line Replacement — S Pipeline Road East..............................................................
240-241
Water System Security Camera Installation............................................................
242-243
Line Replacement — Westwood Drive.....................................................................
244-245
Line Replacement — Collin Drive/Dallas Drive/Harwood Road ................................
246-247
Iff
Line Replacement — Collin Drive/Denton Drive/Dallas Drive ..................................
248-249
Line Replacement — Fuller Drive............................................................................
250-251
Line Replacement — Springwood Court.................................................................
252-253
SH 183 Water Crossing.........................................................................................
254-255
SH 360 Water Crossing........................................................................................
256-257
Line Replacement — Kynette Drive.........................................................................
258-259
Line Replacement — Midcreek Drive/ Rock Creek Drive/Stony Creek Drive ...........
260-261
Line Replacement — Blessing Creek and Little Creek ............................................
262-263
Line Replacement — Eastcliff Drive........................................................................
264-265
Line Replacement — Ector Drive............................................................................
266-267
Line Replacement — Hollow Oak Drive..................................................................
268-269
Line Replacement — Midway Drive East.................................................................
270-271
Line Replacement — Midway Drive West................................................................
272-273
Line Replacement — Dickey Drive South................................................................
274-275
Line Replacement — Dickey Drive North................................................................
276-277
Line Replacement — Paula Lane............................................................................
278-279
Line Replacement — Denton Drive.........................................................................
280-281
Line Replacement — S Main Street (North) .... .................................................. I.....
282-283
Line Replacement — S Main Street (South)............................................................
284-285
Line Replacement — Sunset Drive..........................................................................
286-287
Line Replacement — Wildwood Street....................................................................
288-289
Line Replacement — Woodvine Drive (East)..........................................................
290-291
Line Replacement — Woodvine Drive (West).........................................................
292-293
Line Replacement — Shady Creek Drive and Cliffwood Road ................................
294-295
Line Replacement — Dunaway Drive......................................................................
296-297
Line Replacement — E Huitt Lane..........................................................................
298-299
Line Replacement — Needles Street......................................................................
300-301
Water System Security Land Acquisition...............................................................
302-303
Other Projects
Summary of Other FY10 Proposed & Unfunded Projects ...............................................
305
Texas Star Sports Complex Lighting Improvements ..............................................
306-307
Glade Parks Trail Connection..... ....... m ..... — ... m ....... m. m. m ..... — .............. mmmm .................
308-309
Park Amenities Upgrade........................................................................................
310-311
TrailLighting — Phase I..........................................................................................
312-313
Midway Park FLC — Phase II Outdoor Aquatics Design .........................................
314-315
Midway Park FLC — Phase III Indoor Aquatics Design ...........................................
316-317
Midway Park FLC — Phase II Outdoor Aquatics Construction ................................
318-319
Midway Park FLC — Phase III Indoor Aquatics Construction ..................................
320-321
Fire Training Facility and Tower.............................................................................
322-323
AnimalShelter. ...... m ...................... m .... mmmm .......... m-m ............... m ... ......... m. m ... - M. M M. —
324-325
Development/Engineering Building... .......... m—m ........ — ...... m ........ ........... — m m m ..........
326-327
Blessing Branch Park Improvements.....................................................................
328-329
Texas Star Sports Complex Parking Lot Improvements .........................................
330-331
South Euless Water Feature. ... m m m ....... — m ............ ................... m .... m m ...
332-333
Wilshire Park Water Feature..................................................................................
334-335
Texas Star Sports Complex Improvements.... ......... ....... m-mmm ....... m ......... m m —
336-337
TrailConnection S Euless.....................................................................................
338-339
Texas Star Sports Complex — Softball World Turf ..................................................
340-341
Trail Lighting — Phase II.........................................................................................
342-343
Texas Star Sports Complex — PATS, Phase IV ......................................................
344-345
Trail Enhancements — Villages Bear Creek... m .......... mmmmm .............. m mm—mm ......
346-347
Trail Enhancements — Phase I...............................................................................
348-349
iv
Trail Enhancements — Phase II .......
Trailwood Park Improvements.........
�--� Community Center for South Euless
Emergency Call Boxes ....................
Kiddie Carr Park Improvements .....
COMPLETED PROJECTS
Summary of Completed Projects
Drainage Projects
Summary of Completed Drainage Projects
Street Projects
Summary of Completed Street Projects ...............................
PS0002 West Pipeline Road — Raider Drive to Hwy10
PS0704 Disability Access Study ..................................
PS0705 Signal Gateway Blvd @ Glade Road .............
PS0801 Overlay North Main Street/Cullum Drive........
PS9905 Traffic Studies ................................................
Wastewater Proiects
Summary of Wastewater Projects.................................................................
WW0701 Line Replacement — McCormick Court & Copher Court .......
WW0703 Line Replacement — Jean Lane ............................................
WW0704 Line Replacement — W Fuller Drive ......................................
Water Projects
Summary of Water Projects...............................................................................
WT0402 Water & Wastewater Impact Fee Update ...................................
WT0801 Line Replacement — Signet Drive/Mesa Drive ............................
WT0802 CDBG 33`d Oakwood Terrace (Simmons Drive) .........................
Other Proiects
Summary of Other Completed Projects ...................................................
FMO504 Building "B" Remodel.......................................................
FM0801 Texas Star Golf Course & Conference Center Expansion
FM0802 Senior Citizen Center Design ...........................................
FM0803 Midway Recreation Improvements ...................................
FMO804 Library Shell Expansion ....................................................
PR0602 Mid Cities Landscaping....................................................
PR0719 Midway Park Trail.............................................................
v
350-351
352-353
354-355
356-357
358-359
361-365
367
369
370-371
372-373
374-375
376-377
378-379
..... 381
..... 382-383
..... 384-385
..... 386-387
389
390-391
392-393
394-395
..... 397
..... 398-399
..... 400-401
402-403
..... 404-405
..... 406-407
..... 408-409
..... 410-411
N iC 1 T Y O F
VI
1
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5131108
Appropriation/
Amendment
Budget as of
5131/09
Expended as
of 05/31/09
Remaining
Funds to
Complete
Budget
Estimated
Project Costs
Unfunded/
(Excess
Funding)
DRAINAGE
PROJECTS
DR9903
DR0701
Misc Drainage Improvements(min bal $150,000)
Eastcliff Drive-G reen briar Drainage Improvements
$162,833
$340,000
$200,000
$0
$3623833
$340,000
$12,833
$31,890
$350,000
$308,110
$362,833
$340,000
$0
$0
DR0801
Rockwall Drive -Lamar Drainage Improvements
$430,000
$0
$4309000
$30,913
$399,087
$430,000
$0
DR0802
Hurricane Creek & Bridge at Marlene Drive Design
$335,000
$0
$335,000
$42,679
$292,321
$335,000
$0
DR0901
Bear Creek Parkway Erosion Repair
$0
$530,000
$530,000
$0
$530,000
$530,000
$0
FB9902
Fund Balance - Drainage CIP
$0
$0
$0
$0
$0
$0
($1043461)
Sub-TotalDrainage Projects
$11267,833
$730,000
$1,9971833
$118,315
$11879,518
$1,997,833
($104,461)
STREET PROJECTS
PS9901
North Main Street
$6,820,047
$0
$6,820,047
$6,697,130
$1223917
$6,820,047
$0
PS9904
Harwood Road
$5,695,211
$0
$5,695,211
$5,662,473
$32,738
$5,695,211
$0
PS9909
FM157 North-SH183 to SH121
$129,215
$0
$129,215
$88,930
$40,285
$129,215
$0
PS0304
Glade Road
$30077,976
$0
$3,077,976
$2,895,573
$182,403
$3,0771976
$0
PS0605
PS0802
South Pipeline Road Bridge Replacement
I Fuller -Wiser Road Connector
$157,000
$495,000
$0
$0
$1571000
$495,000
$0
$33,030
$157,000
$461,970
$157,000
$495,000
$0
$0
PS0901
Ash Lane/Denton Drive/Fair Oaks Boulevard Overlay
$0
$320,000
$320,000
$216,659
$103,341
$3209000
$0
PS0902
Vine Street Design
$0
$100,000
$100,000
$0
$100,000
$100,000
$0
PS0903
Traffic Signals Mid Cities Blvd. @ Gateway Blvd. and @
Baze Road
$0
$320,000
$320,000
$2,168
$317,832
$320,000
$0
FB9907
Fund Balance - Street CIP
$0
$0
$0
$0
$0
$0
($7757082)
Total Street Projects
$161374,449
$7403000
$171114,449
$15,595,963
$13518,486
$17,114,449
($775,082)
WASTEWATER PROJECTS
Misc Wastewater Rehab(min bal $100,000)
$259,169
$56,917
$316,086
$216,086
$1003000
$316,086
$0
TRA Wastewater Payments - Impact
$180,000
$60,000
$240,000
$180,000
$600000
$240,000
$0
r
Line Replacement Arnett Addition
Line Re lacement Fayette Drive
Line Replacement South Mills Drive CDBG-R
Line Replacement Woodridge Circle/Koen Lane
Line Replacement West Mills Drive-34th CDBG
$313,322
$750,000
$0
$0
$0
$0
$262,000
$262,000
$795,000
$46,855
$313,322
$488,000
$262,000
$795,000
$46,855
$229,006
$30,176
$0
$0
$0
$843316
$457,824
$262,000
$795,000
$460855
$313,322
$488,000
$262,000
$795,000
$461855
$0
$0
$0
$0
$0
FB - Wastewater Impact (Restricted)
$0
$0
$0
$0
$0
$0
($661,141)
-Total Wastewater Projects
$1,5021491
$958,772
$2,461,263
$655,268
$19805,995
$214611263 ($661,141)
N
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Remaining
Funds to
Unfunded/
Project
Budget as of
Appropriation/
Budget as of
Expended as
Complete
Estimated
(Excess
Number Project Description
5131/08
Amendment
5131109
of 05/31/09
Budget
Project Costs
Funding)
WATER PROJECTS
WT0001
Misc Utility Rehab - Water(min bal $1509000)
$253,511
$0
$253,511
$103,775
$149,736
$253,511
$0
WT0101
Water Tank Debt Payment
$29175,514
$257,000
$2,432,514
$2,346,848
$85,666
$2,4323514
$0
WT0104
Well Repairs (min bal $75,000)
$513,617
$0
$513,617
$438,617
$75,000
$513,617
$0
WT0201
Well Rehabilitation/Disinfection
$600,000
$0
$600,000
$522,285
$77,715
$600,000
$0
WT0202
Effluent Water Main
$2502000
$0
$2507000
$0
$2502000
$1,5003000
$1,2503000
WT0803
Transponders/Meters(annualtransfer $158,000)
$331,875
$3312875
$663,750
$555,247
$1081503
$663,750
$0
WT0901
TRA Water Payments4rnpact
$0
$100,000
$100,000
$0
$1000000
$100,000
$0
FB9910 FB- Water Impact (Restricted)
$0
$0
$0
$0
$0
$0
($2,534,906)
FB9901 FB - Water & Sewer CIP
$0
$0
$0
$0
$0
$0
($489,964)
Sub-TotalWater Projects
$4,124,517
$688,875
$4,813,392
$3,966,772
$846,620
$6,063,392
($1,774,870)
OTHER
AC0901 Texas Star Sports Complex Study/Fence
$0
$100,000
$100,000
$85,204
$14,796
$100,000
$0
CM0304 Entry Monument Sign Program
$1153782
$0
$1151782
$93,027
$22,755
$115,782
$0
CM0804 Redevelopment
$951,947
$15,525
$967,472
$659,642
$307,830
$967,472
$0
DV9901 EDC Incentive Funds
$325,854
$25,000
$350,854
$3001854
$50,000
$350,854
$0
ED0101 PlanningConsultants
$100,000
$0
$1009000
$0
$100,000
$200,OOD
$100,000
ED0801 Redi-Mix Regional Headquarters
$5,450,000
($250,000)
$5,200,000
$1,175,036
$4,0242964
$51200,000
$0
PD9901 Police and Municipal Courts Facility
$112717,134
$462
$111717,596
$112609,560
$1081036
$111717,596
$0
PRO601 Park Amenities Upgrade
$150,000
$0
$150,000
$145,316
$4,684
$1502000
$0
PR0720 Misc. Park Structures
$225,000
$0
$2252000
$131,275
$93,725
$225,000
$0
PRO804 Park Irrigation
$25,000
$25,000
$50,000
$770
$49,230
$50,000
$0
PR0901 Trail Enhancement- Bob Eden Park
$0
$135,000
$135,000
$0
$135,000
$135,000
$0
PR0902 Senior Citizen Center at Midway Park
$0
$43856,821
$43856,821
$0
$4,856,821
$40856,821
$0
PRO907 Midway Park Family Life Center Phase 1
$0
$1,330,000
$1,330,000
$66,644
$1,263,356
$2,105,000
$775,000
F69906 FB EDC CIP
$0
$0
$0
$0
$0
$0
($9583496)
FB9908 FB-Athletic Complex CIP
$0
$0
$0
$0
$0
$0
($740,639)
FB9909 FB-General CIP
$0
$0
$0
$0
$0
$0
($34,342)
FB9913 FB-Car Rental CIP
$0
$0
$0
$0
$0
$0
($74,674)
Sub -Total Other Projects
$19,060,717
$6,237,808
$251298,525
$14,2673328
$111031,197
$26,173,525
($933,151)
TOTAL FUNDED PROJECTS
$421330,007 $9,355,455 $51,6851462
$34,603,645
$17,081,817
$53,810,462
($4,248,704)
CITY OF EULESS
CAPITAL IMPROVEMENT PROGRAM
AMENDMENTS - FUNDED PROJECT BUDGETS
Project # Project Description Amendment
AC0901
TX Star Sports Complex Feasibility Study
Approved in the FY2008-09 budget.
CM0804
Redevelopment
Interest earnings for $15,525.
DR9903
Misc Drainage Improvements
Approved in the FY2008-09 budget,
DR0901
Bear Creek Erosion
Approved in the FY2008-09 budget,
DV9901
EDC Incentive Funds
Approved in the FY2008-09 budget.
ED0801
Redi-Mix Regional Headquarters
Approved in the FY2008-09 budget. Project decrease $800,000. Transfer
to FB9906.
FM0504
Building "B" Remodeling
Project complete, Transfer balance to FB9913.
FM0801
TX Star Conference Center Expansion
Project complete.
FM0802
Senior Citizens Center - Land Acquisition
Project cancelled. Transfer $250,000 to PR0907.
FM0803
Midway Recreation Improvements
Project cancelled. Transfer $271,524 to PR0907.
FMO804
Libra -Shell Expansion
Project complete, Transfer balance to FB9909.
PD9901
Police and Municipal Court Facility
Interest earnings for $462.
PR0602
Mid Cities Landscaping
Project complete. Transfer balance to FB9913.
PR0719
Midway Park Trail Enhancements
Project complete, Transfer balance to FB9906.
PRO804
Park Irrigation
A roved in the FY2008-09 bud et.
PRO901
Bob Eden Park Trail Enhancements
Approved in the FY2008-09 budget,
PRO902
Senior Citizens Center at Midway Park.
Approved in the FY2008-09 budget. Project reduction. Transfer $726,138
to PR0907.
PRO907
Family Life Center at Midway Park -Phase I
Approved in the FY2008-09 budget. Transfer from PRO902 $726,138,
FMO802 $250,000 and FM0803 $271,524,
PS0002
West Pipeline-Raider-HwyPipellne-Raicler-Hwy 10
Project complete. Transfer balance to FB9907.
PS0704
Disability Access Study
Project complete, Transfer balance to FB9907.
PS0705
Signal Gateway Blvd, Glade
Project complete.
PS0801
Overlay -North Main/Cullum Drive
Project complete, Transfer balance to FB9907.
PS0901
FY'2009 County Overlay Projects
Approved in the FY2008-09 budget,
PS0902
Vine Street Design
Approved in the FY2008-09 budget,
PS0903
Traffic Signal Mid Cities 0. Gatewa /Baze
Approved in the FY2008-09 budget. Project increase. Transfer $18,155
from FB9907 and $161,845 from escrow.
PS9905
Traffic Studies
Project complete, Transfer balance to F139907.
WT0101
Water Tank Debt Payment
Approved in the FY2008-09 budget.
WT0402
Water & Wastewater Impact Fee Study
Project complete, Transfer balance to F69911.
WT0801
Line Replacement, Si na/Mesa
Project complete, Transfer balance to F139901.
WT0802
CDBG FY'08-33rd Oakwood Terrace Simmons Dr.
Project complete,
Transfer balance to FB9901.
WT0803
Transponders/Meters
Approved in the FY2008-09 budget.
WT0901
TRA Water Pa ments-Im act
Approved in the FY2008-09 budget,
WW0002
Miscellaneous Sewer Rehabilitaion
Approved in the FY2008-09 budget.
WW0402
Line Replacement, Carr Park/SH10
Project Complete. Project deficit $3,547, Transfer from FB9901
WW0603
Little Bear Creek Collection Line
Project Complete, Project deficit $8,657, Transfer from FB9911
WW0605
TRA Sewer Payments - Impact
Approved in the FY2008-09 budget.
WW0701
Line Replacement, McCormick & Co her
Project Complete, Transfer balance to FB9901.
WW0703
Line Replacement, Jean Lane
Project Complete, Transfer balance to FB9901
WW0704
Line Replacement, W. Fuller
Project Complete, Transfer balance to FB9901
WW0801
Line Replacement, Fayette
Transfer $162,000 to WW0802. Transfer excess funding $100,000 to
FB9901.
WW0802
Line Replacement, South Mills
CDBG-ARRA $100,000. Transfer $162,000 from WWO801
WWO901
Line Replacement, Woodridge Circle/Koen
Approved in the FY2008-09 budget,
WW0902
Line Replacement, West Mills Drive
lApproved in the FY2008-09 budget as part of 34th CDBG.
3
T N E��°=r� G 0 T Y O F
C!
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Remaining
Funds to
Unfunded/
Project
Number
Project Description
Budget as of
5131108
Appropriation/
Amendment
Budget as of
5131109
Expended as
of 05131/09
Complete
Budget
Estimated
Project Costs
(Excess
Funding)
DRAINAGE
PROJECTS
Misc Drainage Improvements(min bal $150,000)
$162,833
$200,000
$362,833
$12,833
$350,000
$362,833
$0
Eastcliff Drive-Greenbriar Drainage Improvements
$340,000
$0
$340,000
$31,890
$308,110
$340,000
$0
Rockwall Drive -Lamar Drainage Improvements
$430,000
$0
$430,000
$30,913
$3990087
$4301000
$0
k
Hurricane Creek & Bridge at Marlene Drive Design
$335,000
$0
$335,000
$42,679
$292,321
$335,000
$0
Bear Creek Parkway Erosion Repair
$0
$530,000
$530,000
$0
$530,000
$530,000
$0
Fund Balance - Drainage CIP
$0
so
$0
$0
$0 $0 ($104,461)
Sub -Total Drainage Projects
$1,267,833
$730,000
$11997,833
$1183315
$1,879,518 $1,997,833 ($104,461)
+3
Department:
Submitted By.
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared
Date Completed:
Project Title: MISCELLANEOUS DRAINAGE IMPROVEMENTS PROGRAM
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project No.: DR9903 Priority: A
COUNCIL AUTHORIZATION:
TIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
July 23, 1999
PROJECT DESCRIPTION:
This project includes funds for various small projects or emergency repairs that are identified throughout the
year. Often corrections of these problems require design services and the installation of improvements. As
large projects are identified, they will be tracked separately and assigned a different project number.
(PROJECT SCHEDULE:
(JUSTIFICATION:
Failure to correct these problems can often cause damage to existing infrastructure.
aRrtiFr_T TIT1 F• RAIRraPI I AWN IS DRAINAGE IMPROVEMENTS PROJECT #: DR9903
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Full Time
Part Time
TOTAL ESTIMATED CAPITAL COST:
Storm Drain
(Minimum balance recommended $150,000)
Total Estimated
(Subtotal: $O�FUNDING SOURCE:
Subtotal:
Cost
Transfer From:
Drainage Operating Fund - FY99
Drainage Operating Fund - FY02
Drainage Operating Fund - FY03
Drainage CIP Fund Balance - FY08
Drainage Operating Fund - FY09
(Total Estimated Annual Cost $O�Total Funding
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+)
Fence $559 $559 $0
Storm Drain $362,079 $12,079 $350,000
Meters & Setting $195 $195 $0
AL PROJECT $362,833 $12,833 $350,000
$51,609
$501000
$501000
$111224
$2001000
$362,833
EXPENDED
100%
3%
100%
7
Department:
Submitted By.
Project Title:
Project Type
Proiect No.:
City Of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared:
Date Completed:
EASTCLIFF-GREENBRIAR DRAINAGE IMPROVEMENTS
DRAINAGE
DR0701
Sub -Type: IMPROVEMENTS
Priority: A
April 15, 2005
COUNCIL AUTHORIZATION:
November 28, 2006: Authorized the city manager to execute a design contract with Freese and Nichols,
Inc. in the amount of $32,550,
March 10, 2009: Authorized the city manager to execute a contract with 2L Construction, LLC, in the
amount of $240,105 for drainage improvements.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005 the city commissiorred and received a drainage plan from Freese and Nichols, Inc.
EJECT DESCRIPTION:
tional inlets and pipe systems will be constructed to contain the flows wn the city drainage systems.
system will extend from the low point on Eastcliff Drive up Greenbriar Drive several hundred feet.
PROJECT SCHEDULE:
Award Engineering Contract: November 2006
Award Construction Contract: March 2009
Begin Construction: May 2009
Complete Construction: August 2009
JUSTIFICATION:
�,In moderate storms the drainage capacity in the streets is exceeded causing flooding of several homes. The
construction of this project will help prevent the flooding of those homes.
E3
PRn.[FCT TiTi F• FARM IFF-rRFFNBRIAR DRAINAGE IMPRV. PROJECT #: DR0701
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL.
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
(Maintenance Costs
I Subtotal:
(Total Estimated Annual Cost
TOTAL ESTIMATED CAPITAL COST:
Engineering
Construction
Total Estimated Capital Cost
$0 FUNDING SOURCE:
Transfers From:
Drainage Operating Fund
Drainage CIP Fund Balance
$0 � Total Funding
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +)
Engineering $40,000 $28,060 $11,940
Storm Drain $300,000 $3,830 $296,170
TOTAL PROJECT $340,000 $31,890 $308,110
$40,000
$3001000
340,000
$320,00
$20,00
$340,000
EXPENDED
70%
1%
Department:
Submitted By:
Project Title:
Project Type:
No.
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
ROCKWALL-LAMAR DRAINAGE IMPROVEMENTS
DRAINAGE
DR0801
Date Prepared:
Date Completed:
Sub -Type: IMPROVEMENTS
Priority: A
COUNCIL AUTHORIZATION:
April 30, 2008: Design contract awarded to Halff Associates for $38,000,
April 15, 2005
May 26, 2009: Authorized City Manager to execute a contract with N.A.E. Enterprises, Inc. for draina
improvements in an amount of $269,359,75,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005, the city commissioned and received a drainage plan from Freese and Nichols, Inc.
PROJECT DESCRIPTION:
A flume is to be reconstructed and additional inlets
up Lamar Drive to the intersection of Rockwall Drive,
PROJECT SCHEDULE:
Award Design Contract: April 2008
'Plans Complete: March 2009
Right Of Way Complete: March 2009
Award Construction Contract: May 2009
Anticipate Construction Complete: January 2010
and
pipe systems are to be built from Midway Drivel
JUSTIFICATION:
In moderate storms the drainage capacity in a flume and the streets is exceeded, causing flooding of several
homes. The construction of the project will help prevent the flooding of those homes.
10
PROJECT TITLE' ROCKWALL-LAMAR DRAINAGE IMPRV.
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
(Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
(Maintenance Costs
I Subtotal:
(Total Estimated Annual Cost
m
PROJECT #: DR0801
TOTAL ESTIMATED CAPITAL COST:
Engineering $50,0
Construction $38010
otal Estimated Capital Cost $430
$0 (FUNDING SOURCE:
Transfers From:
Drainage Operating Fund $300,000
Drainage CIP Fund Balance $130,000
$0 � Total Funding $430,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Engineering $50,000 $30,913 $19,087 62%
Storm Drain $380,000 $380,000 0%
TOTAL PROJECT $430,000 $30,913 $399,087 7%�
11
Department:
Submitted By:
Project Title:
Project Type:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared
Date Completed:
HURRICANE CREEK & BRIDGE AT MARLENE DRIVE DESIGN
DRAINAGE
IProlect No.: DR0802
COUNCIL AUTHORIZATION:
Sub -Type: DESIGN
Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 1996, the City received the storm drainage master plan for Hurricane Creek,
July 26, 1999
PROJECT DESCRIPTION:
This project includes the design of a bridge at Marlene Drive, for the improved concrete channel lining that
will extend approximately to the confluence of Cyclone Branch and to Hurricane Creek south of SH10. The
engineering includes hydraulic studies, modeling, field surveying for plant preparation, easements, permit
fees, coordination with Federal Emergency Management Agency and the Army Corps of Engineers, and
preparation of construction plans and bid documents.
PROJECT SCHEDULE:
Award Study Contract: August 2008
Flood Study Complete: May 2009
Additional Engineering Design: Pending
JUSTIFICATION:
The culvert and concrete channel may require rebuilding to prevent structural flooding of a number of homes
in a 100-year flood event. These improvements will also help prevent erosion.
12
PROJECT TITLE: HURRICANE CREEK & BRIDGE @ MARLENE DESIGN PROJECT #: DR0802
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $335,000
Personnel: Full Time
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost $335,000
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from Car Rental $335,000
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $335,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $335,000 $42,679 $292,321 13%
TOTAL PROJECT $335,000 $42,679 $292,321 13%
13
Department:
Submitted By:
Project Title:
Project Type
Project No..
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
BEAR CREEK PARKWAY EROSION REPAIR
DRAINAGE
DR0901
Date Prepared
Date Completed:
Sub -Type: IMPROVEMENTS
Priority: A
March 15, 2007
COUNCIL AUTHORIZATION:
May 26, 2009: Authorize City Manager to execute a design contract with Jerry Parche for bank stabilization
design in an amount of $54,500,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2007, the City received an erosion study for Little Bear Creek from Halff Associates,
PROJECT DESCRIPTION:
Construct erosion control for the eastern embankment of Little Bear Creek just downstream of Bear C
Parkway.
!PROJECT SCHEDULE:
Begin Design: May 2009
Anticipate Begin Construction: 3rd Quarter 2010
Anticipate Construction Complete: 4th Quarter 2010
JUSTIFICATION:
Continued erosion of the banks will cause the loss of a portion of the trail system and trees adjacent to
banks.
14
PROJECT TITLE: BEAR CREEK PARKWAY EROSION REPAIR PROJECT #: DR0901
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Subtotal:
Total Estimated Annual Cost
PHASEIFUNDING SOURCE
Engineering
Storm Drain
TOTAL PROJECT
TOTAL ESTIMATED CAPITAL COST:
Engineering
Construction
Total Estimated Ca ital Cost
$0 FUNDING SOURCE:
Transfer from Car Rental
$0 (Total Funding
CURRENT STATUS
$70,000
$460,000
000 I
$530,000 �
$530,000 �
OVER/UNDER
BUDGET EXPENDED BUDGET(-+) %EXPENDED
$70,000 $0 $70,000 0%
$460,000 $0 $460,000 0%
000 $0 $530,000 0%I
15
16
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Remaining
Funds to
Unfunded/
Project
Budget as of
Appropriation/
Budget as of
Expended as
Complete
Estimated
(Excess
Number
Project Description
5131/08
Amendment
5/31109
of 05/31/09
Budget
Project Costs
Funding)
STREET PROJECTS
North Main Street
$6,820,047
$0
$61820,047
$6,697,130
$122,917
$6,820,047
$0
Harwood Road
$5,695,211
$0
$5,695,211
$5,662,473
$32,738
$5,6951211
$0
LPS0605
FM157 North-SH183 to SH121
$129,215
$0
$129,215
$88,930
$40T285
$129,215
$0
Glade Road
$3,077,976
$0
$3,077,976
$2,895,573
$182,403
$3,077,976
$0
South Pipeline Road Bridge Replacement
$157,000
$0
$157,000
$0
$157,000
$157,000
$0
PS0802
Fuller -Wiser Road Connector
$495,000
$0
$495,000
$33,030
$461,970
$495,000
$0
PS0901
Ash Lane/Denton Drive/Fair Oaks Boulevard Overlay
$0
$3201000
$320,000
$216,659
$103,341
$320,000
$0
PS0902
Vine Street Design
$0
$100,000
$100,000
$0
$1007000
$100,000
$0
Traffic Signals Mid Cities Blvd. @ Gateway Blvd. and @
$0
PS0903
Baze Road
$0
$320,000
$320,000
$20168
$317,832
$320,000
FB9907 Fund Balance - Street CIP
$0
$0
$0
$0 $0 $0 ($775,062)
Total Street Projects
$16,374,449
$740,000
$171114,449
$15,595,963 $1,518,486 $17,114,449 ($775,082)
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 241 1999
Submitted By: RON YOUNG Date Completed,
Project Title: NORTH MAIN STREET
Project Type, STREET Sub -Type: CONSTRUCTION
Project No., PS9901 Priority: A
COUNCIL AUTHORIZATION:
April 14, 1998: Authorized bond election for the purpose of funding construction.
November 24, 1998. Approved contract with Cummings & Prewitt, Inc. for paving and drainage design.
February 8, 2000: Authorized the acquisition of ROW to allow for widening and paving improvements.
August 22, 2000: Ratified the expenditure of $30,000 of EDC funds for ROW acquisition along Main Street.
August 22, 2000: Ratified EDC Resolution 11-00 authorizing a project involving facility improvements along
North Main Street,
November 14, 2000, Authorized Resolution #00-1083 declaring public necessity for acquisition of ROW.
February 27, 2001 a Authorized publication of notice of intent to issue Certificates of Obligation.
April 9, 2001: Approved Ord. 1468 authorizing issuance of General Obligation Bonds, Series 2001 in the
amount of $6,000,000,
September 11, 2001: Authorized city manager to negotiate and execute a contract with TXU Electric for
the relocation of utilities along North Main Street at an estimated cost of $550,000,
December 11, 2001: Awarded Bid # 004-02 to Southlake Construction for the demolition and removal of
single-family houses along North Main Street.
March 11, 2003: Authorized City Manager to seek competitive bids for paving & drainage construction.
April 8, 2003: Awarded contract to McClendon Construction Co. for construction of street, utility, and
drainage for North Main Street for $3,370,035.15, provided for a $180,000 contingency.
September 28, 20049 Award bid contract to Whitmore and Sons for landscaping/irrigation for $83,275.
April 26, 2005: Award bid to Durable Specialties, Inc., for traffic signalization in the amount of $68,780.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a part of the $13.5 million bond package approved by the voters in October 1998.
PROJECT DESCRIPTION:
The project consists of reconstruction and widening of North Main Street from SH10 to Harwood Road. It
also consists of relocating overhead utilities, the addition of a subsurface drainage system, and the
addition of street lights and landscaping improvements.
PROJECT SCHEDULE:
Construction Complete: October 2005
Landscaping and compliance of Americans with Disabilities Act for sidewalks: FY 2010
JUSTIFICATION:
1. Improvement of traffic flow and traffic safety.
2. Improve aesthetics with relocation of overhead utilities and addition of landscaping.
3. Subsurface drainage system needed.
4. Reduction of maintenance requirements.
PR".IPCT TIT( E' NORTH MAIN STREET
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
Average Annual Debt Service
(Total Estimated Annual Cost
PHASEIFUNDING SOURCE
Engineering
Right of Way
Utility Relocation (City)
Appraisal Services
Surveying Services
Other Professional Services
Special Services
Landscaping
Signs & Markings
Construction
Lighting
Contingency
Issuance Cost
Contract Labor
TOTAL PROJECT
$412,567
$412, 567
PROJECT #: PS9901
TOTAL ESTIMATED CAPITAL COST:
La
*Engineering $698,156
Right of Way (ROW) $1,447,814
Utility Relocation (City) $290,878
Appraisal Services $114,673
Street Lights $102,443
ndscaping $115,808
Construction $3,386,609
Signs & Markings $497,419
Contingency $824
Issuance Cost $62,261
Contract Labor $103,162
* Added $70,000 for work related to medians.
Total Estimated Capital Cost $6,820,047
FUNDING SOURCE:
Transfer from:
Street CIP Fund Balance FY99
Developer's Escrow
EDC Operating Fund
W/S Operating Fund
C.O. Bond Proceeds FY01
G.O. Bond Proceeds FY01
Interest Income
Miscellaneous
Less Transfer To:
Streets CIP Fund Balance
Total Funding
CURRENT STATUS
BUDGET
$698,156
$11447, 814
$290,878
$101,495
$5,170
$2,955
$5,053
$115,808
$497,419
$31386,609
$102,443
$824
$62,261
$103,162
EXPENDED
$698,156
$1,447,814
$290,878
$101,495
$5,170
$2,955
$5,053
$115,808
$466, 321
$3,386,609
$10,624
$824
$62,261
$103,162
130
OVER/UNDER
$0
$0
$0
$0
$0
$0
$0
$0
$31,098
$0
$91,819
$0
$0
$0
$1,416,185
$17,276
$430,000
$5,053
$1,012,961
$4,820,919
$1631667
$450
($1, 046,464
$6,820,047
EXPENDED
100%
100%
100%
100%
100%
100%
100%
100%
98%
19
Department:
Submitted By.
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared:
Date Completed.
Project Title: HARWOOD ROAD, N. MAIN STREET TO SH360
Project Type. STREET Sub -Type: CONSTRUCTION
Project No.. PS9904 Priority: A
July 29, 1999
COUNCIL AUTHORIZATION:
April 14, 1998: Authorized bond election for the purpose of funding construction.
November 24, 1998: Authorized contract for appraisal services for parcels necessary to project.
May 24, 1999: Approved resolution determining the necessity for and ordering the improvement.
May 24, 1999: Authorized the acquisition of the necessary right-of-way.
June 22, 1999: Approved right-of-way acquisition.
December 14, 1999. Authorized City Manager to negotiate for and acquire additional rights -of -way.
February 8, 2000: Awarded construction contract to Larry H. Jackson Construction,
March 28, 2000: Authorized issuance of G.O. bonds for Harwood, Main, and West Pipeline.
April 8, 2003: Awarded contract to J&J Sprinkler & Landscaping for median pavers for $151,836.30,
February 10, 2004: Approved bid 009-04 to Whitmore and Sons, Inc for median irrigation and la
in the amount of $74,627,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the $13.5 million bond program approved by the voters in October 1998. Project is
identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION:
Reconstruction of Harwood Road from a point approximately 350 feet west of North Main Street to SH360.
New roadway will be a six lane boulevard with sidewalks, landscaping, and lighting. Signals will be
added at Fuller -Wiser Road and Bear Creek Parkway.
PROJECT SCHEDULE:
Construction Complete: June 2002
Landscaping Improvements: FY2010
JUSTIFICATION:
The existing two lane roadway does not meet current and future needs.
20
PROJECT TITLE: HARWOOD ROAD, N. MAIN STREET TO 5H360 PRUJtC: I if: F'J`J`JU4
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Appraisal Services $54,036
Personnel: Full Time Professional Services -Soil Test $52,123
Part Time Acquisition $800,637
Total Salary $0 Engineering $415,597
Purchase of Services Construction $4,021,668
Materials & Supplies Contingency $3,150
Utilities Landscaping $278,000
Issuance Cost $70,000
Total Estimated Capital Cost $5,695,211
Subtotal: $0
FUNDING SOURCE:
Maintenance Costs
Transfer from:
Developer's Escrow $301,677
Other Street CIP Fund Balance $283,634
Average Annual Debt Service $465,722 W/S Operating Fund $16,919
G.O. Bond Proceeds $5,392,302
Subtotal: $465,722 Less Inter -Project Transfer to:
Pipeline Road - PS0002 ($299,321)
Total Estimated Annual Cost $465,722 Total Funding $5,695,211
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $415,597 $415,597 $0 100%
Construction $4,021,668 $4,013,177 $8,491 100%
Right of Way $800,637 $8001637 $0 100%
Appraisal Services $54,036 $53,750 $286 99%
Issuance Cost $70,000 $70,000 $0 100%
Contingencies $3,150 $3,092 $58 98%
Other Professional Services $52,123 $52,123 $0 100%
Landscaping $278,000 $254,097 $23,903 91%
TOTAL PROJECT $5,695,211 $5,662,473 $32,738 99%
21
Department:
Submitted By:
Project Title:
� Project Type:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
FM157 NORTH, SH183 TO SH121
STREET
IProiect No.: PS9909
Sub -Type:
0
Date Prepared:
Date Completed:
CONSTRUCTION
July 173 1999
COUNCIL AUTHORIZATION:
February 2003: Signed an agreement with Oncor for street light installation.
March 2003: Began negotiations with the Texas Department of Transportation for landscape projects in the
medians.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Department of Transportation (TXDOT) widened FM157 between SH183 and SH121 to a seven
lane (5+2) undivided roadway section.
PROJECT DESCRIPTION:
This project includes the addition of landscaping in the FM157 medians and improvements to the existing
pavement under the SH183 bridge.
PROJECT SCHEDULE:
Landscaping Completed: FY2007-08
Intersection Improvements: FY2008-09
Construction Complete: July 2009
JUSTIFICATION:
Improved visibility and enhanced aesthetics.
22
PRf11F("T TIT( F• FAA1F,7 �%M IMA I" �%H1/1
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
(Total Estimated Annual Cost
(PHASE/FUNDING SOURCE
Streets/Highways
TOTAL PROJECT
PROJECT #: PS9909
TOTAL ESTIMATED CAPITAL COST:
Streets/Highways
I Estimated Capital Cost
$O�FUNDING SOURCE:
Transfers from:
Streets CIP Fund Balance
Escrow Funds
Less Interproject Transfers to:
FM 157 Utility Relocation PS0001
$0 Streets CIP Fund Balance
Total Funding
CURRENT STATUS
BUDGET
$129,215
29,215
EXPENDED
$88,930
930
OVER/UNDER
BUDGET (-+)
$40,285
$129,215�
129,215
$239,820
$541215
($26,516)
($138,304)
$129,215
EXPENDED(
69%
69%
23
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 31, 1999
Submitted By: RON YOUNG Date Completed:
Project Title: GLADE ROAD
Project Type: STREET Sub -Type: CONSTRUCTION
Project No.. PS0304 Priority: A
COUNCIL AUTHORIZATION:
December 9, 2003: Approval of Res # 03-1162 declaring intent to reimburse expenditures with proceeds
future debt.
June 22, 2004: Approval of Res #04-1181 authorizing the interlocal agreement with the City of Grapevine.
March 28, 2006: Approved recommending the City of Grapevine to award construction contract to J
Contracting, LP in the amount of $5,228,709.56 with the City of Euless portion of the cost for paving, draina
and relocation of water mains to be $2,753,458,53,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Glade Road is identified as a minor arterial in the 1999 Master Thoroughfare Plan. This is a continuation of the
roadway improvements on Glade Road from SH121 to Champagne Drive completed in 2001. The City of
Grapevine awarded a design contract in April 2003. The utility relocation began in January 2006. The street
construction improvements began in May 2006.
PROJECT DESCRIPTION:
The roadway project consists of replacing the existing two-lane asphalt pavement with a four - lane concrete
roadway, including a median and protected turn lanes. Signalization will be provided at Baze Road and at
North Main Street. The southern half of the project lies within the City of Euless. Adjustment or relocation of
the City of Euless water main along the south side of Glade Road from approximately Roxboro Road to SH360
in advance of the road construction is also required.
PROJECT SCHEDULE:
Construction Complete: June 2008
JUSTIFICATION:
The City of Grapevine had scheduled design for Glade Road in 2002-2003 and assumed the entire cost for
plan preparation. Since the southern half of the proposed roadway construction lies within the City of Euless,
that portion of construction costs lies with the City of Euless.
24
PW"1 IF[`T ITI F- rnI A"rF R(iA"
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
PROJECT its PS0304
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Right of Way $90,000
Personnel: Full Time Contract Labor $20,000
Part Time Construction $2,302,871
Total Salary $0 Utility Relocation $326,000
Purchase of Services Issuance Cost $25,000
Materials & Supplies Contingency $314,105
Utilities
� Subtotal:
Subtotal:
Total Estimated Capital Cost $3,077,976
$0 FUNDING SOURCE:
Developer's Escrow $144,105
Street CIP Fund Balance $206,000
(PS0004 Transfer $65,651)
(Street Fund Balance $140,349)
Certificates of Obligation $2,725,000
Developer's Escrow: $2,871
$0 (ES0287 $938, ES0290 $1,933)
Estimated Annual Cost $0 Total Funding $3,077,976
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Right of Way $90,000 $39,816 $50,184 44%
Contract Labor $20,000 $17,604 $2,396 88%
Streets and Highways $2,302,871 $2,302,871 $0 100%
Utility Relocation $326,000 $326,000 $0 100%
Contingency $314,105 $184,282 $129,823 59%
Issuance Cost $25,000 $25,000 $0 100%
TOTAL PROJECT $3,077,976 $2,895,573 $182,403 94%�
25
Department:
Submitted By:
Project Title
Project Type
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared
Date Completed:
April 15, 2005
SOUTH PIPELINE ROAD BRIDGE REPLACEMENT(Fuller Branch/Post Oak Channel)
STREET
Project No.: PS0605
Sub -Type: BRIDGE
Priority: A
COUNCIL AUTHORIZATION:
June 26, 2007: Approved an interlocal agreement between the City of Euless and the City of Fort Worth,
The City of Euless estimated cost is $157,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is related to the proposed asphalt overlay of South Pipeline Road to be accomplished by
County and jointly funded by the City of Euless and the City of Fort Worth,
PROJECT DESCRIPTION:
Bridge and related channel improvements are planned at South Pipeline Road over Post Oak Channel. The
existing structure .is to be replaced because of structural and geometric deficiencies, as well as load
restrictions. The City of Fort Worth will manage the project and the City of Euless will pay for 25 percent of
the construction cost representing the area which falls within the City of Euless city limits.
(PROJECT SCHEDULE:
'Pending: Delayed due to City of Fort Worth water main conflict. Fort Worth is working on a new bridge
design.
JUSTIFICATION:
South Pipeline Road is an important east -west thoroughfare providing access to the southeast portion of the
City of Euless. This project will correct structural and geometric deficiencies as well as alleviate load
restrictions.
26
Mna[FCT TITI Fe R01 ITH PIPFI INE ROAD BRIDGE REPLACE PROJECT M PS0605
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR =) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
ITotal Estimated Annual Cost
IPHASEIFUNDING SOURCE
Streets/Highways
TOTAL ESTIMATED CAPITAL COST:
Streets/Highways
Total Estimated Ca ital Cost
$0 FUNDING SOURCE:
Transfer from:
Street CIP Fund Balance
m
$0 ITotal Funding
CURRENT STATUS
$157,000�
157.000 I
$157,000 �
$157,000 �
OVER/UNDER
BUDGET EXPENDED BUDGET(-+) %EXPENDED
$157,000 $0 $157,000 0%
TOTAL PROJECT $157,000 $0 $157,000 0%�
27
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 23, 1999
Submitted By: RON YOUNG Date Completed:
Project Title: FULLER -WISER ROAD CONNECTOR
Project Type: STREET Sub -Type: CONSTRUCTION
Project No.: PS0802 Priority: A
COUNCIL AUTHORIZATION:
May 26, 2009: Authorized the City Manager to award a contract to McClendon Construction for $390,810.10
for the reconstruction of Fuller -Wiser Road,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN.
This project is identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION:
Fuller -Wiser Road is a minor local arterial connection between SH360 on the north and SH183 on the south.
This street is presently constructed to a design standard of four lanes undivided in a 70400t right-of-way from
SH183 to north of Mid Cities Boulevard. From the north of Mid Cities Boulevard to SH360, the road will
transition from a four lane undivided to a three lane undivided to tie into the existing Texas Department of
Transportation connection at SH360.
PROJECT SCHEDULE:
Award Design: April 2008
Right of Way Complete: March 2009
Anticipate Construction Complete: October 2010
JUSTIFICATION:
Completing this connector will upgrade this portion of the roadway from a two-lane county road section with
open drainage to a standard curb and gutter street section with underground drainage systems.
PRt7.IF:rT TITI F• FI11 1 FIR -WISER ROAD CONNECTOR
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
(Total Estimated Annual Cost
PHASEIFUNDING SOURCE
Engineering
Streets/Highways
Right -of -Way
TAL PROJECT
PROJECT #: PS0802
TOTAL ESTIMATED CAPITAL COST:
Engineering
Streets/Highways
Right -of -Way
Total Estimated
$0 FUNDING SOURCE:
I Cost
Transfer from:
Streets CIP Fund Balance
$0 Total Funding
CURRENT STATUS
BUDGET
$45,000
$410,000
$40,000
000
EXPENDED
$33,030
$0
$0
OVER/UNDER
$11,970
$410,000
$40,000
1,970
$45,000
$4101000
$401000
$495,000
$495,000
EXPENDED
73%
0%
0%
7%I
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 11, 2008
Submitted By. RON YOUNG Date Completed:
Project Title: ASH LANE/DENTON DRIVE/FAIR OAKS BOULEVARD OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project No.: PS0901 Priority: A
COUNCIL AUTHORIZATION:
January 13, 2009: Authorized the city manager to execute an interlocal agreement between the City of
Euless and Tarrant County for asphalt overlay improvements.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Ash Lane, Denton Drive, and Fair Oaks Boulevard are collector streets that the City of Euless plans to
overlay in a cooperative project with Tarrant County,
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on Ash Lane from Aransas Drive to
FM157, on Fair Oaks Boulevard from North Main Street to Ash Lane, and on Denton Drive from North Main
Street to Fuller -Wiser Road,
PROJECT SCHEDULE.
Begin Construction: April 2009
Construction Complete: June 2009
JUSTIFICATION:
The existing asphalt pavement is deteriorating and is becoming a maintenance problem. The asphalt overlay
will provide an improved riding surface, will extend the life of the roadway, and will enhance the appearance of
the street.
30
PROJECT TITLFn ASH I ANF/DFNTON DR/FAIR OAKS OVERLAY PROJECT #: PS0901
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR =) ANNUAL:
Direct Operatic Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
ITotal Estimated Annual Cost
IPHASEIFUNDING SOURCE
Overlay
TOTAL PROJECT
TOTAL ESTIMATED CAPITAL COST:
Construction
Total Estimated Ca ital Cost
$0 FUNDING SOURCE:
Transfer from:
Streets CIP Fund Balance
$0 ITotal Funding
CURRENT STATUS
$320,000
$320,000 �
$320,000 �
OVER/UNDER
BUDGET EXPENDED BUDGET(-+) %EXPENDED
$320,000 $216,659 $103,341 68%
000 $216,659 $103,341
68%
Department:
Submitted By.
Project Title:
Project Type:
No.
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
VINE STREET, SH183 TO SH10 DESIGN
STREET
PS0902
COUNCIL AUTHORIZATION:
Date Prepared:
Date Completed:
Sub -Type: DESIGN
Prioritv: A
(RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Vine Street is not identified in the 1999 Master Thoroughfare Plan,
July 23, 1999
PROJECT DESCRIPTION:
The City has received street escrow funds from several developments along Vine Street. When development
is complete, it would be appropriate for the City to reconstruct the existing roadway.
(PROJECT SCHEDULE:
Pending: Completion of development
JUSTIFICATION:
Street escrow funds are being deposited for use in reconstruction.
32
PROJECT TITLE: VINE STREET, SH183 TO SH10 DESIGN PROJECT #: PS0902
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR =) ANNUAL:
Direct Operating Cost Engineering $80,000
Personnel: Full Time Right of way $20,000
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost $100,000
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from:
Street CIP Fund Balance $100,000
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $100,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $80,000 $0 $80,000 0%
Right of Way $20,000 $0 $20,000 0%
TOTAL PROJECT $100,000 $0 $100,000 0%
Kk'.
Department:
Submitted By:
Project Title:
Project Type
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared:
Date Completed:
April 12, 2004
TRAFFIC SIGNALS -MID CITIES BLVD AT GATEWAY BLVD AND AT BAZE ROAD
STREET
Project No.: PS0903
COUNCIL AUTHORIZATION:
Sub -Type: SIGNALIZATION
Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic signals are located at the intersections of arterial and collector thoroughfares identified in the City
Euless Master Thoroughfare Plan adopted in 1999.
PROJECT DESCRIPTION:
The project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection, and signal controllers for the intersection of Mid Cities Boulevard and
Gateway Boulevard and for the intersection of Mid Cities Boulevard and Baze Road,
PROJECT SCHEDULE:
Award Design: March 2009
Anticipate Plans Complete: July 2009
Anticipate Award Construction: September 2009
JUSTIFICATION:
Traffic volumes at these intersections have
determine the justification for signal installation,
been monitored and signal warrant studies performed
These intersections require a traffic signal.
34
PROJECT TITLE: SIGNALS -MID CITIES GATEWAY & BAZE PROJECT #: PS0903
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $40,000
Personnel: Full Time Traffic Signals $280,000
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost $320,000
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from:
Car Rental Operating Fund $140,000
Street CIP Fund Balance $18,155
Escrow Funds $161,845
ES0249-ES0254, ES0290
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $320,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $40,000 $2,168 $37,832 5%
Traffic Signals $280,000 $0 $280,000 0%
TOTAL PROJECT $320,000 $2,168 $317,832 1%
35
T H E `µC I T Y (� F
36
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Remaining
Funds to
Unfunded/
Project
Budget as of
Appropriation/
Budget as of
Expended as
Complete
Estimated
(Excess
Number
Project Description
5131108
Amendment
5131109
of 05131/09
Budget
Project Costs
Funding)
WASTEWATER PROJECTS
WW0002 Misc Wastewater Rehab (min bal $100,000)
$259,169
$56,917
$316,086
$216,086
$100,000
$316,086
$0
WW0605 TRA Wastewater Payments - Impact
$1801000
$60,000
$2400000
$180,000
$603000
$240,000
$0
WW0702 Line Replacement Arnett Addition
$313,322
$0
$313,322
$2297006
$847316
$313,322
$0
WW0801 Line Replacement Fayette Drive
$750,000
($262,000)
$488,000
$303176
$457,824
$4881000
$0
WW0802 Line Replacement South Mills Drive CDBG-R
$0
$262,000
$262,000
$0
$262,000
$262,000
$0
WW0901 Line Replacement Woodridge Circle/Koen Lane
$0
$795,000
$795,000
$0
$795,000
$795,000
$0
IAW0902 Line Replacement West Mills Drive-34th CDBG
$0
$46,855
$46,855
$0
$46,855
$46,855
$0
FB9911 FB - Wastewater Impact (Restricted)
$0
$0
$0
$0 $0 $0 ($661,141)
Sub -Total Wastewater Projects
$1,502,491
1 $958,772
1 $2,461J263
$655,268 1 $11805,995 $23461,263 ($661,141)
W
Department:
Submitted By:
Project Title
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared
Date Completed:
MISCELLANEOUS WASTEWATER REHABILITATION
Project Type: WASTEWATER Sub -Type: MAINS
Project No.: WW0002
Priority: A
July 26, 1999
COUNCIL AUTHORIZATION:
March 28, 2006: Authorized the City Manager to proceed with emergency repair by GRA-TEX Utilities
the aerial wastewater main crossing Hurricane Creek at a cost of $55,000,
RELATIONSHIP TO OTHER
PROJECT DESCRIPTION:
This project is for small unidentified wastewater main problems that may be idented during the fiscal year.
Large projects will be identified on an "as needed" basis and presented for funding under a new project
number.
(PROJECT SCHEDULE:
JUSTIFICATION:
Most of these lines are clay the and are seriously deteriorated.
38
PROJECT TITLE: MISCELLANEOUS WASTEWATER REHAB
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
(Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Wastewater Mains
Engineering
Contingency
TOTAL PROJECT
m
PROJECT #: WW0002
TOTAL ESTIMATED CAPITAL COST:
Wastewater Mains
(Minimum balance recommended $100,000)
Total Estimated Capital Cost
FUNDING
SOURCE:
Transfer from W/S Operating Fund
Inter -project Transfer from:
Misc Wastewater Rehab (WW9903)
W/S CIP Fund Balance (FB9901)
I Funding
CURRENT STATUS
BUDGET
$283,567
$1,939
$30,580
16,086
EXPENDED
$183,567
$1,939
$30,580
16,086
OVER/UNDER
$100,000
$0
$0
100,000
$165,000
$37,013
$1141073
EXPENDE
65'
68%
�'7
Department:
Submitted By
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared:
Date Completed:
Project Title: TRINITY RIVER AUTHORITY WASTEWATER PAYMENT
Project Type: WASTEWATER Sub -Type: PAYMENTS
Project No.: WW0605 Priorlty: A
(COUNCIL AUTHORIZATION:
TIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
'PROJECT D
March 3, 2006
Based on a review by Birkoff, Hendricks, and Conway of the water and wastewater impact fees, it was
determined that a substantial portion of the wastewater impact fee is attributed to Trinity River Authority
("TRA") capital projects. Therefore, these fees should be used to pay a portion of the annual TRA expense, as
these funds are directly attributed to the expansion of TRA. Based on the available fund balance, a
systematic drawdown over a ten year period has been developed.
PROJECT SCHEDULE:
Annual payments of $60,000 over a ten year period from FY2006-FY2015.
(JUSTIFICATION:
�iThe expansion at TRA provides additional capacity and it was determined through the wastewater impact fee
study that these funds could be used to pay a portion of TRA wastewater payments. It was determined a ten
year drawdown would approximate the Capital Improvement Plan Review time frame, as well as provide for a
systematic drawdown that would not impact the annual budget.
PROJECT TITLE: TRA WASTEWATER PAYMENT PROJECT #: WW0605
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost TRA Wastewater Payments $240,000
Personnel: Full Time
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities ($60,000)
Total Estimated Capital Cost $240,000
Subtotal: ($60,000) FUNDING SOURCE:
FB9911: FY 2006 $60,000
Maintenance Costs FB9911: FY 2007 $60,000
FB9911: FY 2008 $60,000
FB9911: FY 2009 $60,000
Subtotal: $0
Total Estimated Annual Cost ($60,000) Total Funding $240,000
CURRENT STATUS
OVERIUNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Wastewater - TRA Service $240,000 $180,000 $60,000 75%
TOTAL PROJECT $240,000 $180,000 $60,000 75%
41
Department:
Submitted By:
Project Title:
Project Type:
Proiect No.:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
LINE REPLACEMENT - ARNETT ADDITION
WASTEWATER
WW0702
Sub -Type: MAINS
A
Date Prepared:
Date Completed:
March 27, 2003
COUNCIL AUTHORIZATION:
November 14, 2006. Authorized city manager to execute an Engineering design contract with Elliot &
Hughes, Inc. not to exceed $89,322 for projects WW0701, WW0702, WW0703, and WW0704.
June 24, 2008: Award Bid #004-08 to Horseshoe Construction Company, Inc. for replacement wastewater
mains in portions of the Fuller, Arnett, Oakwood Terrace East, Twin Creek Estates and Oak Crest
Estates Additions, in the amount of $559,933 for projects WW0701, WW0702, WW0703, and WW0704.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Systematic replacement of wastewater lines in drainage basin areas using a worst first approach.
PROJECT DESCRIPTION:
Design and construction of wastewater mains
deteriorated wastewater mains will be replaced.
PROJECT SCHEDULE:
Design Contract: November 2006
Plans Complete: December 2007
Award Construction Bid: June 2008
Begin Construction: August 2008
Construction Complete: February 2009
in the northern portion of the Arnett Addition.
JUSTIFICATION:
Wastewater mains in the Arnett Addition have deteriorated as they have aged and they need to be replaced.
42
IN of Euless LINE REPLACEMENT - ARNETT ADDITION PROJECT #: WW0702
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $38,322
Personnel: Full Time Wastewater Line Replacement $275,000
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost $313,322
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from W/S Operating Fund $394,000
Transfer to W/S CIP Fund Balance ($80,678)
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $313,322
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (=+) % EXPENDED
Engineering $38,322 $26,968 $11,354 70%
Wastewater Mains $275,000 $202,038 $72,962 73%
TOTAL PROJECT $313,322 $229,006 $84,316 73%
43
Department:
Submitted By
Project Title:
ITYpe:
No..
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
LINE REPLACEMENT- FAYETTE DRIVE
WASTEWATER
WW0801
Sub -Type: MAINS
Priority: A
Date Prepared:
Date Completed:
April 30, 2007
COUNCIL AUTHORIZATION:
August 12, 2008: Authorized city manager to execute an engineering design contract with Elliott & Hughes,
Inc. in an amount not to exceed $70,544 for projects WWO801 and WW0802.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater main included in this project is part of the City of Euless Wastewater System Mc
Plan. This project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
Replace wastewater lines on the west side of Fayette Drive from Harwood Road to Ector Drive.
PROJECT SCHEDULE:
Award Design Contract: August 2008
Design Complete: June 2009
Anticipate Award Construction Contract: August 2009
Anticipate Construction Complete: February 2010
JUSTIFICATION:
Many wastewater lines throughout the city are 40 plus years old. Most of the lines are vitrified clay the
are susceptible to ground movement, pulled joints, root infiltration and deterioration from hydrogen sL
gas and other chemicals. Many are substandard in size and have inflow/infiltration problems. Syster
replacement will prevent a mandatory widespread replacement.
C'L��
PROJECT TITLE: LINE REPLACEMENT- FAYETTE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
m
PROJECT #: WW0801
TOTAL ESTIMATED CAPITAL COST:
Engineering
Wastewater Line Replacement
Estimated Capital Cost
$0 (FUNDING SOURCE:
E�
nsfer from W/S Operating Fund
Less Interproject Transfers to:
S. Mills Wastewater Line (WW0802)
W/WW CIP Fund Balance
$47,000
$4411000
$750,000
($162,0
($100,0
Total Estimated Annual Cost $0 Total Funding $488,000
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Engineering $47,000 $30,176 $16,824 64%
Wastewater Mains $441,000 $0 $441,000 0%
TOTAL PROJECT $488,000 $30,176 $457,824 6%�
45
Department:
Submitted By:
Project Title
ITYPe:
No..
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared
Date Completed:
LINE REPLACEMENT- SOUTH MILLS DRIVE (CDBG-R)
WASTEWATER
WW0802
Sub -Type: MAINS
Priority: A
April 30, 2007
COUNCIL AUTHORIZATION:
August 12, 2008: Authorized city manager to execute an engineering design contract with Elliott & Hughes,
Inc. in an amount not to exceed $70,544 for projects WW0801 and WW0802.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater main included in this project is part of the City of Euless Wastewater System M(
Plan. This project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
Replace wastewater lines on the west side of South Mills Drive from Pipeline Road to the south side
SH10.
PROJECT SCHEDULE:
Award Design Contract: August 2008
Design Complete: June 2009
Anticipate Award Construction Contract: August 2009
Anticipate Construction Complete: February 2010
JUSTIFICATION:
Many wastewater lines throughout the city are 40 plus years old. Most of the lines are vitrified clay the and
are susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide
gas and other chemicals. Many are substandard in size and have inflow/infiltration problems. Systematic
replacement will reduce maintenance cost and customer problems.
m
PROJECT TITLE: LINE REPLACEMENT- SOUTH MILLS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
ISubtotal:
ITotal Estimated Annual Cost
PHASE/FUNDING SOURCE
Engineering
Wastewater Mains
TOTAL PROJECT
PROJECT #: WW0802
TOTAL ESTIMATED CAPITAL COST:
Engineering
Wastewater Line Replacement
Estimated Ca
$0 FUNDING SOURCE:
Cost
Transfer from W/S CIP Fund
CDBG-R Funding
$0 Total Funding
CURRENT STATUS
BUDGET
$23,500
$238,500
000
EXPENDED
$0
$0
OVER/UNDER
BUDGET (-+)
$23,500
$238,500
00
$23,500
$2381500
$162,000
$1001000
$262,000
EXPENDED
0%
0%
0%
47
Department:
Submitted By:
Project Title:
Type:
ect No.:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
Date Prepared:
Date Completed:
LINE REPLACEMENT-WOODRIDGE CIRCLE/KOEN LANE
WASTEWATER
WW0901
Sub -Type: MAINS
Priority: A
July 10, 2000
COUNCIL AUTHORIZATION:
April 14, 2009: Authorized City Manager to execute a design contract with Elliot and Hughes, Inc. for
design of replacing wastewater mains in an amount not to exceed $6110004
(RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Systematic replacement of wastewater lines in drainage basin areas using a worst first approach.
PROJECT DESCRIPTION:
Replace the following wastewater lines on Wood Ridge Circle:
1. West side of Driftwood Drive from Tanglewood Trail to Pipeline Road
2. East side of Driftwood Drive from Woodridge Circle to Pipeline Road
3. Briarwood Court and Penoak Court, and
4. West end of Koen Lane to South Pipeline Road.
PROJECT SCHEDULE:
Award Design: March 2009
Anticipate Plans Complete: 1st Quarter 2010
Anticipate Begin Construction: 2nd Quarter 2010
Anticipate Construction Complete: 4th Quarter 2010
JUSTIFICATION:
Many wastewater lines throughout the city are 40 plus years old. Most of the lines are clay the and are
subject to ground movement, grease, root infestation and deterioration due to hydrogen sulfide gas and other
chemicals. Many are not functional at an acceptable level and are often inundated with infiltration and inflow.
Systematic replacement will prevent a mandatory wide spread replacement.
PROJECT TITLE' LINE REPLACEMENT-WOODRIDGE/KOEN
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Maintenance Costs
I Subtotal:
Full Time
Part Time
(Total Estimated Annual Cost
PHASEIFUNDING SOURCE
Engineering
Wastewater Mains
TOTAL PROJECT
PROJECT #: WW0901
AL ESTIMATED CAPITAL COST:
Engineering
Wastewater Line Replacement
Total Estimated Capital Cost
$0 (FUNDING SOURCE:
Transfer from W/S Operating Fund
E�
$0 Total Funding
CURRENT STATUS
BUDGET
$87,000
$708,000
EXPENDED
$0
$0
OVER/UNDER
BUDGET (-+)
$87,000
$708,000
795,000
$87,000
$7081000
000
$795,000
$795,000
EXPENDED
0%
0%
C�7
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15, 2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -WEST MILLS DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project No.: WWO902 Priority: A
COUNCIL AUTHORIZATION:
February 26, 2008: Approved the recommended project selection for the 34th year Community Development Block
Grant project for wastewater main line replacement.
February 10, 2009: Recommended Tarrant County award construction contract to Hall Albert Construction
Company in the amount of $46,855.05 representing the total amount of the project.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The West Mills Drive wastewater main is part of the City of Euless Wastewater System Master Plan. Systematic
replacement is based on the worst first approach.
PROJECT DESCRIPTION:
Replace wastewater mains along West Mills Drive between South Mills Drive and Simmons Drive.
PROJECT SCHEDULE:
Begin Construction: March 2009
Construction Complete: April 2009
JUSTIFICATION:
Many wastewater mains throughout the city are 40 plus years old. Most of these lines are clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas. Many
are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce maintenance
costs and customer problems.
50
PROJECT TITLE: LINE REPLACEMENT -WEST MILLS DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
(Total Estimated Annual Cost
(PHASE/FUNDING SOURCE
Wastewater Mains
TOTAL PROJECT
F�
PROJECT #: WW0902
TOTAL ESTIMATED CAPITAL COST:
Wastewater Line Replacement
Total Estimated Ca
$0 FUNDING SOURCE:
34th CDBG FY 2009
$0 Total Funding
CURRENT STATUS
BUDGET
$46,855
855
EXPENDED
$0
I Cost
OVER/UNDER
$46,855
$46,855 �
$46,855 �
$46,855 �
EXPENDED(
0%
51
52
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Remaining
Funds to
Unfunded/
Project
Number
Project Description
Budget as of
5131108
Appropriation/
Amendment
Budget as of
5/31109
Expended as
of 05/31109
Complete
Budget
Estimated
Project Costs
(Excess
Funding)
WATER PROJECTS
WT0o01
Misc Utility Rehab - Water (min bal $150,000)
$2530511
$0
$253,511
$1039775
$149,736
$253,511
$0
WT0101
Water Tank Debt Payment
$2,175,514
$257,000
$2,432,514
$2,346,848
$85,666
$2,432,514
$0
WT0104
Well Repairs (min bal $75,000)
$5133617
$0
$513,617
$438,617
$75,000
$513,617
$0
WT0201
Well Rehabilitation/Disinfection
$600,000
$0
$600,000
$522,285
$77,715
$600,000
$0
WT0202
Effluent Water Main
$250,000
$0
$250,000
$0
$250,000
$1,500,000
$1,250,000
WT0803
Transponders/Meters(annual transfer $158,000)
$331,875
$331,875
$663,750
$555,247
$108,503
$663,750
$0
WT0901
TRA Water Payments -Impact
$0
$1003000
$100,000
$0
$100,000
$100,000
$0
FB9910 FB- Water Impact (Restricted)
$0
$0
$0
$0
$0
$0
($2,534,906)
FB9901 FB - Water & Sewer CIP
$0
$0
$0
$0
$0
$0
($489,964)
Sub -Total Water Projects
$41124,517
$688,875
$4,813,392
$33966,772
$846,620
$6,0632392
($1,774,870)
CSt
W
Department: PUBLIC WORKS
City of Euless
Capital Project Request
Date Prepared: July 26, 1999
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS WATER UTILITY REHABILITATION
Project Type: WATER
Project No.: WT0001
(COUNCIL AUTHORIZATION:
TIONSHIP TO OTHER PROJECTS
Sub -type: MAINS
0
TER PLAN:
PROJECT DESCRIPTION:
This project is for the correction of small unidentified water main problems that may arise throughout the
fiscal year. Large projects that are identified will be prepared on an "as needed" basis and funded under a
new project number.
(PROJECT SCHEDULE:
JUSTIFICATION:
Some of the City's older water mains have deteriorated and need replacement or repair. Staff requests
this project be funded on an annual basis.
54
PH"aJFCT ITLEff MISCELLANEOUS UTILITY REHAB - WATER
PROJECT IF: WT0001
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Water Mains
Direct Operating Cost
Personnel: Full Time (Annual minimum funding $150,000)
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
(Subtotal: $O�FUNDING SOURCE:
Maintenance Costs Transfer from:
W/S CIP Fund Balance $265,000
W/S Operating Fund $100,000
Misc Water Rehab WT9905 $6,251
Less Inter -project Transfer to:
Milam - Denton/Midway WT0005 ($7,020)
Subtotal: $0 Well Repairs WT0104 ($110,720)
Total Estimated Annual Cost $O�Total Funding $253,511
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (-+) %Expended
Contingencies $49,231 $24,852 $24,379 50%
Water Mains $204,280 $78,923 $125,357 39%
TOTAL PROJECT $253,511 $103,775 $149,736 41
55
Department: PUBLIC WORKS
Submitted By: RON YOUNG
Project Title:
Project Type:
ect No.:
City of Euless
Capital Project Request
WATER TANK DEBT PAYMENT
WATER
WT0101
COUNCIL AUTHORIZATION:
Approved in the annual budget.
(RELATIONSHIP TO OTHER PROJECTS AN
Date Prepared:
Date Completed:
Sub -type: PAYMENTS
F_1
TER PLAN:
May 1, 2001
PROJECT DESCRIPTION:
This project includes the transfer of funds from the water impact fee to pay the debt service related to the
construction of the new water tower.
(PROJECT SCHEDUL
JUSTIFICATION:
The water tower provides additional capacity and was included in the water impact fee study.
PROJECT TITLE: WATER TANK DEBT PAYMENT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Subtotal:
Total Estimated Annual Cost
PROJECT #: WT0101
TOTAL ESTIMATED CAPITAL COST:
Debt Service - FY01 $249,012
Debt Service - FY02 $291,759
Debt Service - FY03 $279,671
Debt Service - FY04 $277,921
$0 Debt Service - FY05 $280,834
Debt Service - FY06 $278,071
Debt Service - FY07 $258,314
Debt Service - FY08 $259,932
Debt Service - FY09 $257,000
Total Estimated
$OIFUNDING SOURCE:
Cost
Transfer from:
Water Impact CIP Fund Balance
Total Funding
CURRENT STATUS
PHASEIFUNDING SOURCE BUDGET EXPENDED
Transfer to Debt Service $2,432,514 $2,346,848
�TAL PROJECT $2,432,514 $2,346
OVERIUNDER
BUDGET (-+)
$85,666
514
$2,432,514
$2,432,514
Expended
96%
96%
57
Department:
Submitted By:
Project Title:
Project Type:
Project No.:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
WELL REPAIRS
WATER
WT0104
Date Prepared:
Date Completed:
Sub -Type: WELL REPAIR
Priority: A
June 1, 2001
COUNCIL AUTHORIZATION:
April 22, 2003: Awarded Bid # 01 &03 for Far North Well Pump Repair to Layne -Texas for $32,790,
February 14, 2006: Award bid #011-06 to Millican Well Services, L.L.C., for rehabilitation and installation
new Centrilift submersible motor and pump for the Far North Main Well in the amount of $250,035,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER
PROJECT DESCRIPTION:
This funding is being utilized to repair well pumps and for unexpected well repairs.
PROJECT SCHEDULE:
Rehabilitation/installation of submersible motor and pump for Far North Main Well complete: February 2007
JUSTIFICATION:
Maintaining the City's wells results in the ability to produce water at a substantial reduction in cost.
m
PROJECT TITLE: WELL REPAIRS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
m
PROJECT #: WT0104
TOTAL ESTIMATED CAPITAL COST:
Well Repairs
(Minimum Balance Maintained $75,000)
Subtotal: $0 FUNDING SOURCE:
Transfer from:
Maintenance Costs Misc Water Rehab $110,720
W/S CIP Fund Balance $77,897
W/S Operating Fund $325,000
I Subtotal:
m
Total Estimated Annual Cost $O�Total Funding $513,617
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (-+) %EXPENDED
Well Repairs $513,617 $438,617 $75,000 85%
TOTAL PROJECT $513,617 $438,617 $75,000 85%
59
Department:
Submitted By
Project Title:
Project Type.
ect No.:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
WELL REHABILITATION/DISINFECTION
WATER
WT0201
Date Prepared:
Date Completed:
Sub -Type: WATER PRODUCTION
Priority: A
July 26, 1999
COUNCIL AUTHORIZATION:
October 9, 2001 Bid #054-01 awarded to Millican Well Services, LLC for $55,130 for plugging three water
wells at 1100 Central Drive with a contingency of $13,750.
October 23, 2001 Authorized city manager to proceed with emergency plugging of Harwood Trinity water
well by Layne -Texas in the amount of $29,450.
October 23, 2001 Authorized city manager to proceed with emergency rehabilitation of the Far North Trinity
water well by Layne -Texas at an estimated expenditure of $92,254.
October 8, 2002 Awarded contract to Tank Builders for the Fuller ground storage reservoir in the amount of
$222,600, plus a 5% contingency in the amount of $11,180.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project consists of inspecting deep wells to determine condition of well pipe, casing, screens, and gravel
packing and rehabilitating items that are found to be in need. It also includes adding ammonia injection
facilities at each of our three well sites.
PROJECT SCHEDULE:
Fuller Tank Complete
Designs Complete: Ammonia/Chlorine Feed Buildings
Begin Construction: Fall 2007
Construction Complete: June 2009
JUSTIFICATION:
Wells are old and heavily used. All three deep wells need to be rehabilitated according to needs determined
by inspection. The Environmental Protection Agency, Texas Natural Resources Conservation Commission,
and Safe Drinking Water Act mandate disinfection by-product limits. If test results indicate non-compliance,
the need to modify the disinfection process or cease well operations will be necessary.
PROJECT TITLE: WELL REHABILITATION/DISINFECTION
PROJECT #: WT0201
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Water Rehabilitation
$600,000
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$600,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from W/S Operating Fund
$600,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$600,000
CURRENT
STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (-+) %
EXPENDED
Well Rehabilitation
$600,000
$522,285 $77,715
87%
TOTAL PROJECT
600,000
522,285 77,715
87%
61
Department:
Submitted By:
Project Title:
Project Type:
City of Euless
Capital Project Request
COMMUNITY SERVICES
RON YOUNG
EFFLUENT WATER MAIN
WATER
Project No.: WT0202
Date Prepared:
Date Completed:
Sub -Type: INSTALLATION
0
June 29, 2000
COUNCIL AUTHORIZATION:
March 11, 2008, Approved resolution #08-1272 committing to negotiate with the City of Fort Worth
regarding purchase of reclaimed water delivery through Fort Worth's proposed reclaimed water delivery
system.
May 26,2009: Authorized the city manager to negotiate and execute an agreement with the City of Fort
Worth for the purchase of reclaimed water, including the related Memorandum of Understanding for a term of
twenty years from the effective date.
� RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER
PROJECT DESCRIPTION:
Effluent water main from City of Ft. Worth Village Creek Wastewater Treatment Facility to the Texas
property.
PROJECT SCHEDULE:
JUSTIFICATION:
Utilization of this source of water would ensure the city could continue irrigation in the event of drought and
mandatory water restrictions.
[:3�i
PROJECT TITLE: EFFLUENT WATER MAIN
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Costs
I Subtotal:
(Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Water Mains
TOTAL PROJECT
PROJECT #: WT0202
TOTAL ESTIMATED CAPITAL
COST:
Installation
Total Estimated Capital Cost
FUNDING
SOURCE:
Transfer from W/S Operating Fund
ADDITIONAL FUNDING NEEDED:
Government Funds
Transfer from:
$0 W/S Operating Fund
W/S CIP Fund Balance
W/S Excess Reserves
$0 Total Funding
CURRENT STATUS
BUDGET
$250,000
000
EXPENDED
$0
OVER/UNDER
$250,000
000
$1,500,000
$1,500,000
$250,000
$500,000
$400,000
2201000
$1,500,000
EXPENDED
0%
City of Euless
Capital Project Request
NEENE
Department: PUBLIC WORKS Date Prepared: May 31, 2007
Submitted By. RON YOUNG Date Completed,
Project Title: TRANSPONDERS/METERS
Project Type, WATER Sub -Type: EQUIPMENT REPLACEMENT
Project No.: WT0803 Priority: A
COUNCIL AUTHORIZATION,
November 13, 2007: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the city manager to enter into an agreement with Atlas Utility Supply Company in the amount of
$383,875. Amount for project not to exceed $331,875.
November 11, 2008: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the city manager to enter into an agreement with Atlas Utility Supply Company in the amount of
$356,875. Amount for project not to exceed $331,875,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Partial replacement of transponders occurred in FY2006 and FY2007. The balance of the old transponders needs
to be replaced.
PROJECT DESCRIPTION:
Purchase and installation of electronic transponders. Transponders are affixed to water meters allowing for
electronic or remote reading of water consumption. These water meters (transponders) are read with an electronic
device located inside of a vehicle which is driven along a predefined route.
PROJECT SCHEDULE:
Purchase and Installation transponders complete: FY2009
Purchase and Installation of meters: Annually
JUSTIFICATION,
The Trace transponders technology is approximately 15 years old. The dependability of the reading equipment, the
transponder size, and the battery life expectancy of the Trace automated reading system has not kept pace with
developing technology. Trace transponders are failing at a high rate. The reading equipment is also approximately
15 years of age and requires frequent returns to the factory for repairs.
MENE
PROJECT TITLE, TRANSPONDERS/METERS PROJECT #: WT0803
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
(Annual Transfer -Operating Funds $158,000)
Personnel: Full Time
Part Time FY2007-08Transponders/Meters $331,875
Total Salary $0 FY2008-09 Transponders/Meters $331,875
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Estimated Capital Cost $663,750
$0 FUNDING SOURCE:
Maintenance Costs Transfer from;
W/S CIP Fund Balance - FY08 $173,875
W/S Operating Fund - FY08 $158,000
W/S CIP Fund Balance- FY09 $173,875
W/S Operating Fund - FY09 $158,000
Subtotal: $0
Total Estimated Annual Cost $0 ITotal Funding $663,750
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Meters/Transponders $663,750 $555,247 $108,503 84%
(TOTAL PROJECT $663,750 $555,247 $108,503 84%
65
Department:
bmitted By
Project Title:
Project Type:
City of Euless
Capital Project Request
PUBLIC WORKS
RON YOUNG
TRINITY RIVER AUTHORITY WATER PAYMENT
WATER
I Proiect No.: WT0901
(COUNCIL AUTHORIZATION:
Date Prepared:
Date Completed:
Sub -Type: PAYMENTS
SHIP TO OTHER PROJECTS AND/OR MASTER P
May 31, 2008
PROJECT DESCRIPTION:
Based on a review by Birkoff, Hendricks, and Conway of the water and wastewater impact fees, it wa
determined that a substantial portion of the water impact fee is attributed to Trinity River Authority ("TRA'
capital projects. Therefore, these fees should be used to pay a portion of the annual TRA expense, as thes
funds are directly attributed to the expansion of TRA. Based on the available fund balance, a systemat
drawdown over a ten year period has been developed.
PROJECT SCHEDULE:
Annual payments of $100,000 over a ten year period from FY2009-FY2018.
JUSTIFICATION:
The expansion at TRA provides additional capacity and it was determined through the water impact fee stu
that these funds could be used to pay a portion of TRA water payments. It was determined a ten ye
drawdown would approximate the Capital Improvement Plan Review time frame, as well as provide for
systematic drawdown that would not impact the annual budget.
PROJECT TITLE: TRINITY RIVER AUTHORITY WATER PAYMENT PROJECT #: WT0901
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
TRA Water Payments FY2009
$100,000
Personnel: Full Time
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$100,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfers from:
Water Impact Fund Balance - FY09
100,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$100,000
CURRENT
STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED' BUDGET (- +) %
EXPENDED
Water - TRA Service
$100,000
$0 $100,000
0%
TOTAL PROJECT
$100,000
$0 $100,000
0%
[:1r1
T H E ,�,� C I T Y O F
C�3
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5131108
Appropriation/
Amendment
Budget as of
5/31109
Expended as
of 05/31/09
Remaining
Funds to
Complete
Budget
Estimated
Project Costs
Unfunded/
(Excess
Funding)
OTHER
AC0901
ITexas Star Sports Complex Study/Fence
$0
$100,000
$100,000
$85,204
$143796
$100,000
$0
M0304
En Monument Sign Pro ram
$115,782
$0
$115,782
$93,027
$22,755
$115,782
$0
M0804
Redevelopment
$951,947
$15,525
$967,472
$659,642
$307,830
$967,472
$0
V9901
i
EDC Incentive Funds
$325,854
$25,000
$350,854
$3009854
$503000
$350,854
$0
D0101
Plannin Consultants
$100,000
$0
$100,000
$0
$1003000
$2009000
$1001000
D0801
Redi-Mix Regional Headquarters
$5,4501000
($250,000)
$5,200,000
$1,175,036
$4,0249964
$5,200,000
$0
PD9901
Police and Municipal Courts Facility
$11,717,134
$462
$11,717,596
$11,609,560
$108,036
$11,717,596
$0
PR0601
Park Amenities Upgrade
$150,000
$0
$150,000
$1453316
$4,684
$150,000
$0
PR0720
Misc. Park Structures
$225,000
$0
$225,000
$131J275
$933725
$225,000
$0
PR0804
Park Irrigation
$25,000
$25,000
$50,000
$770
$49,230
$50,000
$0
PR0901
Trail Enhancement - Bob Eden Park
$0
$135,000
$135,000
$0
$135,000
$135,000
$0
PRO902
Senior Citizen Center at Midway Park
$0
$4,856,821
$4,856,821
$0
$4,8563821
$4,856,821
$0
PR0907
I Midway Park Family Life Center Phase 1
$0
$1,330,000
$1,330,000
$66,644
$1,263,356
$2,105,000
$775,000
FB9906
FB-EDC CIP
$0
$0
$0
$0
$0
$0
($958,496)
FB9908
FB-Athletic Complex CIP
$0
1 $0
1 $0
$0
$0
$0
($740,639)
FB9909
FB-General CIP
$0
$0
$0
$0
$0
$0
($34,342)
FB9913
FB-Car Rental CIP
$0
$o
$0
$0
$0
$0
($74,674)
Sub -Total Other Projects
$191060,717
$65237,808
$25,298,525
$14,267,328
$11,031,197
$26,173,525
($9339151)
Department:
Submitted By.
Project Title:
Project Type:
City of Euless
Capital Project Request
COMMUNITY SERVICES
RAY MCDONALD
Date Prepared:
Date Completed.
TEXAS STAR SPORTS COMPLEX -STUDY/FENCING
LAND
Project No.: AC0901
COUNCIL AUTHORIZATION:
Sub -Type: IMPROVEMENTS
Priority: A
July 13, 2008
Identified in the recently adopted Parks Master Plan is the need for additional playing fields to accommodate
the growing number of participants in the Parks at Texas Star baseball league as well as the need to make
the necessary improvements to the aging fields, fencing, and structures at Softball World.
It is important that staff remains committed to the vision that the City Council has promoted for
over ten years of positioning the Texas Star Sports Complex as a premier facility that serves the
athletic needs of the city as well as a facility that spurs economic opportunities. This proposal would
allow staff the ability to conduct the necessary research, through a consultant and/or design firm, to make
the necessary renovations to this facility and develop it into a more multi -use facility that could
accommodate the Parks at Texas Star Baseball League and tournament play, additional programming for
adult softball as well as the opportunity to accommodate a girl's fast pitch league and tournament play.
Consultant .and/or design firm services to explore the many options available and costs associated with
converting Softball World from its current state into a more programmable complex to accommodate
multiple sports/uses as well as to work with staff in determining cost and design of practice fields at the
Parks at Texas Star and to replace the fencing at Softball World.
With the proposed Midway Park Family Life Center project, staff recognizes the project's impact on our
athletic programs due to the loss of the existing fields at Midway Park. The fields at Midway Park are
currently used as practice fields for teams participating in the Parks at Texas Star Baseball League on an
assigned and rental basis. The Midway Park fields are also used as game fields primarily for tournaments,
but also in league play for make-up games in the event of rain -outs. Losing the fields entirely would limit
staff's ability to register the same number of teams as previously for tournaments and could extend the
season by several weeks for make-up games.
T
PROJECT TITLE: TX STAR SPORTS COMPLEX - STUDY/FENCE PROJECT #: AC0901
NET EFFECTS ON OPERATING AND (TOTAL ESTIMATED CAPITAL COST
MAINTENANCE COST (+ OR -) ANNUAL.
Direct Operating Cost Feasibility Study $15,000
Personnel: Full Time Improvements/Fencing $85,000
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
otal Estimated Capital Cost $100
Subtotal: $0 FUNDING SOURCE:
(Maintenance Costs Transfer from
Texas Star Sports Complex CIP 100,000
athletic needs of the city as well as a fai $0
Total Estimated Annual Cost $0 Total Funding $100,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) %EXPENDED
Architectural Services $15,000 $15,000 $0 100%
Improvements $85,000 $70,204 $14,796 83%
(TOTAL PROJECT $100,000 $85,204 $14,796 85%�
71
Department:
Submitted By
Project Title:
City of Euless
Capital Project Request
CITY MANAGER
GARY MCKAMIE
ENTRY MONUMENT SIGN PROGRAM
Project Type: OTHER IMPROVEMENTS
Project No.: CM0304
COUNCIL AUTHORIZATION.
Sub -Type
Pri
Date Prepared
Date Completed:
IMPROVEMENTS
I1
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Continuation of the original CM0304 City of Euless Entry Monument Sign Program.
July 11, 2006
PROJECT DESCRIPTION:
Continued construction of City of Euless entry monument signs at key high visibility points throughout the
city furthering Euless beautification and branding efforts.
PROJECT SCHEDULE:
Projects will be identified and completed on an as needed basis.
JUSTIFICATION:
To enable continued efforts to identify, beautify, and brand the City of Euless.
72
�Rn_IFrT TITI F• FNTRY mnN[IMPNT SIGN PROGRAM
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
I Subtotal:
ITotal Estimated Annual Cost
IPHASEIFUNDING SOURCE
Land Betterments
TOTAL PROJECT
PROJECT #: CM0304
TOTAL ESTIMATED CAPITAL COST:
Land Betterments
Total Estimated Ca ital Cost
$0 FUNDING SOURCE:
Transfer from Car Rental
E�
$0 ITotal Funding
CURRENT STATUS
$115,782
115
$115,782 �
$115,782 I
OVER/UNDER
BUDGET EXPENDED BUDGET(-+) %EXPENDED
$115,782 $93,027 $22,755 80%
115,782 $93,027 $22,755 80%
73
City of Euless
Capital Project Request
Department: CITY MANAGER
Date Prepared:
Submitted By: GARY MCKAMIE Date Completed:
May 31, 2007
Project Title: REDEVELOPMENT
Project Type: DEVELOPMENT Sub -Type: DEVELOPMENT PROJECT
No.: CM0804
Priority: A
COUNCIL AUTHORIZATION:
October 23, 2007: Authorized the mayor to negotiate and execute conveyance documents for the purchase
of property on Lot 27, Block 2, Cresthaven Addition, located at 1010 Highland Drive,
November 27, 2007: Authorized the mayor to negotiate and execute conveyance documents for the
purchase of property on Lot 24, Block 1, Cresthaven Addition, located at 1010 Cresthaven Drive.
December 11, 2007: Authorized the mayor to negotiate and execute conveyance documents for the
purchase of property on Lots 17 & 18, Block 8, Cedar Hill Estates Addition, located at 710 S Main Street,
October 28, 2008: Authorized the mayor to negotiate and execute conveyance documents for the purchase
of property on Lot 3, Block 2, Cresthaven Addition, located at 1007 Cresthaven Drive,
January 13, 2009: Authorized the mayor to negotiate and execute conveyance documents for the purchase
of property on Lot 18, Block 1, Cresthaven Addition, located at 912 Cresthaven Drive; and Lot 4, Block 2,
Cresthaven Addition, located at 1005 Cresthaven Drive; and Lot 23, Block 2, Cresthaven Addition, located at
1002 Highland Drive,
PROJECT DESCRIPTION AND RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding to allow the City to participate in redevelopment projects and other community
improvements or make acquisitions of property that will be of economic benefit to the City of Euless.
PROJECT SCHEDULE:
This will be a long-term project that will be on -going for many years in an effort to continuously improve
community.
JUSTIFICATION:
As the City ages, it is imperative that the economic vitality of the City remain strong. Reinvestment into
community will protect property values from deterioration and keep commercial properties occupied
PROJECT TITLE: REDEVELOPMENT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
F�
PROJECT #: CM0804
TOTAL ESTIMATED CAPITAL COST:
Land Acquisition
Demolition Svc
Minor Apparatus
Total Estimated
$O�FUNDING SOURCE:
m
Cost
Transfer from General Fund
Interest
Drill Site Surface Damage
$932,018
$351357
97
72
$930,000
$271472
$105000
Total Estimated Annual Cost $O�Total Funding $967,472
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (-+) %EXPENDED
Land Acquisition $932,018 $614,834 $317,184 66%
Demolition Svc $35,357 $44,712 ($9,355) 126%
Minor Apparatus $97 $96 $1 99%
TOTAL PROJECT _ _ $967,472 $659,642 $307,830 68%
75
City of Euless
Capital Project Request
(Department: ECONOMIC DEVELOPMENT Date Prepared: JUIy 26, 1999
(Submitted By: BILL RIDGWAY Date Completed:
Project Title: EDC INCENTIVE FUNDS
Project Type: HALF -CENT SALES TAX Sub -Type: DEVELOPMENT PROJECT
Project No.: DV9901 Priority: A
COUNCIL AUTHORIZATION:
Approved in Sales Tax Revenue Bonds, Series 1994,
March 27, 2001: Approved transfer of $325,000 to North Main Street for right of way to free up funds for a
sign program.
May 30, 2006: Approved payment to Professional Turf Products, Inc. in the amount of $300,000 per
agreement
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Euless Development Corporation funds that have been set aside to aid the City of Euless in attracting
development opportunities.
PROJECT SCHEDULE:
Projects will be identified on an as needed basis.
JUST(
76
PROJECT TITLE: EDC INCENTIVE FUNDS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
PROJECT #: DV9901
TOTAL ESTIMATED CAPITAL COST:
(Annual Transfer -Operating Funds $25,000)
$0 (Will be based on the merits
of each opportunity.
Total Estimated Capital Cost Unknown
$O�FUNDING SOURCE:
Maintenance Costs Transfers from:
EDC CIP Fund Balance $888,454
EDC Operating Fund $250,000
Less Inter -project Transfer to:
Fire Station #2 SS0010 ($432,600)
North Main Street PS9901 ($355,000)
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $350,854
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Economic Development Incentives* $350,000 $300,000 $50,000 86%
Irrigation Supplies $854 $854 $0 100%
(TOTAL PROJECT $350,854 $300,854 $50,000 86%�
77
City of Euless
Capital Project Request
(Department: ECONOMIC DEVELOPMENT Date Prepared: JUIy 7, 2000
Submitted By: BILL RIDGWAY Date Completed:
'Project Title: PLANNING CONSULTANTS
Project Type: ECONOMIC DEVELOPMENT Sub -Type: DEVELOPMENT PROJECT
No.: ED0101
(COUNCIL AUTHORIZATION:
Priority: A
(RELATIONSHIP TO OTHER PROJECTS ANDIOR MASTER PLAN:
This project involves the funding for evaluating various development opportunities.
PROJECT DESCRIPTION:
Commission a study to determine the highest and best use of this valuable commercial land.
'PROJECT SCHEDULE:
JUSTIFICATION:
Poor planning can result in tower than desired tax revenue, hodge podge development activity, and less than
optimal development quality. City needs to be proactive to guide the development of these vital tracts.
PROJECT TITLE: PLANNING CONSULTANTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Subtotal:
Full Time
Part Time
(Total Estimated Annual Cost
PHASEIFUNDING SOURCE
Planning Study
TOTAL PROJECT
PROJECT #: ED0101
TOTAL ESTIMATED CAPITAL COST:
Planning Study
Total Estimated Ca ital Cost
$0 FUNDING SOURCE:
Transfer from Car Rental
ADDITIONAL FUNDING NEEDED:
Transfer from Car Rental
F�
$OlTotal Funding
CURRENT STATUS
$200,000
0,000 I
$100,000 �
$100,000 �
$200,000 �
OVERIUNDER
BUDGET EXPENDED BUDGET(-+) %EXPENDED
$100,000 $0 $100,000 0%
100,000
00,000 0%�
79
Department:
Submitted By:
Project Title:
Project Type,
City of Euless
Capital Project Request
ECONOMIC DEVELOPMENT
KYLE MCADAMS
REDI-MIX REGIONAL HEADQUARTERS
DEVELOPMENT
Project No.: ED0801
Date Prepared
Date Completed:
Sub -Type: INCENTIVES
Priority: A
May 31, 2007
COUNCIL/EDC AUTHORIZATION:
October 22, 2007: EDC held public hearing to consider Resolution 15-07 regarding declaration of project.
October 23, 2007: Ratified EDC action to amend and modify existing project with Beall Concrete.
February 25, 2008: EDC authorized acquisition of approximately 2 acres in the Main Centre Addition.
February 259 2008: EDC authorized acquisition of approximately 4 acres in the James P. Hallford Survey.
February 25, 2008: Authorized architectural contract for design of corporate headquarters and job training
facility.
February 26, 2008: Ratified EDC action to purchase property and to authorize architectural contract.
June 23, 2008: EDC authorized lease and incentive agreement between EDC, City of Euless, Redi Mix and
U.S. Concrete, Inc.
June 24, 2008: Ratified EDC action regarding lease and incentive agreement.
June 24, 2008: Approved resolution #08-1284 approving a lease and incentive agreement by and between
City of Euless, EDC, U.S. Concrete, Inc & Redi Mix, LLC and authorize the mayor to modify and execute such
agreement.
August 26, 2008: Approved Chapter 380 Construction Agreement between EDC, City of Euless, Redi-Mix,
LLC, and U.S. Concrete, Inc and authorize the mayor to execute such agreement.
November 11, 2008. Awarded bid for concrete only to Redi-Mix Concrete in the amount of $303,974.75
April 14, 2009: Authorized the City Manager to enter into a contract with Vratsinas Construction Company,
LLC in the amount of $3,333,244.00 for construction of the facility.
PROJECT DESCRIPTION AND RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project includes the purchase of land and the construction of building that is approximately 25,936
square feet. This facility will be used as a regional corporate headquarters and training facility and will
provide for job retention within the City and will provide substantial economic benefit to the City of Euless.
PROJECT SCHEDULE:
Land Acquisition -April 2008
Design - October 2008
Award Construction Contract: April 2009
Anticipate Construction Complete: December 2009
JUSTIFICATION:
Providing incentive to current business to attract and retain primary jobs within the city and promote
economic growth.
PROJECT TITLE: REDI-MIX REGIONAL HEADQUARTERS
PROJECT #: ED0801
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Construction $3,333,244
Direct Operating Cost Concrete $400,000
Personnel: Full Time Architect $4051000
Part Time Engineering/Survey $57,500
Total Salary $0 Utility relocation $50,000
Land Acquisition $650,000
Purchase of Services Contingency $150,000
Materials & Supplies Landscape/Irrigation $140,000
Utilities Data and Telephone $14,256
Total Estimated Capital Cost $51200,000
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from:
Car Rental Fund $3,450,000
EDC Operating Fund $1,750,000
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $5,200,000
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Construction $3,333,244 $106,585 $3,226,659 3%
Architect $405,000 $399,893 $5,107 99%
Land Acquisition $650,000 $633,453 $16,547 97%
Contingency $150,000 $128 $149,872 0%
Landscape/Irrigation $140,000 $0 $140,000 0%
Engineering/Survey $57,500 $0 $57,500 0%
Equipment $14,256 $0 $14,256 0%
Utility relocation $50,000 $34,977 $15,023 70%
Concrete $400,000 $0 $400,000 0%
TOTAL PROJECT $5,200,000 $1,175,036 $4,024,964 23%�
City of Euless
Capital Project Request
Department: POLICE DEPARTMENT Date Prepared. July 15, 1999
Submitted By: GARY MCKAMIE Date Completed:
Project Title: POLICE &MUNICIPAL COURTS FACILITY
Project Type, BUILDINGS/FACILITIES Sub -Type: CONSTRUCTION
Project No.: PD9901 Priority: A
COUNCIL AUTHORIZATION:
January 13, 1998 - Authorized contract with Phillips Swager for architectural services.
April 14, 1998 - Authorized the acquisition of the Western Hills Inn and Western Hills Annex,
June 9, 1998 - Awarded Bid No. 98-13 for demolition services.
October 9, 1998 - Awarded change order to West Excavation for abatement of asbestos.
February 23, 1999 - Authorized additional funds for demolition.
June 22, 1999 - Declared expectation to reimburse expenditures with proceeds of future debt.
June 22, 1999 - Authorized City Manager to request qualifications for construction management service.
February 22, 2000 - Public Hearing and approval of Special Use Permit.
February 22, 2000 - Approval of request for site plan.
May 9, 2000 -Approval of Ordinance No. 1426 authorizing sale of Cert. Of Obligation Series 2000A,
May 9, 2000 - Awarded bid for construction to Ratcliff Construction,
November 14, 2000 - Authorized execution of contract for Project Management Services
January 9, 2001 - Granted City Manager approval to authorize change orders not to exceed $25,000,
January 23, 2001 - Ratified contract for inspection services to increase limit to $65,000
January 23, 2001 - Approved Change Order #1 to credit contract $152,391,
January 23, 2001 - Approved Change Order #3 for payment of $48,372.79 on new piers and removal.
March 27, 2001 - Approved Change Order #4 to credit contract $42,871.41.
May 22, 2001 - Awarded bid #044=01 for furniture in the amount of $332,400.70,
June 12, 2001 - Authorize City Manager to execute contract with DataTex not to exceed $74,257.86.
August 28, 2001 - Awarded contract to DFW Communication in the amount of $33,009 for relocating and
installing police and public works radio system.
PROJECT DESCRIPTION AND RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This 53,000 square foot facility will accommodate police, jail and courts.
(PROJECT SCHEDULE:
JUSTIFICATION:
Current facility space is grossly inadequate for these areas.
E�
PROJECT TITLE: POLICE & MUNICIPAL COURTS
PROJECT #: PD9901
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Bond Issuance Cost $761000
Direct Operating Cost Construction 91071,257
Personnel: Full Time $128,000 Contingency 127,575
Part Time Demolition 606,709
Architectural/ Surveying/ Geotech 826,439
Other Professional Services 36,310
Utilities 106,000 Equipment 67,912
Furnishings 350,000
Land Purchase 43,592
Planning Services 70,428
Subtotal: $234,000 Owner Equipment 441,344
Total Estimated Capital Cost $11,717,566
Maintenance Costs
HVAC Maintenance 18,084 FUNDING SOURCE:
Maintenance 24,850 Transfers from:
Janitorial Services & Supplies 37,500 General Fund $394,890
Elect. Supplies 81000 W/S Operating Fund 175,000
Pest Control 11500 CCPD Operating Fund 21160,000
Subtotal: $89,934 DEA Funds 450,000
Bond Proceeds 81600,000
Other Interest Income 576,479
Average Annual Debt Service $750,815 Less Interproject Transfer to.
Building D FMO101 (638,803)
Total Estimated Annual Cost $1,074,749 Total Funding $11,717,566
CURRENT STATUS
'OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %EXPENDED
Bond Issuance Cost 76,000 76,000 0 100%
Construction 91071,257 91071,267 0 100%
Contingency plus interest earnings 127,605 61,264 66,341 48%
Demolition 606,709 606,709 0 100%
Architectural Services 745,369 745,369 0 100%
Surveying Services 61070 61071 (1) 100%
Geo-Technical Services 75,000 72,511 21489 97%
Other Professional Services 36,310 36,310 0 100%
Equipment 67,912 67,912 0 100%
Furnishings 350,000 348,347 11653 100%
Land Purchase 43,592 43,591 1 100%
Off -Site Utilities 0 0 0 0%
Owner Equipment 441,344 403,791 37,553 91%
Planning Services 70,428 70,428 0 100%
�* -This project transferred $638,803 to FM0101.
TOTAL PROJECT
11,717,596 $11,609,560
08,036
99%
E:k3
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES
Submitted By: RAY MCDONALD
Project Title: PARK AMENITIES UPGRADE
Date Prepared:
Date Completed.
Project Type: FIXTURES Sub
-Type: IMPROVEMENTS
Project No.: PR0601 Priority: A
March 23, 2004
COUNCIL AUTHORIZATION:
December 13, 2006. Approved purchase of playground equipment for Villages of Bear Creek Park from
Miracle Recreation Equipment Company for estimated expenditure of $67,000,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Master Plan recommends funding for system -wide park facilities and amenities upgrades.
PROJECT DESCRIPTION:
This project addresses the upgrade of all city parks to modernize amenities from water fountains to play
components to picnic stations and pavilions. The project provides funding for the replacement of aged
playground units that are approaching 10-15 years old; these units will include, but not be limited to,
components in AJ Carr Park, Midway Park, Villages of Bear Creek Park, Trailwood Park, and McCormick
Park. Additionally, this project will provide contingency funding for minor improvements at all parks with
respect to playground surfaces, structures, and minor landscaping features.
PROJECT SCHEDULE:
Projects will be identified and completed on an as needed basis.
JUSTIFICATION: --
Pursuant to the recommendations in the Parks Master Plan, parks should be brought into accessibility a
Americans with Disabilities Act compliance. The existing equipment in many park areas is becoming ag
and outdated and will require refurbishment or replacement in the near term.
PR"Jrot T TIT( F PARK AMFNITIFS UPGRADE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
'Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
otal Estimated Annual Cost
PHASE/FUNDING SOURCE
Park Furnishings
Landscaping
Contingencies
TOTAL PROJECT
E�
PROJECT #: PR0601
AL ESTIMATED CAPITAL COST:
Park Furnishings
Landscaping
Contingencies
Total Estimated Capital Cost
$0 FUNDING SOURCE:
Transfer from:
EDC Operating Fund
m
$0 Total Funding
CURRENT STATUS
BUDGET
$110,070
$28,476
$11,454
150
EXPENDED
$110,070
$28,476
$6,770
145,316
OVER/UNDER
$0
$0
$4,684
$110,070
28,476
11,454
150,000
$150,000�
$150,000
EXPENDED
100%
100%
59%
97%
m
Department:
Submitted By:
Project Title:
City of Euless
Capital Project Request
COMMUNITY SERVICES
RAY MCDONALD
MISC PARK STRUCTURE IMPROVEMENTS
Project Type: FIXTURES
Project No.: PR0720
COUNCIL AUTHORIZATION:
Date Prepared
Date Completed:
Sub -Type: IMPROVEMENTS
I1
March 23, 2004
adopted Master Plan recommends funding for system -wide park facilities and amenities upgrades
PROJECT DESCRIPTION:
This project continues the upgrade of all city parks to modernize amenitie
components to picnic stations and pavilions. This project provides funding
structures to include pavilions, picnic tables, gazebos, signage, safety
amenities including the addition of a gazebo on Main Street,
PROJECT SCHEDULE:
Begin upgrade: March 2007
Anticipate project completion: Winter 2009
s from
for
water fountains to pl:
the replacement of agf
components, and other pa
JUSTIFICATION:
Pursuant to the recommendations in the Parks Master Plan, parks should be brought into accessibility and
Americans with Disabilities Act compliance. The existing equipment in many park areas is becoming aged
and outdated and will require refurbishment or replacement in the near term.
PROJECT TITLE: MISC PARK STRUCTURES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Subtotal:
(Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Landscaping
Park Furnishings
Contingencies
TOTAL PROJECT
E�
PROJECT IT: PR0720
TOTAL ESTIMATED CAPITAL COST:
Fixtures
Contingencies
Landscaping
I Estimated
$0 FUNDING SOURCE:
Transfer from:
EDC Operating Fund
$0 Total Funding
CURRENT STATUS
BUDGET
$24,870
$166,792
$33,338
EXPENDED
$24,870
$73,067
$33,338
131,275
I Cost
OVER/UNDER
$0
$93,725
$0
725
$166,792
$331338
$241870
5
225,000
$225,000
EXPENDED(
100%
m
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: October 1, 2007
Submitted By: RAY MCDONALD Date Completed:
Project Title: PARK IRRIGATION
Project Type: LANDSCAPING Sub -Type: IMPROVEMENTS
Project No.: PR0804 Prioritv: A
(COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides annual funding to continue the City's efforts to meet gation needs throughout
City's park system.
PROJECT SCHEDULE:
Projects will be identified and completed on an as needed basis.
JUSTIFICATION:
This will allow for expansion of the irrigation systems throughout parks to enhance the overall cond
of the landscape and green space.
PROJECT TITLE: PARK IRRIGATION
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Subtotal:
Total Estimated Annual Cost
',PHASE/FUNDING SOURCE
Irrigation
TOTAL PROJECT
E�
PROJECT #: PR0804
TOTAL ESTIMATED CAPITAL COST:
(Annual Transfer -Operating Funds $25,000)
Irrigation
Total Estimated
$0 FUNDING SOURCE:
Transfer from:
EDC Operating Fund
$0 Total Funding
CURRENT STATUS
BUDGET EXPENDED
$50,000 $770
Cost
OVER/UNDER
BUDGET (-+)
$49,230
$50,000
000
$50,000
EXPENDED
2%
Department:
Submitted By:
City of Euless
Capital Project Request
COMMUNITY SERVICES
RAY MCDONALD
Date Prepared:
Date Completed.
Project Title: TRAIL ENHANCEMENTS -BOB EDEN PARK
Project Type, TRAIL Sub -Type: IMPROVEMENT
Project No.: PRO901 Prioritv: A
April 29, 2008
COUNCIL AUTHORIZATION:
June 9, 2009: Award contract to Ratliff Hardscape, Ltd. for the construction of concrete trail in the amoun
of $92,664,48,
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project will connect the trail of Bob Eden Park with the trail that was recently constructed in the
Creekwood Addition north of Mid Cities Boulevard. This particular connection was originally identified in the
update to the Trails Master Plan in 2001 and is part of an overall trail expansion project that was identified
as a high priority in the adopted Parks Master Plan,
PROJECT DESCRIPTION:
This project includes approximately 1525 linear feet of 4" x 10' concrete trail to connect the existing trail
in Bob Eden Park to the recently constructed trail in the Creekwood Addition. Also included is a
retaining wall under the Mid Cities bridge, hand rails, and rip rap for bank stabilization. This connection
provides safer access to five parks: Trailwood Park, Bob Eden Park, McCormick Park, The Preserve at
McCormick Park, and Villages of Bear Creek Park. The ultimate goal is to connect the City of Euless trail
system to the trail system in the City of Colleyville at Heritage Road.
:CT SCHEDULE:
construction contract: June 2009
ste construction complete: September 2009
JUSTIFICATION:
This trail connection opportunity will be consistent
identified in the adopted Parks Master Plan. The
comprehensive trail enhancement project,
master
with the identified need for further trail expansions as
plan recommendation will be part of a city-wide
PROJECT TITLE: TRAIL ENHANCEMENTS -BOB EDEN PARK
PROJECT #: PR0901
NET EFFECTS ON OPERATING AND (TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost 1525 LF 4" x 10' concrete trail
Personnel: Full Time Retaining wall section
Part Time Rip rap and hand rails
Total Salary $0 Contingency
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from:
EDC CIP Fund Balance
Subtotal: $0
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Hike and Bike Trail
Contingency
TOTAL PROJECT
$0 Total Funding
CURRENT STATUS
BUDGET
$120,000
$15,000
35,000
EXPENDED
$0
$0
OVER/UNDER
$120, 000
$15,000
135,000
$110,000
5,000
5,000
15,000
135
135,000
$135,000
EXPENDED
0%
91
Department:
Submitted By
City of Euless
Capital Project Request
COMMUNITY SERVICES
RAY MCDONALD
Date Prepared:
Date Completed,
Project Title: SENIOR CITIZEN CENTER AT MIDWAY PARK
Project Type: BUILDINGS Sub -Type: CONSTRUCTION
Project No., PR0902 Priority: A
February 11, 2009
COUNCIL AUTHORIZATION:
February 26, 2008: Approved as part of the 34th year Community Development Block Grant.
February 24, 2009: Approved as the 35th year Community Development Block Grant
The City of Euless has identified, as part of the city's five year master plan, the need for a new senior citizen
center facility. Construction of a new senior citizen center facility will allow the City to serve the growing
elderly population by expanding services and programs for senior citizens.
The project encompasses the construction of a new 20,000 square foot senior citizen center to include
approximately 51000 square feet of multi -use space at Midway Recreation Center. The facy includes
several programmable classroom spaces, a fitness component, staff offices, restrooms, kitchen with serving
area, game room, lobby, and other areas for accommodating senior activities.
The City of Euless has for many years recognized the importance of planning for parks, recreation, and
open space based on the needs as expressed by the citizens. In the plan development process for the
recent update to the Parks Master Plan and as part of the City's five year master plan, a scientific survey
of park, recreation, and open space needs was conducted from a sample of randomly selected citizens of
Euless. From this valuable information, a list of priorities was identified. A new senior center was
identified as a primary need of the citizens. A new senior center with state-of-the-art support facilities and
programmable space for an ever growing senior population will allow the City to serve its elderly population by
expanding services and programs for them.
92
PROJECT TITLE: SENIOR CITIZEN CENTER AT MIDWAY PARK PROJECT #: PRO902
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost *Engineering/Architectural/Testing
Personnel: Full Time Construction
Part Time Contingency 10%
Total Salary $0 Furnishings/Equipment
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
(Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from Car Rental
Mineral/Gas Lease Bonus
*34th year CDBG-FY2009
*35th year CDBG-FY2010
Less Inter -Project Transfer to:
Subtotal: $0 Midway Park FLC - Phase I
Total Estimated Annual Cost $0 Total Funding
CURRENT STATUS
OVER/UNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +)
Engineering $500,000 $0 $500,000
(Construction $3,630,685 $0 $3,630,685
Contingency $363,068 $0 $363,068
Furnishings/Equipment $363,068 $0 $363,068
TOTAL PROJECT $4,856,821 $0 $4,856,821
$500,000
$3,630,685
$363,068
$363,068
821
$1,750,000
$3,332,95.9
$186,224
$313,776
($726,138
$4,856,821
EXPENDED
0%
0%
0%
0%
0%
Department:
Submitted By:
Project Title:
Project Type,
Proiect No.,
City of Euless
Capital Project Request
COMMUNITY SERVICES
RAY MCDONALD
MIDWAY PARK FAMILY LIFE CENTER PHASE I
Date Prepared:
Date Completed:
February 11, 2009
BUILDINGS Sub -Type: CONSTRUCTION/EXPANSION
PR0907 Priority: A
COUNCIL AUTHORIZATION:
October 14, 2008: Authorized the city manager to negotiate and execute a contract with Kimley-Horn
Associates, Inc for a feasibility study.
The City of Euless has identified, as part of the city's five year master plan, the need to expand and
renovate the existing park and recreation facilities for both indoor and outdoor activities. Standards were
customized for the City of Euless based on citizen demand, compared with the existing public facility
inventories coupled with population projections through 2017 to determine needs over the next ten years.
Renovating and expanding the current recreation center received favorable consideration among the
residents that responded to the survev.
This vproject� addresses, some of the immediate needs identified in the citizen survey by creating
additional programmable spaces for youth and adult classes, expanding or constructing a new fitness
center and aerobics area, creating additional space for pre-school aged children, dedicating space for
programming activities for teens, and general upgrades to the facility. Staff proposes connecting the
recreation center to the senior center to allow for shared, programmable space as well as resources.
The City of Euless has for many years recognized the importance of planning for parks, recreation, and
open space based on the needs as expressed by the citizens. The Midway Recreation Center is
established as the City's only recreational community center. The role of the facility has grown since it
opened and is now reaching maximum capacity for many of the programs and services currently offered.
Attendance numbers at the Midway Recreation Center continue to rise and with a growing population, the
ability to serve the needs of the citizens becomes more of a challenge with limited space and resources.
PROJECT TITLE: MIDWAY PARK FAMILY LIFE CENTER PHASE I PROJECT #: PRO907
NET EFFECTS ON OPERATING AND (TOTAL ESTIMATED CAPITAL COST
MAINTENANCE COST (+ OR -) ANNUAL,
Direct Operating Cost Construction
Personnel: Full Time Contingency
Part Time Furnishings/Equipment
Total Salary $0 Architectural Fees/Engineering
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
Subtotal: $0 FUNDING SOURCE:
Transfers from General CIP Fund:
Maintenance Costs FB9909 - Fund Balance
FM0802 Senior Citizen Design (GF)
FM0803 Rec Cntr Improvement (GF)
PRO902 Senior Citizens Center (CR)
ADDITIONAL FUNDING NEEDED;
Subtotal: $0
Car Rental FY 2010
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Architectural/Engineering
Construction
Contingency
Furnishings/Equipment
TOTAL PROJECT
$0 Total Funding
CURRENT STATUS
BUDGET
$155,000
$925,000
$100,000
$150,000
$1,330,000
EXPENDED
$66,644
$0
$0
$0
OVER/UNDER
$88,356
$925,000
$100,000
$150,000
263,356
$1,700,000
$100,000
$150,000
$155,000
105,000
$136,338
$2501000
$2171524
$7261138
775,000
$2,105,000
EXPENDED
43%
0%
0%
0%
5%
T H E„ �.��j = C 1 T Y O F
;; .
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED &UNFUNDED PROJECTS -SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental Tax
Other
EDC
To Be
Determined
DRAINAGE PROJECTS
Huninne Creek 8 Bridge at Marlene Drive ROWj10j
A
$ 300,000
$ 200,000
$ 100,000
Boyd Branch Improvements '
A
$ 10,000,000
XX
XX
XX
Sut~Total Drainage PrionryA-Proposed FY'10
$ 10,300,000
Hurticane Creek & Bridge at Marlene Drive Conswction
B
$ 3,420,000
XX
Hollow Oak Channel Erosion
B
TBD
XX
Sub -Total Dreina a Priori B-Unfunded
$ 3,420,000
Marlene Drive Culvert Replacement
C
TBD
XX
Flooding Mi5 ation
C
TBD
XX
Kynet[e Drive Culvert Modfications
C
TBD
XX
Bell Hi Addition
C
TBD
XX
Blessi Branch
-Main Street to SH 360
C
TBD
XX
Little Bear Creek -Land A uisition
C
TBD
XX
Little
Bear Creek-Im
rovements
C
TBD
XX
Simmons Culvert Improvements
C
TBD
XX
Sub-TotalOraina a Prio " C-Unfunded
5
DRAINAGE PROJECTS -TOTAL
$ 13,7zo,000
STREET PROJECTS
Baze Road Design/ROW
A
$ 290,000
$125,062
$164,938
Wilshire
Drive/Marlene
Drive Overlay
A
$ 268,000
XX
Ash Lane Design/ROW
A
$ 330,000
$ 330,000
Sub -Total Street PriorrtyA-Pro ed FY10
$ 906,000
Baze Road -Glade Road to Mid Cities Blvd. Constructions"�
B
$ 1,590,000
XX
Ash Lane -Aransas Driveto NMain Street<"�
B
$ 1,920,000
$307,000
$665,000
$728,000
Vine S1reetSH183 to SH10
B
$ 580,000
$66,OD0
$514,000
Traffic Signal -Harwood Road at Bear Creek Parkway
B
$ 170,000
XX
CullumDmre/AlexanderLane
B
$ 1,350,000
$61,000
$1,269,000
Sub -Total Street Prio " B-Unfunded
$ 5,610,000
Bear Creek Pa
C
TBD
XX
Ross Avenue
C
TBD
XX
Cresthaven Drive
C
TBD
XX
Hi hland Drive
C
TBD
XX
South Pipeline Road
C
TBD
XX
Fuller -Wiser Road-SH183 To Harwood Road
C
TBD
XX
Fuller -Wiser Road -Harwood Road to Mid Cites Boulevard
C
TBD
XX
Sub-Totaf Street Prio " C-UrAunded
$
STREET PROJECTS -TOTAL
$ 6,518,000
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
CIP Fund
Bond Sale
Grants/
Impact
Escrow
Car Rental Tax
Other
To Be
Fund
Balance
Contrib
Fees
Funds
EDC
Determined
WASTEWATER PROJECTS
Line Replacement, W Alexander Ln/Norman Dr/Franklin Dr
A
$ 510,000
XX
SulrTotal Wastewater Priority A -Proposed FY10
$ 510,000
Line Replacement, Arnett Drive(")
B
$ 351,000
XX
Line Replacement, Pauline Street 36th
B
$ 405,000
XX
Line Replacement, Alexander/Ascot Outfall
B
$ 2429000
XX
Line Replacement, Whitener/Ascot Outfall'
B
$ 176,000
XX
Line Replacement, Collin Drive
B
$ 405,000
XX
Line Replacement, Blanco/Aransas/Crane
B
$ 327,000
XX
Line Replacement, Slaughter Lane/E Huitt Lane
B
$ 475,000
XX
Line Replacement, Ross Avenue
B
$ 150,000
XX
Line Replacement, Oakwood Terrace Phase I
B
$ 3459000
XX
Line Replacement,
Oakwood Terrace Phase Il
B
$ 635,000
XX
SulrTotal Wastewater Prioriy B-Unfunded
$ 375119000
SH 183 Utility Relocation
C
TBD
XX
Line Replacement N Midway Park
C
TBD
Line Replacement, S Main Street
C
TBD
XX
Line Replacement Aransas Drive
C
TBD
XX
Line Replacement Glenn Drive/Crane Drive
C
TBD
XX
Line Replacement, Boyd Branch
C
I TBD
XX
Line Replacement Cedar Hills Estates/Hollywood Blvd,
C
TBD
XX
Line Replacement, Cedar Hills EstateslSunset Drive
C
TBD
XX
Line Replacement, Eastcliff/Wndlea/Si net
C
TBD
XX
Line Replacement, Huntin ton/Koen/Atkerson
C
TBD
XX
Line Replacement, Ector Drive/Favette Drive
C
TBD
XX
Line Replacement, Donle /Shelmar Drive
C
TBD
XX
Line Replacement Denton Drive
C
TBD
XX
Line Replacement, Collin Drive/Harris Drive/Irion Drive
C
TBD
XX
Line Replacement, Ector Drive/DonleyDrive/Crane Drive
C
TBD
XX
Line Replacement Evans/Ganyon Rid e/N K nette
C
TBD
XX
Line Replacement JanannBrownstone/Shelmar Drive
C
TBD
XX
Line Replacement K ette�lshire/Sierra
C
TBD
XX
Line Replacement Lakewood/Do od Circle
C
TBD
XX
Line Replacement, Ma /Mariene/Commerce
C
TBD
XX
Line Replacement, NW Midway/Rusk/Parker
C
TBD
XX
Line Replacement, Northcliff/Toplea/Winlea
C
TBD
XX
Line Replacement, Sagebrush-TopleaMlilshire
C
TBD
XX
Line Replacement, W MidwaylUctoria/Delta
C
TBD
XX
Line Replacement, W Donley/Private Drive/Mimosa
C
TBD
XX
XX
Su&Total Wastewater Priority GUnfunded
$
WASTEWATER PROJECTS - TOTAL
$ 4,021,000
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED 8 UNFUNDED PROJECTS -SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants!
Contrib
Impact
Fees
Escrow
Funds
Car Rental Tax
Other
EDC
To Be
Determined
WATER PROJECTS
A
N/A
Sub -Total Water Prio ' A -Pro osed FY10
$
Line Replacement, Live Oak CULive Oak DrlMarlene Drive"'�
B
$ 320,000
XX
Line Replacement, S Pipeline Road West
B
$ 260,000
XX
Water 8 Wastewater Impact Fee Update
B
$ 30,000
XX
Line Replacement, S Pipeline Road East
B
$ 240,000
XX
Water System Severity Camera Installation �
B
$ 75,000
XX
Sub -Total Water Priority B-Unfunded
$ 925,000
Line Replacement, Westwood Drive
C
TBD
�
Line Replacement, Collin/Dallas Drive/Harwood Road
C
TBD
�
Line Replacement, Collin/Denton Drive/Dallas Drive
C
TBD
XX
Line Replacement, Fuller Drive
C
TBD
�
Line Replacement, Springwood Court
C
TBD
XX
Hwy 183 Water Crossing
C
TBD
XX
Hwy 360 Water Crossing
C
TBD
XX
Line Replacement, K nette Drive
C
TBD
XX
Line Replacement, Midueek/Rock Creek/Stony Creek
C
TBD
XX
Line Replacement, Blessing Creek and L"rt[le Creek
C
TBD
XX
Line Replacement, EastGitl Drive
C
TBD
�
Line Replacement, Ector Drive
C
TBD
XX
Line Re lacement, Hollow Oak Drive
C
TBD
�
Line Re lacement. Midw Drive East
C
TBD
XX
Line Re lacement, Mid Drive West
C
TBD
XX
Line Re lacement, Dick Drive South
C
TBD
�
Line Re lacement, Dick
Drive North
C
TBD
XX
Line Re lacement, Paula Lane
C
TBD
XX
Line Re lacement. Denton Drive
C
TBD
XX
Line Replacement, S Main Street (North)
C
TBD
�
Line Replacement, S Main Street (South)
C
TBD
�
Line Replacement, Sunset Drive
Line Replacement, Wildwood Street
C
C
TBD
TBD
XX
�
Line Replacement, Woodvine
(East)
C
TBD
�
Line Replacement, Woodvine (West)
Line Replacement, Shady Creek and ClifTwood
Line Replacement, Dunaway Drive
Line Replacement, E Huitt Lane
Line Replacement, Needles Street
Water System Securi Land Acquisition
C
C
C
C
C
C
TBD
.TBD
TBD
TBD
TBD
TBD
XX
XX
XX
�
�
XX
SulrTotal Water Priority C-Unfunded
$
WATER PROJECTS -TOTAL
$ 925,000
O
O
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
CIP Fund
Bond Sale
Grants/
Impact
Escrow
Car Rental Tax
Other
EDC
To Be
Fund
Balance
Contrib
Fees
Funds
Determined
OTHER PROJECTS
Texas Star Sports Complex Lighting Improvements
A
$ 600*000
XX
Glade Parks Trail Connection
A
1 $ 21000,000
XX
Sub -Total Other PriorityA-ProposedFY10
$ 2,600,000
Park Amenities Upgrade
B
$ 150,000
XX
Trail Lighting -Phase 1
B
$ 50,000
XX
Midway Park FLC Phase-ll Design Outdoor Aquatics '
B
$ 468,453
XX
Midway Park FLC Phase -III Design Indoor Aquatics
B
$ 317,500
XX
Midway Park FLC Phase4l Outdoor Aquatics Construction
B
$ 5,1999836
XX
$500,000
Midway Park FLC Phase -III Indoor Aquatics Construction"
B
$ 314929500
$750,000
XX
Fire Training Facility and Tower
B
$ 1,793,000
XX
Animal Shelter
B
$ 6929900
XX
Development/Engineering Building
B
$ 111591100
XX
Blessing Branch Park Improvements77
B
$ 275,040
XX
Texas Star Sports Complex Parking Lot Improvements
B
$ 999550
XX
South Euless Water Feature B
TBD
XX
Wilshire Park Water Feature B
TBD
XX
Sub -Total Other Priority 8-Unfunded
$ 130697,879
Texas Star Sports Complex Improvements
C
TBD
XX
Trail Connection - S Euless
C
TBD
XX
Texas Star Sports ComplexSoftball World Turf
C
TBD
XX
Trail Lighting -Phase II
C
TBD
XX
Texas Star Sports Complex -PATS, Phase IV C
TBD
XX
Trail Enhancements -Villages Bear Creek C
TBD
XX
Trail Enhancements -Phase I C
TBD
XX
Trail Enhancements -Phase II C
TBD
XX
Trailwood Park Improvements C
TBD
XX
Community Center for South Euless C
TBD
XX
Emergency Call Boxes C
TBD
I XX
Kiddie Carr Park Improvements C
TBD
XX
Sub -Total Other Prior' C-Unfunded
$
OTHER PROJECTS - TOTAL
$ 161297,879
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated
Operating
CIP Fund
Bond Sale
Grantsi
Impact
Escrow
Car Rental
Other
EDC
To Be
Cost
Fund
Balance
Contrib
Fees
Funds
Tax
Determined
DRAINAGE PROJECTS
Hurricane Creek & Bridge at Marlene Drive ROW0)
A
$ 3001000
$ 200,000
$100,000
Boyd Branch Improvements A
$ 10,000,000
XX XX XX
Sub -Total Drainage PriorityA-Proposed FY'10
$ 10,3009000
Hurricane Creek & Bridge at Marlene Drive Constwctio B
$ 31420,000
XX
Hollow Oak Channel ErosionErosion7zT
B
TBD
XX
Sub -Total Drainage Priority B-Unfunded
1 $ 33420,000
Marlene Drive Culvert Replacement C
TBD
XX
Flooding Mitigation
C
TBD
XX
Kynette Drive Culvert Modifications
C
TBD
XX
Bell Hi Addition
C
TBD
XX
Blessing Branch -Main Street to SH 360
C
TBD
XX
Little Bear Creek -Land Acquisition
C
TBD
XX
Little Bear Creek -Improvements C
TBD
XX
Simmons Culvert Improvements C
TBD
XX
Sub -Total Drainage Priority C-Unfunded
$
DRAINAGE PROJECTS - TOTAL
$ 13,7209000
City of Euless
Capital Project Request
Department: DRAINAGE Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: HURRICANE CREEK & BRIDGE AT MARLENE DRIVE ROW ACQUISTION
Project Type: DRAINAGE Sub -Type: ROW ACQUISITION
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 1996, the City received the storm drainage master plan for Hurricane Creek.
PROJECT DESCRIPTION:
This project consists of the property, right-of-way or other acquisition for drainage improvements on Hurricane
Creek, north and south of the bridge at Marlene.
PROJECT SCHEDULE:
Anticipate Begin: FY2010
Anticipate Complete: Summer 2011
JUSTIFICATION:
The culvert and concrete channel may require rebuilding to prevent structural flooding of a number of homes in
a 100 year flood event. Easements may be at the back door of east -side properties and properties on cukde-
sac. The City may also need ROW from west side properties. Two homes on Canyon Ridge will remain in the
flood plain. Acquisitions may be an alternative consideration.
102
PROJECT TITLE: HURRICANE CREEK & BRIDGE AT MARLENE DRIVE ROW ACQUISTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Right of Way/Acquisition $300I
E�
m
$0I Total Estimated Capital Cost $300,000
CURRENT STATUS:
Operating Fund � Conceptual Design % 0%
Fund Balance XX Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
103
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 17,2009
Submitted By: RON YOUNG Date Completed:
Project Title: BOYD BRANCH IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Drainage improvements are included in the Boyd Branch Watershed Study.
PROJECT DESCRIPTION:
This project includes the portion of Boyd Branch from S Pipeline Road to SH183 and may include structural and
non-structural activities to reduce or minimize the effects of large stormwater events. A large portion of this
project occurs on a section of Boyd Branch that lies in a platted private drainage easement which also shows
the maintenance responsibility to rest on the property owner(s). Since the City of Euless has no easement
rights along these sections of Boyd Branch, the city is of the opinion that improving the capacity of Boyd Branch
to handle large stormwater events is the responsibility of the property owner(s). The City of Euless may have
some utility relocation expenses related to any improvements made to Boyd Branch,
PROJECT SCHEDULE:
FY2010
JUSTIFICATION:
Large stormwater events result in runoff exceeding the capacity of Boyd Branch. This project is intended to
reduce or minimize property losses associated with stormwater runoff exceeding the capacity of Boyd Branch.
104
PROJECT TITLE: BOYD BRANCH IMPROVEMENTS
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Full Time
Part Time
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds XX
Escrow Funds
Other XX
Car Rental Tax Fund XX
To Be Determined
TOTAL ESTIMATED CAPITAL COST:
Property Owners) Contribution
to Construction
City of Euless Construction (Max.)
(See Comments)
Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design
Preliminary Design %
Final Plans %
Specifications
Construction io
$6,000,000
$4,000,000
$10,000,000 �
ADDITIONAL COMMENTS:
It is estimated that the City of Euless related construction items will be limited to $4,000,000 or less depending
on the scope of work defined.
105
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed,
Project Title: HURRICANE CREEK & BRIDGE AT MARLENE DRIVE CONSTRUCTION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 1996, the City received the storm drainage master plan for Hurricane Creek,
PROJECT DESCRIPTION:
This project consists of the construction of a bridge at Marlene Drive and for the improved concrete channel
lining that will extend approximately to the confluence of Cyclone Branch and channel improvements south of
SH10.
PROJECT SCHEDULE:
Anticipate Begin: FY2012
Anticipate Complete: 4th Quarter 2013
JUSTIFICATION:
The culvert and concrete channel will be rebuilt to prevent structural flooding of a number of homes in a 100-
year flood event. These improvements will also help prevent erosion.
PROJECT TITLE: HURRICANE CREEK & BRIDGE AT MARLENE DRIVE CONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Construction $3,400,000
Project Oversight $201000
m
m
E�
$0I Total Estimated Capital Cost $3,420,OOO
CURRENT STATUS:
0
Conceptual Design % 0 °
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
107
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 03,2008
Submitted By: RON YOUNG Date Completed:
Project Title: HOLLOW OAK CHANNEL EROSION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In May 2008 the City authorized a drainage study for the creek area that runs at the rear of the lots fronting on
Hollow Oak Drive and Linkwood Drive. The completed drainage study was received in July 2008.
PROJECT DESCRIPTION:
The creek area along the rear of the lots on Hollow Oak Drive and Linkwood Drive exists in a natural state. The
creek bank along the south has experienced some slope failures. The drainage study recommended installation
of "bag wall" slope protection.
PROJECT SCHEDULE:
JUSTIFICATION:
The City has received complaints that fences and other improvements on private property will be threatened if
additional slope failures take place. Currently no residences are threatened.
PROJECT TITLE: HOLLOW OAK CHANNEL EROSION
NET EFFECTS ON OPERATING AND
INTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering -To Be Determined
Construction -To Be Determined
E�
m
$0 � Total Estimated Capital Cost
CURRENT STATUS:
0
Conceptual Design % 0 0
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
ADDITIONAL COMMENTS:
The most recent cost for this project is approximately $347,113. If this project moves forward, an updated
opinion of probable cost will need to be prepared.
Due to the expected impact to the native conditions, this project would require broad support from all impacted
neighbors. Alternatives, such as possible assistance with removal or relocation of improvements on affected
properties, should also be considered.
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2008
Submitted By: RON YOUNG Date Completed:
Project Title: MARLENE DRIVE CULVERT REPLACEMENT
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Marlene Drive is noted as a collector street on the City's Master Thoroughfare Plan,
PROJECT DESCRIPTION:
The scope of the project includes construction of a new culvert at Cyclone Branch to meet current
load and
drainage capacity standards. A portion of the concrete channel will also need to be reconstructed
both
upstream and downstream to ensure a smooth transition.
PROJECT SCHEDULE:
JUSTIFICATION:
The existing culvert is load limited. The new culvert will be designed to convey sufficient drainage
to comply
with current standards.
110
PROJECT TITLE: MARLENE DRIVE CULVERT REPLACEMENT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering -To Be Determined
ConstructionJo Be Determined
m
$0I Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 00 0
Construction % 0%
111
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 03,2008
Submitted By: RON YOUNG Date Completed:
Project Title: FLOODING MITIGATION
Project Type: DRAINAGE Sub -Type:
Project Code, Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project consists of identifying chronic flooding locations within the City of Euless and determining the
cost/benefit of property acquisition compared to extensive drainage relief projects. Property acquisition will be
recommended after consideration of flooding history, appraisals and feasible alternative drainage solutions have
been evaluated. It is recommended that this be established as an ongoing project.
PROJECT SCHEDULE:
JUSTIFICATION:
Buildings throughout the City of Euless situated adjacent to creeks have experienced drainage problems for
several years. The cost for implementing drainage improvement projects to mitigate flooding at isolated
locations may be much greater than property acquisition. Chronic flooding lowers the property values and this
program will offer a means of relief for affected property owners.
112
PROJECT TITLE: FLOODING MITIGATION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Flooding Mitigation -To Be Determined
m
E�
$0 � Total Estimated Capital Cost
CURRENT STATUS:
0
Conceptual Design % 0 °
Preliminary Design % 0%
Final Plans % 0%
Specifications % 00 °
Construction % 00 0
113
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,1999
Submitted By: RON YOUNG Date Completed:
Project Title: KYNETTE DRIVE CULVERT MODIFICATIONS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
Wilshire Village Addition was constructed prior to the adoption of the City's Uniform Development Code ("UDC").
The requirements prior to the UDC were lower than what the City now requires. The current construction
configuration of Wilshire Village causes more water to remain above ground than is acceptable under current
standards. The drainage system in the Wilshire Village Addition needs to be upgraded to meet current
requirements.
PROJECT DESCRIPTION:
The project involves the installation of a small drainage system on Kynette Drive up to Sierra Drive. It is Project
No. 16 in the 1990 Knowlton, English, Flowers study.
PROJECT SCHEDULE:
JUSTIFICATION:
Surface water flow within Kynette Drive exceeds the City's current development standards. A large amount of
storm water drains to an existing culvert on Kynette Drive between East Cliff and West Cliff Drives. The existing
drainage facilities collecting this storm water are inadequate according to current standards.
114
PROJECT TITLE: KYNETTE DRIVE CULVERT MODIFICATIONS
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
',Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering -To Be Determined
ConstructionJo Be Determined
E�
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design
Preliminary Design %
Final Plans %
Specifications
Construction
115
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: BELL HI ADDITION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005 the City commissioned and received a drainage plan from Freese and Nichols, Inc. In this plan, the Bell
Hi Addition was identified as an area in need of flood relief.
PROJECT DESCRIPTION,
The proposed project ties into an existing storm drainage system on Needles Street. A substantial portion of the
cost of this project is related to street repair, indicating the need to combine this project with a street
reconstruction project.
PROJECT SCHEDULE:
JUSTIFICATION:
The construction of this project will prevent the flooding of Paula Lane, David Drive, and Needles Street during
most intense rainfall events. The terrain in this location is very flat, which causes the streets to have a very low
capacity to remove storm water.
116
PROJECT TITLE: BELL HI ADDITION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time $0 Construction -To Be Determined
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
m
Subtotal: $0
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
117
Clty of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: BLESSING BRANCH -MAIN STREET TO SH360
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Blessing Branch Drainage Master Plan included a conceptual plan to convey storm water through the creek
more efficiently.
PROJECT DESCRIPTION:
This project involves the channeling and lining of Blessing Branch in accordance with the Blessing Branch
Master Plan.
PROJECT SCHEDULE:
JUSTIFICATION:
The City expects to receive significant developer contributions toward this project. However, the City may be
required to fund a portion of this project.
PROJECT TITLE: BLESSING BRANCH -MAIN STREET TO SH360
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering -To Be Determined
Construction -To Be Determined
$0 I Total Estimated Capital Cost
CURRENT STATUS:
0
Operating Fund Conceptual Design % 0 °
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
119
City of Euless
Capltal Project Request
Department: PUBLIC WORKS
Date Prepared: July 21,1999
Submitted By: RON YOUNG
Date Completed,
Project Title: LITTLE BEAR CREEK LAND
ACQUISITION
Project Type: DRAINAGE
Sub -Type: ACQUISITION
Project Code:
Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2007, the City received an erosion study for
Little Bear Creek from Halff Associates,
PROJECT DESCRIPTION:
Acquire property located adjacent to Little Bear
Creek at 2101 N. Main,
PROJECT SCHEDULE:
JUSTIFICATION:
Erosion of property is a possibility in the future.
Acquisition is anticipated to be a voluntary buy-out.
120
PROJECT TITLE: LITTLE BEAR CREEK LAND ACQUISITION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Engineering -To Be Determined
Construction -To Be Determined
E�
$0I Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
121
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,1999
Submitted By: RON YOUNG Date Completed:
Project Title: LITTLE BEAR CREEK DRAINAGE IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The improvements proposed for Bob Eden Park are identified in the Little Bear Creek Watershed Master Plan,
The Little Bear Creek Park portion of this project was identified in the 1990 Knowlton, English and Flowers
Drainage Utility System Study of Selected Improvement Projects,
PROJECT DESCRIPTION:
Both parts of this drainage project involve erosion control and channelization improvements to Little Bear Creek,
The Bear Creek Park part is a portion of Project No. 11 in the above -referenced study. This project will be re-
evaluated to determine if the scope and proposed improvements should be modified. This part of the project will
be redefined and re -estimated.
PROJECT SCHEDULE:
JUSTIFICATION:
Continued erosion will eventually undermine the creek in both parks and cause damage to existing City facilities.
122
PROJECT TITLE: LITTLE BEAR CREEK DRAINAGE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Engineering -To Be Determined
Construction -To Be Determined
m
$0 I Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
123
City of Euless
Capital Project Request
Department: SIMMONS CULVERT IMPROVEMENTS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: SIMMONS CULVERT IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005 the City commissioned and received a drainage plan from Freese and Nichols, Inc.
PROJECT DESCRIPTION:
An additional culvert will extend from the apartment complex on the east side of Simmons Drive and will outfall
into the creek area on the north side of Carr Park,
PROJECT SCHEDULE:
JUSTIFICATION:
In intense storms the capacity of the existing culvert is exceeded. Additional culverts will be required to convey
the design storm flows. The construction of this project will enable the safe use of Simmons Drive in intense
storm events.
124
PROJECT TITLE: SIMMONS CULVERT IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Cost -To Be Determined
E�
E�
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
125
126
CAPITAL IMPROVEMENT PROGRAMS
FYI PROPOSED & UNFUNDED PROJECTS - SORTED
BY TYPE
PROPOSED METHOD OF FINANCING
Operating
CIP Fund
Bond Sale
Grants/
Impact
Escrow
Car Rental
Other
EDC
To Be
Project Description
Priority
Estimated
Cost
Fund
Balance
Contrib
Fees
Funds
Tax
Determined
STREET PROJECTS
Baze Road De n/ROW
A
$
290,000
$1259062
$164,938
Wilshire DriveIMariene Drive Overlay
A
$
286,000
XX
Ash Lane Design/ROW
A
$
330,000
$ 330,000
Sub -Total Street Priority A -Proposed FY10
$
908,000
Baze Road -Glade Road to Mid Cities Blvd, Construction(")
B
$
11590,000
XX
Ash Lane -Aransas Drive to N Main Street""
B
$
11920,000
$3071000
$885,000
$728,000
Vine Street-SH183 to SH10
B
$
580,000
$66,000
$514,000
Traffic Signal -Harwood Road at Bear Creek Parkwa
B
$
170,000
XX
Cullum Drive/Alexander Lane
B
$
11350,000
$61,000
$1,289,000
Sub -Total Street Priority B-Unfunded
$
596109000
Bear Creek Parkway
C
TBD
XX
Ross Avenue
C
TBD
XX
Cresthaven Drive
C
TBD
XX
Hi hland Drive
C
TBD
XX
South Pi eline Road
C
TBD
XX
Fuller -Wiser Road-SH183 To Harwood Road
C
TBD
Fuller -Wiser Road -Harwood Road to Mid Cities Boulevard
C
TBD
Sub -Total Street Priority GUnfunded
$
STREET PROJECTS = TOTAL
$ 61518,000
tV
J
Department
Project Title:
PUBLIC WORKS
• RON YOUNG
City of Euless
Capital Project Request
Date Prepared:
Date Comolete
July 22,1999
BAZE ROAD -GLADE ROAD TO MID CITIES BLVD DESIGN &ROW ACQUISITION
Project Type: STREET
ect Code:
Sub -Type: DESIGN
Pri
RELATIONSHIP TO OTHER PROJECTS ANDIOR MASTER PLAN:
The reconstruction and expansion of Baze Road was identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION:
This project consists of the detailed engineering design and right-of-way acquisition for the construction of a
31' (back to back) concrete roadway to replace an existing deteriorating two-lane asphalt roadway. The project
will include underground drainage, sidewalks, and street lighting.
PROJECT SCHEDULE:
Anticipate Award Design: December 2009
Anticipate Plans Complete: August -September 2010
Anticipate right-of-way complete: November -December 2010
JUSTIFICATION:
Baze Road is an important north -south residential collector that is planned to connect Glade Road and Mid
Cities Boulevard. This roadway exists as a four -lane divided roadway north of Glade Road in Grapevine. In
Euless, it is constructed partially as a 40 foot undivided roadway and as a 36 foot (two lane) undivided roadway
from Mid -Cities Boulevard to Priest Lane. The portion of Baze Road from Priest Lane to Glade Road is the only
portion that is not constructed to City standards.
128
PROJECT TITLE: BAZE ROAD -GLADE ROAD TO MID CITIES BLVD DESIGN & ROW ACQUISITION
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
I Subtotal:
Full Time
Part Time
I Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
XX
Other
Supplemental Sales Tax
XX
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Engineering $200,000
Right of Way $90,000
Total Estimated Capital Cost $290,000
CURRENT STATUS:
Conceptual Design
Preliminary Design %
Final Plans %
Specifications
Construction
129
City of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: April 11,2008
Submitted B : RON YOUNG Date Completed:
Project Title: WILSHIRE DRIVE/MARLENE DRIVE -OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
Wilshire Drive and Marlene Drive are collector streets that the City of Euless plans to overlay in a cooperative
project with Tarrant County,
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping of:
1. Wilshire Drive from SH10 to SH183 and
2. Marlene Drive from Canyon Ridge Drive to SH10.
PROJECT SCHEDULE:
Anticipate Begin Construction: April 2010
Anticipate Construction Complete: June 2010
JUSTIFICATION:
The existing asphalt pavement is deteriorating and is becoming a maintenance problem. The asphalt overlay
will provide an improved riding surface, will extend the life of the roadway, and will enhance the appearance of
the street.
130
PROJECT TITLE: WILSHIRE DRIVE/MARLENE DRIVE -OVERLAY
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Material
$288,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$288,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
131
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 01,2002
Submitted By: RON YOUNG Date Completed,
Project Title: ASH LANE-ARANSAS DRIVE TO N MAIN STREET DESIGN & ROW ACQUISTION
Project Type: STREET Sub -Type: DESIGN
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Ash Lane is identified in the Master Thoroughfare Plan as a four -lane minor arterial roadway from Industrial
Boulevard to Fuller -Wiser Road.
PROJECT DESCRIPTION:
This project consists of the design and right-of-way acquisition necessary to facilitate removal of the existing two
lanes of asphalt pavement from Aransas Drive to N. Main Street which is to be replaced by a four lane concrete
roadway. The associated sidewalks and storm drainage are included in the project scope.
PROJECT SCHEDULE:
Anticipate Award Design: December 2009
Anticipate Plans Complete: August -September 2010
Anticipate Right -of -Way Complete: November=December 2010.
JUSTIFICATION:
The portion of Ash Lane from Aransas Drive to N. Main Street is the only portion that is not constructed to the
Master Thoroughfare Plan standards. Completion of this section of Ash Lane will provide an orderly flow of
traffic from Industrial Boulevard to Fuller -Wiser Road.
132
PROJECT TITLE: ASH LANE-ARANSAS DRIVE TO N MAIN STREET DESIGN & ROW ACQUISTION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$230,000
Personnel: Full Time
Right of Way
$100,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$330,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
XX
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
133
City of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: July 22,1999
Submitted By: RON YOUNG Date Completed,
Project Title: BAZE ROAD, GLADE ROAD TO MID CITIES BOULEVARD CONSTRUCTION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The reconstruction and expansion of Baze Road was identified in the 1999 Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the construction of a 31' (back-to-back) concrete roadway including underground
drainage, sidewalks, and street lighting. This project will replace the existing deteriorating two-lane asphalt
roadway.
PROJECT SCHEDULE:
Anticipate Begin Construction: February -March 2011
Anticipate Construction Complete: December 2011
JUSTIFICATION:
Baze Road is an important north -south residential collector that is planned to connect Glade Road and Mid
Cities Boulevard. This roadway exists as a four -lane divided roadway north of Glade Road in Grapevine. In
Euless, it is constructed partially as a 40 foot undivided roadway and as a 36 foot (two lane) undivided roadway
from Mid -Cities Boulevard to Priest Lane. The portion of Baze Road from Priest Lane to Glade Road is the only
portion that is not constructed to City standards.
134
PROJECT TITLE: BAZE ROAD, GLADE ROAD TO MID CITIES BOULEVARD CONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
Full Time
Part Time
m
TOTAL ESTIMATED CAPITAL COST:
Construction $1,590,000
Total Estimated Annual Cost $0 Total Estimated Capital Cost $1,590,000
� PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
135
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 01,2002
Submitted By: RON YOUNG Date Completed:
Project Title: ASH LAN&ARANSAS DRIVE TO N MAIN STREET CONSTRUCTION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Ash Lane is identified in the Master Thoroughfare Plan as a four -lane minor arterial roadway from Industrial
Boulevard to Fuller -Wiser Road.
PROJECT DESCRIPTION:
This project consists of the removal of the existing two lanes of asphalt pavement from Aransas Drive to N Main
Street to be replaced by a four lane concrete roadway. The associated sidewalks and storm drainage are
included in the project scope.
PROJECT SCHEDULE:
Anticipate Begin Construction: February -March 2011
Anticipate Construction Complete: February 2012
JUSTIFICATION,
The portion of Ash Lane from Aransas Drive to N Main Street is the only portion that is not constructed to the
Master Thoroughfare Plan standards. Completion of this section of Ash Lane will provide an orderly flow of
traffic from Industrial Boulevard to Fuller -Wiser Road.
136
PROJECT TITLE: ASH LANE-ARANSAS DRIVE TO N MAIN STREET CONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
E�
E�
TOTAL ESTIMATED CAPITAL COST:
Construction $1,920,000
(Total Estimated Annual Cost $0 Total Estimated Capital Cost $1,920,OOOI
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
307,000
885,000
728,000
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
137
City of Euless
Capital Project Request
Department: PUBLIC WORKS
Date Prepared: July 23,1999
Submitted By: RON YOUNG
Date Completed,
Project Title: VINE STREET-SH 183 TO SH10
Project Type: STREET Sub -Type:
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Vine Street is not identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION,
The projects consists of the reconstruction of Vine Street from SH 183
to SH 109
PROJECT SCHEDULE,
Anticipate Begin Construction: Summer 2012
Anticipate Complete Construction: Winter 2013
JUSTIFICATION:
The City has received street escrow funds from several developments
along Vine Street. When development is
complete, it would be appropriate for the City to reconstruct the existing roadway.
138
PROJECT TITLE: VINE STREET-SH 183 TO SH10
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST.
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$580,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$580,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS.
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Other
XX
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
Escrow Funds will also be used to finance
a portion of this project.
139
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: TRAFFIC SIGNAL-HARWOOD ROAD @ BEAR CREEK PARKWAY
Project Type: STREET Sub -Type: SIGNALIZATION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic signals are located at the intersections of arterial and collector thoroughfares identified in the City of
Euless Master Thoroughfare Plan adopted in 1999.
PROJECT DESCRIPTION:
The project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection, and signal controller for the intersection of Harwood Road and Bear
Creek Parkway,
PROJECT SCHEDULE:
Traffic signal warrant studies will be performed to determine the appropriate timing for construction.
JUSTIFICATION,
Traffic volumes at this intersection will be monitored and signal warrant studies will be performed to determine
the justification for signal installation. This intersection will ultimately require a traffic signal.
140
PROJECT TITLE: TRAFFIC SIGNAL-HARWOOD ROAD @ BEAR CREEK PARKWAY
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$20,000
Personnel: Full Time
Traffic Signals
$150,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1707000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
141
City of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: CULLUM DRIVE AND ALEXANDER LANE RECONSTRUCTION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
These two minor streets serve as collector type streets by conveying traffic to major arterials.
PROJECT DESCRIPTION:
Cullum Drive will be reconstructed from SH 10 to Huitt Lane and Alexander Lane will be reconstructed from
Main Street to Cullum Drive. Both streets will be reconstructed from two lane county type roads to standard 31'
wide residential streets with underground drainage.
PROJECT SCHEDULE:
Anticipate Award Design: 2nd Quarter 2013
Anticipate Right -of -Way Complete: 3rd Quarter 2013
Anticipate Plans Complete: 1 st Quarter 2014
Anticipate Begin Construction: 3rd Quarter 2014
Anticipate Construction: 3rd Quarter 2015
JUSTIFICATION:
Reconstruction of the streets will decrease the annual maintenance and provide a standard residential street in
compliance with City standards.
142
PROJECT TITLE. CULLUM DRIVE AND ALEXANDER LANE RECONSTRUCTION
NET EFFECTS ON OPERATING AND
INTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering
Right of Way
$p Construction
$0
E�
m
$p � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design
Preliminary Design %
Final Plans %
Specifications %
Construction %
ADDITIONAL COMMENTS:
Escrow Funds will also be used to finance a portion of this project.
$150,000
$20,000
$1,180,000
$1,350,000 �
143
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 03,2008
Submitted By: RON YOUNG Date Completed:
Project Title: BEAR CREEK PARKWAY
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Bear Creek Parkway is identified as a local collector thoroughfare in the City of Euless Master Thoroughfare
Plan,
PROJECT DESCRIPTION:
This project consist of the complete reconstruction of Bear Creek Parkway from Harwood Road to Ash Lane to
current City Standards,
PROJECT SCHEDULE:
JUSTIFICATION:
Bear Creek Parkway is an aging roadway nearing the end of its service life. Portions of the roadway are
beginning to deteriorate and require maintenance work. As the pavement deteriorates and fails, maintenance
costs increase.
144
PROJECT TITLE: BEAR CREEK PARKWAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -j ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering/Design- To Be Determined
Construction- To Be Determined
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
145
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2005
Submitted By: RON YOUNG Date Completed,
Project Title: ROSS AVENUE EXTENSION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This extension of Ross Avenue from the recently completed section adjacent to the fire station will complete the
upgrading of this street.
PROJECT DESCRIPTION:
The construction of the remainder of Ross Avenue from the fire station to the west limit will be in accordance
with City standards which includes concrete pavement.
PROJECT SCHEDULE:
JUSTIFICATION:
This construction, in accordance with City Standards, will allow the road a long service life and lower the annual
maintenance.
146
PROJECT TITLE: BOSS AVENUE EXTENSION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering- To Be Determined
Personnel: Full Time Right of Way- To Be Determined
Part Time $0 Construction- To Be Determined
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
Subtotal: $0
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
$0 � Total Estimated Capital Cost
CURRENT STATUS:
0
Operating Fund Conceptual Design % 0 °
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
147
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: CRESTHAVEN DRIVE RECONSTRUCTION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Cresthaven Drive is not identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION:
This project includes the reconstruction of Cresthaven Drive from a two-lane asphalt roadway to 31' wide, curb
and guttered concrete street from SH 10 to S Pipeline Road,
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade Cresthaven Drive to a standard City concrete curb and gutter section.
PROJECT TITLE: CRESTHAVEN DRIVE RECONSTRUCTION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering -To Be Determined
Personnel: Full Time
Construction- To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
149
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: HIGHLAND DRIVE RECONSTRUCTION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Highland Drive is not identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION:
The project includes the reconstruction of Highland Drive from SH 10 to S Pipeline Road from a two lane asphalt
roadway to a 31' wide curb and guttered concrete street.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade Highland Drive to a standard City concrete curb and gutter section.
150
PROJECT TITLE: HIGHLAND DRIVE RECONSTRUCTION
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
I Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering- To Be Determined
Construction- To Be Determined
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
151
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed,
Project Title: S PIPELINE ROAD
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
South Pipeline Road is not identified in the 1999 Master Thoroughfare Plan,
PROJECT DESCRIPTION:
The project consists of reconstruction of South Pipeline Road from a two-lane asphalt roadway to a 31' wide,
curb and guttered concrete street from east of Royal Parkway to East of Highland Drive,
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade South Pipeline Road to a standard City concrete curb and gutter section.
152
PROJECT TITLE: S PIPELINE ROAD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Engineering- To Be Determined
Construction- To Be Determined
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 00 °
Specifications % 0%
Construction % 0%
153
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: ROBERT BARKER Date Completed:
Project Title: FULLER -WISER ROAD=SH 183 TO HARWOOD ROAD
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Fuller -Wiser Road is identified as a minor arterial in the City of Euless Master Thoroughfare Plan,
PROJECT DESCRIPTION:
The project consists of the complete reconstruction of Fuller -Wiser Road to current standards from SH 183 to
Harwood Road,
PROJECT SCHEDULE:
JUSTIFICATION:
Fuller -Wiser Road is an aging roadway nearing the end of its service life. Portions of the roadway are beginning
to deteriorate and require maintenance work. As the pavement deteriorates and fails, maintenance costs
increase.
154
PROJECT TITLE: FULLER -WISER ROAD-SH 183 TO HARWOOD ROAD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
F�
m
$g I Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % �%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
155
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: ROBERT BARKER Date Completed:
Project Title: FULLER -WISER ROAD-HARWOOD ROAD TO MID CITIES BLVD
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code, Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
Fuller -Wiser Road is identified as a minor arterial in the City of Euless Master Thoroughfare Plan,
PROJECT DESCRIPTION:
This project consist of the complete reconstruction of Fuller -Wiser Road to current City standards from Harwood
Road to Mid -Cities Boulevard.
PROJECT SCHEDULE:
JUSTIFICATION:
Fuller -Wiser Road is an aging roadway nearing the end of its service life. Portions of the roadway are beginning
to deteriorate and require maintenance work. As the pavement deteriorates and fails, maintenance costs
increase.
156
PROJECT TITLE: FULLER -WISER ROAD-HARWOOD ROAD TO MID CITIES BLVD
NET EFFECTS ON OPERATING AND
TENANCE COST k+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$� � Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund Conceptual Design % �%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
157
T H � s?�C
T Y t7 F
158
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Priority
Estimated Cost
Operating CIP Fund
Bond Sale
Grants/ Impact Escrow Car Rental
Cobntri Other
To Be
EDC
Project Description
Fund Balance
Fees Funds Tax
Determined
WASTEWATER PROJECTS
Line Replacement, W Alexander Ln/Norman Dr/Franklin Dr
A
$
510,000
XX
Sub -Total Wastewater PriorityA-Proposed FY10
$
6109000
Line Replacement, Amett Drivel11l
B
$
351,000
XX
Line Replacement, Pauline Street 36t
B
$
405,000
XX
Line Replacement, Alexander/Ascot Outfal
B
$
242,000
XX
Line Replacement, Whitener/Ascot Outfall
B
$
176,000
XX
Line Replacement, Collin Drive
B
$
405,000
XX
Line Replacement, Blanco/Aransas/Crane
B
$
327,000
XX
Line Replacement, Slaughter Lane/E Huitt Lan
B
$
475,000
XX
Line Replacement, Ross Avenue
B
$
150,000
XX
Line Replacement, Oakwood Terrace Phase
B
$
345,000
XX
Line Replacement, Oakwood Terrace Phase if 141
B
$
6350000
XX
Sub -Total Wastewater Priority B-Unfunded
$
31511,000
SH 183 Utility Relocation
C
TBD
XX
Line Replacement, N Midway Park
C
TBD
XX
XX
Line Replacement, S Main Street
C
TBD
XX
Line Replacement, Aransas Drive
C
TBD
XX
Line Replacement, Glenn Drive/Crane Drive
C
TBD
XX
Line Replacement, Bo d Branch
C
TBD
XX
Line Replacement, Cedar Hills Estates/Hollywood Blvd,
C
TBD
XX
Line Replacement, Cedar Hills Estates/Sunset Drive
C
TBD
XX
Line Replacement, Eastcliff�ndlea/Signet
C
TBD
XX
Line Replacement, Huntin ton/Koen/Atkerson
C
TBD
XX
Line Replacement, Ector Drive/Fayette Drive
C
TBD
XX
Line Replacement, Donley/Shelmar Drive
C
TBD
XX
Line Replacement, Denton Drive
C
TBD
XX
Line Replacement, Collin Drive/Harris Drive/Trion Drive
C
TBD
XX
Line Replacement, Ector Drive/Donley Dnve/Crane Drive
C
TBD
XX
Line Replacement, EvanslCan on Rid e/N K nette
C
TBD
Line Replacement, Janann/Brownstone/Shelmar Drive
C
TBD
XX
Line Replacement, Kynette/Wilshire/Sierra
C
TBD
I
XX
Line Replacement, Lakewood/Dogwood Circle
C
TBD
XX
Line Replacement, Mary/Madene/Commerce
C
TBD
XX
Line Replacement, NW Midway/Rusk/Parker
C
TBD
XX
Line Replacement, Northcliff/To leatWinlea
C
TBD
XX
Line Replacement, Sagebrush -To lea/Wilshire
C
TBD
XX
Line Replacement, W Midway/Victoria/Delta
C
TBD
XX
Line Replacement, W Donley/Private Drive/Mimosa
C
TBD
XX
Sub -Total Wastewater Priority C-Unfunded
$
WASTEWATER PROJECTS - TOTAL
$ 410219000
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 30,2003
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT -WEST ALEXANDER LANE/NORMAN DRIVE/FRANKLIN DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Ross Avenue and West Alexander Lane
2. Between Norman Drive and Franklin Drive, and
3. Between Franklin Drive and Simmons Drive, North of Bayless Drive.
PROJECT SCHEDULE:
Anticipate Design Award: 2nd Quarter 2010
Anticipate Design Award: 1st Quarter 2011
Anticipate Begin Construction: 2nd Quarter 2011
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
160
PROJECT TITLE: LINE REPLACEMENT -WEST ALEXANDER LANE/NORMAN DRIVE/FRANKLIN DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$60,000
Personnel: Full Time
Construction
$450,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$510,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design 9 %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction ova
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
161
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 30,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-ARNETT DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between West Alexander and Arnett Drive
2. Outfall to Arnett Drive, and
3. Between Linda Lane and W Huitt Lane,
PROJECT SCHEDULE,
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
tC
PROJECT TITLE: LINE REPLACEMENT-ARNETT DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR =) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Full Time
Part Time
m
m
TOTAL ESTIMATED CAPITAL COST:
Engineering $401000
Construction $311,000
Total Estimated Annual Cost $0I Total Estimated Capital Cost $351,000
� PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund � Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
163
City of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT=PAULINE STREET
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Pauline Street and Jones Street
2. Between Pauline Street and Bayless Drive, and
3. North of Bayless Drive between South Mills Drive and Simmons Drive,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
164
PROJECT TITLE: LINE REPLACEMENT-PAULINE STREET
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
I Subtotal:
Full Time
Part Time
I Total Estimated Annual Cost
I PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering $451000
Construction $360,000
m
m
$0 Total Estimated Capital Cost $405,000
CURRENT STATUS:
Operating Fund Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding XX Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
This project lies within the current Community Development Block Grant area and will be submitted as the 36th
year CDBG Project.
165
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 30,2003
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-ALEXANDER LANE/ASCOT DRIVE OUTFALL
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of wastewater mains from Ascot Drive to the north along Fuller Branch
to E Huitt Lane,
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
166
PROJECT TITLE: LINE REPLACEMENT-ALEXANDER LANE/ASCOT DRIVE OUTFALL
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$22,000
Personnel: Full Time
Construction
$220,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$242,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
�
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
00 °
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S P
0%
County, State, Federal Funding
Construction %
0
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
167
City of Euless
Capital Project Request
Department, PUBLIC WORKS Date Prepared: May 30,2003
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT -WHITENER ROAD/ASCOT DRIVE OUTFALL
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Ascot Drive
2. Dunaway Court, and
3. Dunaway Drive between Dunaway Court and Ascot Drive,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
168
PROJECT TITLE: LINE REPLACEMENT -WHITENER ROAD/ASCOT DRIVE OUTFALL
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
E�
TOTAL ESTIMATED CAPITAL COST:
Engineering $163 1
Construction $160,000
Total Estimated Annual Cost $0I Total Estimated Capital Cost $176,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund � Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-COLLIN DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Along Collin Drive from Falls Drive to Travis Drive
2. Between Falls Drive and Fannin Drive east of Collin Drive
3. Between Fannin Drive and Travis Drive east of Collin Drive
4. Between Travis Drive and Dallas Drive east of Collin Drive, and
5. Between Dallas Drive and Tarrant Drive east of Collin Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. The project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
170
PROJECT TITLE: LINE REPLACEMENT-COLLIN DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$45,000
Personnel: Full Time
Construction
$360,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$4051000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conce tual Design %
p
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S P
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
171
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-BLANCO DRIVE/ARANSAS DRIVE/CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN.
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Between Blanco Drive and Aransas Drive from south of Harwood Road and
2. Between Blanco Drive and Crane Drive from Harwood Road to Aransas Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
172
PROJECT TITLE: LINE REPLACEMENT-BLANCO DRIVE/ARANSAS DRIVE/CRANE DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$35,000
Personnel: Full Time
Construction
$292,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$327,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
�
n %
Conceptual Design
P g
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S p
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
173
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SLAUGHTER LANE/E HUITT LANE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priorit : B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The project is part of the City of Euless Wastewater System Master Plan,
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between John Vernon Lane and Slaughter Lane east of Dunaway Drive
2. East of Dunaway Drive from Slaughter Lane to E Huitt Lane, and
3. Along E Huitt Lane from S Main Street to Dunaway Drive,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
174
PROJECT TITLE: LINE REPLACEMENT -SLAUGHTER LANE/E HUITT LANE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
m
TOTAL ESTIMATED CAPITAL COST:
Engineering $551000
Construction $420,000
,Total Estimated Annual Cost $0 Total Estimated Capital Cost $475,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund � Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
175
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 30,2003
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-ROSS AVENUE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains located on Ross Avenue and outfall to West
Alexander Lane,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
176
PROJECT TITLE: LINE REPLACEMENT-ROSS AVENUE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$15,000
Personnel: Full Time
Construction
$135,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$150,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S P
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
177
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2006
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE I
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Between Hollywood Boulevard/Reaves Court from Vine Street to the end of Reaves Court and
2. From Hollywood Boulevard to Reaves Court along 306 Hollywood Boulevard.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
178
PROJECT TITLE: LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE I
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$40,000
Personnel: Full Time
Cosntruction
$305,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$345,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
179
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2006
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE II
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Along 608 and 610 Martha Street
2. Between Martha Street/Cannon Drive from Reaves Court to W Huitt Lane
3. Between Jefflyn Court/W Huitt Lane from Martha Street to S Main Street, and
4. Between Henslee Drive/Cannon Drive from Reaves Court to Jefflyn Court,
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
�I]
PROJECT TITLE: LINE REPLACE MEN T-OAKWOOD TERRACE ADDITION PHASE II
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$75,000
Personnel: Full Time
Construction
$560,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$635,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
�
n %
Conceptual Design
P g
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S P
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
181
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,2000
Submitted By: RON YOUNG Date Completed:
Project Title: SH 183 UTILITY RELOCATION
Project Type: WASTEWATER Sub -Type: RELOCATION
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Texas Department of Transportation ("TxDOT") plans to widen SH183 within the next ten years.
PROJECT DESCRIPTION:
The City has a number of wastewater mains that might require relocation. The scope of the work is unknown at
this time.
PROJECT SCHEDULE:
JUSTIFICATION:
Relocation required where conflicts occur with the TxDOT's highway project.
182
PROJECT TITLE: SH 183 UTILITY RELOCATION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Cost -To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
$0
Subtotal:
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
0
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
The scope of work will be determined as TxDOT
completes
the highway reconstruction plans.
183
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2006
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-N MIDWAY PARK
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. East of Denton Drive between Bell Drive and Dallas Drive
2. Between Denton Drive/Trion Drive from Dallas Drive to Harwood Road
3. Along Denton Drive from Harwood Road to Collin Drive, and
4. Along Milam Drive from Blanco Drive to Midway Park Drive,
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, open joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
PROJECT TITLE: LINE REPLACEMENT-N MIDWAY PARK
NET EFFECTS ON OPERATING AND
186
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction - To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S P
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2006
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-S MAIN STREET
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater main along S Main Street from Jean Lane to W
Alexander Lane,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
PROJECT TITLE: LINE REPLACEMENT-S MAIN STREET
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction - To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
187
City of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-ARANSAS DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priori t : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION,
The project consists of the replacement of the wastewater mains east of Aransas Drive between Harwood Road
and Douglas Street,
PROJECT SCHEDULE.
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
PROJECT TITLE: LINE REPLACEMENT-ARANSAS DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction - To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S p
0%
County, State, Federal Funding
Construction %
0 %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-GLENN DRIVE/CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains located west of Glenn Drive from Aransas
Drive to Glenn Drive and West of Crane Drive from Harwood Road to upstream of Glenn Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
190
PROJECT TITLE: LINE REPLACEMENT-GLENN DRIVE/CRANE DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction- To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
191
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2007
Submitted By: RON YOUNG Date Com leted:
Project Title: LINE REPLACEMENT-BOYD BRANCH
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of replacing the existing 12" clay tile wastewater line west of S Mills Drive extending north
of S Pipeline Road to Carr Park,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
192
PROJECT TITLE: LINE REPLACEMENT-BOYD BRANCH
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction - To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P g
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S p
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
193
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT -CEDAR HILLS ESTATES/HOLLYWOOD BOULEVARD
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consist of the design and construction of wastewater mains in the Cedar Hill Addition along
Hollywood Boulevard from Vine Street to the east of Cannon Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Wastewater mains in the Cedar Hill Estates Addition area have deteriorated as they have aged and they need to
be replaced.
194
PROJECT TITLE: LINE REPLACEMENT -CEDAR HILLS ESTATESIHOLLYWOOD BOULEVARD
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
p g
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
195
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Com leted:
Project Title: LINE REPLACEMENT -CEDAR HILLS ESTATES/SUNSET DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains in the Cedar Hills Estates Addition:
1. Sunset Drive from Vine Street to S. Main Street,
2. Henslee Drive from Sunset Drive to Hollywood Boulevard, and
3. Hollywood Boulevard from Henslee Drive to S Main Street,
PROJECT SCHEDULE:
JUSTIFICATION:
Wastewater mains in the Cedar Hills Estates Addition area have deteriorated as they have aged and need to be
replaced.
196
PROJECT TITLE: LINE REPLACEMENT -CEDAR HILLS ESTATES/SUNSET DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
197
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-EASTCLIFF/WINDLEA/SIGNET
Project Type: WASTEWATER Sub -Type: MAIN
Project Code, Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project includes the replacement of the following wastewater mains:
1. Eastcliff Drive from Tyler Avenue to Signet Drive
2. Windlea Drive from Eastcliff Drive to Wilshire Drive, and
3. Between Windlea Drive/Signet Drive from Eastcliff Drive to Wilshire Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
PROJECT TITLE: LINE REPLACEMENT-EASTCLIFF/WINDLEA/SIGNET
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: HUNTINGTON/KOEN/ATKERSON/E HUITT/SLAUGHTER/MARTIN
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. East of Huntington Drive from S Atkerson Lane to E Alexander Lane,
2. Between Koen Lane/S Atkerson Lane from Huntington Drive to FAA Road,
3. Between S Atkerson Lane/N Atkerson Lane from Huntington Drive to FAA Road,
4. Between N Atkerson Lane/E Huitt Lane from Huntington Drive to FAA Road,
5. Between E Huitt Lane/Slaughter Lane from Huntington Drive to FAA Road,
6. Between Slaughter Lane/Martin Lane from Huntington to FAA Road, and
7. Between Martin Lane/E Alexander Lane from Huntington Drive to FAA Road,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the city are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
PROJECT TITLE: HUNTINGTON/KOEN/ATKERSON/E HUITT/SLAUGHTER/MARTIN
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
'Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
201
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-ECTOR DRIVE/FAYETTE DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code, Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains between Fayette Drive and Ector Drive from
Harwood Road to the end of the line.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
202
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE/FAYETTE DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
$0
Subtotal:
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S p
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
203
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-DONLEYDRIVE/SHELMAR DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project consists of the replacement of the wastewater lines on:
1. Donley Drive from Shelmar Drive to W Ash Lane
2. Donley Drive from Harwood Road to Shelmar Drive, and
3. Shelmar Drive from Green Hill Street to the end of Shelmar Drive.
PROJECT SCHEDULE:
JUSTIFICATION.
Many wastewater mains throughout the city are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
204
PROJECT TITLE: LINE REPLACEMENT-DONLEYDRIVE/SHELMAR DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
(ADDITIONAL COMMENTS:
XX
205
City of Euless
Capital Project Request
Department: PUBLIC WORKS
Date Prepared: April 05,2007
Submitted By: RON YOUNG
Date Completed.
Project Title: LINE REPLACEMENT-DENTON DRIVE
Project Type: WASTEWATER
Sub -Type: MAINS
Project Code:
Priority: C
RELATIONSHIP TO OTHER PROJECTS
AND/OR MASTER PLAN:
The wastewater mains included in this
project are part of the City of Euless Wastewater System Master Plan,
PROJECT DESCRIPTION:
This project consists of the replacement of wastewater mains located on Denton Drive between Collin Drive and
Harwood Road to include Bell Drive,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the
susceptible to ground movement, pulled
Many are substandard in size and have
replacement of wastewater mains using
problems.
city are 40+ years old. Most of these lines are clay tile and are
joints, root infiltration, and deterioration from hydrogen sulfide gas.
inflow/infiltration problems. This project is part of the systematic
a worst first approach to reduce maintenance costs and customer
206
PROJECT TITLE: LINE REPLACEMENT-DENTON DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Construction - To Be Determined
m
E�
m
�� � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % �%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 00 °
207
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-COLLIN DRIVE/HARRIS DRIVE/IRION DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
PROJECT DESCRIPTION:
The project consists of the following wastewater main replacements:
1. West of Collin Drive between Denton Drive and Harwood Road
2. West of Harris Drive from Dallas Drive to Harwood Road
3. Dallas Drive from west of Collin Drive to west of Harris Drive
4. South of Dallas Drive from west of Collin Drive to Dallas Drive, and
5. West of Irion Drive from Dallas Drive to Harwood Road
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
PROJECT TITLE: LINE REPLACEMENT-COLLIN DRIVE/HARRIS DRIVE/IRION DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
'i Total Salary
Purchase of Services
Materials & Supplies
Utilities
i Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Construction - To Be Determined
m
E�
$0 � Total Estimated Capital Cost
CURRENT STATUS:
0
Conceptual Design % 0 °
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 00 °
r�•
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT=ECTOR DRIVE/DONLEY DRIVE/CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Ector Drive and Donley Drive from Aransas Drive to Harwood Road and
2. Between Donley Drive/Crane Drive from Aransas Drive to Harwood Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the city are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
210
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE/DONLEY DRIVE/CRANE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
,PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
E�
$0 I Total Estimated Capital Cost
CURRENT STATUS:
0
Operating Fund Conceptual Design % 0 °
Fund Balance Preliminary Design ova 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
211
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-EVANS DRIVE/CANYON RIDGE DRIVE/N KYNETTE DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code, Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Evans Drive/Canyon Ridge Drive from Cyclone Branch to north of Kynette Drive and
2. North of Kynette Drive from Canyon Ridge Drive to Cyclone Branch,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the city are 40+ years old. Most of these lines are vitrified clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
212
PROJECT TITLE: LINE REPLACEMENT-EVANS DRIVE/CANYON RIDGE DRIVE/N KYNETTE DRIVE
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering- To Be Determined
Construction- To Be Determined
E�
$0 � Total Estimated Capital Cost
CURRENT STATUS:
0
Operating Fund Conceptual Design % 0 °
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
213
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By. RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-JANANN STREET/BROWNSTONE DRIVE/SHELMAR DRIVE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Janann Street from Aransas Drive to Donley Drive
2. Brownstone Drive from Aransas Drive to Donley Drive
3. Shelmar Drive from Greenhill Street to Aransas Drive, and
4. Aransas Drive from 500' south of Shelmar Drive to Janann Street.
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
Am 4
214
PROJECT TITLE: LINE REPLACEMENT-JANANN STREET/BROWNSTONE DRIVE/SHELMAR DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
m
$0 � Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund Conceptual Design % 0
0
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 00 °
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
215
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-KYNETTE/WILSHIRE/SIERRA/EASTCLIFF, E OF SIERRA
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Kynette Drive from Eastcliff Drive to Wilshire Drive
2. Wilshire Drive from Kynette Drive extending 800' north
3. Between Sierra Drive/Eastcliff Drive from Kynette Drive to Signet Drive, and
4. East of Sierra Drive from Signet Drive to Wilshire Park.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
PROJECT TITLE: LINE REPLACEMENT-KYNETTE/WILSHIRE/SIERRA/EASTCLIFF, E OF SIERRA
NET EFFECTS ON OPERATING AND
NTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0I Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 00
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
217
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT=LAKEWOOD BLVD/DOGWOOD CIRCLE/BOCOWOOD CIRCLE
Project Type: WASTEWATER Sub -Type: MAINS
Project Code, Priorlt : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Lakewood Boulevard from Dogwood Circle north to Private Drive, and
2. Dogwood Circle, Cypress Circle, Bocowood Circle, and Aspenway Circle,
PROJECT SCHEDULE,
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
218
PROJECT TITLE: LINE REPLACEMENT-LAKEWOOD BLVD/DOGWOOD CIRCLE/BOCOWOOD CIRCLE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
$0I Total Estimated Capital Cost
CURRENT STATUS:
0
Conceptual Design % 0 °
Preliminary Design % 0%
Final Plans % 0%
Specifications % 00 °
Construction % 0%
219
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-MARY/MARLENE/COMMERCE-WILSHIRE/GREEN BRIAR
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priorit : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Mary Drive/Marlene Drive from Cyclone Branch to Marlene Drive
2. Between Commerce Street/Wilshire Drive from Marlene Drive to Sagebrush Trail
3. South of Greenbriar Drive from Cyclone Branch to Debra Drive
4. Between Greenbriar Drive/Mary Street from Eastcliff Drive to Debra Drive, and
5. East of Debra Drive and south of Mary Drive,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
220
PROJECT TITLE: LINE REPLACEMENT-MARY/MARLENE/COMMERCE-WILSHIRE/GREENBRIAR
NET EFFECTS ON OPERATING AND
NANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
m
$� � Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund Conceptual Design % �%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
(ADDITIONAL COMMENTS:
XX
221
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -NW MIDWAY/RUSK/PARKER/ROCKWALL DRIVES
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION,
The project consists of the replacement of the following wastewater mains:
1. North of West Midway Drive from FM 157 to Parker Drive
2. West Midway Drive from Parker Drive to Rusk Drive
3. Rusk Drive from West Midway Drive to Parker Drive
4. Parker Drive from West Midway Drive to Rockwall Drive, and
5. Rockwall Drive from west of Parker Drive to 400' west of Lamar Drive.
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
222
PROJECT TITLE: LINE REPLACEMENT -NW MIDWAY/RUSI</PARKER/ROCKWALL DRIVES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
1�
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
�� � Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % �%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
223
City of Euless
Capltal Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-NORTHCLIFF/TOPLEA/WINDLEA/SIGNET/KYNETTE/WESTCLIFF
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
I. Between Northcliff Drive/Toplea Drive from Canyon Ridge to Cyclone Branch
2. Between Toplea Drive/Windlea Drive from Canyon Ridge to Cyclone Branch
3. Between Windlea Drive/Signet Drive from Canyon Ridge to Cyclone Branch
4. Signet Drive/Kynette Drive from the church to Cyclone Branch, and
5. Westcliff Drive from Toplea Drive to north of Windlea Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
224
PROJECT TITLE: LINE REP-NORTHCLIFF/TOPLEA/WINDLEA/SIGNET/KYNETTE/WESTCLIFF
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
225
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REPLACEMENT-SAGEBRUSH-TOPLEA/WILSHIRE-YORKSHIRE/SAGEBRUSH
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Sagebrush Trail/Toplea Drive from Cyclone Branch to east of Wilshire Drive
2. Between Wilshire Drive/Yorkshire Drive from Signet Drive to south of Toplea Drive
3. Between Sagebrush Trail/Tyler Avenue from Cyclone Branch to Commerce Street
4. Eastcliff Drive from /Tyler Avenue to the apartments, and
5. Between Marlene Drive/Tyler Avenue from Eastcliff Drive to Commerce Street,
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
226
PROJECT TITLE: LINE REPLACEMENT-SAGEBRUSH-TOPLEA/WILSHIRE-YORKSHIRE/SAGEBRUSH
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials &Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
E�
m
$0I Total Estimated Capital Cost
CURRENT STATUS:
0
Operating Fund Conceptual Design % 0 °
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
227
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed,
Project Title: LINE REP-W MIDWAY/VICTORIA/DELTA/LAMAR/ROCKWALL
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. West Midway Drive from FM 157 to Victoria Drive
2. Victoria Drive from West Midway Drive north 700'
3. Delta Drive from West Midway Drive north 1000'
4. Lamar Drive from West Midway Drive north to Fayette Drive, and
5. Rockwall Drive from Lamar Drive west and north 800'.
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are vitrified clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
PROJECT TITLE: LINE REP-W MIDWAY/VICTORIA/DELTA/LAMAR/ROCKWALL
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
m
m
$0I Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
229
City of Euless
Capital Project Request
Department, PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-W DONLEY/PRIVATE DRIVE/MIMOSA/MAGNOLIA/REDBUD
Project Type: WASTEWATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN,
The wastewater mains included in this project are part of the City of Euless Wastewater System Master Plan.
The project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. West of Donley Drive from West Ash Lane to Private Drive
2. Private Drive from west of Redbud Drive to Lakewood Boulevard
3. Mimosa Lane from Bocowood Drive to Private Drive
4. Magnolia Lane from Bocowood Drive to Private Drive, and
5. Redbud Drive from Bocowood Drive to Private Drive,
PROJECT SCHEDULE:
JUSTIFICATION,
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. Systematic replacement will reduce
maintenance costs and customer problems.
230
PROJECT TITLE: LINE REPLACEMENT-W DONLEY/PRIVATE DRIVE/MIMOSA/MAGNOLIA/REDBUD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Full Time
Part Time
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
E�
E�
$0I Total Estimated Capital Cost
CURRENT STATUS:
0
Conceptual Design % 0 °
Preliminary Design % 0%
Final Plans % 00 °
Specifications % 00 °
Construction % 0%
231
232
PROPOSED AND
UNFUNDED
WATER PROJECTS
N
W
W
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
WATER PROJECTS
Priority Estimated Cost Fund Balance Operating CIP Fund Bond Sale Grants/ Contrib Impact Fees Funds Escrow Car Rental Tax Other EDC
To Be
Determined
A
N/A
Sub -Total Water Priod A-Proosed FY10
$
Line Replacement, Live Oak Ct/Live Oak Dr /Marlene Driv
B
$ 320,000
XX
Line Replacement, S Pipeline Road West
B
$ 260,000
XX
Water & Wastewater Impact Fee Update
B
$ 30,000
XX
Line Replacement, S Pipeline Road East
B
$ 240,000
XX
Water System Security Camera Installation
B
$ 75,000
XX
Sub -Total Water Priori B-Unfunded
$ 925,000
Line Replacement, Westwood Drive
C
TBD
XX
Line Replacement, Collin/Dallas Drive/Harwood Road
C
TBD
XX
Line Replacement, Collin/Denton Drive/Dallas Drive
C
TBD
XX
Line Replacement, Fuller Drive
C
TBD
XX
Line Replacement, Sprin wood Coun
C
TBD
XX
Hwy 183 Water Crossing
C
TBD
XX
Hwy 360 Water Crossing
C
TBD
XX
Line Replacement, K nette Drive
C
TBD
XX
Line Replacement, Midcreek/Rock Creek/Stony Creel,
C
TBD
XX
Line Replacement, Blessing Creek and Little Creel,
C
TBD
XX
Line Replacement, Eastdiff Drive
C
TBD
XX
Line Replacement, Ector Drive
C
TBD
XX
Line Replacement, Hollow Oak Drive
C
TBD
XX
Line Replacement, Midway Drive East
C
TBD
XX
Line Re lacement, Midway Drive West
C
TBD
XX
Line Replacement, Dickey Drive ; &-t, -
G -
TBD
XX
Line Replacement, DickrMVe North
C
TBD
XX
Line Re4(�rA,rWft. aula Lane
C
TBD
XX
L r,Z,Replacement, Denton Drive
C
TBD
XX
Line Replacement, S Main Street North
C
TBD
XX
Line Replacement, S Main Street South'
C
TBD
-
XX
Line Replacement, Sunset Drive
C
TBD
XX
Line Replacement, Wildwood Street
C
TBD
XX
Line Replacement, Woodvine East
C
TBD
XX
Line Replacement, Woodvine (West)
C
TBD
XX
Line Replacement, Shady Creek and Cliffwooc
C
TBD
XX
Line Replacement, Dunaway Drive
C
TBD
XX
Line Re lacement, E Huitt Lane
C
TBD
XX
Line Replacement, Needles Street
C
TBD
XX
Water System Security Land Ac uisitior
C
TBD
XX
Sub -Total Water Priority C-Unfunded
$
WATER PROJECTS -TOTAL
$ 926,000
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -LIVE OAK CT/LIVE OAK DRIVE/MARLENE DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
These water mains are included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing'#' cast iron water main with an 8" PVC main along Cedar
Court to Marlene Drive and Live Oak Court. Additionally, the replacement of the existing 8" cast iron water main
with an 8" PVC water main from Canyon Ridge to West Cliff Drive is also included in the scope of the project.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water main provides
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
f
OR
\./
234
PROJECT TITLE: LINE REPLACEMENT -LIVE OAK CT/LIVE OAK DRIVE/MARLENE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering
Construction
$0
$0
$0
$0
$0
$0
$40,000
$280,000
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $320,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
PAC1.1
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted B : RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-S PIPELINE ROAD WEST
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" cast iron water main with an 8" PVC water main along
S Pipeline Road west from Simmons Drive to Vine Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
236
PROJECT TITLE: LINE REPLACEMENT-S PIPELINE ROAD WEST
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$30,000
Personnel: Full Time
Construction
$230,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$260,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
237
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2009
Submitted By: RON YOUNG Date Completed:
Project Title: WATER AND WASTEWATER IMPACT FEE UPDATE
Project Type: WATER Sub -Type:
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Water and wastewater impact fee charges were instituted by the City of Euless in 1990 in accordance with
applicable state law to generate revenue for funding of capital improvements attributable to new development.
Impact fees are related to the items identified by the Capital Improvements Plan and the Water and Wastewater
System Master Plan.
PROJECT DESCRIPTION:
This project will consist of reviewing the City's Land Use Assumptions, the costs of future infrastructure needs,
system capacity available for future growth, the cost of Trinity River Authority service and update the Capital
Improvements Plan. Calculations based on state dictated requirements will be made to determine the maximum
allowable impact fees. The city council will determine what percentage of the maximum allowable fee to impose.
PROJECT SCHEDULE:
JUSTIFICATION:
Legislation passed in 2001 provided an automatic five year extension to the 2002 Update. The impact fees
were updated in 2007 as required. The next impact fee update will be in 2012 barring any new legislative action.
--*N
238
PROJECT TITLE: WATER AND WASTEWATER IMPACT FEE UPDATE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Engineering $30,000 1
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$30,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
XX
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
The proposed method of financing is impact fees.
I.,
239
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-S PIPELINE ROAD EAST
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project will replace the existing 6" cast iron water main with an 8" PVC water main along S Pipeline Road
east from Vine Street to S Main Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
240
PROJECT TITLE: LINE REPLACEMENT-S PIPELINE ROAD EAST
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $30,000
Construction $210,000
$0
$0
$0
Elie]
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$240,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
241
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: WATER SYSTEM SECURITY CAMERA INSTALLATION
Project Type: WATER Sub -Type:
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
2004 Water System Vulnerability Assessment of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
The project provides for the installation of security cameras at the water production and storage sites (ground
storage tanks and towers) located at West Fuller Drive, Heritage Park, 1400 N Main Street, 2591 N Main Street,
and 2700 N Main Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Increase water system security by addressing vital elements recommended in the 2004 Water System
Vulnerability Assessment as identified by Lockwood, Andrews, and Newman, Inc. and submitted to the
Environmental Protection Agency (EPA).
242
PROJECT TITLE: WATER SYSTEM SECURITY CAMERA INSTALLATION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost
Equipment Installation
$75,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$75,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
243
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-WESTWOOD DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main with an 8" PVC main along Westwood Drive from Fuller Drive to
Carter Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water main provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
244
PROJECT TITLE: LINE REPLACEMENT-WESTWOOD DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering- To Be Determined
Personnel: Full Time Construction- To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
245
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-COLLIN DR, DALLAS DRIVE TO HARWOOD ROAD
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main with an 8" PVC main along Collin Drive from Dallas Drive to Harwood
Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
RQ
'�
246
PROJECT TITLE: LINE REPLACE MENT-COLLIN DR, DALLAS DRIVE TO HARWOOD ROAD
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
247
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-COLLIN DR, DENTON DRIVE TO DALLAS DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main to an 8" PVC main along Collin Drive from Denton Drive to Dallas
Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
io
248
PROJECT TITLE: LINE REPLACEMENT-COLLIN DR, DENTON DRIVE TO DALLAS DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
249
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT -FULLER DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of replacing a 6" cast iron water main with an 8" PVC water main along Fuller Drive from
Salem Drive to Carter Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
".-r
PROJECT TITLE: LINE REPLACEMENT -FULLER DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
251
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-SPRINGWOOD COURT
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 4" water main with an 8" main on Springwood Court.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance cost. Substandard size water mains provide
a reduced flow of water. Systematic annual replacement of deteriorated and substandard size water mains will
reduce maintenance costs.
252
PROJECT TITLE: LINE REPLACEMENT-SPRINGWOOD COURT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Engineering- To Be Determined
Personnel: Full Time
Construction- To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
253
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July21,2000
Submitted By: RON YOUNG Date Completed:
Project Title: SH 183 WATER CROSSING
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Texas Department of Transportation ("TxDOT") plans to widen SH 183 within the next 10 years.
PROJECT DESCRIPTION:
The City has a 24" water main and many other smaller mains that will have to be relocated when SH 183 is
reconstructed. The scope/magnitude of relocation work is unknown at this time.
PROJECT SCHEDULE:
JUSTIFICATION:
Relocation required where conflicts occur with TxDOT's highway project.
0"*N
254
PROJECT TITLE: SH 183 WATER CROSSING
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Costs- To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
M
255
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,2000
Submitted By: RON YOUNG Date Completed:
Project Title: SH 360 WATER CROSSING
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is related to the DFW International Airport Master Plan for property in Euless.
PROJECT DESCRIPTION:
This project consists of the extension of three water mains across SH 360 right of way to provide service to a
portion of the DFW Airport property.
PROJECT SCHEDULE:
JUSTIFICATION:
Development on the airport property could potentially increase the City's tax revenues. This development is
dependent upon the availability of water service to this area.
"00*N
256
L.—
L
PROJECT TITLE: SH 360 WATER CROSSING
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Costs -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
257
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-KYNETTE DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of a 6" cast iron water main with an 8" PVC main along Kynette Drive
from Cyclone Creek to Wilshire Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
.1 1
258
PROJECT TITLE: LINE REPLACEMENT-KYNETTE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction- To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications ova
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
11
259
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACE MENT-MIDCREEK/ROCK CREEK/STONY CREEK
Project Type: WATER Sub -Type:
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
This project consists of the replacement of a 6" AC main with an 8" PVC main on Midcreek Drive, Rock Creek
Drive, and Stony Creek Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water.
260
PROJECT TITLE: LINE REPLACEMENT-MIDCREEK/ROCK CREEK/STONY CREEK
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction - To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
261
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -BLESSING CREEK AND LITTLE CREEK
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
This project will replace the 6" AC main with an 8" PVC main for Blessing Creek and Little Creek.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
ig
262
L
PROJECT TITLE: LINE REPLACEMENT -BLESSING CREEK AND LITTLE CREEK
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Engineering -To Be Determined
Personnel: Full Time
Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
1► -IN
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-EASTCLIFF DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" AC main to an 8" PVC main along Eastcliff Drive from Toplea
Drive to Del Prado Apartments.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs and increase water flow.
264
PROJECT TITLE: LINE REPLACEMENT-EASTCLIFF DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
265
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-ECTOR DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main on Ector Drive from
Trojan Trail to Midway Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
266
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
polo
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
267
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT -HOLLOW OAK DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron main with an 8" PVC main along Hollow Oak Drive
from Woodridge Circle to Pebble Creek Drive and Woodridge Circle south of Hollow Oak Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
268
PROJECT TITLE: LINE REPLACEMENT -HOLLOW OAK DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Engineering- To Be Determined
Personnel: Full Time
Construction- To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
269
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -MIDWAY DRIVE EAST
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
This project replaces the 6" cast iron water main with an 8" PVC main on Midway Drive east from N Main Street
to Freestone Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains
provided inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size
water mains will reduce maintenance costs.
270
PROJECT TITLE: LINE REPLACEMENT -MIDWAY DRIVE EAST
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost
Engineering -To Be Determined
Personnel: Full Time
Construction- To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
M
271
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -MIDWAY DRIVE WEST
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
This project replaces the 6" cast iron water main with an 8" PVC main along Midway Drive west from Freestone
Drive to Ector Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
272
ON
ON
OR
PROJECT TITLE: LINE REPLACEMENT -MIDWAY DRIVE WEST
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction- To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
273
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Com leted:
Project Title: LINE REPLACEMENT -DICKEY DRIVE SOUTH
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
This project consists of the replacement of a 6" cast iron water main with an 8" PVC main along Dickey Drive
south from E Huitt Lane to Hilton Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
274
PROJECT TITLE: LINE REPLACEMENT -DICKEY DRIVE SOUTH
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
00
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
RIM
275
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -DICKEY DRIVE NORTH
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
This project consists of replacing the 6" cast iron water main with an 8" PVC main along Dickey Drive north from
SH 10 to E Huitt Lane.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
''1
276
PROJECT TITLE: LINE REPLACEMENT -DICKEY DRIVE NORTH
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
Oval l III19XIFTWO141"Wil�►���
277
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACE M ENT-PAU LA LANE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main along Paula Lane
from Needles Street to S Pipeline Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
278
PROJECT TITLE: LINE REPLACEMENT-PAULA LANE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Costs -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
o
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
279
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-DENTON DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main along Denton Drive
from Tarrant Drive to Harwood Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
Ra
PROJECT TITLE: LINE REPLACEMENT-DENTON DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering -To Be Determined
Personnel: Full Time Construction -To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
/_1T1111 ulL11i14►II&
XX
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
4.1
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-S MAIN STREET (NORTH)
Project Type: WATER Sub -Type: MAIN
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along S Main Street from E Huitt Lane to SH 10 from a 6"
cast iron main to an 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
282
PROJECT TITLE: LINE REPLACEMENT-S MAIN STREET (NORTH)
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
283
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Com leted:
Project Title: LINE REPLACEMENT-S MAIN STREET (SOUTH)
Project Type: WATER Sub -Type: MAIN
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along S Main Street from Landover Drive to E Huitt Lane
from a 6" cast iron main to an 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
284
PROJECT TITLE: LINE REPLACEMENT-S MAIN STREET (SOUTH)
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
285
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SUNSET DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along Sunset Drive from S Pipeline Road to S Main Street
from a 6" cast iron main to an 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
286
"I --
PROJECT TITLE: LINE REPLACEMENT -SUNSET DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
287
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACE MENT-WI LDWOOD STREET
Project Type. WATER Sub -Type: MAINS
Project Code. Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along Wildwood Street from a 6" cast iron main to an 8"
PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
288
PROJECT TITLE: LINE REPLACEMENT-WILDWOOD DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction- To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
289
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-WOODVINE DRIVE (EAST)
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along Woodvine Drive from Cliffwood Road to El Camino
Real from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
290
PROJECT TITLE: LINE REPLACEMENT-WOODVINE DRIVE (EAST)
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction- To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
291
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-WOODVINE DRIVE (WEST)
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along Woodvine Drive form Pebble Creek to Cliffwood
Road from a 6" cast iron main to an 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
.,
292
PROJECT TITLE: LINE REPLACEMENT-WOODVINE DRIVE (WEST)
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction- To Be Determined
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
P*X
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SHADY CREEK DRIVE AND CLIFFWOOD DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water mains along Shady Creek Drive and Cliffwood Drive from the
existing 6" cast iron mains to 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
W
294
PROJECT TITLE: LINE REPLACEMENT -SHADY CREEK DRIVE AND CLIFFWOOD DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX _
ADDITIONAL COMMENTS:
295
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-DUNAWAY DRIVE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" AC water main with an 8" PVC water main on
Dunaway Drive from E Alexander Lane to E Ascot Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
WE
Moll
N...
PROJECT TITLE: LINE REPLACEMENT-DUNAWAY DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering -To Be Determined
Personnel: Full Time
Construction -To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
a
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
297
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-E HUITT LANE
Project Type: WATER Sub -Type: MAINS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" PVC water main with an 8" PVC water main along E
Huitt Lane from S Main Street to Dunaway Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
298
L.
PROJECT TITLE: LINE REPLACEMENT-E HUITT LANE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering- To Be Determined
Personnel: Full Time
Construction- To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
299
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -NEEDLES STREET
Project Type: WATER Sub -Type: MAINS
Project Code: Priori! : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" cast iron water main with an 8" PVC water main along
Needles Street from Paula Lane to Raider Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
300
PROJECT TITLE: LINE REPLACEMENT -NEEDLES STREET
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering -To Be Determined
Personnel: Full Time
Construction- To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
301
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: WATER SYSTEM SECURITY LAND ACQUISITION
Project Type: WATER Sub -Type:
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
2004 Water System Vulnerability Assessment of the City of Euless Water Systems Master Plan.
PROJECT DESCRIPTION:
The project consists of the acquisition of a small residential property which shields the Fuller ground storage
tank from public view. Removal of the residence in order to provide greater security, access and visibility is also
included in the scope of the project.
PROJECT SCHEDULE:
JUSTIFICATION:
Increase water system security by addressing vital elements recommended in the 2004 Water System
Vulnerability Assessment as identified by Lockwood, Andrews and Newman, Inc. and submitted to the
Environmental Protection Agency (EPA).
302
PROJECT TITLE: WATER SYSTEM SECURITY LAND ACQUISITION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Land Acquisition -To Be Determined
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
303
.1
T H E I T Y 0 E
4172
L
PROPOSED AND
UNFUNDED
OTHER PROJECTS
W
CD
Cn
CAPITAL IMPROVEMENT PROGRAMS
FY10 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
OTHER PROJECTS
Texas Star Sports Complex Lighting Improvements
A
$ 600,000
XX
Glade Parks Trail Connection
A
$ 2,000,000
XX
Sub -Total Other Priority A-Proosed FYf 0
$ 2,600,000
Park Amenities Upgrade
B
$ 150,000
XX
Trail Lighting -Phase I
B
$ 50,000
XX
Midway Park FLC Phase -II Design Outdoor Aquatics
B
$ 468,453
XX
Midway Park FLC Phase -III Design Indoor Aquatics
B
$ 317,500
XX
Midway Park FLC Phase -II Outdoor Aquatics Construction
B
$ 5,199,836
XX
$500,000
Midway Park FLC Phase -III Indoor Aquatics Construction" I
B
$ 3,492,500
$750,000
XX
Fire Training Facility and Tower
B
$ 1,793,000
XX
Animal Shelter
B
$ 692,900
XX
Development/Engineering Building
B
$ 1,159,100
XX
Blessing Branch Park Improvements
B
$ 275,040
XX
Texas Star Sports Complex Parking Lot Improvements
B
$ 99,550
XX
South Euless Water Feature
B
TBD
XX
Wilshire Park Water Feature
B
TBD
XX
Sub -Total Other PrioriB-Unfunded
$ 13,697,879
Texas Star Sports Complex Improvements
C
TBD
XX
Trail Connection - S Euless
C
TBD
XX
Texas Star Sports Complex -Softball World Turf
C
TBD
XX
Trail Lighting -Phase II
C
TBD
XX
Texas Star Sports Complex -PATS, Phase IV
C
TBD
XX
Trail Enhancements -Villages Bear Creek
C
TBD
XX
Trail Enhancements -Phase I
C
TBD
XX
Trail Enhancements -Phase II
C
TBD
XX
Trailwood Park Improvements
C
TBD
XX
Community Center for South Euless
C
TBD
XX
Emergency Call Boxes
C
TBD
XX
Kiddie Can Park Improvements
C
TBD
XX
Sub -Total Other PrioriC-Unfunded
$
OTHER PROJECTS - TOTAL
I $ 16,297,879
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 29,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX LIGHTING IMPROVEMENTS
Project Type. FIXTURES Sub -Type: IMPROVEMENTS
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The feasibility study recommended the removal of the existing light fixtures, poles, and foundations, and the
replacement with new Sports lighting poles and fixtures.
PROJECT DESCRIPTION:
The project replaces the existing field lighting fixtures, poles and foundations with Musco "Light Structure Green"
or "LSG" lighting which is the best product on the market for spill/glare control and maintaining constant light
levels. The system includes a remote ballast for easy maintenance, constant illumination levels, pre -wired and
pre -aimed fixtures from the factory, and a 25-year maintenance free warranty. The "LSG' is considerably more
efficient than the existing sport lighting fixtures installed, requires approximately 30% fewer fixtures than the
existing system to achieve 50/30 foot-candle levels, and reduces utility costs.
PROJECT SCHEDULE:
JUSTIFICATION:
The existing poles, which were originally installed in 1982, are integral ballasted 1500 watt metal halide sports
lighting fixtures that require maintenance approximately two times per year to replace fixtures, lenses and bulbs.
There are numerous cracks and erosion points in the light pole foundations and do not meet current wind load
requirements.
306
14I - _✓
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX LIGHTING IMPROVEMENTS
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Disconnect and remove existing lights $600,000
Personnel: Full Time fixtures, poles and footings and replace
Part Time $0 with MUSCO LSG and reconnect to
Total Salary $0 existing circuits and switchgear
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding XX
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
This project is contingent upon the receipt of grant funding.
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
$600,000 1
0%
0%
0%
0%
0%
307
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 05,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: GLADE PARKS TRAIL CONNECTION
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code. Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
As identified in the Glade Parks development, this project proposes to connect the existing Trails of Euless to
the City of Colleyville trails through the Glade Park Development.
PROJECT DESCRIPTION:
Very high interest in trails and trail connectivity was identified in the scientific survey conducted for the adopted
Parks Master Plan. Eighty-eight percent of those who participated in the survey singled out trail connections
between existing and future park developments as their number one priority. Additionally, seventy-six percent
identified the need for trail connectivity to other cities as their top priority. This trail would link the Trails of Euless
to the City of Colleyville trail system through the Glade Park Development. The trail would tie-in to the existing
trail to the east, go under SH 121, and tie-in to the City of Colleyville trail system to the west.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The continued development and maintenance of our
trails system received a great deal of support from the citizens as indicated in the responses to the scientific
survey and has also been supported by past updates to the Parks Master Plan.
RIO
308
PROJECT TITLE: GLADE PARKS TRAIL CONNECTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Cost $2,000,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$2,000,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
This project is contingent upon the receipt of grant funding.
309
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 01,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: PARK AMENITIES UPGRADE
Project Type: FIXTURES Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment section of the adopted Parks Master Plan, are projects related to park
infrastructure, fixtures, and amenities that are recommended for either renovation, upgrade, or repair.
PROJECT DESCRIPTION:
This project addresses park infrastructure needs and/or renovation of current park amenities such as: park
structure painting (gazebos, pavilions, etc.), minor trail repairs, playground renovations, installation of shaded
"stopping stations" along the Trails of Euless, and other projects identified in the Parks Master Plan.
PROJECT SCHEDULE:
Anticipate Begin: FY2011
JUSTIFICATION:
Pursuant to the recommendations in the Parks Master Plan, parks and related infrastructure should be
maintained at levels that meets the citizens' expectations. The needs have been identified in the Parks Master
Plan based on staff and citizen input. This project addresses some of those request.
310
L
PROJECT TITLE: PARK AMENITIES UPGRADE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Fixtures
Personnel: Full Time
Park Amenities
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$100,000
$50,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$150,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
The proposed method of finance is the EDC Fund Balance.
311
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 30,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL LIGHTING -PHASE I
Project Type. FIXTURES Sub -Type: IMPROVEMENTS
Project Code. Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment section of the adopted Parks Master Plan is the addition of trail lighting in
various parks where trails are located. This request is for the first phase of a project dedicated to satisfying that
need.
PROJECT DESCRIPTION:
This project includes the installation of trail lighting along the Trails of Euless similar to what was installed along
the trail through Midway Park. Additional parks that have been identified as needing trail lighting are: Trailwood
Park, The Preserve at McCormick Park, The Villages of Bear Creek Park and Heritage Park. Not all of the parks
identified would be included in this phase, but rather in future phases of an overall Trail Lighting project.
PROJECT SCHEDULE:
JUSTIFICATION:
Trails in the area have become popular and lighting trails could extend hours of usage as well as provide for
increased visibility/security for remote trail areas.
W
312
PROJECT TITLE: TRAIL LIGHTING -PHASE I
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Fixtures $50,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$50,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
The proposed method of financing is EDC fund balance.
313
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: February 11,2009
Submitted By: RAY MCDONALD Date Completed:
Project Title: MIDWAY PARK FLC PHASE II- OUTDOOR AQUATICS DESIGN
Project Type: DESIGN Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless has for many years recognized the importance of planning for parks, recreation, and open
space based on the needs as expressed by the citizens. In the plan development process for the recent update
to the Parks Master Plan and as part of the City's five year master plan, a scientific survey of park, recreation,
and open space needs was conducted from a sample of randomly selected citizens in Euless. From this
valuable information, a list of priorities was identified. A new Outdoor Aquatic Center was identified as a top
priority.
PROJECT DESCRIPTION:
The project consists of the design of an outdoor family aquatic center which will include various play
components such as a leisure pool, slides, aqua play features, shade structures, a bath house, and all the
necessary filtration systems to support the aquatic features. The project also involves redevelopments/
improvements to the entire site such as relocating the tennis courts and the construction of various trails, a
group pavilion, an amphitheater, multi -use sport courts, additional picnic stations with grills, a nature area, a
botanical garden, and public art display(s).
PROJECT SCHEDULE:
JUSTIFICATION:
The City population is sufficient to support an outdoor family aquatic center. The City's existing aquatic facilities
have aged and maintaining the pools and support facilities has been an ongoing issue and concern. The
expenses necessary to maintain and operate the pools each season continue to increase, far exceeding the
revenue generated by the pools. Continuing in repair mode is no longer possible at the Wilshire and South
Euless Pools and a long-term plan is necessary. Given the fact that two of the neighborhood pools are over
thirty years old and the cost to renovate, repair, or replace them is estimated at over one million dollars each, it
is recommended that the city concentrate its efforts and resources toward the family aquatic facility to serve the
citizens of Euless. Project approval requires revision of the master planning of Midway Park. The FLC project
eliminates the current ball fields and requires the relocation of the the existing tennis courts, which will be
replaced with the necessary support facilities to serve the project such as parking, lighting, landscaping, and
recreational amenities such as pavilions, picnic stations, open space, sand volleyball court(s), and trails.
314
11-11
PROJECT TITLE: MIDWAY PARK FLC PHASE II- OUTDOOR AQUATICS DESIGN
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Engineering
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$468,453 1
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$468,453
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0
0 /o
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
The proposed method of finance is EDC CIP Fund Balance
315
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: February 11,2009
Submitted By: RAY MCDONALD Date Completed:
Project Title: MIDWAY PARK FLC PHASE III- INDOOR AQUATICS DESIGN
Project Type. DESIGN Sub -Type: INDOOR AQUATIC CENTER
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless has identified, as part of the city's five year master plan, the need for an indoor aquatic
center. The design of an indoor aquatic center will allow the City to serve the growing population by expanding
services and programs for citizens.
PROJECT DESCRIPTION:
The project consist of the design of an indoor aquatic center (approximately 8,600 square feet) that includes a
lap / leisure pool, current channel, slide, and therapy pool. This multi -purpose facility would be attached to the
senior center and would serve the senior population, as well as the general public and would be used for various
aquatic programs including aerobics / wellness classes, swim lessons, rehabilitation opportunities, and would
also be used as a rental facility for birthday and private parties.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has for many years recognized the importance of planning for parks, recreation, and open
space based on the needs as expressed by the citizens. In the plan development process for the recent update
to the Parks Master Plan and as part of the City's five year master plan, a scientific survey of park, recreation
and open space needs was conducted from a full sample of randomly selected citizens in Euless. From this
valuable information, a list of priorities was identified. An indoor aquatic center was identified as a high priority
for aquatic facilities that the city currently lacks. An indoor aquatic center would allow staff the opportunity to
serve the growing population by expanding services and programs for all citizens.
0.
316
IM
PROJECT TITLE: MIDWAY PARK FLC PHASE III- INDOOR AQUATICS DESIGN
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Engineering $317,500
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$317,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
317
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: February 11,2009
Submitted By: RAY MCDONALD Date Completed:
Project Title: MIDWAY PARK FLC PHASE II -OUTDOOR AQUATICS CONSTRUCTION
Project Type: CONSTRUCTION Sub -Type: PARK IMPROV./OUTDOOR AQUATIC CENTER
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless has for many years recognized the importance of planning for parks, recreation, and open
space based on the needs as expressed by the citizens. In the plan development process for the recent update
to the Parks Master Plan and as part of the City's five year master plan, a scientific survey of park, recreation,
and open space needs was conducted from a sample of randomly selected citizens in Euless. From this
valuable information, a list of priorities was identified. A new Outdoor Aquatic Center was identified as a top
priority.
PROJECT DESCRIPTION:
The project consists of the construction of an outdoor family aquatic center which will include various play
components such as a leisure pool, slides, aqua play features, shade structures, a bath house, and all the
necessary filtration systems to support the aquatic features. The project also involves redevelopments/
improvements to the entire site such as relocating the tennis courts and the construction of various trails, a
group pavilion, an amphitheater, multi -use sport courts, additional picnic stations with grills, a nature area, a
botanical garden, and public art display(s).
PROJECT SCHEDULE:
JUSTIFICATION:
The City population is sufficient to support an outdoor family aquatic center. The City's existing aquatic facilities
have aged and maintaining the pools and support facilities has been an ongoing issue and concern. The
expenses necessary to maintain and operate the pools each season continue to increase, far exceeding the
revenue generated by the pools. Continuing in repair mode is no longer possible at the Wilshire and South
Euless Pools and a long-term plan is necessary. Given the fact that two of the neighborhood pools are over
thirty years old and the cost to renovate, repair, or replace them is estimated at over one million dollars each, it
is recommended that the city concentrate its efforts and resources toward the family aquatic facility to serve the
citizens of Euless. Project approval requires revision of the master planning of Midway Park. The FLC project
eliminates the current ball fields and requires the relocation of the the existing tennis courts, which will be
replaced with the necessary support facilities to serve the project such as parking, lighting, landscaping, and
recreational amenities such as pavilions, picnic stations, open space, sand volleyball court(s), and trails.
,.N
318
MR
PROJECT TITLE: FIRE TRAINING CENTER & TOWER
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Construction
Personnel: Full Time
Architect 8%
Part Time
Survey & Testing Fees
Total Salary
Engineering
Purchase of Services $2,200
Instruments & Apparatus
Materials & Supplies $5,800
Contingency
Utilities
Insurance $1,000
Subtotal: $9,000
PM & Minor Repairs
Unscheduled Maintenance
Renewal & Replacement
Pest Control
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
$3,000
$3,250
$5,500
$294
$12,044
$21,044 Total Estimated Capital Cost
1l
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
$1,575,000
$126,000
$8,000
$15, 750
$15,750
$52,500
$1,793,0001
25%
0%
0%
0%
0%
323
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: May 07,2007
Submitted By: KYLE MCADAMS Date Completed:
Project Title: ANIMAL SHELTER-EXPANSION/RENOVATION
Project Type: CONSTRUCTION Sub -Type: REMODEL/EXPANSION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the City's five year master plan and is the fourth of six proposed projects.
PROJECT DESCRIPTION:
The project consists of the expansion of the current animal shelter facility to better accommodate visitors,
adoptions and animal services. The addition of ten (10) enclosed dog runs, six (6) quarantine runs, an adoption
room, additional room for cat containment and an area for animal washing. Office space expansion will be
included in the renovation as well as updates to the public / employee restrooms.
PROJECT SCHEDULE:
JUSTIFICATION:
324
PROJECT TITLE: ANIMAL SHELTER-EXPANSION/RENOVATION
NET EFFECTS ON OPERATING AND
AAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Insurance
Subtotal:
PM& Minor Repairs
Unscheduled Maintenance
Renewal & Replacement
Pest Control
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Construction
Architect 8%
Survey & Testing Fees
Engineering
$1,000 HVAC Units
$2,500 Office Furniture
Instruments & Apparatus
$400 Kitchen Appliances
Data & Telephone
Alarm & Security Service
$3,900 Contingency
Landscaping
$5,200 Irrigation
$5,100
$16,800
$575
$27,675
$31,575 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
XX Specifications %
Construction %
$550,006
$44,000
$8,200
$4, 500
$21,500
$6,500
$3,300
$3,300
$9,100
$3,700
$30,000
$5,500
$3,300
$692,900
25%
0%
0%
0%
0%
325
City of Euless
Capital Project Request
Jepartment: FLEET & FACILITIES OPERATIONS Date Prepared: May 07,2007
Submitted Bv: KYLE MCADAMS nnfa Cmmnlnfarl-
Project Title: DEVELOPMENT/ENGINEERING BUILDING
Project Type: BUILDING Sub -Type: REMODEL/EXPANSION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the City's five year master plan and is the third of six proposed projects.
PROJECT DESCRIPTION:
The development and engineering building received a major remodel in 1996 with renovation of the building's
interior. But due to limited funding at that time, certain elements could not be justified as part of the remodel.
This upgrade will allow for construction of a new entrance facade to match the other campus structures. Security
issues pertaining to controlled access will be addressed as well as renovation of the Fuller Room into a
functional conference area. Public restroom facilities will be relocated to meet ADA/Texas Accessibility
Standards, the interior will be upgraded, and new carpet will be installed throughout the facility.
PROJECT SCHEDULE:
JUSTIFICATION:
326
PROJECT TITLE: DEVELOPMENT/ENGINEERING BUILDING
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$775,000
Personnel: Full Time
Architect 8%
$62,000
Part Time
Survey & Testing Fees
$2,800
Total Salary
Interior Upgrades (Paint & Carpet)
$92,000
Purchase of Services
$2,000
Furniture
$26,500
Materials & Supplies
$3,500
Fixtures
$21,500
Utilities
Instruments & Apparatus
$1,300
Insurance
$750
Data & Telephone
$2,750
Alarm & Security Services
$2,750
Window Frame Repairs
$21,000
Subtotal:
$6,250
Sprinkler System
$94,000
Maintenance Costs
Interior & Exterior Signage
$5,500
Janitorial Service/Pest Control
$2,000
HVAC Units
$52,000
PM & Minor Repairs
$9,100
Unscheduled Maintenance
$11,250
Renewal & Replacement
$25,000
Subtotal:
$47,350
Total Estimated Annual Cost
$53,600
Total Estimated Capital Cost
$1,159,100
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
250 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
XX
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
327
X_�
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 30,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: BLESSING BRANCH PARK IMPROVEMENTS
Project Type: PARKLAND Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a continuation of the overall trails expansion and general park improvements as identified in the
Parks Master Plan.
PROJECT DESCRIPTION:
Blessing Branch Park is a 7.3 acre linear park located on the east side of Main Street across from Midway Park.
Currently, the park has only one swing set. This project includes construction of a trail connection from Main
Street to the west and Fuller -Wiser to the east. Additionally, the project includes a new playground, picnic pad
(s) with grill(s), and some type of shade shelter/pavilion/gazebo. This area currently gets a high volume of foot
traffic. Constructing a trail in this linear greenbelt would not only provide safe, paved access for the residents
east of Main Street to Midway Park, Midway Park Elementary, and to Trinity High School, but also help create a
renewed sense of quality of life for the residents in that area by enhancing the recreational amenities available.
PROJECT SCHEDULE:
JUSTIFICATION:
The number one request from our citizens as it relates to trails, based on the responses to the survey as
identified in the Parks Master Plan, was to construct trail connections between existing and/or future park
developments. This project not only satisfies that request, but also provides trail connections to neighborhoods,
schools, between major thoroughfares, and potentially to future commercial developments to the southeast.
""IN
328
PROJECT TITLE: BLESSING BRANCH PARK IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance XX
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
TOTAL ESTIMATED CAPITAL COST:
Approximately 28,000 square feet of
4"x8' concrete trail @ $6 square foot $168,000
$0
Playground/Border $30,000
$0
Picnic pads w/grills $10,000
Shade shelter/pavilion/gazebo $30,000
Trail Lighting $20,000
$0
Playground chips $5,400
Contingency 10% $11,640
$0
$0
$0
$0 Total Estimated Capital Cost $275,040
CURRENT STATUS:
Conceptual Design % 00
Preliminary Design % 0%
Final Plans % 00
Specifications % 0%
Construction % 0%
ADDITIONAL COMMENTS:
The proposed method of finance is EDC Fund Balance.
329
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 29,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PARKING LOT IMPROVEMENTS
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the feasibility study was the need to provide additional parking at Softball World to accommodate
the overflow during certain league and tournament events.
PROJECT DESCRIPTION:
The project allows for an additional 24 head -in parking spaces on the east of the existing parking lot and 9
additional head -in parking spaces behind the red field along with additional netting to allow for a substantial
amount of additional parking.
PROJECT SCHEDULE:
JUSTIFICATION:
This project helps satisfy the need for additional parking during certain league and tournament events and
allows staff the opportunity to create a recreational area that would include picnic areas, outdoor grills, picnic
tables, horseshoe pit, etc. in the unimproved area on the east end of the facility.
bo
'-t
330
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PARKING LOT IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
6" thick concrete paving for an
additional 33 parking spaces
at $1,500 each $49,500
160'x40' and 250'x40' of Dupont
Nylon barrier netting $27,600
Four post flat carports to cover
20 parking spaces behind red field
20 spaces @ $675 per space $13,500
Contingency 10% $9,050
Subtotal:
Total Estimated Annual Cost
Total Estimated Capital Cost
$99,650
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Other
XX
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
331
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 05,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: SOUTH EULESS WATER FEATURE
Project Type: FACILITY Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan calls for the renovation of the South Euless Pool. This aquatic facility has not
received any major renovations since it opened in 1972. This request will probably be revised and/or withdrawn
upon completion of the family aquatic facility.
PROJECT DESCRIPTION:
Recommendations made in both the adopted Parks Master Plan and the Swimming Pool Audit addressed major
renovations that were needed at South Euless Pool. The estimated cost for these renovations was
approximately $1.3 million. Because of limited space as well as parking, this project will need to be carefully
thought through and a decision will need to be made to either spend the money to renovate this existing facility
or use the funds toward the construction of a family aquatic facility.
PROJECT SCHEDULE:
JUSTIFICATION:
This has been documented in both the Swimming Pool Audit and the adopted Parks Master Plan.
,.�
.-IN
332
PROJECT TITLE: SOUTH EULESS WATER FEATURE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
I�
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
333
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 05,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: WILSHIRE PARK WATER FEATURE
Project Type: FACILITY Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan calls for the renovation of Wilshire Pool. This aquatic facility has not received
any major renovations since it opened in 1972. This request will most probably be revised and/or withdrawn
upon completion of the family aquatic facility.
PROJECT DESCRIPTION:
Recommendations made in both the adopted Parks Master Plan and the Swimming Pool Audit addressed major
renovations that were needed at Wilshire Pool. The estimated cost for these renovations was approximately
$1.3 million. Because of limited space as well as parking, this project will need to be carefully thought through
and a decision will need to be made to either spend the money to renovate this existing facility or use the funds
toward the construction of a family aquatic facility.
PROJECT SCHEDULE:
JUSTIFICATION:
Documented in both the Swimming Pool Audit and the adopted Parks Master Plan.
'-1
334
PROJECT TITLE: WILSHIRE PARK WATER FEATURE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
M—
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
335
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: July 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX IMPROVEMENTS
Project Type: OTHER Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Based on the information gathered from the Texas Star Sports Complex Feasibility Study, this project is to make
the necessary renovations to this facility to develop it into a multi -use facility that accommodates the Parks at
Texas Star Baseball League and tournament play, additional programming for adult softball, and a girl's fast
pitch softball league and tournament play.
PROJECT DESCRIPTION:
This project makes the necessary renovations to the existing fields at Softball World to convert what is now a
dedicated adult softball facility into a multi -use facility, joined with the Parks at Texas Star to be able to
accommodate softball (adult and girl's fast pitch), and boys baseball (recreational and select), and to convert an
aging facility into a state-of-the-art sports complex which also includes creating an improved area at the Parks at
Texas Star for much -needed practice fields.
PROJECT SCHEDULE:
JUSTIFICATION:
It is important that staff remain committed to the vision the City Council has promoted for over ten years, of
positioning the Texas Star Sports Complex as a premier facility that serves the athletic needs of the City as well
as a facility that spurs economic opportunities. This project enables staff to program the Texas Star Sports
Complex as a multi -use facility that accommodates the Parks at Texas Star Baseball League and tournament
play, additional programming for adult softball, a girl's fast pitch softball league, and tournament play.
W
336
:.-.
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Costs- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
337
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 12,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL CONNECTION -SOUTH EULESS
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the adopted Parks Master Plan is the need for additional trail connections from neighborhoods to
parks.
PROJECT DESCRIPTION:
There is as very high interest in trails and trail connectivity as identified in the scientific survey in the adopted
Parks Master Plan. Eighty-eight percent of those participating in the survey identified the need for trail
connections between neighborhoods and parks. Additionally, sixty-eight percent identified the need for trail
connectivity to schools as a top priority. This project would allow for safe access to South Euless Park from
adjacent neighborhoods as well as South Euless Elementary from the adjacent neighborhood to the south.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trail system is a valuable asset to the community as
it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The continued development and maintenance of the
trails system received a great deal of support from the citizens as indicated in the responses to the scientific
survey and has also been supported by past updates to the Parks Master Plan.
,.*N
338
PROJECT TITLE: TRAIL CONNECTION -SOUTH EULESS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
0A
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
339
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: February 19,2009
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX -SOFTBALL WORLD TURF
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This request is identified in the Parks Master Plan as well as in the feasibility study as a needed renovation to
improve the playability of the fields as well as to meet the expectations of today's players and bring the quality of
the fields up to the same standards of the other facilities within the Texas Star Sports Complex.
PROJECT DESCRIPTION:
This project is to remove existing sod, laser level outfields, prepare soil, fertilization, and planting of
approximately 28,600 square yards of Tifway 419 Bermuda grass in the outfields.
PROJECT SCHEDULE:
JUSTIFICATION:
Originally constructed in 1982, Softball World has carved out a unique niche in the softball arena as "the place
to play" competitive softball. Twice recognized as the Softball Complex of the year, Softball World is recognized
for creating a premier softball experience for both the player and spectator. Many renovations have taken place
at this facility over the past several years, keeping focused on the vision of offering a premier product as a
member of the Texas Star Sports Complex. This request is a continuation of the needed renovations to bring
the facility up to the standards expected by the users, staff and citizens of Euless.
340
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX -SOFTBALL WORLD TURF
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 00
Specifications % 00
Construction % 0%
341
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL LIGHTING -PHASE II
Project Type: FIXTURES Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment section of the adopted Parks Master Plan is the addition of trail lighting in
various parks where trails are located. This request is for the second phase of a project dedicated to satisfying
that need.
PROJECT DESCRIPTION:
This project continues the installation of trail lighting along the Trails of Euless similar to what was installed
along the trail through Midway Park. Parks that have been identified as needing trail lighting are: Trailwood
Park. The Preserve at McCormick Park, The Villages of Bear Creek Park, and Heritage Park. Not all of the
parks identified are included in this phase, but rather in future phases of an overall Trail Lighting project.
PROJECT SCHEDULE:
JUSTIFICATION:
Trails in the area have become popular and lighting trails could extend hours of usage as well as provide for
increased visibility/security for remote trail areas.
..,
342
PROJECT TITLE: TRAIL LIGHTING -PHASE II
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 00
Specifications % 0%
a
Construction %
343
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 01,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX -PARKS AT TEXAS STAR, PHASE IV
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project was identified in the adopted Park's Master Plan as a high priority.
PROJECT DESCRIPTION:
This project includes the design and construction of additional parking, restroom facilities and an additional
concession stand at the Parks at Texas Star that would serve the growing number of participants in youth
soccer as well as the growing number of participants in t-ball, coach -pitch, and 10U baseball.
PROJECT SCHEDULE:
JUSTIFICATION:
The success of the Parks at Texas Star Baseball League, as well as increased participation in youth soccer and
hockey, has emphasized the need for additional parking. Since the completion of Phase III improvements at the
Parks at Texas Star, the facility has been severely under served in parking, restroom facilities, and concessions.
Due to the large volume of foot traffic throughout the facility, the parking situation has become a safety concern.
This project addresses current concerns of the parents of the participants by alleviating: parking issues; the lack
of restrooms near the t-ball, coach -pitch, soccer, and 10U baseball fields; and the need for additional
concessions.
"1
344
PROJECT TITLE: TRAIL ENHANCEMENTS -VILLAGES OF BEAR CREEK
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
�11
XX
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
347
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 12,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title. TRAIL ENHANCEMENTS- PHASE I
Project Type: TRAILS Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment and Identification section of the adopted Parks Master Plan are a number of
trail related improvements.
PROJECT DESCRIPTION:
This project consists of the first phase of implementation of park improvements identified in the adopted Parks
Master Plan which includes additional water fountains, additional benches, construction of shaded seating areas
along the trail, additional and/or installation of new exercise equipment along the trails, picnic stations, and
construction of additional pedestrian bridges in high water areas. Also identified is the need to address various
areas along the trail that need to be converted from unpaved to paved trails.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The continued development and maintenance of our
trails system received a great deal of support from the citizens as indicated in the responses to the Scientific
Survey and has also been supported by past updates to the Parks Master Plan.
348
L
PROJECT TITLE: TRAIL ENHANCEMENTS- PHASE I
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
XX Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
349
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title. TRAIL ENHANCEMENTS- PHASE II
Project Type: TRAILS Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This enhancement was identified in the Needs Assessment and Identification section of the adopted Parks
Master Plan are a number of trail related improvements.
PROJECT DESCRIPTION:
This project is phase 11 of the trail enhancements that continues implementation of park Improvements identified
in the adopted Parks Master Plan which includes additional water fountains, additional benches, construction of
shaded seating areas along the trail, additional and/or installation of new exercise equipment along the trails,
picnic stations, and construction of additional pedestrian bridges in high water areas. Also identified is the need
to address various areas along the trail that need to be converted from unpaved to paved trails.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The continued development and maintenance of our
trails system received a great deal of support from the citizens as indicated in the responses to the scientific
survey and has also been supported by past updates to the Parks Master Plan.
W
'-1
350
PROJECT TITLE: TRAIL ENHANCEMENTS- PHASE II
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
351
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title. TRAILWOOD PARK IMPROVEMENTS
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a continuation of the overall park improvement plan as identified in the Parks Master Plan.
PROJECT DESCRIPTION:
Trailwood Park is an eleven acre site that currently has a playground and a half -mile hike/bike trail. This project
includes the installation of a new pavilion, a parking lot, a non -paved nature trail on the east end of the park,
upgrade the playground to meet ADA standards, park lighting, new park signs, benches along the trail, and trail
lighting. The project scope also addresses the erosion problems along the retaining wall on the back side of the
homes facing the trail.
PROJECT SCHEDULE:
JUSTIFICATION:
As identified in the adopted Parks Master Plan, the municipal park is the foundation of any solid parks and
recreational system. The City of Euless parks and recreation system provides the residents and visitors with
significant personal, social, environmental and economic benefits. The revitalization efforts that the Euless City
Council has focused on over the years has increased the sense of community pride. This proposed project will
continue those efforts by creating an area that will serve both the passive and active leisure needs of the
residents in the vicinity.
352
PROJECT TITLE: TRAILWOOD PARK IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined XX
ADDITIONAL COMMENTS:
L
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
353
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 12,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: COMMUNITY CENTER FOR SOUTH EULESS
Project Type: LAND/FACILITY Sub -Type: IMPROVEMENTS
Project Code. Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the adopted Parks Master Plan is the need for an additional recreation center to serve the citizens in
South Euless.
PROJECT DESCRIPTION:
Constructing a community recreation center in south Euless would satisfy a demand that was clearly identified in
the scientific survey of the adopted Parks Master Plan. Presently, the citizens living in south Euless must travel
across major thoroughfares in order to participate in any recreational activities and/or programs that necessitate
an indoor setting or that are programmed currently at the Midway Recreation Center.
PROJECT SCHEDULE:
JUSTIFICATION:
Current membership at the Midway Recreation Center would substantiate the claim that the residents in south
Euless will not travel north to participate in recreational activities. A computer -generated report proved in 2007
that of the 2,576 members, 1,892 of them lived in the 76039 zip code as compared to 684 in the 76040 zip code.
354
PROJECT TITLE: COMMUNITY CENTER FOR SOUTH EULESS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Detertmined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
355
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 12,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: EMERGENCY CALL BOXES
Project Type: AMENITY Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment and Identification section of the adopted Parks Master Plan is the
installation of emergency call boxes in various parks within the park system.
PROJECT DESCRIPTION:
As the population grows and participation in park related leisure activities increases, it's important to consider
opportunities to make parks safe for citizens. By installing emergency call boxes in various parks and along the
trail system, citizens would be able to reach first responders immediately should an emergency situation arise
where a person would need critical public safety assistance.
PROJECT SCHEDULE:
JUSTIFICATION:
This project would provide the citizens the ability to call directly to public safety dispatch should an emergency
situation occur in one of the many park facilities located in Euless.
356
PROJECT TITLE: EMERGENCY CALL BOXES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
1"O
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
357
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: KIDDIE CARR PARK IMPROVEMENTS
Project Type: LAND Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project includes the construction or installation of a pavilion, a concrete trail connection to Carr Park, bank
stabilization along Boyd Branch Creek which runs through the park, a playground, park lighting, picnic stations,
an irrigation system, new perimeter fencing, a drinking fountain, benches, and a dedicated parking lot at Kiddie
Carr Park.
PROJECT SCHEDULE:
JUSTIFICATION:
As identified in the adopted Parks Master Plan, the municipal park is the foundation of any solid parks and
recreational system. The City of Euless parks and recreation system provides residents and visitors with
significant personal, social, environmental, and economic benefits. The revitalization efforts that the Euless City
Council has focused on over the years has increased the sense of community pride. Kiddie Carr Park is a 4
acre park located adjacent to Carr Park off Pauline. The current amenities at this park include the Parks
Department's in -ground tree farm, a greenhouse, and an outdoor basketball court. The park is located in a
section of town that needs something to stimulate community pride. The proposed project will continue the City
Council's revitalization efforts by creating an area that will serve both the passive and active leisure needs of the
residents in this area.
358
PROJECT TITLE: KIDDIE CARR PARK IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
359
H E C i T Y 0 F
360
COMPLETED PROJECTS
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
DRAINAGE PROJECTS
DR9901
Sulphur Branch Phase II
08/01/99
$ 123,404
$ 120,128
$ 3,276
DR9902
Windlea & WestCliff
08/01/99
$ 4,396
$ 1,159
$ 3,237
DR9904
Hurricane Creek
04/31/02
$ 257,500
$ 69,906
$ 187,594
DR0302
Flooding Mitigation
Cancelled
$ 250,000
$ -
$ 250,000
DR0303
Aransas Glenn
12/31/04
$ 250000
$ 250,000
$ -
DR0304
Live Oak Drainage
04/15/05
$ 218,000
$ 175,958
$ 42,042
DR0305
Sierra Drive Drainage
04/15/05
$ 40,738
$ 40,738
$ 0
DR0306
Flood Mitigation Plan FEMA
04/15/05
$ 32,000
$ 7,750
$ 24,250
DR0307
Simmons Drainage
04/15/05
$ 22,995
$ 22,995
$ -
DR0301
Fuller Branch Channel Stabilization
05/31/07
$ 279,136
$ 232,176
$ 46,960
DR0401
Channel Stabilization Tributary WFA
05/31/07
$ 437,462
$ 438,070
$ 608
DR0402
Drainage Project Stud
05/31/07
$ 60,000
$ 51,000
1 $ 9,000
DR0601
Little Bear Creek Study Update
04/25/08
$ 50,000
$ 49,000
$ 1,000
DR0602
McCormick Park
04/25/08
$ 250,000
$ 247,925
$ 2,075
Drainage Projects - Prior Years
$ 2.275,631
$ 1,706.805
$ 568,826
Drainage Projects - Current Year
$ -
$ -
$
Sub -Total Drainage Projects
$ 2,275,631
$ 1,706,805
$ 568,826
361
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
STREET PROJECTS
PS9902
Mid Cities Blvd.
05/02/02
$ 1,075,074
$ 963,635
$ 111,439
PS9903
HWY 183 Service Road
Cancelled
$ -
$ -
$
PS9907
West ark Wa -SH10 to SH183
09/30/00
$ 605,542
$ 479,915
$ 125,627
PS9906
Traffic Safe /Si nalization
05/31/08
$ 128,027
$ 127,939
$ 88
PS9908
Si nalization
05/31/06
$ 168,055
$ 168,055
$
PS9910
Sidewalks
06/30/03
$ 200,000
$ 200,000
$
PS9911
Ovefiav Projects
03/30/00
$ 294,687
$ 294,687
$
PS9912
Harwood -Main Intersection
04/30/00
$ 1,126,935
$ 1,077,303
$ 49,632
PS0001
FM 157 S Pipeline to SH10 (UtilitV Relocation
04/30/04
$ 378,207
$ 371,318
$ 6,889
PS0003
Glade from Heritage to SH121
04/30/04
$ 1,866,612
$ 1,866,612
$
PS0004
Glade Rd East - SH121 to Champagne
04/30/04
$ 1,210 014
$ 1,162,009
$ 48,005
PS0201
Gateway Blvd - Southem Portion
04/30/04
$ 510,000
$ 473,817
$ 36,183
PS0301
Mid Cities Roadway Illumination
04/15/05
$ 160,000
$ 148,115
$ 11,885
PS0302
Driftwood Pipeline Traffic Signal
04/15/05
$ 100,000
$ 68,665
$ 31,335
PS0303
Aransas/Harwood Traffic Signal
04/15/05
$ 120,000
$ 89,118
$ 30,882
PSO401
West Pipeline - Raider to City Limits
05/31/06
$ 223,000
$ 104,859
$ 118,141
PSO402
South Pipeline Road Bride
04/30/05
$ 28,208
$ 28,208
$
PSO403
Raider Dr-SH10 to South Pipeline
05/31/06
$ 330,000
$ 293,435
$ 36,565
PSO404
South Pipeline Road Overlay
05/31/08
$ 114,750
$ 85,062
$ 29,688
PS0501
Ross Avenue/S.Main 300' W
05/31 /06
$ 95,688
$ 95,638
1 $ 50
PS0502
Industrial Signal Timing
05/31/06
$ 50,000
$ 50,000
1 $
PS0503
Oveda -Harwood 157/Main
05/31/06
$ 137,000
$ 119,816
$ 17,184
PS0604
Oveda-S.Main, SH10/S.PI eline
05/31/06
$ 137,000
$ 140,211
$ 3,211
PS0601
Oveda -East Midway
05/31/07
$ 83,000
$ 73,550
$ 9,450
PS0602
Overlay -Midway, N Main,/FM157
05/31/07
$ 105,000
$ 67,632
$ 37,368
PS0603
Overlay -Fuller Wiser, Midway/Harwood
05/31/07
$ 40,000
$ 28,695
$ 11,305
PS0701
Overlay -Dickey Drive
05/31/08
$ 122,200
$ 48,435
$ 73,765
PS0702
Overlay -East Hui"
05/31/08
$ 89,000
$ 64,895
$ 24,105
PS0703
Overly -Huntin ton Drive
05/31/08
$ 69,500
$ 42,884
$ 26,616
PS0706 lGateway
Blvd Screening Wall
05/31/08
$ 135,800
$ 138,862
$ 3,062
Street Projects - Prior Years
$ 9.703.299
$ 8,873,369
$ 829,930
PS0002
West Pipeline Road-Raider/H 10
12/01/08
$ 6,082,621
$ 6,081,392
$ 1,229
PS0704
Disability Access Stud
05/31/09
$ 30,000
$ 13,950
$ 16,050
PS0705
Signal Gateway Blvd @ Glade
10/28/08
$ 98,000
$ 98,000
$
PS0801
Overlay -North Main/Cullum Drive
12/31/08
$ 290,000
$ 211,130
$ 78,870
PS9905
Traffic Studies
05/30/09
$ 27,286
$ 27,197
$ 89
Street Projects - Current Year
$ 6,527,907
$ 6,431,669
$ 96,238
Sub -Total Street Projects
$ 16,231,206 1
$ 15,305,038 1
$ 926,168
362
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs
--Budget
WASTEWATER PROJECTS
WW9901
CDBG B/98-UC-48-0001/B95-22-50
08/19/00
$ 150,000
$ 72,927
$ 77,073
WW9902
Impact Fee Stud
09/30/99
$ 13,000
$ 12,238
$ 762
WW9903
Misc Sewer Rehab FY99
09/30/99
$ 50,000
$ 12,987
$ 37,013
WW9904
Hydraulic Analsis
06/30/00
$ 27,000
$ 27,000
$
WW0001
CDBG B/99-UC-48-0001
09/30/01
$ 150,000
$ 121,682
$ 28,318
WW0003
TRADebt Pa ment
05/31/01
$ 822,037
$ 822,037
$
WW0101
CDBG B00-UC480001-2250
02/20/02
$ 251,485
$ 247,790
$ 3,695
WWO102
Manhole Rehab. Program
03/31/03
$ 250,000
$ 184,520
$ 65,480
WW0201
CDBG - B01-UC-48-0001-22-50
03/31/03
$ 237,086
$ 172,948
$ 64,138
WWO103
Line replacement-S. Pi eline,Heather-Vine
04/15/05
$ 489,759
$ 464,504
$ 25,255
WW0202
Line Replacement -Dunawa
02/28/05
$ 140,000
$ 139,955
$ 45
WW0203
Line Replacement - E. Alexander
02/28/05
$ 20000
$ 20,000
$
WW0204
Line Replacement - Paula Lane
02/28/05
$ 79000
$ 79,000
$
WW0205
Line Replacement - MidwayPark
04/30/05
$ 366000
$ 318,149
$ 47851
WW0301
CDBG B02-UC-48-0001-22-50
07/26/05
$ 271454
$ 1
WWO303
Line Replacement, Canyon Ride
08/31/06
19
$ 173,516
$ 22,684
WW0304
Line Replacement, Sagebrush
08/31/06
$ 160,900
$ 136,470
$ 24,430
WW0305
Line Replacement, Short
08/31/06
$ 251400
$ 219932
$ 31,468
WW0306
Line Replacement, E. Fuller
08/31/06
$ 231,372
$ 180,089
$ 51,283
WW0401
CDBG B03-UC-48-0001-22-50
04/30/05
$ 217,000
$ 161,170
$ 55,830
WW0402
Line Replacement, Carr Park/SH10
05/31/08
$ 588,000
$ 528,302
$ 59,698
WW0403
Line Replacement, Ector Drive
05/31/OB
$ 373,000
$ 328,309
$ 44,691
WW0501
Line Replacement, Pebble Creek
08/31/06
$ 172,600
$ 145,655
$ 26,945
WW0302
Inflow & Infiltration
Cancelled
$ 200,000
$ -
$ 200,000
WW0601
Line Replace ent, Cedar Hills Estate
05/31/08
$ 319,000
$ 200,201
$ 118,799
WW0602
Line Re lacement, Ector Drive
05/31/081
$ 425,000
$ 285,758
$ 139,242
WW0603
Little Bear Creek Collection Line
05/31/08
$ 575,000
$ 464,293
$ 110,707
WW0604 ILine
Replacement, CDBG-Oakwood Terrace
05/31/071
$ 293,723
$ 232,274
$ 61,449
WastewaterPro"ects - Prior Years
1 $ 7,320,017
$ 6,023,160
$ 1,296,857
WW0701
Line Replacement, McCormick & Co her
02/05/09
$ 243,000
$ 194,254
$ 48,746
WW0703
Line Replacement, Jean Lane
02/05/09
$ 111,000
$ 70,603
$ 40,397
WW0704
Line Replacement, W. Fuller
02/05/09
$ 132,000
$ 82,708
$ 49,292
Wastewater Projects- Current Year
$ 486,000
$ 347,565
$ 138,435
Sub -Total Wastewater Projects
$ 7,606,017 1
$ 6,370,725 1
$ 1,435,292
363
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WATER PROJECTS
WT9901
Meter Change Out Program
10/30/99
$ 101,917
$ 98,365
$ 3,552
WT9903
Master Plan
08/30/99
$ 42,000
$ 5,445
$ 36,555
WT9904
Well Repairs
09/30/99
$ 66,921
$ 66,921
$ -
WT9905
Misc Water Rehab
06/30/00
$ 50,000
$ 43,749
$ 6,251
WT9906
Hwy 10Water Line
01/30/00
$ 150,000
$ 138,883
$ 11,117
WT9907
Impact Fee Stud
09/30/991
$ 13,000
$ 12,238
$ 762
WT9908
Mid Cities Blvd. 12" Line
04/30/04
$ 342,080
$ 313,354
$ 28,726
WT9909
2MG Water Tank
03/31/03
$ 2,430,881
$ 2,289,571
$ 141,310
WT9910
Water Line for Elevated Tank
05/31/02
$ 1,608 386
$ 1,201 698
$ 406,688
WT9911
Water Distribution - Master Plan
09/30/99
$ 25,600
$ 24,000
$ 1,600
WT0002
Emerqency Repair - H10
11/30/99
$ 15,450
$ 14,214
$ 1,236
WT0003
Waterline Replacement - Aransas
06/30/01
$ 12,057
$ 7,089
$ 4,968
WT0004
Water Line Milam - Ector/Midwa
06/301001
$ 18,248
$ 13,743
$ 4,505
WT0005
Waterline Re lacement - Milam- Denton/Mid
04/30/021
$ 26,988
$ 26,988
$ -
WT0006
Central Drive Water Mains
03/31/00
$ 92,814
$ 90,742
$ 2,072
WTO102
SCADA Upgrade
04/09/01
$ 93,400
$ 93,400
$ -
WT0103
Fire Hydrant Replacement Program
03/31/03
$ 50,000
$ 49.626
$ 374
WT0401
Line Replacement, West Pipeline Main
05/31/06
$ 1,215,663
$ 1,215,663
$ -
WT0403
Waterline Replacement - Fairlawn Court
Cancelled
$ 35,000
$
$ 35,000
WT0404
Waterline Replacement - Atkerson Lane
Cancelled
$ 1134,000
$
$ 104,000
WT0405
Line Replacement, West Ash Lane
08/31/06
$ 30,000
$ 11 626
$ 18 374
WT0406
Line Replacement, Westport/Newport/Asbury
08/31/06
$ 67,000
$ 9,866
$ 57,134
WT0501
System Security Upgrade
05/31/08
$ 40,000
$ 28,319
$ 11,681
WT0502
FY'2005 CDBG
08/31/06
$ 69,300
$ 29,549
$ 39,751
WT0503
Line Replacement, S. Atkerson Lane
08/31/06
$ 79,000
$ 51,294
$ 27,706
Wi0504
Line Replacement, Blanco Drive
08/31/06
$ 112,620
$ 112,620
$ -
WT0505
Line Replacement, Henslee
08/31/06
$ 183,000
$ 123,859
$ 59,141
WT0506
Line Replacement, Vemon/Slau hter
08/31/06
$ 161,000
$ 113,052
$ 47,948
WT0601
Wir Sys Security Perimeter Fence Upgrade
05/31/08
$ 75,000
$ 49,567
$ 25,433
WT0602
Line Replacement, Cannon Drive
05/31/08
$ 250,000
1 $ 223,055
$ 26,945
WT0701
Line Replace entCanyon Ride
05/31/08
$ 116.000
$ 78,136
$ 37,864
WT0702
1CDBG FY07 - 32nd Oakwood Terrace
05/31/08
$ 334,481
$ 296,223
$ 38,258
WT9902
ITank Painting
05/31/07
$ 1,317,763
$ 957 542
$ 360,221
Water Projects - Prior Years
$ 9,329,569
$ 7,790,397
$ 1,539,172
WT0402 I
Water & Wastewater Impact Fee Update
05/31/09
$ 30.000
$ 17,729
$ 12,271
WT0801
Line Replacement, Signet/Mesa
05/31/09
$ 255,000
$ 218,663
$ 36,337
WT0802
CDBG-33rd Oakwood Terrace -Simmons
12/31/08
$ 451,639
$ 384,173
$ 67,466
Water Projects- Current Year
$ 736,639
$ 620,565
$ 116,074
Sub -Total Water Projects
$ 10,066,208
1 $ 8,410,962
$ 1,655,246
W
364
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
OTHER PROJECTS
AC9901
Athletic Complex Phase II
06/30/02
$ 123,654
$ 76,047
$ 48,607
ACO202
Athletic Complex Phase 111
05/31/06
$ 1,252 221
$ 1,251,915
$ 306
ED0102
Bell Ranch Terrace
Cancelled
$ 200,000
$ -
$ 200,000
FM0101
Building D
09/30/02
$ 930,610
$ 930,608
$ 2
FM0209
Midway Recreation Upgrade
06/30/02
$ 557,125
$ 557,125
$
FM0308
Building A Remodel
05/31/07
$ 1,663,238
$ 1,651,325
$ 11,913
FM0309
Fire Station #3
05/31/07
$ 2,286 798
$ 2,286,229
$ 569
FM0601
Public Works Facility
05/31/08
$ 2,210,956
$ 2,213,507
$ 2,551
PR9901
Hike/Bike Trail
04/30/05
$ 237,714
$ 237,714
$
PR9902
Senior Citizen Remodel
04/30/05
$ 16130
$ 16,130
$
PR9903-
PR9918
Various EDC Park Projects
09/30/06
$ 259,566
$ 248,891
$ 10,675
PR9922
Teas Remodel
11/30/01
$ 430,000
$ 455,885
$ 25,885
PR9927
Park Improvements - Texas Star
09/30/01
$ 1,036,500
$ 1,025,298
$ 11,202
PR0015
Purchase of Dallas Stars Center
05/31/00
$ 10,327,978
$ 10,327,978
$
PR0016
Wilshire Park Improvements
06/30/02
$ 150,000
$ 149,926
$ 74
PR0110
Sloe Protection/Screening Wall
03/31/03
$ 1 275 203
$ 1,273,923
$ 1,280
PR0302
Bob Eden Parkin
04/30/05
$ 75,000
$ 74,854
$ 146
PR0303
Youth Ballpark
04/30/05
$ 600,000
$ 600,000
$
PR0407
Parking Improvements, Midway
Cancelled
$ 11,000
$ -
$ 11,000
PR0408
Parking Improvements, S. Euless Park
05/31/06
$ 55,000
$ 20,991
$ 34,009
PR0409
Parking Improvements, Simmons
07/29/04
$ 6,960
$ 6,960
$
PR0410
Parking Improvements, Villages Bear Creek
07/29/04
$ 33,666
$ 33,666
$
PR0411
Preserve at McCormick Park
05/31/06
$ 1,168,427
$ 1,168,427
$
PR0412
Splash Pool
05/31/06
$ 125,000
$ 124,477
$ 523
SS9901
Fire Station II
03/30/00
$ 49,688
$ 49,688
$
SS9902
Library Books
08/15/00
$ 3,302
$ 3,302
$
SS9919
Fire Station #3 - Structural Repairs
03/30/00
$ 30,000
$ 17,344
$ 12,656
SS0010
Former Fire Station #2
06130/021
$ 599,600
$ 595,257
$ 4,343
SS0113
Park Building
06/30/02
$ 1,492,400
$ 1492,100
$ 300
Other Projects - Prior Years
$ 27,207,736
$ 26,888,567
$ 319,169
FMO504
Building "B" Remodel
05/31/09
$ 1,322,490
$ 1,315,697
$ 6,793
FMO801
TX Star Golf Course & Conference Ctr Expand
05/31/09
$ 3,630,079
$ 3,630,079
$
FM0802
Senior Citizen Center Design
cancelled
$ 250,000
$ -
$ 250,000
FMO803
Midway Recreation Improvements
03/31/09
$ 293500
$ 75,976
$ 217,524
FMO804
Library -Shell Expansion
12/31/08
$ 307,034
$ 305,664
$ 1,370
PR0602
Mid -Cities Landscaping
05/31/09
$ 40,000
$ 33,199
$ 6,801
PR0719
Midway Park Trail
05/31/09
$ 210.000
$ 190,473
$ 19,527
OtherPro"ects- Current Year 1
$ 6,053,103
$ 5,551088 1
$ 502,015
Sub -Total Other Projects
$ 33,260,839
$ 32,439,655
$ 821,184
TOTAL COMPLETED PROJECTS
$ 69,639,901
$ 64,233,185 1
$ 5,406,716
365
T H E C I T Y O F
."*N
366
COMPLETED PROJECTS
DRAINAGE PROJECTS
ON
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
DRAINAGE PROJECTS
DR9901
Sulphur Branch Phase II
08/01/99
$ 123,404
$ 120,128
$ 3 276
DR9902
Windlea & WestCliff
08/01/99
$ 4,396
$ 1,159
$ 3,237
DR9904
Hurricane Creek
04/31/02
$ 257,500
$ 69,906
$ 187,594
DR0302
Flooding Mitigation
Cancelled
$ 250,000
$
$ 250,000
DR0303
Aransas @ Glenn
12/31/04
$ 250,000
$ 250,000
$
DR0304
Live Oak Drainage
04/15/05
$ 218,000
$ 175,958
$ 42,042
DR0305
Sierra Drive Drainage
04/15/05
$ 40,738
$ 40,738
$ 0
DR0306
Flood Mitigation Plan FEMA
04/15/05
$ 32,000
$ 7,750
$ 24,250
DR0307
Simmons Drainage
04/15/05
$ 22,995
$ 22,995
$
DR0301
Fuller Branch Channel Stabilization
05/31/07
$ 279,136
$ 232,176
$ 46,960
DR0401
Channel Stabilization Tributary WFA
05/31/07
$ 437,462
$ 438,070
$ 608
DR0402 I
Drainage Project Study
0,000
$ 51,000
$ 9,000
DR0601
Little Bear Creek Study Update
04/25/08
$ 50,000
$ 49,000
$ 1,000
DR0602
McCormick Park
04/25/08
$ 250,000
$ 247,925
$ 2,075
Drainage Projects - Prior Years
$ 2,275,631
$ 1,706,805
$ 568,826
Drainage Projects - Current Year
$ -
$ -
$
Total Drainage Projects
$ 2,275,631
$ 1,706,805
$ 568,826
367
'"1
T H E I T Y
sl
''1
368
COMPLETED PROJECTS
STREETS PROJECTS
M
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
STREET PROJECTS
PS9902
Mid Cities Blvd.
05/02/02
$ 1 075 074
$ 963,635
$ 111 439
PS9903
HWY 183 Service Road
Cancelled
$
$
$
PS9907
West ark Wa -SH10 to SH183
09/30/00
$ 605 542
$ 479,915
$ 125,627
PS9906
Traffic Safe /Si nalization
05/31(08
$ 128,027
$ 127,939
$ 88
PS9908
Si nalization
05/31/06
$ 168.055
$ 168,055
$
PS9910
Sidewalks
06/30/031
$ 200,000
$ 200,000
$
PS9911
Ovedav Projects
03/30/00
$ 294,687
$ 294,687
$
PS9912
Harwood -Main Intersection
04/30/00
$ 1,126,935
$ 1,077,303
$ 49632
PS0001
FM 157 S Pipeline to SH10(Utility Relocation
04/30/04
$ 378,207
$ 371,318
$ 6,889
PS0003
Glade from Heritage to SH121
04/30/04
$ 1,866,612
$ 1,866 612
$
PS0004
Glade Rd East - SH121 to Champagne
04/30/04
$ 1,210,014
$ 1,162,009
$ 48,005
PS0201
Gatewa Blvd - Southern Portion
04/30/04
$ 510.000
$ 473,817
$ 36,183
PS0301
Mid Cities Roadway Illumination
04/15/05
$ 160,000
$ 148,115
$ 11,885
PS0302
Driftwood Pipeline Traffic Signal
04/15/05
$ 100,000
$ 68,665
$ 31,335
PS0303
Aransas/Harwood Traffic Signal
04/15/05
$ 120,000
$ 89,118
$ 30,882
PSO401
West Pipeline - Raider to CityLimits
05/31/06
$ 223,000
$ 104,859
$ 118,141
PSO402
South Pipeline Road Bride
04/30/05
$ 28,208
$ 28,208
$
PSO403
Raider Dr-SH10 to South Pipeline
05/31/06
$ 330 000
$ 293,435
$ 36,565
PSO404
South Pipeline Road Overlay
05/31/08
$ 114,750
$ 85,062
$ 29,688
PS0501
Ross Avenue/S.Main 300' W
05/31/06
$ 95,688
$ 95,638
$ 50
PS0502
Industrial Signal Timing
05/31/06
$ 50,000
$ 50,000
$
PS0503
Oveda -Harwood 157/Main
05/31/06
$ 137,000
$ 119,816
$ 17,184
PS0604
Overla-S.Main, SH10/S.Pi eline
05/31/06
$ 137,000
$ 140,211
$ (3,211)
PS0601
Overlay -East Midway
05/31/07
$ 83,000
$ 73 550
$ 9,450
PS0602
Oveda -Midwa N Main /FM157
05/31/07
$ 105,000
$ 67,632
$ 37,368
PS0603
Overlay -Fuller Wiser Midway/Harwood
05/31/07
$ 40000
$ 28,695
$ 11,305
PS0701
Overlay -Dickey Drive
05/31/08
$ 122,200
$ 48,435
$ 73,765
PS0702
Oveda -East Huitt
05/31/08
$ 89,000
$ 64,895
$ 24,105
PS0703
Oveda-Huntin ton Drive
05/31/08
$ 69,500
$ 42,884
$ 26,616
PS0706
Gateway Blvd Screening Wall
05/31/08
$ 135,800
$ 138,862
$ 3,062
Street Projects - Prior Years 1$
9,703,299
$ 8,873,369
$ 829,930
PS0002
West Pipeline Road-Raider/Hwy 10
12/01/08
$ 6,082,621
$ 6,081,392
$ 1,229
PS0704
Disability Access Stud
05/31/09
$ 30,000
$ 13,950
$ 16,050
PS0705
Signal Gateway Blvd Glade
10/28/08
$ 98,000
$ 98,000
$
PS0801
Overlay -North Main/Cullum Drive
12/31/08
$ 290,000
$ 211,130
$ 78,870
PS9905
Traffic Studies
05/30/09
$ 27,286
$ 27,197
$ 89
Street Projects - Current Year
$ 6,527,907
$ 6,431,669
$ 96,238
Total Street Projects
$ 16,231,206
$ 15,305,038
$ 926,168
369
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 7/26/1999
Submitted By: RON YOUNG Date Completed: 12/01/2008
Project Title: WEST PIPELINE - RAIDER/SH10
Project Type: STREET Sub -Type: CONSTRUCTION
Project No.: PS0002 Priority: A
COUNCIL AUTHORIZATION:
April 14, 1998 - Authorized bond election for the purpose of funding construction.
January 1, 2000 - Authorized the City Manager to execute an engineering contract for design.
June 12, 2001 - Declared intent to reimburse expenditures from proceeds of future debt.
December 14, 2004 - Declared the necessity to acquire land for reconstruction improvements.
March 08, 2005 - Authorized the City Manager to execute an amendment with Teague Nall and Perkins,
Inc. for engineering design in the amount of $89,875.
April 12, 2005 - Authorized the City Manager to amend the contract with Teague Nall and Perkins, Inc. for
design widening the road to design gas pipeline adjustments in an additional amount $77,600.
November 8, 2005-Authorized the City Manager to enter into construction contract with JLB Contracting,
LP, in the amount of $5,823,149.64. Also, authorized execution of Change Order No. 1 for credit to the City
in the amount of $249,971 and authorized contingency of $250,000 for potential change orders.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project was approved as part of the 1998 bond election along with Main Street and Harwood Road.
PROJECT DESCRIPTION:
Project consists of widening West Pipeline Road from two lanes to a proposed four lane boulevard street.
This project will encompass the section of West Pipeline from SH10 to Raider Drive. The project will also
include modifications to the intersection of Pipeline Road and SH10.
PROJECT SCHEDULE:
Award construction contract: November 2005
Construction complete: December 2006
SH10/Pipeline Road Intersection: December 2008
JUSTIFICATION:
The street exists in an expanded condition on either end of this proposed widening. The traffic greatly
overloads the existing roadway.
bo
370
PROJECT TITLE: WEST PIPELINE - RAIr)FRiSH1n
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
I Personnel
Total Salary
Purchase of Services
Materials & Supplies
Utilities
DOn Mf-r 44- 00f%f% l7
TOTAL ESTIMATED CAPITAL COST:
Engineering
Full Time ROW Appraisal / Geotech Svc
Part Time ROW Acquisition
$0 Utility Relocation & Gas Line
Construction
Contingency/Signs & Markings
Issuance Cost
Contract Labor
Subtotal. -
Maintenance Costs
Subtotal:
Other
Average Annual Debt Service
Total Estimated Annual Cost
Total Estimated Capital Cost
$0
FUNDING SOURCES:
Interest Income
City of Bedford Contributions
Street CIP Fund Balance
(Transfer from PS0004)
$0
(Transfer from PS9904)
GO Bond Proceeds FY01
GO Bond Proceeds
Certificates of Obligations
$279,745
Transfer from FB9907
Transfer to FB9907
$279,745
Total Funding
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (- +)
Engineering
$422,243
$422,243
$0
Utility Relocation
$107,177
$107,177
$0
Contract Labor
$46,925
$46,925
$0
Appraisal Services
$15,800
$15,800
$0
Right of Way
$299,061
$299,061
$0
Construction
$4,705,705
$4,705,705
$0
Issuance Cost
$55,000
$55,000
$0
Contingency
$351,574
$349,694
$1,880
Geotech Svcs
$70,136
$70,136
$0
Signs/Markings
$9,000
$9,651
($651)
TOTAL PROJECT
082,621 $6,081,392 $1,229
$422,243
$85,936
$299, 033
$107,177
$4, 706, 077
$360,230
$55,000
$46,925
$6,082,621 I
$980,351
$220,000
$298,180
$299,321
$86,779
$3,200,000
$1,102, 000
$473,690
($577,700)
$6,082,621
% EXPENDED
100%
100%
100%
100%
100%
100%
100%
99%
100%
107%
1
371
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 4/13/2006
Submitted By: RON YOUNG Date Completed: 5/31/2009
Project Title: DISABILITY ACCESSIBILITY STUDY
Project Type: STREET Sub -Type: SIDEWALK
Project No.: PS0704 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Sidewalks are a part of the City of Euless street system.
PROJECT DESCRIPTION:
This will be the initial assessment for Americans with Disabilities Act compliance within the City. A multi-
year effort is anticipated. The initial effort will focus on City facilities and arterial thoroughfares.
PROJECT SCHEDULE:
Begin Study: February 2007
Completed: May 2009
JUSTIFICATION:
All City facilities including buildings and streets must be Americans with Disabilities Act compliant per
federal and state regulations.
372
L
L
PROJECT TITLE: DISABILITY ACCESSIBILITY STUDY PROJECT #: PS0704
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$30,000
Personnel: Full Time
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$30,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from FB9907
$30,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$30,000
d
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (- +) % EXPENDED
Engineering
$30,000
$13,950 $16,050
47%
TOTAL PROJECT
$30,000
$13,950 $16,050
47%
373
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 5/10/2005
Submitted By: RON YOUNG Date Completed: 10/28/2008
Project Title: TRAFFIC SIGNAL - GATEWAY BLVD AT GLADE RD
Project Type: STREET Sub -Type: SIGNALIZATION
Project No.: PS0705 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic Signals are located at the intersections of arterial and collector thoroughfares identified in the City of
Euless Master Thoroughfare Plan adopted in 1999. This signal will be needed in conjunction with the Glade
Road widening project.
PROJECT DESCRIPTION:
This project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection and signal controller for the intersection of Gateway Boulevard and
Glade Road.
PROJECT SCHEDULE:
Design complete: March 2007
Installation complete: April 2008
JUSTIFICATION:
The extension of north Gateway Boulevard to Glade Road in conjunction with development on the Wilkins
property will generate anticipated traffic volumes that will warrant a traffic signal. Signal warrant studies will
be performed to determine the need and justification for the signal installation.
'"1
374
YKVJtU 1 11 I Lt: I KH1-NU NUNAL-UA 1 tVVHY bLVU (a) ULHUt F'KVJtU 1 ;F: F'JU/U*
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $20,000
Personnel: Full Time Traffic Signals $78,000
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost $98,000
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from FB9907 $98,000
Subtotal: $0
Total Estimated Annual Cost $0 ITotal Funding $98,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Traffic Signals $98,000 $98,000 $0 100%
'AL PROJECT $98,000 $98,000 $0 100%I
375
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 4/30/2007
Submitted By: RON YOUNG Date Completed: 9/30/2008
Project Title: NORTH MAIN STREET
Project Type: STREET Sub -Type: OVERLAY
Project No.: PS0801 Priority: A
COUNCIL AUTHORIZATION:
December 11, 2007: Approved an interlocal agreement with Tarrant County for overlay improvements on
North Main Street from Harwood Road to Little Bear Creek and Cullum Drive from SH10 to Iron Bridge Place
in the amount of $290,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
North Main Street is a minor arterial street and is one of the two streets that the City of Euless plans to
overlay in a cooperative project with Tarrant County.
PROJECT DESCRIPTION:
This project consists of edge milling, asphalt overlay, and restriping from Harwood Road to Little Bear Creek
Drive approximately 5300 linear feet. It will also include adjusting manholes and water valve covers.
PROJECT SCHEDULE:
Construction Complete: September 2008
JUSTIFICATION:
The existing asphalt pavement is deteriorating and is becoming a maintenance problem. The asphalt overlay
will provide an improved riding surface, will extend the life of the roadway and will enhance the appearance of
this street.
,,*N
376
PROJECT TITLE: NORTH MAIN STREET OVERLAY
PROJECT #: PS0801
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$290,000
Personnel: Full Time
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$290,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from FB9907
$290,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$290,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET
EXPENDED BUDGET (- +) % EXPENDED
Overlay
$290,000
$211,130 $78,870
73%
TOTAL PROJECT $290,000 $211,130 $78,870 73%I
377
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 7/17/1999
Submitted By: RON YOUNG Date Completed: 5/30/2009
Project Title: TRAFFIC STUDIES
Project Type: STREET Sub -Type: STUDY
Project No.: PS9905 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
These funds are utilized with projects PS9906 Traffic Safety and PS9908 Signalization to address traffic
needs throughout the City.
PROJECT DESCRIPTION:
Staff utilizes these funds to investigate concerns related to traffic movements and volumes.
PROJECT SCHEDULE:
JUSTIFICATION:
The change of traffic patterns and the increased volume of traffic are causing problems on the existing
streets. Funds are needed to compensate consultants in the investigation process.
378
PROJECT TITLE: TRAFFIC STUDIES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
I Subtotal:
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Engineering Services
Other Professional Services
Traffic Signals
TOTAL PROJECT
PROJECT #: PS9905
TOTAL ESTIMATED CAPITAL COST:
Engineering
Other Professional Services
Traffic Signals
$0
(Total Estimated Capital Cost
$0 FUNDING SOURCE:
Street Fund Balance
W/S Operating Fund
Transfer from PS9906
$0
$01Total Funding
CURRENT STATUS
$26, 352
$164
$770
$7,198
$20,000
$88
$27,286 1
OVERIUNDER
BUDGET
EXPENDED
BUDGET (-+)
% EXPENDED
$26,352
$26,351
$1
100%
$164
$76
$88
46%
$770
$770
$0
100%
197 $89 100%1
379
91-111
COMPLETED PROJECTS
WASTEWATER PROJECTS
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WASTEWATER PROJECTS
W W9901
CDBG B/98-UC-48-0001 /B95-22-50
08/19/00
$ 150,000
$ 72,927
$ 77,073
WW9902
Impact Fee Study
09/30/99
$ 13,000
$ 12,238
$ 762
W W9903
Misc Sewer Rehab FY99
09/30/99
$ 50,000
$ 12,987
$ 37,013
W W9904
Hydraulic Analysis
06/30/00
$ 27,000
$ 27,000
$
WW0001
CDBG B/99-UC-48-0001
09/30/01
$ 150,000
$ 121,682
$ 28,318
WW0003
TRA Debt Payment
05/31/01
$ 822,037
$ 822,037
$
WW0101
CDBG B00-UC480001-2250
02/20/02
$ 251,485
$ 247,790
$ 3,695
WWO102
Manhole Rehab. Program
03/31/03
$ 250,000
$ 184,520
$ 65,480
WW0201
CDBG -B0I-UC-48-0001-22-50
03/31/03
$ 237,086
$ 172,948
$ 64,138
WWO103
Line replacement-S. Pi eline,Heather-Vine
04/15/05
$ 489,759
$ 464,504
$ 25,255
WW0202
Line Replacement -Dunaway
02/28/05
$ 140,000
$ 139,955
$ 45
WW0203
Line Replacement - E. Alexander
02/28/05
$ 20,000
$ 20,000
$
WW0204
Line Replacement - Paula Lane
02/28/05
$ 79,000
$ 79,000
$
WW0205
Line Replacement - Midway Park
04/30/05
$ 366,000
$ 318,149
$ 47,851
WW0301
CDBG B02-UC-48-0001-22-50
07/26/05
$ 271,455
$ 271,454
$ 1
WW0303
Line Replacement, Canyon Ride
08/31/06
$ 196,200
$ 173,516
$ 22,684
WW0304
Line Replacement, Sagebrush
08/31/06
$ 160,900
$ 136,470
$ 24,430
WW0305
Line Replacement, Short
08/31/06
$ 251400
$ 219932
$ 31468
WW0306
Line Replacement, E. Fuller
08/31/06
$ 231,372
$ 180,089
$ 51,283
WW0401
CDBGB03-UC-48-0001-22-50
04/30/05
$ 217,000
$ 161170
$ 55830
WWO402
Line Replacement, Carr Park/SH10
05/31/08
$ 588,000
$ 528,302
$ 59,698
WW0403
Line Replacement, Ector Drive
05/31/08
$ 373,000
$ 328,309
$ 44,691
WW0501
Line Replacement, Pebble Creek
08/31/06
$ 172,600
$ 145,655
$ 26,945
WW0302
Inflow & Infiltration
Cancelled
$ 200,000
$ -
$ 200,000
WW0601
Line Replacement, Cedar Hills Estate
05/31/08
$ 319,000
$ 200,201
$ 118,799
WW0602
Line Replacement, Ector Drive
05/31/08
$ 425,000
$ 285,758
$ 139,242
WW0603
Little Bear Creek Collection Line
05/31/08
$ 575,000
$ 464,293
$ 110,707
WW0604
Line Replacement, CDBG-Oakwood Terrace
05/31/07
$ 293,723
$ 232,274
$ 61,449
WastewaterPro'ects - Prior Years
$ 7,320,017
$ 6,023,160
$ 1,296,857
WW0701
Line Replacement, McCormick & Co her
02/05/09
$ 243,000
$ 194,254
$ 48,746
WW0703
Line Replacement, Jean Lane
02/05/09
$ 111,000
$ 70,603
$ 40,397
WW0704
Line Replacement, W. Fuller
02/05/09
$ 132,000
$ 82,708
$ 49,292
Wastewater Projects. Current Year
$ 486,000
$ 347,565
$ 138,435
Total Wastewater Projects
$ 7,806,017
$ 6,370,725
$ 1,435,292
381
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 07/10/2000
Submitted By: RON YOUNG Date Completed: 02/05/2009
Project Title: LINE REPLACEMENT, MCCORMICK & COPHER
Type: WASTEWATER Sub -Type: SEWER MAINS
Project No.: WW0701 Priority: A
COUNCIL AUTHORIZATION:
November 14, 2006: Authorized the city manager to execute an Engineering design contract with Elliot and
Hughes, Inc. not to exceed $89,322 for projects WW0701, WW0702, WW0703, and WW0704.
June 24, 2008: Award Bid #004-08 to Horseshoe Construction Company, Inc. for replacement sanitary
sewer mains in portions of the Fuller, Arnett, Oakwood Terrace East, Twin Creek Estates and Oak Crest
Estates Additions, in the amount of $559,933 for projects WW0701, WW0702, WW0703, and WW0704.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Systematic replacement of sanitary sewer lines in drainage basin areas using a worst first approach.
PROJECT DESCRIPTION:
Replace sanitary sewer line servicing the south side of McCormick and Copher Courts and Creekside Drive
from Hilton Drive to Evergreen.
PROJECT SCHEDULE:
Construction complete: January 2009
JUSTIFICATION:
Many sanitary sewer lines throughout the city are 40 plus years old. Most of the lines are clay tile and are
subject to ground movement, grease, root infestation and deterioration due to hydrogen sulfide gas and other
chemicals. Many are not functional at an acceptable level and are often inundated with infiltration and inflow.
Systematic replacement will prevent a mandatory wide spread replacement.
/N
''\
382
Mw
ROJECT TITLE- I INF RFPI ACFMFNT MCCORMICK P. rnPHFR PRC)JFCT #k 1AMR17n1
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$23,000
Personnel: Full Time
Sewer Line Replacement
$220,000
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$243,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from W/S FB9901
$190,000
Transfer from WW0702
$53,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$243,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (- +)
% EXPENDED
Engineering
$28,380
$29,214 ($834)
103%
Sewer Mains
$214,620
$165,040 $49,580
77%
TOTAL PROJECT $243,000 $194,254 $48,746 80%I
41;X,
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 7/10/2000
Submitted By: RON YOUNG Date Completed: 2/05/2009
Project Title: LINE REPLACEMENT, JEAN LANE
Type: WASTEWATER Sub -Type:
Project No.: WW0703 Priority: A
COUNCIL AUTHORIZATION:
November 14, 2006: Authorized the city manager to execute an Engineering design contract with Elliot and
Hughes, Inc. not to exceed $89,322 for projects WW0701, WW0702, WW0703, and WW0704.
June 24, 2008: Award Bid #004-08 to Horseshoe Construction Company, Inc. for replacement sanitary
sewer mains in portions of the Fuller, Arnett, Oakwood Terrace East, Twin Creek Estates and Oak Crest
Estates Additions, in the amount of $559,933 for projects WW0701, WW0702, WW0703, and WW0704.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Systematic replacement of sanitary sewer lines in drainage basin areas using a worst first approach.
PROJECT DESCRIPTION:
Replace sanitary sewer lines on the north side of Jean Lane from Henslee Drive to S. Main. Also, on the
east side of Henslee Drive from Jefflyn Court to Jean Lane and on Gayle Court.
PROJECT SCHEDULE:
Construction Complete: January, 2009
JUSTIFICATION:
Many sanitary sewer lines throughout the city are 40 plus years old. Most of the lines are clay tile and are
subject to ground movement, grease, root infestation and deterioration due to hydrogen sulfide gas and other
chemicals. Systematic replacement will prevent a mandatory wide spread replacement.
384
PROJECT TITLE: LINE REPLACEMENT - JEAN LANE
PROJECT #: WW0703
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$16,000
Personnel: Full Time
Sewer Line Replacement
$95,000
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$111,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from W/S Operating Fund
$130,000
Transfer to FB9901
($19,000)
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$111,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (-+) % EXPENDED
Engineering
$16,000
$9,569 $6,431
60%
Sewer Mains
$95,000
$61,034 $33,966
64%
TOTAL PROJECT
$111,000
$70,603 $40,397
64%
385
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 7/10/2000
Submitted By: RON YOUNG Date Completed: 2/05/2009
Project Title: LINE REPLACEMENT, WEST FULLER
Type: WASTEWATER Sub -Type:
Project No.: WW0704 Priority: A
COUNCIL AUTHORIZATION:
November 14, 2006: Authorized the city manager to execute an Engineering design contract with Elliot and
Hughes, Inc. not to exceed $89,322 for projects WW0701, WW0702, WW0703, and WW0704.
June 24, 2008: Award Bid #004-08 to Horseshoe Construction Company, Inc. for replacement sanitary
sewer mains in portions of the Fuller, Arnett, Oakwood Terrace East, Twin Creek Estates and Oak Crest
Estates Additions, in the amount of $559,933 for projects WW0701, WW0702, WW0703, and WW0704.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Systematic replacement of sanitary sewer lines in drainage basin areas using a worst first approach.
PROJECT DESCRIPTION:
Replace sanitary sewer lines on West Fuller Drive between Byers Street and North Main.
PROJECT SCHEDULE:
Design contract: November 2006
Plans complete: December 2007
Construction bid: June 2008
Begin construction: August 2008
Construction complete: January 2009
JUSTIFICATION:
Many sanitary sewer lines throughout the city are 40 plus years old. Most of the lines are clay tile and are
subject to ground movement, grease, root infestation and deterioration due to hydrogen sulfide gas and other
chemicals. Systematic replacement will prevent a mandatory wide spread replacement.
'"\
bo
0.1
PROJECT TITLE: LINE REPLACEMENT, WEST FULLER PROJECT #: WW0704
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$12,000
Personnel: Full Time
Sewer Line Replacement
$120,000
Part Time
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$132,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from W/S Operating Fund
$105,000
Transfer from FB9901
$27,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$132,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (-+) % EXPENDED
Engineering
$14,268
$14,735 ($467)
103%
Sewer Mains
$117,732
$67,973 $49,759
58%
TOTAL PROJECT
$132,000
$82,708 $49,292
63%
387
'1-N
388
COMPLETED PROJECTS
WATER PROJECTS
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WATER PROJECTS
WT9901
Meter Chan a Out Program
10/30/99
$ 101,917
$ 98,365
$ 3,552
WT9903
Master Plan
08/30/99
$ 42,000
$ 5,445
$ 36,555
WT9904
Well Repairs
09/30/99
$ 66,921
$ 66,921
$
WT9905
Misc Water Rehab
06/30/00
$ 50,000
$ 43,749
$ 6,251
WT9906
Hwy 10 Water Line
01/30/00
$ 150,000
$ 138,883
$ 11,117
WT9907
Impact Fee Stud
09/30/99
$ 13,000
$ 12,238
$ 762
WT9908
Mid Cities Blvd. 12" Line
04/30/04
$ 342,080
$ 313,354
$ 28,726
WT9909
2MG Water Tank
03/31/03
$ 2,430,881
$ 2,289,571
$ 141,310
WT9910
Water Line for Elevated Tank
05/31/02
$ 1,608,386
$ 1,201,698
$ 406,688
WT9911
Water Distribution - Master Plan
09/30/99
$ 25,600
$ 24,000
$ 1,600
WT0002
EmerqencV Repair - H10
11/30/99
$ 15,450
$ 14,214
$ 1,236
WT0003
Waterline Replacement - Aransas
06/30/01
$ 12,057
$ 7,089
$ 4,968
WT0004
Water Line Milam - Ector/Midwa
06/30/00
$ 18,248
$ 13,743
$ 4,505
V T0005
Waterline Replacement - Milam- Denton/Mid
04/30/02
$ 26,988
$ 26,988
$
WT0006
Central Drive Water Mains
03/31/00
$ 92,814
$ 90,742
$ 2,072
WT0102
SCADA Upgrade
04/09/01
$ 93,400
$ 93,400
$
WT0103
Fire Hydrant Replacement Program
03/31/03
$ 50,000
$ 49,626
$ 374
WT0401
Line Replacement, West Pipeline Main
05/31/06
$ 1,215,663
$ 1,215,663
$
WT0403
Waterline Replacement - Fairlawn Court
Cancelled
$ 35,000
$ -
$ 35,000
WT0404
Waterline Replacement - Atkerson Lane
Cancelled
$ 104,000
$ -
$ 104,000
WT0405
Line Replacement, West Ash Lane
08/31/06
$ 30,000
$ 11,626
$ 18,374
WTO406
Line Replacement, West ort/New ort/Asbu
08/31/06
$ 67,000
$ 9,866
$ 57,134
WT0501
System Security Upgrade
05/31/08
$ 40,000
$ 28.319
$ 11,681
WT0502
FY'2005 CDBG
08/31/06
$ 69,300
$ 29,549
$ 39,751
WT0503
Line Replacement, S. Atkerson Lane
08/31/06
$ 79,000
$ 51,294
$ 27,706
WT0504
Line Replacement, Blanco Drive
08/31/06
$ 112,620
$ 112,620
$
WT0505
Line Replacement, Henslee
08/31/06
$ 183,000
$ 123,859
$ 59,141
W70506
Line Replacement, Vemon/Slau hter
08/31/06
$ 161,000
$ 113,052
$ 47,948
WT0601
Wtr Sys Securi Perimeter Fence Upgrade
05/31/08
$ 75,000
$ 49,567
$ 25,433
Wf0602
Line Replacement, Cannon Drive
05/31/08
$ 250,000
$ 223,055
$ 26,945
W70701 ILine
Replacement, Canyon Ride
05/31/08
$ 116,000
$ 78,136
$ 37,864
WT0702 1CDBG
FY07 - 32nd Oakwood Terrace
05/31/08
$ 334,481
$ 296,223
$ 38,258
WT9902 ITank
Painting
05/31/07
$ 1,317 763
$ 957,542
$ 360,221
WaterPro"ects - Prior Years
$ 9,329,569
$ 7,790,397
$ 1,539,172
WT0402 I
Water & Wastewater Impact Fee Update
05/31/09
$ 30,000
$ 17,729
$ 12,271
WT0801
Line Replacement, Signet/Mesa
05/31/09
$ 255,000
$ 218,663
$ 36,337
WT0802 I
CDBG-33rd Oakwood Terrace -Simmons
12/31/08
$ 451,639
$ 384,173
$ 67,466
Water Projects- Current Year
$ 736,639
$ 620,565
$ 116,074
Total Water Projects
$ 10,066,208
$ 8,410,962
$ 1,655,246
389
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 3/28/2003
Submitted By: RON YOUNG Date Completed: 5/31/2009
Project Title: WATER AND WASTEWATER IMPACT FEE UPDATE
Project Type: WATER Sub -Type:
Project No.: WT0402 Priority: A
COUNCIL AUTHORIZATION:
September 25, 2007: Approved resolution #07-1263 affirming that the water and wastewater impact fees for
developments in the City of Euless shall continue in effect as adopted by ordinance number 1364.
September 23, 2008: Authorized the city mayor to certify to the Attorney General that the impact fees of
the City of Euless comply with state law.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Water and Wastewater Impact Fee charges were instituted by the City of Euless in 1990 in accordance with
applicable State law to generate revenue for funding of capital improvements attributable to new development.
Impact fees are related to the items identified by the Capital Improvements Plan and the Water and
Wastewater System Master Plan.
PROJECT DESCRIPTION:
The project will consist of reviewing the City's Land Use Assumptions, the costs of future infrastructure
needs system capacity available for future growth, the cost of Trinity River Authority service and update the
Capital Improvements Plan. Calculations based on State dictated requirements will be made to determine
the maximum allowable impact fees. The City Council will determine what percentage of the maximum
allowable fees to impose.
PROJECT SCHEDULE:
Updated impact fees: August 2004
Certified compliance of state law: September 2008
Anticipate next study: August 2012
JUSTIFICATION:
Legislation passed in 2001 provided an automatic five year extension to the 2002 Update. The Impact Fees
were updated in 2007 as required. The next Impact Fee update will be in 2012 barring any new legislative
action.
"*N
01%N
390
ROJECT TITLE: WATER & WASTEWATER IMPACT FEE UPDATE PROJECT #: WT0402
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Engineering
TOTAL PROJECT
TOTAL ESTIMATED CAPITAL COST:
Engineering $30,000
$0
Total Estimated Capital Cost
$0 FUNDING SOURCE:
Transfers from. -
Water Impact Fees
Wastewater Impact Fees
$0
$0 Total Funding
CURRENT STATUS
$30
$15,000
$15,000
$30,000 1
OVER/UNDER
BUDGET EXPENDED BUDGET (-+) % EXPENDED
$30,000 $17,729 $12,271 59%
$30,000 $17,729 $12,271 59%1
391
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 4/30/2007
Submitted By: RON YOUNG Date Completed: 5/31/2009
Project Title: LINE REPLACEMENTS, SIGNET/MESA
Project Type: WATER Sub -Type: MAINS
Project No.: WT0801 Priority: A
COUNCIL AUTHORIZATION:
March 10, 2009: Award bid and authorize city manager to execute a contract with McMahon Contracting,
L.P., to replace water mains in an amount of $192,615.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water Master Plan.
PROJECT DESCRIPTION:
Replace four inch cast iron water main with eight inch poly vinyl chloride water main along Mesa from
Marlene to Northcliff and along Signet from Canyon Ridge to Westcliff.
PROJECT SCHEDULE:
Award Engineering Design: June 2008
Award Construction Contract: March 2009
Begin construction: April 2009
Construction complete: May 2009
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains
provide inadequate flow of water.
.�\
''1
392
rMVJM1. 1 11 I LC: LINE Kt=VLAUt=MEN 16, blUNE I /MESA PROJECT #: WT0801
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $30,000
Personnel: Full Time Construction $225,000
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Total Estimated Capital Cost
$255,000
Subtotal:
$0
FUNDING SOURCE:
Maintenance Costs
Transfer from:
W/S CIP Fund Balance
$255,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$255,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (- +)
% EXPENDED
Engineering
$30,000
$23,858 $6,142
80%
Water Mains
$225,000
$194,805 $30,195
87%
TOTAL PROJECT $255,000 $218,663 $36,337 86%I
393
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 04/04/2007
Submitted By: RON YOUNG Date Completed: 12/16/2008
Project Title: CDBG-33rd OAKWOOD TERRACE (SIMMONS DRIVE)
Project Type: WATER Sub -Type: MAINS
Project No.: WT0802 Priority: A
COUNCIL AUTHORIZATION:
February 27, 2007: Approved 33rd CDBG project for fiscal year 2007-08 to replace water main lines in the
Oakwood Terrace West Addition. The estimated total cost is $451,639 and the CDBG funding is anticipated
to be $334,029 with the remaining balance of $117,610 to be funded by the City.
March 26, 2008: Recommended to Tarrant County to award construction contract to Bristow Contracting,
LLC for the replacement of a water line main in the Oakwood Terrace West Add'n in the amount of $323,311,
of which Tarrant County will pay $269,704.80 and the City of Euless will pay $53,606.20 and authorizing an
additional $16,165.80 to cover change orders.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City of Euless Water System Master Plan. This
project is part of the systematic replacement of substandard water mains. This project is part of the 33rd
year Community Development Block Grant program.
PROJECT DESCRIPTION:
Replace the existing 2,800 linear feet of six inch cast iron water main with an eight inch poly vinyl chloride
water main along Simmons Drive from Bayless Drive to Whitener Road and from Whitener Road to South
Pipeline Road.
PROJECT SCHEDULE:
Design complete: January 2008
Begin construction: June 2008
Construction Completed: October 2008
JUSTIFICATION:
Existing water mains are old, deteriorated and substandard in size which provides inadequate water flow and
require more maintenance than newer mains.
394
rr[vJr-%, 1 111 Lc: tutsu-.ssra uAKvvuuu I tKKHct(5IMMUN6) PROJECT #: W10802
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Total Estimated Cost $451,639
Personnel: Full Time
Part Time
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
(Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Sewer Mains
TOTAL PROJECT
Total Estimated Capital Cost $0
$0 FUNDING SOURCE:
Transfer From FB9901 $117,610
CDBG Funding $334,029
$0
$0 1Total Funding $451,639
CURRENT STATUS
OVER/UNDER
BUDGET EXPENDED BUDGET (-+) % EXPENDED
$451,639 $384,173 $67,466 85%
$451,639 $384,173
395
"\
396
I%- COMPLETED PROJECTS
OTHER PROJECTS
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
OTHER PROJECTS
AC9901
Athletic Com lex Phase II
06/30/02
$ 123,654
$ 75,047
$ 48,607
ACO202
Athletic Com lex Phase III
05/31/06
$ 1 252 221
$ 1,251,915
$ 306
ED0102
Bell Ranch Terrace
Cancelled
$ 200.000
$
- $ 200,000
FMO101
Buildin D
09/30/02
$ 930,610
$ 930,608
$ 2
FM0209
Midwa Recreation U rade
06/30/02
$ 557,125
$ 557,125
$
FM0308
Buildin ARemodel
05/31/07
$ 1,663238
$ 1,651,325
$ 11913
FM0309
Fire Station #3
05/31/07
$ 2,286 798
$ 21286,229
$ 569
FM0601
Public Works Facility
05/31/08
$ 2,210,956
$ 2,213,507
$ 2,551
PR9901
Hike/Bike Trail
04/30/05
$ 237,714
$ 237,714
$
PR9902
Senior Citizen Remodel
04/30/05
$ 16,130
$ 16,130
$
PR9903-
PR9918
Various EDC Park Projects
09/30/06
$ 259,566
$ 248,891
$ 10,675
PR9922
Teas Remodel
11/30/01
$ 430,000
$ 455.885
$ 25,885
PR9927
Park Improvements - Texas Star
09/30/01
$ 1,036 500
$ 1,025 298
$ 11,202
PR0015
Purchase of Dallas Stars Center
05/31/00
$ 10,327,978
$ 10,327,978
$
PR0016
Wilshire Park Improvements
06/30/02
$ 150,000
$ 149,926
$ 74
PR0110
Slope Protection/Screenin Wall
03/31/03
$ 1,275,203
$ 1,273,923
$ 1,280
PR0302
Bob Eden Parkin
04/30/05
$ 75,000
$ 74,854
$ 146
PR0303
Youth Ballpark
04/30/05
$ 600 000
$ 600.000
$
PR0407
Parking Improvements, Midway
Cancelled
$ 11 000
$
$ 11.000
PR0408
Parking Improvements, S. Euless Park
05/31/06
$ 55 000
$ 20,991
$ 34.009
PR0409
Parking Improvements, Simmons
07/29/04
$ 6 960
$ 6.960
$
PR0410
Parkinq improvements, Villages Bear Creek
07/29/04
$ 33,666
$ 33 666
$
PR0411
Preserve at McCormick Park
05/31/06
$ 1,168,427
$ 1,168,427
$
PR0412
Splash Pool
05131 /06
$ 125,000
$ 124 477
$ 523
SS9901
Fire Station II
03/30/00
$ 49,688
$ 49,688
$
SS9902
Library Books
08/15/00
$ 3,302
$ 3,302
$
SS9919
Fire Station #3 - Structural Repairs
03/30/00
$ 30,000
$ 17,344
$ 12,656
SS0010
Former Fire Station #2
06/30/02
$ 599,600
$ 595,257
$ 4,343
SS0113 lPark
Building
06/30/02
$ 1,492,400
$ 1,492,100
$ 300
OtherPro"ects - Prior Years
$ 27,207,736
$ 26,888,567
$ 319,169
FM0504
Building "B" Remodel
05/31/09
$ 1,322,490
$ 1,315,697
$ 6,793
FMO801
TX Star Golf Course & Conference Ctr Expand
05/31/09
$ 3,630,079
$ 3,630,079
$
FMO802
Senior Citizen Center Design
cancelled
$ 250,000
$
$ 250,000
FMO803
Midway Recreation Improvements
03/31/09
$ 293,500
$ 75,976
$ 217,524
FM0804
Library -Shell Expansion
12/31/08
$ 307,034
$ 305,664
$ 1,370
PRO602
Mid Cities Landscaping
05/31/09,
$ 40 000
$ 33 199
$ 6 801
PR0719
Midwa Park Trail
05/31/09
$ 210 000
$ 190 473
$ 19 527
OtherPro'ects- Current Year
$ 6,053,103
$ 5,551,088
$ 502,015
Total Other Projects
$ 33.260,839
$ 32.439,655
$ 821,184
397
City of Euless
Capital Project Request
Department: FACILITIES OPERATIONS Date Prepared: 6/27/2000
Submitted By: KYLE MCADAMS Date Completed: 9/30/2006
Project Title: BUILDING "B"-DESIGN & REMODEL
Project Type: BUILDING Sub -Type: DESIGN & REMODEL
Project No.: FM0504 Priority: A
COUNCIL AUTHORIZATION:
January 25, 2005: Byron Folse and Associates contract for architectural services for the renovation of
Building "B" for $74,000.
April 26, 2005: Authorize City Manager to negotiate and execute rental agreement for temporary office
space during renovation of Building "B".
September 27, 2005: Awarded bid #022-05 to Modern Contractors in the amount of $933,500.
March 28, 2006: Approved the purchase of office furniture, cubicles, etc for Building "B" from Tusa Office
Solutions, Inc in the estimated expenditure of $125,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Building "B" is the fifth project of the master plan.
PROJECT DESCRIPTION:
To provide a more efficient work space area, Building "B" will be remodeled to expand the layout for the
following departments: Finance, Water Billing Office, Insurance and Human Resources.
PROJECT SCHEDULE:
Start date: September 2005
Construction complete: September 2006
JUSTIFICATION:
Renovation of Building "B" will provide a more efficient work space area for Finance, Water Department,
Insurance and Human Resource Department offices. Structure will comply to Americans with Disabilities
Act and Texas Accessibility Standards as a result of remodeling.
398
PROJECT TITLE: BUILDING "B" DESIGN & REMODEL PROJECT #: FM0504
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Maintenance Costs
Janitorial Services & Supplies
Pest Control
Subtotal:
Total Estimated Annual Cost
TOTAL ESTIMATED CAPITAL COST:
Architectural Services/Survey $96,506
Construction $936,915
Contingency $15,000
Furniture $122,835
Building Rental $36,000
$0
Moving Expenses $18,334
Asbestos Abatement $23,865
Equipment $17,567
Instr. & Apparatus $25,430
Landscaping $4,156
Owner Equipment $25,882
Total Estimated Capital Cost $1.322.490
$0 IFUNDING SOURCE:
Transfer from Car Rental $1,379,360
$4,000 Transfer to FB9913 ($56,870)
$500
$500
$5,000
$5,000 ITotal Funding
CURRENT STATUS
$1,322,490
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (- +)
% EXPENDED
Architectural Services
$95,711
$95,711
$0
100%
Surveying Service
$795
$795
$0
100%
Building Rental
$36,000
$36,000
$0
100%
Contingency
$15,000
$8,207
$6,793
55%
Moving Expense
$18,334
$18,334
$0
100%
Construction
$936,915
$936,915
$0
100%
Landscaping
$4,156
$4,156
$0
100%
Asbestos Abatement
$23,865
$23,865
$0
100%
Equipment
$17,567
$17,567
$0
100%
Instr. & Apparatus
$25,430
$25,430
$0
100%
Furniture
$122,835
$122,835
$0
100%
Owner Equipment
$25,882
$25,882
$0
100%
TOTAL PROJECT $1,322 490 $1 315 697 $6,793 9
399
City of Euless
Capital Project Request
Department: FLEET & FACILITIES OPERATIONS Date Prepared: 5/7/2007
Submitted By: KYLE MCADAMS Date Completed: 5/31/2009
Project Title: TEXAS STAR GOLF COURSE & CONFERENCE CENTRE EXPANSION
Project Type: CONSTRUCTION Sub -Type: REMODEL/EXPANSION
Project No.: FM0801 Priority: A
COUNCIL AUTHORIZATION:
September 11, 2007: Authorized the city manager to execute a contract for architectural services with
Bryon Folse and Associates for the expansion of Texas Star Conference Center in the amount of $173,277.
February 12, 2008: Awarded Bid No. 003-08 to JC Commercial in the amount of $3,470,777, plus Alternate
No. 1 in the amount of $10,000 and authorized a contingency in the amount of $50,000. Authorized the city
manager to enter into a contract with JC Commercial. Authorized the city manager to execute change Order
No. 1 that will result in a credit to the City in the amount of $532,776.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the city's five year master plan and is the first of six proposed projects.
PROJECT DESCRIPTION:
Expansion of current facility to allow for additional conference room capacity. The current kitchen is grossly
undersized, and expansion will be necessary to accommodate the growth of the conference center. The golf
operations which the pro shop supports does not have the size to support the daily traffic demand. The need
to expand the kitchen and the Treaty Room has a direct impact on being able to expand the pro shop within
the current foot print of the structure. This expansion will allow for a more efficient Golf Club operation for all
operational areas of the facility.
PROJECT SCHEDULE:
Award Design Contract: September 2007
Award Construction Contract: February 2008
Construction Complete: March 2009
JUSTIFICATION:
The Texas Star Golf Course and Conference Centre is an award winning Golf Club. This course operates in
a fashion consistent with a country club. Due to the number of conference centre functions, and the
popularity of Raven's Grill, the facility is in dire need of additional kitchen space. In addition, conference
centre activity continues to grow and this expansion will give the facility the ability to host larger functions.
The additional kitchen space will alleviate some of the pressure on the current kitchen staff and equipment.
These improvements are necessary to compete in today's golf market.
400
N
PROJECT TITLE: TX STAR CONFERENCE CENTRE EXPANSION PROJECT #: FM0801
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST
MAINTENANCE COST (+ OR -) ANNUAL
Construction
$3,098,961
Direct Operating Cost
Architect 8%
$279,154
Personnel: Full Time
Survey & Testing Fees
$6,014
Part Time
Engineering
$7,416
Total Salary
0
Acoustical Consultant
Purchase of Services
$4,000
MEP Additional Work
Materials & Supplies
$5,000
Office Furniture
$32,000
Utilities
Banquet Furniture
$90,000
Insurance
$1,000
Furnishings & Decoratives
$25,000
Total Direct Expenses:
$10,000
Fixtures
$27,000
Audio Visual Equipment
$20,000
Instruments & Apparatus
$15,000
Janitorial Services
$18,000
Kitchen Appliances
Included
PM & Minor Repairs
$12,159
Kitchen Fixtures
Included
Unscheduled Maintenance
$11,766
Data & Telephone
$7,200
Renewal & Replacement
$45,480
Alarm & Security Services
$4,000
Pest Control
$1,000
Contingency
$9,294
Total M&R Costs:
$88,405
Revenue Offset
$9,040
Total Estimated Caoital Cost
$3,630,079
Subtotal: $98,405 FUNDING SOURCE
Car Rental Operating $3,189,350
Transfer from FB9913 $440,729
Total Estimated Annual Cow $98,405 Total Funding $3,630,079
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (-+)
% EXPENDED
Surveying Service
$6,014
$6,013
$1
100%
Architectural Service
$279,154
$279,154
$0
100%
Engineer Service
$7,416
$8,406
($990)
113%
Contingencies
$18,334
$2,231
$16,103
12%
Construction
$3,098,961
$3,079,489
$19,472
99%
Landscaping
Irrigation System
Equipment
$20,000
$23,890
($3,890)
119%
Instr. & Apparatus
$26,200
$26,782
($582)
102%
Furniture
$174,000
$204,114
($30,114)
117%
(TOTAL PROJECT $3,630,079 $3,630,079 $0 100%�
401
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: 5/7/2007
Submitted By: KYLE MCADAMS Date Completed: 3/31/2009
Project Title: SENIOR CITIZENS DESIGN/LAND ACQUISITION
Project Type: DESIGN Sub -Type:
Project No.: FM0802 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the city's five year master plan.
PROJECT DESCRIPTION:
This project includes funding for the design of a new senior citizens center and funding to begin the
acquisition of property upon selection of a site.
PROJECT SCHEDULE:
JUSTIFICATION:
Address the needs of the aging population and the construction of a new Senior Citizens Center allows
Euless to accomplish these needs.
1-,
—\
402
14 .
ROJECT TITLE: SENIOR CITIZENS CENTER nESInN
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Surveying Service
Architectural Service
Engineer Service
Land Purchase
PRn_IF('_T ft- FI1An%Zn )
TOTAL ESTIMATED CAPITAL COST:
Land Purchase (Proposed) $141,500
Architect 8% $96,000
Survey & Testing Fees $7,500
$0 Engineering $5,000
Total Estimated Car
$0 FUNDING SOURCE:
Operating Fund
$0
$0 Total Funding
CURRENT STATUS
Cost x $250,000 1
$250,000 1
$250,000 1
OVER/UNDER
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
$7,500
$7,500
0%
$96,000
$96,000
0%
$5,000
$5,000
0%
$141,500
$141,500
0%
"Funding will be transferred to the Midway Park Family Life Center project, subject to the City Council's
approval of such project.
TOTAL PROJECT $250,000 $0 $250,000 0%
403
City of Euless
Capital Project Request
Department: FLEET AND FACILITIES OPERATIONS Date Prepared: 5/7/2007
Submitted By: KYLE MCADAMS Date Completed: 3/31/2009
Project Title: MIDWAY RECREATION CENTER -BUILDING IMPROVEMENTS
Project Type: CONSTRUCTION Sub -Type: REMODEL/IMPROVEMENTS
Project No.: FM0803 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This improvement project will encompass numerous areas of the facility from cosmetic to building
preservation. The project will call for the reroof of a portion of the structure, replacement of the existing
rubber flooring and exterior repaint. Wallpaper in the hallways will be replaced with an RFP type product for
durability as well as general reconditioning of the bathroom tiles and fixtures. This project will also allow for
the replacement of the parking lot lighting as well as the fixtures surrounding the building.
PROJECT SCHEDULE
Wallpaper/Racquetball Court/Flooring/Restroom Facilities - Completed February 2008
Roof Repairs - Pending
Lighting - Pending
JUSTIFICATION:
Aging facility that is in need of repair.
404
ROJECT TITLE: MIDWAY RECREATION BLDG IMPROVEMENTS PROAFCT #- FftAnRn3
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Insurance
Total Direct Expenses:
Janitorial Services
PM & Minor Repairs
Unscheduled Maintenance
Renewal & Replacement
Pest Control
Total M&R Costs:
(Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Remodel/Improvements
TOTAL ESTIMATED CAPITAL COST:
Roof Replacement
$168,500
Rubberized Flooring
$54,000
Parking Lot & Walk -way Lighting
$50,000
$0
General Carpentry
$10,000
$5,000
Racquet Ball Court Wall Repairs
$11,000
$8,500
1 500
$15,000
Total Estimated Capital Cost
$293,500
$3,000
FUNDING SOURCE:
$13,804
Transfer Operating Fund
293,500
$14,087
$33,504
$80,3951Total Funding
CURRENT STATUS
$293,500 1
OVER/UNDER
BUDGET EXPENDED BUDGET (-+) % EXPENDED
$293,500 $75,976 $217,524 26%
*Funding will be transferred to the Midway Park Family Life Center project, subject to the City Cou
approval of such project.
TOTAL PROJECT $293,500 $75,976 $217,524 26%I
C[op
City of Euless
Capital Project Request
Department: FLEET AND FACILITIES OPERATIONS Date Prepared: 5/7/2007
Submitted By: KYLE MCADAMS Date Completed: 12/31/2008
Project Title: LIBRARY -PARTIAL EXPANSION OF SHELLED AREA
Project Type: CONSTRUCTION Sub -Type: REMODEL/EXPANSION
Project No.: FM0804 Priority: A
COUNCIL AUTHORIZATION:
February 26, 2008: Approved purchase and installation of floor carpeting to Gomez Floor Covering, Inc. in
the amount of $95,187.14
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the city's five year master plan.
PROJECT DESCRIPTION:
Partial expansion into the shelled of the building to allow for additional administration workspace, individual
study rooms, local historical/genealogy area and quiet reading room. This project also includes rehabilitating
the front entrance doors, installation of a oven in the kitchen area, new wallpaper for the conference room,
new carpet in the main library and canopy lighting for the entrance walks.
PROJECT SCHEDULE:
Project start date - January 2008
Project complete - December 2008
JUSTIFICATION:
Patrons have requested the City consider adding additional study rooms. The Historical Preservation
Committee has requested a local historical room to display Euless artifacts and the staff area needs to be
expanded to accommodate the current staffing levels.
406
PROJECT TITLE: LIBRARY -PARTIAL EXPANSION SHELL AREA PROJECT #: FM0804
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Insurance
I Subtotal:
Janitorial Services
PM & Minor Repairs
Unscheduled Maintenance
Renewal & Replacement
Pest Control
Subtotal:
(Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Remodel/Improvements
Equipment
Instr. & Apparatus
Furniture
AL PROJECT
TOTAL ESTIMATED CAPITAL COST:
Construction
$48,534
Architect 8%
$10,000
Office Furniture
$20,000
$0
Furnishings & Decoratives
$10,000
$3,000.00
Fixtures
$10,000
$5,000.00
Instruments & Apparatus
$5,000
Kitchen Appliances
$5,000
$1,500.00
Data & Telephone
$4,000
Automatic Doors
$48,000
Carpet
$96,752
Electrical Work
$8,378
$9,500.00
Misc. Carpentry Work
$2,200
Wallpaper
$17,800
Contingency
$20,000
$1,800.00
Total Estimated Capital Cost
$305,664
$9,598.00
$9, 860.00
$38,270.00
FUNDING SOURCE:
1 100.00
$60,628.00
Transfer from General Fund
$307,034
$70,128.00 (Total Funding
CURRENT STATUS
$307,034 1
OVERIUNDER
BUDGET
EXPENDED
BUDGET (-+)
% EXPENDED
$268,906
$267,658
$1,248
100%
$2,095
$2,095
$0
100%
$5,448
$5,326
$122
98%
$30,585
$30,585
$0
100%
034 $305,664 $1,370 100%�
119YA
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: 4/15/2005
Submitted By: RAY MCDONALD Date Completed: 5/31/2009
Project Title: MID CITIES LANDSCAPING
Project Type: IMPROVEMENTS Sub -Type: LAND BETTERMENTS
Project No.: PR0602 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The parks Master Plan in the approved form includes provision(s)/recommendation(s) to develop open space
and other beautification projects.
PROJECT DESCRIPTION:
Mid Cities Landscape will include a beautification plan for this major road entrance into the city.
PROJECT SCHEDULE:
JUSTIFICATION:
Landscaping of this artery into the city will both beautify the area and could be a catalyst for further future
beautification projects.
408
ROJECT TITLE: MID CITIES LANDSCAPING
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Landscaping
TOTAL PROJECT
PROJECT #.- PR0602
TOTAL ESTIMATED CAPITAL COST:
Landscaping $40,000
$0
Total Estimated Capital Cost
$0 FUNDING SOURCE:
Transfer from Car Rental
$0
$0 Total Funding
CURRENT STATUS
$40,000
$40,000
$40,000 1
OVER/UNDER
BUDGET EXPENDED BUDGET (-+) % EXPENDED
$40,000 $33,199 $6,801 83%
199 $6,801 83%1
409
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: 4/11/2006
Submitted By: RAY McDONALD Date Completed: 5/31/2009
Project Title: MIDWAY PARK TRAIL
Project Type: LAND Sub -Type: IMPROVEMENTS
Project No.: PR0719 Priority: A
COUNCIL AUTHORIZATION:
May 29, 2007: Award bid number 021-07 to Humphrey & Morton Construction Co. in the amount of $165,017
for the construction of trails and bridges.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project will include concrete and/or soft surface trail development at Midway Park. This project includes
the infrastructure improvements as recommended as a high priority in the adopted Parks Master Plan.
PROJECT DESCRIPTION:
Concrete trail varying from eight feet to twelve feet in width with sidewalk connections to existing streets and
new bridges spanning Blessing Branch. Park benches will be provided at random locations with landscaping
provided at the park bench locations. Low intensity, low height lighting will be provided along the Midway
Park Trail. The trail will be approximately .4 miles in length plus the length of associated sidewalks and
bridges to connect Collins Drive and Tarrant Drive and the Midway Recreation Center.
PROJECT SCHEDULE:
Award Bid: May 2007
Construction Complete: June 2007
JUSTIFICATION:
Trail development and enhancement opportunities will be consistent with available land, funding and time
variables. This Master Plan recommendation will be part of a city-wide comprehensive trail enhancement
project. These trails will provide access to the Midway Park Recreation Center, baseball fields, and swimming
pool from nearby residential neighborhoods.
W11
'ROJECT TITLE: MIDWAY PARK TRAIT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
DRn IC!`T fl• OD0710
TOTAL ESTIMATED CAPITAL COST:
Mobilization
$5,000
Excavation
$6,000
Erosion Control
$3,000
$0
Trail
$99,750
Bridges
$90,000
Contingency
$6,250
Total Estimated Capital Cost $210,000
Subtotal: $0 FUNDING SOURCE:
Maintenance Costs Transfer from 1/2 Cent Operating $210,000
Subtotal: $0
Total Estimated Annual Cost $0 Total Funding $210,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Land/Hike & Bike Trails $210,000 $190,473 $19,527 91%
TOTAL PROJECT $210,000 $190,473 $19,527 91%
411
T H E I Y a
x,
412
PROJECT TITLE: MIDWAY PARK FLC PHASE III -INDOOR AQUATICS CONSTRUCTION
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Grading/Utilities/Electrical
Personnel: Full Time Indoor Pool Building
Part Time $0 Furnishings and Equipment
Total Salary $0 Contingency 10%
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$100, 000
$3,000,000
$75,000
$317, 500
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$3,492,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
321
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: May 07,2007
Submitted By: KYLE MCADAMS Date Completed:
Project Title: FIRE TRAINING CENTER & TOWER
Project Type: CONSTRUCTION Sub -Type: NEW CONSTRUCTION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The site will be located in the area surrounded by the Texas Star Sports Complex softball fields and the Parks
Maintenance Facility. The complex will be located on a 236' x 222' concrete slab and will consist of a five story
22' x 33' tower, a two story 22' x 34' training maze room, and a 14' burn room adjacent to the maze room. The
facility must allow room for full maneuvering of fire trucks on all sides of the structure. Since the structure will be
within the Texas Star Sports Complex the area surrounding the training center can be utilized for additional
parking when not in use for training purposes.
PROJECT SCHEDULE:
JUSTIFICATION:
322
PROJECT TITLE: MIDWAY PARK FLC PHASE II -OUTDOOR AQUATICS CONSTI�k,
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
TOTAL ESTIMATED CAPITAL,, '
Construction $4,684,538
Contingency 5% $257,649
$0 Inflation 5% $257,649
$0
$0
$0
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$5,199,836
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
p g
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
°
% 0 --
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
319
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: February 11,2009
Submitted By: RAY MCDONALD Date Completed:
Project Title: MIDWAY PARK FLC PHASE III -INDOOR AQUATICS CONSTRUCTION
Project Type: CONSTRUCTION Sub -Type: INDOOR AQUATIC CENTER
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless has identified, as part of the city's five year master plan, the need for an indoor aquatic
center. Construction of an indoor aquatic center will allow the City to serve the growing population by expanding
services and programs for citizens.
PROJECT DESCRIPTION:
The project consists of the construction of an indoor aquatic center (approximately 8,600 square feet) that
includes a lap / leisure pool, current channel, slide, and therapy pool. This multi -purpose facility would be
attached to the senior center and would serve the senior population, as well as the general public and would be
used for various aquatic programs including aerobics / wellness classes, swim lessons, rehabilitation
opportunities, and would also be used as a rental facility for birthday and private parties.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has for many years recognized the importance of planning for parks, recreation, and open
space based on the needs as expressed by the citizens. In the plan development process for the recent update
to the Parks Master Plan and as part of the City's five year master plan, a scientific survey of park, recreation
and open space needs was conducted from a full sample of randomly selected citizens in Euless. From this
valuable information, a list of priorities was identified. An indoor aquatic center was identified as a high priority
for aquatic facilities that the city currently lacks. An indoor aquatic center would allow staff the opportunity to
serve the growing population by expanding services and programs for all citizens.
ENO
""\
320
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX -PARKS AT TEXAS STAR, PHASE IV
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Cost- To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
345
io
IN
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: March 23,2004
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS -VILLAGES OF BEAR CREEK
Project Type: OTHER Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project includes the infrastructure improvements as recommended as high priority in the adopted Parks
Master Plan.
PROJECT DESCRIPTION:
This project includes the redevelopment/redesign and improvement of the trail at the Villages of Bear Creek
Park to offer multiple uses for the citizens of Euless.
PROJECT SCHEDULE:
JUSTIFICATION:
Trail development and enhancement opportunities will be consistent with available land, funding and time
riables. This Master Plan recommendation will be part of a city-wide comprehensive trail enhancement
t. Due to the continual erosion of the existing trail, a redevelop ment/redesign of the trail system at Villages
eek will be a high priority.
346