HomeMy WebLinkAboutPreliminary Capital Improvements Program FY15-16City 0
Euless
Preliminary Capital
Improvements Program
FY 2015-2016
CITY OF EU SS
FISCAL YEAR 2015-2016
LINDA MARTIN, MAYOR
Tim Stinneford, Council Member - Place One, Mayor Pro Tem
Jeremy Tompkins, Council Member - Place Two
Eddie Price, Council Member - Place Three
Linda Eilenfeldt, Council Member - Place Four
Harry Zimmer,
Council Member -
Place
Five
Perry Bynum,
Council Member -
Place
Six
Loretta Getchell, City Manager
`+ Bob Freeman, Deputy City Manager
Chris Barker, Assistant City Manager
L
TABLE OF CONTENTS
PRELIMINARY CAPITAL IMPROVEMENTS PROGRAM
City Officials
Table of Contents i-v
Letter
vi-vii
FUNDED PROJECTS
Summary of Funded Projects 1
FY15 Amendments 3
Drainaae Projects
Summary of Funded Drainage Projects
5
DR9903 Miscellaneous Drainage Improvements
6
DR1101 Flooding Mitigation
8
DR1201 Miscellaneous Creek Maintenance
10
Street Projects
Summary of Funded Street Projects
13
PS1102 Glade Parks Improvements
14
PS1202 ADA/TAS Infrastructure Improvements
16
PS1203 Miscellaneous Street Repairs
18
PS1501 FY2015 40th CDBG-ADA/TAS Infrastructure Improvements
20
PS1502 FY2015 Street Overlay
22
Wastewater Projects
Summary of Funded Wastewater Projects
25
WW0002 Miscellaneous Wastewater Rehabilitation
26
WW0605 TRA Wastewater Payments — Impact
28
Line Replacement — Crane Drive
30
Line Replacement — Town Creek Drive
32
Water Projects
Summary of Funded Water Projects
35
WT0001 Miscellaneous Water Rehabilitation
36
WT0101 Water Tank Debt Payment — Impact
38
WT0104 Well Repairs
40
WT0803 Meters and Transponders
42
WT0901 TRA Water Payments — Impact
44
WT1201 Reclaimed Water Line Extension Phase 1
46
WT1212 Reclaimed Water Line Extension Phase II
48
WT1402 Fixed Base Meter Reading and Water Meter Changeout
50
WT1403 Reclaimed Water Line Extension Debt Payment — Impact
52
WT1501 24-Inch Valve Replacement Cinnamon, Anice, Fuller -Wiser
54
Other Projects
Summary of Funded Other Projects
57
AC1201 Texas Star Sports Complex Phase IV
58
CM0304 Entry Monument Sign Program
60
CM0804 Redevelopment
62
CM1508 Car Rental Contingency
64
CM1509 Municipal Plaza Improvements Phase 1
66
DV9901 EDC Incentive Funds
68
ED0101 Planning Consultants
70
ED1002 EDC Contingency
72
FM1201 ADA/TAS Facility Improvements
74
FM1510 Development/Engineering Building Design
76
GC1201 TSGC Miscellaneous Improvements
78
PR0720 Miscellaneous Park Improvements
80
PR0804 Park Irrigation
82
PR1401 Glade Parks Trail Connection
84
PROPOSED & UNFUNDED PROJECTS
Summary of FY16 Proposed & Unfunded Projects — Sorted by Type 87
Drainaae Proiects
Summary of FY16 Proposed & Unfunded Drainage Projects
91
Bell Hi Addition
92
Blessing Branch — Main Street to SH360
94
Hollow Oak Channel Erosion
96
Kynette Drive Culvert Modifications
98
Little Bear Creek Drainage Improvements
100
Marlene Drive Culvert Replacement
102
Simmons Drive Culvert Improvements
104
Street Projects
Summary of FY16 Proposed & Unfunded Street Projects
107
East Harwood Road Extension
108
FY2016 41 st CDGB — ADA/TAS Infrastructure Improvements
110
FY2016 Street Overlay
112
FY2017 42"d CDBG — ADA/TAS Infrastructure Improvements
114
FY2017 Street Overlay
116
State Highway 183 East Improvements
118
Traffic Signal — Harwood Road at Bear Creek Parkway
120
FY2018 Street Overlay
122
Traffic Signal — Cheek Sparger Road at Heritage Avenue
124
FY2019 44th CDGB — ADA/TAS Infrastructure Improvements
126
FY2019 Street Overlay
128
Bear Creek Parkway Reconstruction
130
FY2020 Street Overlay
132
Vine Street Reconstruction — SH183 to SH10
134
Cresthaven Drive Reconstruction
136
E Alexander Lane Reconstruction
138
Fuller -Wiser Road Reconstruction — Harwood Road to Mid Cities Boulevard
140
Fuller -Wiser Road Reconstruction — SH183 to Harwood Road
142
Highland Drive Reconstruction
144
Midway Drive Reconstruction
146
Ross Avenue Extension
148
South Pipeline Road Reconstruction
150
Wastewater Projects
Summary of FY16 Proposed & Unfunded Wastewater Projects
153
Line Replacement — Glenn Drive
154
Line Replacement — Cedar Hills Estates/Hollywood Boulevard
156
FY2017 42nd CDBG LR: Oakwood Terrace Phase 1
158
FY2018 43rd CDBG LR: Oakwood Terrace Phase II
160
Line Replacement — Ector Drive/Fayette Drive
162
Line Replacement — Milam Drive
164
SH183 Phase II Wastewater Relocation
166
Line Replacement — Kynette Drive/Wilshire Drive
168
Line Replacement — Donley Drive/Shelmar Drive
170
Line Replacement — Eastcliff Drive/Windlea Drive/Signet Drive
172
Line Replacement — Ector Drive/Donley Drive/Crane Drive
174
Line Replacement — Evans Drive/Canyon Ridge Drive/N Kynette Drive
176
Line Replacement — Huntington/Koen/Atkerson/E Huitt/Slaughter/Martin
178
Line Replacement — Janann Street/Brownstone Drive/Shelmar Drive
180
Line Replacement — Lakewood Boulevard/Dogwood Circle/Bocowood Circle
182
Line Replacement — Live Oak Drive/Silver Creek Drive/Marlene Drive
184
Line Replacement — Mary/Marlene/Commerce/Wilshire/Greenbrier
186
Line Replacement — NorthclifflToplea/Windlea/Signet/Kynette/Westcliff
188
Line Replacement — NW Midway/Rusk/Parker/Rockwall
190
Line Replacement — S Main Street
192
Line Replacement — Sagebrush/Toplea/VVilshire/Yorkshire/Tyler
194
Line Replacement — Sierra Drive
196
Line Replacement — W Don ley/Private/M i mosa/Mag nolia/Red bud
198
Line Replacement — W Midway/Victoria/Delta/Lamar/Rockwall
200
Water Protects
Summary of FY16 Proposed & Unfunded Water Projects
203
Line Replacement — Donley Drive/Shelmar Drive
204
FY2016 41 st CDGB LR: Ector Drive
206
Miscellaneous Valve Replacement
208
Reclaimed Water Line Extension Phase III
210
Fort Worth Interconnect
212
Reclaimed Water Line Extension Phase IV
214
FY2019 44th CDBG LR: Hollow Oak Drive
216
Line Replacement — Kynette Drive, Cyclone Creek to Wilshire Drive
218
SH183 Phase II Water Relocation
220
FY2020 45th CDBG LR: S Main (South)
222
Reclaimed Water Line Extension Phase V
224
Reclaimed Water Line Extension Phase VI
226
t!
Line Replacement — Sunset Drive, S Pipeline Road to S Main Street
228
Line Replacement — Blessing Creek/Stony Creek/Rock Creek
230
Line Replacement — Collin Drive, Dallas Drive to Harwood Road
232
Line Replacement — Collin Drive, Denton Drive to Dallas Drive
234
Line Replacement — Denton Drive, Tarrant Drive to Harwood Road
236
Line Replacement — Dickey Drive North, SH10 to E Huitt Lane
238
Line Replacement — Dickey Drive South, E Huitt Lane to Hilton Drive
240
Line Replacement — Dunaway Drive, E Alexander Lane to E Ascot Drive
242
Line Replacement — E Huitt Lane, S Main Street to Dunaway Drive
244
Line Replacement — Eastcliff Drive, Toplea Drive to Del Prado Apts
246
Line Replacement — Fuller Drive, Salem Drive to Carter Drive
248
Line Replacement — Live Oak Court/Live Oak Drive
250
Line Replacement — Midcreek Drive/Rock Creek Drive/Stony Creek Drive
252
Line Replacement — Midway Drive East, N Main Street to Freestone Drive
254
Line Replacement — Midway Drive West, Freestone Drive to Ector Drive
256
Line Replacement — Needles Street, Paula Lane to Raider Drive
258
Line Replacement — Paula Lane, Needles Street to S Pipeline Road
260
Line Replacement — S Main Street (North), E Huitt Lane to SH10
262
Line Replacement — S Pipeline Road East, Vine Street to S Main Street
264
Line Replacement — S Pipeline Road West, Simmons Drive to Vine Street
266
SH360 Water Crossing
268
Line Replacement — Shady Creek Drive/Cliffwood Road
270
Line Replacement — Springwood Court
272
Line Replacement — Westwood Drive, Fuller Drive to Carter Drive
274
Line Replacement — Wildwood Street
276
Line Replacement — Woodvine Drive (East), Cliffwood Road to El Camino Real
278
Line Replacement — Woodvine Drive (West), Pebble Creek Drive to Cliffwood Rd
280
Other Projects
Summary of FY16 Proposed & Unfunded Other Projects
283
Development/Engineering Building Construction
284
Midtown Development
286
Texas Star Sports Complex Phase V
288
Municipal Plaza Improvements Phase II
290
Texas Star Maintenance Building
292
Texas Star Sports Complex Phase VI
294
Blessing Branch Park Improvements
296
Texas Star Sports Complex Phase VII Design
298
Library Remodel Design
300
Texas Star Sports Complex Phase VI Construction
302
Library Remodel Construction
304
Trail Enhancements Phase 1
306
Animal Shelter Expansion/Renovation
308
Fire Station #2 Remodel
310
Kiddie Carr Park Improvements
312
South Euless Park Upgrades
314
iv
Trail Enhancements Phase II
Trail Enhancements Villages of Bear Creek
Trailwood Park Improvements
Wilshire Park Upgrades
COMPLETED PROJECTS
Drainage Projects
Summary of Completed Drainage Projects
DR0000 Boyd Branch Improvements
Street Proiects
Summary of Completed Street Projects
PS1401 FY2014 39th CDBG-ADA/TAS Infrastructure Improvements
PS1303 Cullum Drive improvements
Wastewater Projects
Summary of Completed Wastewater Projects
WW1203 SH183 Phase I Wastewater Relocation
WW1401 Line Replacement — Denton Drive
Water Projects
Summary of Completed Water Projects
WT1401 Line Replacement — El Camino Real
Other Projects
Summary of Completed Other Projects
GC1401 Golf Course Upgrades
PR1201 Euless Family Life Center Aquatics
PD9901 Police & Courts Facility
316
318
320
322
325
326
329
330
332
335
336
338
341
342
345
346
348
350
v
T H E C I T Y O f
EULESS
July 24, 2015
Honorable Mayor Linda Martin
Honorable City Councilmembers:
Tim Stinneford, Place One, Mayor Pro Tern
Jeremy Tompkins, Place Two
Eddie Price, Place Three
Linda Eilenfeidt, Place Four
Harry Zimmer, Place Five
Perry Bynum, Place Six
INTRODUCTION
The City of Euless' Capital Improvements Program is a comprehensive document
detailing all projects that have been identified to date. Emphasis has been placed on
organizing this data in a manner that will facilitate decision -making processes, assist in
long-range planning, and provide the citizens of Euless with information regarding
planned projects. This document meets the requirements of the City Charter. Article
VII, Section 2 (5) requires, "A statement proposing any capital expenditures deemed
necessary for undertaking during the next budget year and recommended provisions for
financing." Section 2 (6) further requires, "A list of capital projects which should be
undertaken within the five (5) next succeeding years."
We extend special appreciation to the directors and the finance staff for their outstanding
performance in creating this document.
UNDERSTANDING THIS BOOK
Although this book contains a large volume of information, the summaries should make it
easy to understand at a glance. The book is divided into three sections: Funded
Projects, FY2016 Proposed and Unfunded Projects, and Completed Projects. Each
section begins with a summary and is followed by detailed data for those wishing to
research individual projects.
The detail provided includes the project's relationship to City master plans, the project
description and justification, the effect on future maintenance and operating costs, and
the estimated total cost. Within each section, you will find the detailed descriptions
sorted by type. There are five basic project types: Drainage, Streets, Wastewater,
Water, and Other.
201 N Ector Drive, Euless; Texas 76039-3595
817/685-1400 9 Metro 817/267-4403 • Fax 817/685-1416
www eulesstx gov
'1
VI
The Funded Projects section includes all projects that the City Council has previously
authorized. Many of these projects are on -going and require additional funding from
time to time. For each project, a detailed description has been provided that includes
any City Council authorization, the current status of the project, and a financial summary
detailing funding sources and total project budget. Any amendments or additional
appropriations requested are also identified.
Any project that has been authorized by the City Council that is not fully funded will
include a clear explanation as to how the remainder of the project is expected to be
funded.
The FY2016 Proposed and Unfunded Projects section has been classified into three
categories of priority. Priority A indicates the item is recommended and funding has
been identified in the proposed FY2016 budget. Staff recommends City Council
authorization for these projects. Priority B projects should be presented to Council
within two to five years for consideration. Projects that will not begin for at least five
years have been assigned a Priority C. This system has been used to allow the Council
to evaluate and shift priorities, when necessary, and to provide a means of budgeting
capital projects for at least five years. Recommended funding sources have been
indicated if known.
The Completed Projects section provides a summary for each project type indicating
total project budget, actual expenditure, and variance. Funds remaining have been
returned to the appropriate fund balance account for re -appropriation. Details of projects
closed during the prior year have also been included.
FY2016 PROJECTS:
Funding has been identified for all proposed FY2016 projects which are reflected on the
FY2016 Proposed and Unfunded Projects Summary as Priority A. These include:
• East Harwood Road Extension
• FY2016 415t Year CDBG - ADA/TAS Infrastructure Improvements
• FY2016 Street Overlay
• Glenn Drive Wastewater Line Replacement
• Donley Drive/Shelmar Drive Water Line Replacement
• FY2016 41 at Year CDBG - Ector Drive Line Replacement
• Miscellaneous Valve Replacement
• Reclaimed Water Line Extension Phase III
• Development/Engineering Building Construction
• Midtown Development
• Texas Star Sports Complex Phase V
CLOSING COMMENTS
This document is prepared as a comprehensive summary of capital needs that have
been identified throughout the City of Euless. This document will be updated annually to
aid the City Council in allocating resources and determining priorities.
Sin rely, ,,
` retta Getch II
City Manager
vit
um
E- C I T Y O F
U.,LESS
viii
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/14
Appropriation/
Amendment
Budget as of
5/31/15
Expended as
of 5/31/15
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
DRAINAGE PROJECTS
DR9903
Misc. Drainage Improvements
$
837,833
$
95,000
$
932,833
$
348,301
$
584,532
$ 932,833
$
DR1101
Flooding Mitigation
$
500,000
$
-
$
500,000
$
18,334
$
481,666
$ 500,000
$
DR1201
Misc. Creek Maintenance (min bal $100,000)
$
105,000
$
30,000
$
135,000
$
93,521
$
41,479
$ 195,000
$ 60,000
FB9902
Fund Balance - Drainage CIP
$
-
$
-
$
-
$
-
$
-
$ -
$ g
Sub -Total Drainage Projects
$
1,442.833
$
125,000
$
1.567,833
$
460,156
$
1,107,677
$ 1,627,833
$ 59,994
STREET PROJECTS
PS1102
JGiade Parks improvements
$ 12,100,604
$
-
$
12,100,604
$
8,683,573
$
3,417,031
$ 15,369,514
$ 3,268,910
PS1202
ADA/TAS Infrastructure Improvements
$
413,800
$
50,000
$
463,800
$
378,869
$
84,931
$ 463,800
$ -
PS1203
Misc. Street Repairs (min bal $150,000)
$
330,000
$
75,000
$
405,000
$
298,369
$
106,631
$ 511,000
$ 106,000
PS1501
FY2015 40' CDBG-ADA/TAS Infrastructure Improvements
$
-
$
495,600
$
495,600
$
-
$
495,600
$ 519,600
$ 24,000
PS1502
FY2015 Street Overlay
$
$
300,000
$
300,000
$
3,496
$
296,504
$ 300,000
$
FB9907
JFund Balance - Street CIP
$
$
-
$
-
$
-
$
-
$ -
$ 109,221
Sub -Total Street Projects
$ 12,844,404
$
920,600
$
13,765,004
$
9,364,307
$
4,400,697
$ 17,163,914
$ 3,289,689
WASTEWATER PROJECTS
WW0002
Misc. Wastewater Rehab (min bal $100,000)
$
416,086
$
90,000
$
506,086
$
431,605
$
74,481
$ 606,086
$ 100,000
WW0605
TRA Wastewater Payments - Impact
$
580,000
$
100,000
$
680,000
$
580,000
$
100,000
$ 780,000
$ 100,000
WW1 Sol
Line Re - Crane Drive
$
-
$
185,000
$
185,000
$
39,654
$
145,346
$ 247,669
$ 62,669
WW1502
Line Re - Town Creek Drive
$
$
437,000
$
437,000
$
-
$
437,000
$ 440,665
$ 3,665
FB9911
FB - Wastewater Impact Restricted
$
$
-
$
-
$
-
$
-
$ -
$ 434,685
Sub -Total Wastewater Projects
$
996,086
$
812,000
$
1,808,086
$
1,051,259
$
756,827
$ 2,074,420
$ (168,351)
Portion of debt not yet issued.
(1) e."d
r' J
DP
jm�>Cr<.Y
0P Fla
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/14
Appropriation/
Amendment
Budget as of
5/31/16
Expended as
of 5131/15
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
WATER PROJECTS
WT0001
Misc. Water Rehab (min bal $150,000)
$
443,511
$
150,000
$
593,511
$
474,053
$
119,458
$ 703,511
$ 110,000
WT0101
Water Tank Debt Payment -Impact
$
3,730,280
$
248,440
$
3,978,720
$
3,896,004
$
82,716
$ 4.224,202
$ 245,482
WT0104
Well Repairs (min bal $200,000)
$
1,313,992
$
300,000
$
1,613,992
$
1,224,885
$
389,107
$ 1,613,992
$
WT0803
Meters/Transponders annual transfer$158,000
$
1,453,750
$
58,000
$
1,511,750
$
1,032,116
$
479,634
$ 1,669,750
$ 158,000
WT0901
TRA Water Payments -Impact
$
750,000
$
-
$
750,000
$
750,000
$
$ 750,000
$
WT1201
Reclaimed Water Line Extension Phase 1
$
6,650,000
$
3,410,548
$
3,239,452
$
3,239,452
$
$ 3,239,452
$
WT1212
Reclaimed Water Line Extension Phase II
$
-
$
3,129,300
$
3,129,300
$
34,958
$
3,094,342
$ 3,129,300
$
WT1402
Fixed Base Meter Reading and Water Meter Chan eout
$
5,500,000
$
6,950
$
5,493,050
$
$
5,493,050
$ 5,493,050
$ -
WT1403
Reclaimed Water Line Extension Debt Payment -Impact
$
120,369
$
120,894
$
241,263
$
200,969
$
40,294
$ 360,957
$ 119,694
WT1501
24-Inch Valve Replacement Cinnamon, Anice, Fuller -Wiser
$
-
$
220,000
$
220,000
$
100
$
219,900
$ 180,000
$ 40,000
FB9910
FB- Water Impact Restricted
$
$
_
$
_
$
_
$
$
$ 1,298,254
FB9901
IFB - Water & Wastewater CIP
$
$
-
$
$
$
$
$ 194,347
Sub -Total Water Projects
$ 19,961.902
$
809,136
$ 20,771,038
$ 10,852.537
$
9,918,501
$ 21,364,214
$ (899,425)
OTHER
AC1201
Texas Star Sports Complex Phase IV
$
840,687
$
$
840,687
$
556,196
$
284,491
$ 840,687
$
CM0304
Entry Monument Sign Program
$
115.782
$
20,000
$
135.782
$
106,227
$
29,555
$ 135,782
$
CM0804
Redevelopment
$
974,300
$
400,122
$
1,374,422
$
1,053,006
$
321,416
$ 1,374,422
$
CM1508
Car Rental Contingency
$
$
700,000
$
700,000
$
$
700,000
$ 700,000
$
CM1509
Municipal Plaza Improvements Phase I
$
-
$
100,000
$
100,000
$
-
$
100,000
$ 158,500
$ 58,500
DV9901
EDC Incentive Funds
$
500,854
$
25,000
$
525,854
$
450,853
$
75,001
$ 550,854
$ 25,000
ED0101
Planning Consultants
$
204,869
$
-
$
204,869
$
104,869
$
100,000
$ 204,869
$ -
ED1002
EDC Contingency
$
250,000
$
$
250,000
$
$
250,000
$ 250,000
$
FM1201
ADA/TAS Facility Improvements (min bal $75,000)
$
100,000
$
-
$
100,000
$
39,386
$
60,614
$ 115,000
$ 15,000
FM1510
Development/Engineering Building Design
$
$
94,350
$
94,350
$
34,600
$
59,750
$ 94,350
$ -
GC1201
TSGC Misc. Improvements (min bal $150,000)
$
250,000
$
105,000
$
355,000
$
219,212
$
135,788
$ 430,000
$ 75,000
PR0720
Misc. Park Improvements (min bal $100,000)
$
575,000
$
10,500
$
585,500
$
519,569
$
65,931
$ 665,500
$ 80,000
PR0804
Park Irrigation
$
175,000
$
25,000
$
200,000
$
87,116
$
112,884
$ 225,000
$ 25,000
PR1401
Glade Parks Trail Connection
$
117,000
$
1,269,545
$
1,386,545
$
81,677
$
1,304,868
$ 1,396,545
$ 10,000
FB9906
FB-EDC CIP
$
-
$
$
_
$
_
$
$
$ 418,130
FB9908
FB-Texas Star Sports Complex CIP
$
$
$
$
$
$
$ 753,326
FB9909
FB-General CIP
$
$
$
$
$
$
$ 189,645
FB9913
FB-Car Rental CIP
$
$
$
$
$
$
$ 225,173
Sub -Total Other Projects
$
4,103,492
$
2,749,517
$
6,853,009
$
3,252,711
$
3,600,298
$ 7,141,509
$ (1,297,774)
TOTAL FUNDED PROJECTS
2
$ 39,348,717
$
5,416,253
$ 44,764,970
$ 24,980,970
$ 19,784,000
$ 49,371,890
$ 984,133
10jecc vv 1 1 z01 - spu[ Derween rnase 1 and I'nase II (W 11212).
do
:r, r,
Df
r,ff J
CITY OF MESS
CAPTrAL 111111PROVIIIII111112ST PROGRAM
AMENDMENTS — FUNDED PROJECTS
PROJECT#
PROJECT DswRIPTION
DATE
AmENDmzNTS ♦$ ACTIONS
CM0304
Entry Monument Sign Program
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $20,000
from Car Rental Fund.
CM0804
Redevelopment
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $400,000
from Car Rental Fund.
CM0804
Redevelopment
05/31/2015
Increase funding for additional earned interest of $122.
CM1508
Car Rental Contingency
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $700,000 from Car
Rental Fund.
CM1509
Municipal Plaza Improvements Phase I
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $100,000 from Car
Rental Fund.
DR0000
Boyd Branch Improvements
05/31/2015
To close project because it's deemed unnecessary at this time.
DR9903
Miscellaneous Drainage Improvements
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $95,000
from Drainage Operating Fund.
DR1201
Miscellaneous Creek Maintenance
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $30,000
from Drainage Operating Fund.
DV9901
EDC Incentive Funds
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $25,000
from EDC Operating Fund.
FM1510
Development/Engineering Building Design
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $94,350 from Car
Rental Fund.
GC1201
TSGC Miscellaneous Improvements
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $65,000
from TSGC Reserve Fund.
GC1201
TSGC Miscellaneous Improvements
10/01/2014
To transfer funding of $40,000 from project GC1402-TSGC Conference
Center Improvements.
GC1401
Golf Course Upgrades
04/30/2015
To close project and transfer excess funding of $5,704 to TSGC Reserve
Fund.
PD9901
Police and Courts Facility
05/31/2015
Increase funding for additional earned interest of $11.
PD9901
Police and Courts Facility
05/31/2015
To close project.
PR0720
Miscellaneous Park Improvements
09/30/2014
To provide additional funding of $10,500 from TRA reimbursement (check
#164561) for tree replacement.
PR0804
Park Irrigation
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $25,000
from EDC Operating Fund.
PR1201
Euless Family Life Center Aquatics
09/30/2014
To close project and transfer excess funding of $185,673 to Car Rental CIP
Fund Balance.
PR1401
Glade Parks Trail Connection Construction
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $357,545 from Car
Rental Fund.
PR1401
Glade Parks Trail Connection Construction
05/31/2015
To increase budget by $912,000 for grant award.
PS1202
ADA/TASInfrastructure Improvements
10/01/2014
To provide additional funding per FY201S Approved CIP Plan - $50,000
from Car Rental Fund.
PS1203
Miscellaneous Street Repairs
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $75,000
from Car Rental Fund.
PS1303
Cullum Drive Improvements
04/30/2015
To close project and transfer excess funding of $84,990 to Street CIP Fund
Balance.
PS1401
FY2014 39th CDBG-ADA/TAS Infrastructure
04/30/2015
To close project. Any unused funds will be allocated to future CDBG
Improvements
projects.
PS1501
FY2015 40th CDBG-ADA Infrastructure
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $385,028 from
Improvements
Community Development Block Grant and $110,572 from Car Rental
Fund.
PS1502
FY2015 Street Overlay
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $300,000 from Car
Rental Fund.
WT0001
Miscellaneous Water Rehabilitation
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $150,000
from W/WW CIP Operating Fund.
WT0101
Water Tank Debt Payment -Impact
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $248,140
from Water Impact Fee Fund Balance.
WT0101
Water Tank Debt Payment -Impact
05/31/2015
To increase budget by $300 for agent fees.
WT0104
Well Repairs
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $100,000
from W/WW CIP Fund Balance and $200,000 from W/WW Operating
Fund.
WT0803
Meters/Transponders
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $158,000
from W/WW Operating Fund.
WT0803
Meters/Transponders
05/31/2015
To transfer funding of $100,000 to W/WW CIP Fund Balance.
WT1201
Reclaimed Water Line Extension Phase 1
05/31/2015
To split project into phases and transfer authorized funding of $3,129,300
to project WT1212-Reclaimed Water Line Extension Phase II.
WT1201
Reclaimed Water Line Extension Phase 1
05/31/2015
Budget authorization has been reduced by $281,248.
WT1212
Reclaimed Water Line Extension Phase II
05/31/2015
To provide cash of $85,335from W/WW CIP Fund Balance for engineering
design costs.
CITY OF EULESS
CAPITAL DU4t0VZN3CNT PROGRAM
AMZMB CXTS — FUNDED PROJECTS
PROJECT#
PROJECT DESCRIPTION
DATE
AMSIIDxENTS & ACTIONS
WT1212
Reclaimed Water Line Extension Phase II
05/31/2015
To provide cash of $100,000 from W/WW CIP Fund Balance for bond
issuance costs.
WT1212
Reclaimed Water Line Extension Phase II
05/31/2015
To transfer funding authorization of $3,129,300 from project WT1201-
Reclaimed Water Line Extension Phase I.
WT1401
El Camino Real
02/28/2015
To transfer excess funding of $55,000 to W/WW CIP Fund Balance.
WT1401
El Camino Real
04/30/2015
To close project and transfer excess funding of $39,538 to W/WW CIP
Fund Balance.
WT1402
Fixed Base Meter Reading and Water Meter
05/31/2015
Reduce budget in the amount of $6,950 per 2015A W/WW Revenue Bond
Changeout
issue.
WT1403
Reclaimed Water Line Extension Debt Payment-
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $120,894
Impact
from Water Impact Fee Fund Balance.
WT1501
24-Inch Valve Replacement Cinnamon, Anice,
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $220,000 from
Fuller -Wiser
W/WW Operating Fund.
WW0002
Miscellaneous Water Rehabilitation
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $90,000
from W/WW CIP Fund Balance.
WW0605
TRA Wastewater Payments -Impact
10/01/2014
To provide additional funding per FY2015 Approved CIP Plan - $100,000
from WW Impact Fee Fund Balance.
WW1203
SH183 Phase I Wastewater Relocation
05/31/2015
To close project.
WW1401
Denton Drive
05/31/2015
To close project and transfer excess funding of $122,534 to W/WW CIP
Fund Balance.
WW1501
Line Rep - Crane Drive
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $185,000 from
W/WW Operating Fund.
WW1502
Line Rep - Town Drive
10/01/2014
To provide funding per FY2015 Approved CIP Plan - $437,000 from
W/WW Operating Fund.
bo
ba
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5131/14
Appropriation/
Amendment
Budget as of
5/31115
Expended as
of 5/31115
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
DRAINAGE PROJECTS
DR9903
Misc. Draina a Improvements
$ 837,833
$ 95,000
$ 932,833
$ 348,301
$ 584,532
$ 932,833
$
DR1101
Flooding Mitigation
$ 500,000
$
$ 500,000
$ 18,334
$ 481,666
$ 500,000
$
DR1201
Misc. Creek Maintenance min bal $100 000
$ 105,000
$ 30,000
$ 135,000
$ 93,521
$ 41,479
$ 195,000
$ 60,000
FB9902
Fund Balance - Drainage CIP
$
$
$
$
$
$
$ 6
Sub -Total Drainage Projects
$ 1,442,833
$ 125.000
$ 1,567,833
$ 460,156
$ 1,107.677
$ 1,627,833
$ 59,994
Cn
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 23,1999
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS DRAINAGE IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Pro'ect Code: DR9903 Priority: A
COUNCIL AUTHORIZATION:
May 27, 2014: Awarded Bid No. 007-14 for a construction contract to Knight Erosion Control, Inc. for Drainage
Channel Improvements along Hurricane Creek and authorized the City Manager to enter into a contract with
Knight Erosion Control, Inc. The estimated expenditure is $135,487.82.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project provides funding for various drainage projects or emergency repairs identified throughout the year.
Often correction of these problems requires design services and other improvements such as bank stabilization.
As major projects are identified, they will be tracked separately and assigned a different project number.
PROJECT SCHEDULE:
JUSTIFICATION:
Failure to correct these problems often causes damage to existing infrastructure.
'1
100
L
11.1
PROJECT TITLE: MISCELLANEOUS DRAINAGE IMPROVEMENTS PROJECT CODE: DR9903
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operatinq Cost Improvements $932,833
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $932,833
Maintenance Costs Funding Source:
Transfer from:
Drainage Operating Fund $749,609
Drainage CIP Fund Balance $183,224
$0
Subtotal: $0
Total Estimated Annual Cost
$01
Total Funding
$932,833
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (- +)
% EXPENDED
Fence
$559 $559
0
100%
Storm Drain
$932,079 $347,547
584,532
37%
Meters & Setting
$195 $195
0
100%
$932,833 $348,301 $584,532 37%
7
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 30,2010
Submitted By: RON YOUNG Date Completed:
Project Title: FLOODING MITIGATION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: DR1101 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project consists of identifying chronic flooding locations within the City of Euless and determining the
cost/benefit of property acquisition and protection compared to extensive drainage relief projects. Property
acquisition will be recommended after consideration of flooding history, appraisals, and feasible alternative
drainage solutions have been evaluated. It is recommended that this be established as an ongoing project.
PROJECT SCHEDULE:
JUSTIFICATION:
Properties throughout the City of Euless situated adjacent to creeks have experienced drainage problems for
several years. The cost for implementing drainage improvement projects to mitigate flooding at isolated locations
may be much greater than the cost of property acquisition. Chronic flooding lowers the property values and this
program will offer a means of relief for affected property owners.
PROJECT TITLE: FLOODING MITIGATION
PROJECT CODE: DR110'
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Flooding Mitigation $500,000
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $500,000
Maintenance Costs Funding Source:
Transfer from:
Drainage CIP Fund Balance $350,000
Drainage Operating Fund $150,000
I Subtotal:
Total Estimated Annual Cost $01 Total Funding $500,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Storm Sewer $500,000 $18,334 $481,666 4%
TOTAL PROJECT $500,000 $18,334 $481,666 4%
9
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 22,2011
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS CREEK MAINTENANCE
Project Type: DRAINAGE Sub -Type: CREEK MAINTENANCE
Project Code: DR1201 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless completed drainage master plan studies for the major creeks that traverse the City. They
include Little Bear Creek, Hurricane Creek, Boyd Branch and Blessing Branch.
PROJECT DESCRIPTION:
The project provides for maintenance in the creeks described above including removal of fallen trees that impede
the flow of creek water in the natural creek channels, clearing brush and debris at major bridge crossings, and
preventative maintenance. This project does not address items that are deemed cosmetic enhancements.
PROJECT SCHEDULE:
JUSTIFICATION:
Natural creek erosion undermines the root systems of trees adjacent to creek banks which results in trees falling
into or across creek channels. These fallen trees together with accumulated brush and debris can impede the
flow of storm water in the natural creek channels resulting in a rise in the normal water surface elevation. Fallen
trees that are conveyed down stream in the natural creek channels may cause damage to the substructure of
bridges spanning the creek channels.
10
'. 1
PROJECT TITLE: MISCELLANEOUS CREEK MAINTENANCE
PROJECT CODE: DR120'
[NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
I MAINTENANCE COST (+ OR -) ANNUAL:
Uirect Operating Cost Improvements
Personnel: Full Time (Minimum balance $100,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
I Subtotal: $01 Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
Drainage CIP Fund Balance $105,000
Drainage Operating Fund $30,000
$0
Subtotal: $0 Additional Funding Needed:
Transfer from:
Drainage Operating Fund $60,000
Total Estimated Annual Cost $0 Total Funding $195,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Storm Sewers $195,000 $93,521 $101,479 48%
TOTAL PROJECT $195,000 $93,521 $101,479 48% I
I I
w
T H E C I T Y O F
EULESS
'1
12
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5131/14
Appropriation/
Amendment
Budget as of
5/31/15
Expended as
of 5/31115
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
STREET PROJECTS
PS1102
lGiade Parks Improvements
$ 12,100,604
$ -
$ 12,100,604
$ 8,683,573
$ 3,417,031
$ 15,369,514
$ 3,268,910
PS1202
ADA/TAS Infrastructure Improvements
$ 413,800
$ 50,000
$ 463,800
$ 378,869
$ 84,931
$ 463,800
$ -
PS1203
Misc. Street Repairs (min bal $160,000)
$ 330,000
$ 75,000
$ 405,000
$ 298,369
$ 106,631
$ 511,000
$ 106,000
PS1501
FY2015 40th CDBG-ADA/TAS Infrastructure Improvements
$ -
$ 495,600
$ 495,600
$ -
$ 495,600
$ 519,600
$ 24,000
PS1502
FY2015 Street Overlay
$
$ 300,000
$ 300,000
$ 3,496
$ 296,504
$ 300,000
$ -
FB9907
Fund Balance - Street CIP
$
$ -
$ -
$ -
$ -
$ -
$ 109,221)
Total Street Projects
$ 12,844,404
$ 920,600
$ 13,765,004
$ 9.364,307
$ 4,400,697
$ 17.163,914
$ 3,289,689
Portion of debt not yet issued.
W
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: GLADE PARKS IMPROVEMENTS
Project Type: STREET Sub -Type: CONSTRUCTION
Proiect Code: PS1102 Priority: A
COUNCIL AUTHORIZATION:
December 14, 2010: Approval of Resolution #10-1352 authorizing the publication of intention to issue COs.
January 25, 2011: Consider all matters incident and related to the issuance of and sale of up to $3.1 M in COs.
January 25, 2011: Consider acceptance of ROW and easements necessary for public improvements.
January 25, 2011: Awarded Bid #001-11 for a construction contract to McMahon Contracting LP in the amount of
$1,973,615.95 for the construction of Rio Grande Boulevard, Heritage Avenue, and widening of the SH121
service road.
February 24, 2011: Issued COs for funding of first segment of public improvements at Glade Parks.
February 14, 2012: Authorized the City Manager to enter into a contract with Jackson Construction, LTD in the
amount of $1,696,277.25 for the construction of Glade Parks Phase II streets (Brazos Drive, Red River Drive, and
Heritage Avenue).
October 23, 2012: Authorized the City Manager to enter into a contract with All Around Lawn Care, Inc. in the
amount of $213,925.65 for the construction of the Glade Parks Phase II Streetscape project.
August 13, 2013: Authorized the City Manager to execute an Engineering Design Contract with Mycoskie,
McInnis & Associates for the design of portions of the Glade Parks Infrastructure. The estimated expenditure is
$114,800, plus reimbursable expenses and additional services.
June 9, 2015: Approved Resolution No. 15-1461, creating, authorizing and establishing the Glade Parks Public
Improvement District Number Two; authorizing assessment method and collection service, and providing for
publication and an effective date.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The infrastructure located in the Glade Parks development is included in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project represents the funding required for the infrastructure improvements at the Glade Parks Development
per the Project and Financing Plan. The project scope includes the construction of Rio Grande Blvd., portions of
Heritage Ave., the Little Bear Creek bridge, SH121 improvements, landscaping, wetland mitigation, Brazos Blvd.
and remaining streets, main entrance and medians, underground drainage and associated utility installations,
parking garage, park and amenities, as well as administrative and financing costs.
PROJECT SCHEDULE:
Design: Winter 2010 Phase I Complete: FY2012 Phase IV Construction: FY2016
ROW: Winter 2010 Phase II Complete: August 2012
Begin Construction: Spring 2011 Phase III Complete: April 2015
JUSTIFICATION:
The construction of public infrastructure at Glade Parks will spur economic development in the area and complete
an access route to existing Euless businesses.
Milk
14
OW
PROJECT TITLE: GLADE PARKS IMPROVEMENTS
PROJECT CODE: PS1102
INET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Rio Grande Blvd.
$3,911,023
Personnel: Full Time
Little Bear Creek Bridge
$1,016,065
Part Time
$0
Heritage Ave.
$231,767
Total Salary
$0
Highway 121 Improvements
$1,297,164
Purchase of Services
Landscaping
$517,029
Materials & Supplies
Wetland Mitigation
$296,000
Utilities
$0
Brazos and Remaining Streets
$3,494,309
Main Entrance and Median
$587,247
Parking Garage
$1,901,793
Park and Park Amenities
$1,287,387
Administrative Costs
$829,730
Subtotal:
$0
Total Estimated Caoital Cost
$15,369,514
Maintenance Costs
Funding Source:
2011 Certificates of Obligation
$2,854,870
Street CIP Fund Balance
$180,130
2015 Certs. of Ob. Proceeds
$6,000,000
$0
Subtotal:
$0
Additional Funding Needed. -
Future Bond Issue #3
$3,065,604
Future Bond Issue #4
$3,268,910
Total Estimated Annual Cost
$0
Total Funding
$15,369,514
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Design
$300,000 $226,292 $73,708
75%
Construction/Administrative Costs
$15,028,399 $8,416,166 $6,612,233
56%
Transfer to Debt Service
$15,000 $15,000 $0
100%
Other Professional Services
$26,115 $26,115 $0
100%
TOTAL PROJECT $15,369,514 $8,683,573 $6,685,941 56% I
1s
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREETS Sub -Type: SIDEWALKS
Project Code: PS1202 Priority: A
COUNCIL AUTHORIZATION:
October 23, 2012: Authorized the City Manager to enter into a contract with Estrada Concrete, LLC in the
amount of $111,026 for the construction of ADA ramp improvements.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Master Thoroughfare Plan includes and addresses sidewalks, crosswalks, and curb ramps for City streets.
PROJECT DESCRIPTION:
This project provides for the continued improvements to City infrastructure as required by Federal and State
mandated Americans with Disabilities Act/Texas Accessibility Standards ("ADA/TAS"). City sidewalks,
crosswalks, curb ramps, and other areas covered under both ADA and TAS requirements will be part of these
improvements.
PROJECT SCHEDULE:
JUSTIFICATION:
Many sidewalks, curb ramps, and other similar items are outdated and do not meet current ADA/TAS standards.
Updating accessibility on a continuing basis will help keep the City in compliance with government standards and
will address the growing needs of citizens with accessibility issues.
16
PROJECT TITLE: ADA/TAS INFRASTRUCTURE IMPROVEMENTS PROJECT CODE: PS120:
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
TOTAL ESTIMATED CAPITAL COST:
Improvements $463
Subtotal:
$0
Total Estimated Capital Cost
$463,800
Maintenance Costs
Funding Source:
Transfer from:
Car Rental Fund
$300,000
Harwood Road - PS9904
$83,655
$0
Escrow Funds
$80,145
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$463,800
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Sidewalks/Curbs
$380,145 $300,339 $79,806
79%
Utility Relocation
$83,655 $78,530 $5,125
94%
AL PROJECT
$463,800 $378,869 $84,931
82%
17
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MISCELLANEOUS STREET REPAIRS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: PS1203 Priority: A
COUNCIL AUTHORIZATION:
April 24, 2012: Authorized the City Manager to enter into a contract with Estrada Concrete Co. LLC for concrete
road repairs at various locations on North Main Street, Fuller -Wiser Road and Bear Creek Parkway in the amount
of $93,390.
March 11, 2014: Authorized the City Manager to negotiate and execute a contract for a citywide pavement
management analysis and asset management inventory with Infrastructure Management Services (IMS). The
estimated expenditure is $82,155.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Master Thoroughfare Plan identifies the various street types within the City of Euless. These street types
include residential streets through regional arterial streets.
PROJECT DESCRIPTION:
This project includes the removal and replacement of deteriorated sections of pavement along identified
roadways.
PROJECT SCHEDULE:
JUSTIFICATION:
Continuing repair of the existing street pavement will maintain safe driving conditions and will extend the overall
life of the City streets.
18
'I-,'
��
PROJECT TITLE: MISCELLANEOUS STREET REPAIRS
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
PROJECT CODE: PS1W
TOTAL ESTIMATED CAPITAL COST:
-onstruction
;Minimum balance $150,000)
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
Street CIP Fund Balance
$330,000
Car Rental Fund
$75,000
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
Street CIP Fund Balance
$106,000
Total Estimated Annual Cost
$0
Total Funding
$511,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Other Professional Services
$83,156 $82,331 $825
99%
Construction
$427,844 $216,038 $211,806
50%
$511,000 $298,369 $212,631 58% I
19
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: 40TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET/FACILITIES Sub -Type: CDBG
Proiect Code: PS1501 Priority: A
COUNCIL AUTHORIZATION:
February 25, 2014: Conducted a Public Hearing for the proposed 40th Year CDBG projects and approved the
recommendation regarding the selected CDBG projects.
April 28, 2015: Approved Resolution No. 15-1460 recommending award of a construction contract for the 40th
Year Community Development Block Grant (CDBG) Project No. B-14-UC-48-0001-22-30-B to Reliable Paving,
Inc. for the replacement of sidewalk accessibility ramps in the amount of $116,010.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides for continued improvements to accessibility by removing architectural barriers to
accessibility as required by the Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards (ADA/TAS). This project includes identification of architectural barriers to accessibility that meet
CDBG eligibility guidelines and the subsequent replacement thereof.
PROJECT DESCRIPTION:
The 40th Year CDBG project consists of two separate scopes of work. The first is the replacement of fifty (20)
sidewalk ramp locations identified by the Engineering Department. These areas are primarily located along W.
Pipeline Road, Kynette Drive, and Signet Drive. Sidewalk accessibility ramp installations are eligible for CDBG
funding regardless of their location within the community. Secondly, staff has also identified an accessibility
project which affects citizen access to municipal buildings within the City Municipal Complex. This portion of the
project also focuses on the reconstruction of pathways for ADA compliance.
PROJECT SCHEDULE:
Ramps
Begin Construction: July 2015
Anticipate Construction Complete: September 2015
Municipal Complex
Begin Construction: October 2015
Anticipate Construction Complete: April 2016
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
,-*N
W
20
PROJECT TITLE:40TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS PROJECT CODE: PS1501
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $67,876
Personnel: Full Time Construction $451,724
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $519,600
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $110,572
CDBG Award $385,028
$0
Subtotal: $0 Additional Funding Needed:
Transfer from:
Car Rental Fund $24,000
Total Estimated Annual Cost $0 Total Funding $519,600
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Construction $519,600 $0 $519,600 0%
TOTAL PROJECT $519,600 $0 $519,600 0%
21
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2015 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project Code: PS1502 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Begin Construction: June 2015
Anticipate Construction Complete: August 2015
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadways, and will enhance the appearance of the streets.
22
PROJECT TITLE: FY2015 STREET OVERLAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
PROJECT CODE: PS1502
TOTAL ESTIMATED CAPITAL COST:
Construction $300,000
$0
$0
$0
$0 Total Estimated Caoital Cost $300,000
Funding Source:
Transfer from:
Car Rental Fund $300,000
Total Estimated Annual Cost $01 Total Funding $300,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Construction $300,000 $3,496 $296,504 1%
TOTAL PROJ
$300,000 $3,496
504 1%
23
T H
11
E C I T Y O F
ULESS
w
24
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/14
Appropriation/
Amendment
Budget as of
5/31/15
Expended as
of 5/31/16
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
WASTEWATER PROJECTS
WW0002
Misc. Wastewater Rehab(min bal $100,000)
$ 416,086
$ 90,000
$ 506,086
$ 431,605
$ 74,481
$ 606,086
$ 100,000
WW0605
TRA Wastewater Payments - Impact
$ 580,000
$ 100,000
$ 680,000
$ 580,000
$ 100,000
$ 780,000
$ 100,000
WW1501
Line Rep - Crane Drive
$ -
$ 185,000
$ 185,000
$ 39,654
$ 145,346
$ 247,669
$ 62,669
WW1502
Line Re - Town Creek Drive
$
$ 437,000
$ 437,000
$ -
$ 437,000
$ 440,665
$ 3,665
FB9911
I FB - Wastewater Impact (Restricted)
$
$ -
$ -
$ -
$ -
$ -
$ 434,685
Total Wastewater Projects
$ 996,086
$ 812,000
$ 1,808,086
$ 1,051,259
$ 756,827
$ 2,074,420
$ (168,351)
N
Cn
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS WASTEWATER REHABILITATION
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: WW0002 Priority: A
COUNCIL AUTHORIZATION:
March 8, 2005: Awarded contract to Hall -Albert Construction Company for the replacement of various
wastewater lines in the amount of $977,857.50. (This award was only partially for the WW0002 project.)
March 28, 2006: Authorized the city manager to proceed with emergency repair by GRA-TEX Utilities to the
aerial wastewater main crossing Hurricane Creek at a cost of $55,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project is for funding of small wastewater main projects identified throughout the fiscal year. Larger projects
will be determined on an "as needed" basis and presented for funding under a new project number.
PROJECT SCHEDULE:
JUSTIFICATION:
Most of these lines are clay tile and are seriously deteriorated.
ho
-1-11,
26
L
PROJECT TITLE: MISCELLANEOUS WASTEWATER REHABILITATION PROJECT CODE: WW0002
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
$0
TOTAL ESTIMATED CAPITAL COST:
tewater Mains
imum balance $100,000)
Subtotal: $0 Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
W/WW Operating Fund $165,000
WW9903 $37,013
$0 W/WW CIP Fund Balance $304,073
Subtotal: $0 Additional Funding Needed:
Transfer from:
W/WW CIP Fund Balance $100,000
Total Estimated Annual Cost $01 Total Funding $606,086
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Wastewater Mains $557,567 $383,154 174,413 69%
Engineering $17,939 $17,871 68 100%
Contingency $30,580 $30,580 0 100%
$606 086 $431,605 $174,481 71 % 1
27
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 03,2006
Submitted By: RON YOUNG Date Completed:
Project Title: TRINITY RIVER AUTHORITY WASTEWATER PAYMENT
Project Type: WASTEWATER Sub -Type: IMPACT FEE
Pro'ect Code: WW0605 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Based on a review by Birkhoff, Hendricks, and Conway of the water and wastewater impact fees, it was
determined that a substantial portion of the wastewater impact fee is attributed to Trinity River Authority ("TRA")
capital projects. Therefore, these fees should be used to pay a portion of the annual TRA expense, as these
funds are directly attributed to the expansion of TRA. Based on the available fund balance, a systematic
drawdown over a ten year period has been developed.
PROJECT SCHEDULE:
JUSTIFICATION:
The expansion at TRA provides additional capacity and it was determined through the wastewater impact fee
study that these funds could be used to pay a portion of TRA wastewater payments. It was determined a ten
year drawdown would approximate the Capital Improvement Plan Review time frame, as well as provide for a
systematic drawdown that would not impact the annual budget.
.-,
28
PROJECT TITLE: TRINITY RIVER AUTHORITY WASTEWATER PAYMENT PROJECT CODE: WW0605
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
($100
TOTAL ESTIMATED CAPITAL COST:
TRA Wastewater Payments $780,000
Subtotal:
($100,000)
Total Estimated Capital Cost
$780,000
Maintenance Costs
Funding Source:
Transfer from:
WW Impact Fee Fund Balance
$680,000
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
WW Impact Fee Fund Balance
$100,000
Total Estimated Annual Cost
($100,000)l
Total Funding
$780,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Wastewater - TRA Service
$780,000 $580,000 $200,000
74%
TOTAL PROJECT $780,000 $580,000 $200,000 74%
29
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 26,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: WW1501 Priority: A
COUNCIL AUTHORIZATION:
December 9, 2014: Authorized the City Manager to execute an Engineering Design contract with Elliott and
Hughes, Inc. for the design of the FY2015 Sanitary Sewer Rehabilitation Project. The estimated expenditure is
$74, 513.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The project
is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of wastewater mains between Crane Drive and Donley Drive north of
Harwood Road to the upper end of the main north of Glenn Drive.
PROJECT SCHEDULE:
Begin Construction: November 2015
Anticipate Construction Complete: April 2016
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
100
30
PROJECT TITLE: LINE REPLACEMENT -CRANE DRIVE
PROJECT CODE: WW1501
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR •) ANNUAL:
Direct Operating Cost Engineering $74,513
Personnel: Full Time Construction $173,156
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $247
Maintenance Costs Funding Source:
Transfer from:
W/WW Operating Fund $185
Subtotal: $0 Additional Funding Needed:
Transfer from:
W/WW CIP Fund Balance $62,669
Total Estimated Annual Cost $0 Total Funding $247,669
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $74,513 $39,654 $34,859 53%
Construction $173,156 $0 $173,156 0%
TOTAL PROJECT $247,669 $39,654 $208,015 16%'
31
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 26,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -TOWN CREEK DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Pro'ect Code: WW1502 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The project
is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Town Creek Drive from Salem Drive to Carter Drive,
2. Carter Drive south of Town Creek Drive,
3. Westport Circle,
4. Newport Circle,
5. Asbury Circle, and
5. the outfall between Westport Circle and Newport Circle.
PROJECT SCHEDULE:
Begin Construction: November 2015
Anticipate Construction Complete: April 2016
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
32
PROJECT TITLE: LINE REPLACEMENT -TOWN CREEK DRIVE
PROJECT CODE: WW1502
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $57,
Personnel: Full Time Construction $383,
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
0,01
Subtotal: $0 Total Estimated Capital Cost $440,665
Maintenance Costs Funding Source:
Transfer from:
W/WW Operating Fund $437,000
Subtotal: $0 Additional Funding Needed:
Transfer from:
W/WW CIP Fund Balance $3,665
Total Estimated Annual Cost $0 Total Funding $440,665
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %, EXPENDED
Engineering $57,000 $0 $57,000 0%
Construction $383,665 $0 $383,665 0%
665 $0 $440,665 0% I
33
FMO
T H E C I T Y O F
EULESS
,-IN
34
W
Cn
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31114
Appropriation/
Amendment
Budget as of
6/31/15
Expended as
of 5131/15
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
WATER PROJECTS
WT0001
Misc. Water Rehab min bal $150 000
$
443,511
$
150,000
$
593,511
$
474,053
$
119,458
$ 703,511
$ 110,000
W1`0101
Water Tank Debt Payment -impact
$
3,730,280
$
248,440
$
3,978 720
$
3,896,004
$
82,716
$ 4,224,202
$ 245,482
WT0104
Well Repairs min bai $200 000
$
1,313,992
$
300,000
$
1,613,992
$
1,224,885
$
389,107
$ 1,613,992
$
W170803
Meters/Transponders annual transfer$158000
$
1,453,750
$
58,000
$
1,511,750
$
1,032,116
$
479,634
$ 1,669,750
$ 158,000
WT0901
TRA Water Payments -impact
$
750,000
$
$
750,000
$
750,000
$
$ 750,000
$
WT1201
Reclaimed Water Line Extension Phase 1
$
6,650,000
$
3,410,548
$
3,239,452
$
3,239,452
$
$ 3,239,452
$
WT1212
Reclaimed Water Line Extension Phase II
$
-
$
3,129,300
$
3,129,300
$
34,958
$
3,094,342
$ 3,129 300
$
WT1402
Fixed Base Meter Reading and Water Meter Chan eout
$
5,500,000
$
6,950
$
5,493,050
$
$
5,493,050
$ 5,493,050
$
W1`1403
Reclaimed Water Line Extension Debt Payment -Impact
$
120,369
$
120,894
$
241,263
$
200,969
$
40,294
$ 360,957
$ 119,694
WT1501
24-Inch Valve Replacement Cinnamon, Anice, Fuller -Wiser
$
$
220,000
$
220,000
$
100
$
219,900
$ 180,000
$ (40,000)
FB9910
FB- Water Impact Restricted
$
$
$
$
$
$
$ (1,298,254
F89901
FB - Water & Wastewater CIP
$
$
-
$
-
$
$
Is
$ 194,347
Total Water Projects
$19,961,902
$809,136
$20,771.038
$10,852,537
$9,918,501
1 $21,364,214
$899,425
ProjectWT1201 - split between Phase I and Phase II (WT1212).
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MISCELLANEOUS WATER REHABILITATION
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: WT0001 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides funding for small water main projects identified throughout the fiscal year. Large projects
that are identified will be presented for funding under a new project number.
PROJECT SCHEDULE:
JUSTIFICATION:
Some of the City's older water mains have deteriorated and need replacement or repair.
.-IN
36
PROJECT TITLE: MISCELLANEOUS WATER REHABILITATION
PROJECT CODE: WT0001
INET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Water Mains
Personnel: Full Time (Minimum balance $150,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$U
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfers from:
W/WW CIP Fund Balance
$390,000
W/WW Operating Fund
$350,000
$0
Project Transfers
($146,489)
Subtotal:
$0
Additional Funding Needed:
Transfer from:
W/WW Operating Fund
$110,000
Total Estimated Annual Cost
$0
Total Funding
$703,511
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Contingency
$49,231 $24,852 $24,379
50%
Water Mains
$654,280 $449,201 $205,079
69%
$703,511 $474,053 $229,458 67% I
37
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 01,2001
Submitted By: RON YOUNG Date Completed:
Project Title: WATER TANK DEBT PAYMENT - IMPACT
Project Type: WATER Sub -Type: IMPACT FEE
Project Code: WT0101 Priority: A
COUNCIL AUTHORIZATION:
Approved in the annual budget.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water tower was included in the water impact fee study.
PROJECT DESCRIPTION:
This project includes the transfer of funds from the water impact fee to pay debt service (W/S System Revenue
Refunding Bonds, Series 2012) related to the construction of the new water tower (Heritage Park).
PROJECT SCHEDULE:
Last debt payment for the water tower is scheduled for July 15, 2020.
JUSTIFICATION:
The water tower provides additional capacity and was included in the water impact fee study.
111
38
PROJECT TITLE: WATER TANK DEBT PAYMENT - IMPACT
PROJECT CODE: WT0101
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Debt Service FY2001-FY2015
$3,978,720
Personnel: Full Time
Debt Service FY2016
$245,482
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Annual debt payment - water impact fee
$250,000
$0
Subtotal:
$250,000
Total Estimated Capital Cost
$4,224,202
Maintenance Costs
Funding Source:
WT Impact Fee Fund Balance
$3,978,720
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
WT Impact Fee Fund Balance
$245,482
Total Estimated Annual Cost
$250,000
Total Funding
$4,224,202
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Transfer to Debt Service
$4,224,202 $3,896,004 328,198
92%
$4,224,202 $3,896,004 $328,198
39
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: WELL REPAIRS
Project Type: WATER Sub -Type: WELL REPAIR
Project Code: WT0104 Priority: A
COUNCIL AUTHORIZATION:
April 22, 2003: Awarded bid 018-03 for Far North Well pump repair to Layne -Texas for $32,790.
February 14, 2006: Awarded bid 011-06 to Millican Well Service, LLC for rehabilitation and installation of the new
Centrilift submersible motor and pump for the Far North Well in the amount of $250,035.
January 25, 2011: Authorized Millican Well Service, LLC to repair Fuller Well in an amount not to exceed
$117,000, budget increase and additional funding of $117,000 required.
July 20, 2011: Transferred $95,000 from FB9901 to WT0104 for emergency well repairs.
August 9, 2011: Ratified City Manager action to proceed with emergency repairs to the Far North Well site, by
Millican Well Service, LLC in an amount not to exceed $95,000.
June 26, 2012: Ratified City Manager action to proceed with emergency repairs to the well located at 1400 North
Main Street, by Millican Well Service, LLC for an estimated amount of $64,950.
May 14, 2013: Authorized well repairs to the well located at 118 W. Fuller Drive (Fuller Well Site) by Millican Well
Service, LLC for an estimated amount of $120,000.
August 13, 2013: Ratified the City Manager action to proceed with emergency repairs to the City owned and
operated water well located at 1400 North Main Street, by Millican Well Service, LLC. The estimated expenditure
is $75,178.02.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The funding is being utilized to repair well pumps and for other unexpected well repairs.
PROJECT SCHEDULE:
JUSTIFICATION:
Maintaining the City's wells results in the ability to produce water at a substantial reduction in cost.
'—*N
.-**N
40
PROJECT TITLE: WELL REPAIRS
PROJECT CODE: WT0104
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Well Rehabilitation
Personnel: Full Time
(Minimum balance $200,000)
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
WT0001 - Misc Water Rehab
$145,720
W/WW CIP Fund Balance
$893,272
W/WW Operating Fund
$575,000
Subtotal:
Total Estimated Annual Cost
Total Funding
$1,613,992
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Well Rehabilitation
$1,613,992 $1,224,885 $389,107
76%
TOTAL PROJECT
$1,613,992 $1,224,885 $389,107
76%
41
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: METERS AND TRANSPONDERS
Project Type: WATER Sub -Type: METERS/TRANSPONDERS
Project Code: WT0803 Priority: A
COUNCIL AUTHORIZATION:
November 13, 2007: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Supply Company in the amount of
$383,875. Amount for project not to exceed $331,875.
November 11, 2008: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Supply Company in the amount of
$356,875. Amount for project not to exceed $331,875.
February 14, 2012: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Company in the amount of $200,000.
January 14, 2014: Authorized the City Manager to execute an Engineering Services Contract with Alan Plummer
and Associates, Inc. for services in assisting the City with the Texas Water Development Board State Revolving
Fund loan applications and the United States Bureau of Reclamation WaterSMART grant application. The
estimated amount is $78,000 and a portion of this amount is also authorized for project WT1 201 -Reclaimed
Water Line Extension.
February 10, 2015: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Supply Company.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Partial replacement of transponders occurred in FY2006 and FY2007. This project proposes to replace the
balance of the old transponders. The systematic replacement of meters and transponders at or near end of life is
included in the Water System Master Plan.
PROJECT DESCRIPTION:
Purchase and installation of electronic transponders affixed to water meters allowing for electronic or remote
reading of customer water consumption. These water meters (transponders) are read with an electronic device
located inside a vehicle which is driven along a predefined route. System -wide replacement of older meters
beginning with the larger meters first is also included in the scope of the project. Scope also includes engineering
services for WT1402 and debt issuance costs.
PROJECT SCHEDULE:
Ongoing
JUSTIFICATION:
This project provides funding for the systematic replacement of meters and transponders on a regular schedule at
or near end of asset life.
'1
42
OR
PROJECT TITLE: METERS AND TRANSPONDERS PROJECT CODE: WT0803
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
(Annual Funding $158,000)
Personnel: Full Time
Transponders/Meters
Part Time
$0
FY2008 through FY2015
$1,511,750
Total Salary
$0
Transponders/Meters FY2016
$158,000
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
$1,669,750
Maintenance Costs
Funding Source:
Transfer from:
W/WW CIP Fund Balance
$347,750
W/WW Operating Fund
$1,264,000
$0
Transfer to: CIP Fund Balance
($100,000)
Subtotal-
$0
Additional Funding Needed:
Transfer from:
W/WW Operating Fund
$158,000
Total Estimated Annual Cost
$01
Total Funding
$1,669,750
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Meters/Transponders
$1,507,593 $1,032,116 $475,477
68%
Debt Service
$162,157 $0 $162,157
0%
TOTAL PROJECT
$1,669,750 $1,032,116 $637,634
62%
43
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2008
Submitted By: RON YOUNG Date Completed:
Project Title: TRINITY RIVER AUTHORITY WATER PAYMENT -IMPACT
Project Type: WATER Sub -Type: IMPACT FEE
Project Code: WT0901 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Based on a review by Birkhoff, Hendricks, and Conway of the water and wastewater impact fees, it was
determined that a substantial portion of the water impact fee is attributed to Trinity River Authority ("TRA") capital
projects. Therefore, these fees should be used to pay a portion of the annual TRA expense, as these funds are
directly attributed to the expansion of TRA. Based on the available fund balance, a systematic drawdown over a
ten year period has been developed.
PROJECT SCHEDULE:
Annual payment FY2009: $100,000
Annual payments FY2010-2013: $150,000
Annual payment FY2014: $50,000
JUSTIFICATION:
The expansion at TRA provides additional capacity and it was determined through the water impact fee study that
these funds could be used to pay a portion of TRA water payments. It was determined a ten year drawdown
would approximate the Capital Improvement Plan Review time frame, as well as provide for a systematic
drawdown that would not impact the annual budget.
PROJECT TITLE: TRINITY RIVER AUTHORITY WATER PAYMENT -IMPACT PROJECT CODE: WT0901
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost TRA Water Pmts FY2009-2013 $700,000
Personnel: Full Time TRA Water Payments FY2014 $50,000
Part Time $0
Total Salary $0
Purchase of Services ($50,000)
Materials & Supplies
Utilities
Subtotal: ($50,000) Total Estimated Capital Cost $750,000
Maintenance Costs Funding Source:
Transfer from:
WT Impact Fee Fund Balance $750,000
Subtotal: $
Total Estimated Annual Cost ($50,000)1 Total Funding $750,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Water - TRA Service $750,000 $750,000 $0 100%
AL PROJECT $750,000 $750,000 $0 100%
45
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 17, 2011
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE I
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project CODE: WT1201 Priority: A
COUNCIL AUTHORIZATION:
January 22, 2013: Authorized the City Manager to execute an engineering design contract with Alan Plummer and
Associates, Inc. (APAI) with an amount not to exceed $294,678 for the design of a reclaimed water system line
extension project.
May 14, 2013: Authorized the City Manager to seek bids for Phase I of the extended reclaimed water distribution system.
June 25, 2013: Authorized the City Manager to execute a construction contract to Crescent Constructors, Inc. for the
Reclaimed Water Delivery System Extension, Phase I. The estimated expenditure is $3,110,758 which includes a
contingency of $150,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will ultimately
provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities Boulevard as well as the
City's Bear Creek Park. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
Feasibility Study Complete: July 2012
Phase I Construction Began: July 2013
Phase I Construction Complete: September 2014
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
1
46
M
M
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE I PROJECT CODE: *WT1201
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Engineering
$373,622
Direct Operating Cost
Construction
$2,825,809
Personnel: Full Time
Sidewalk/Curb Construction
$17,988
Part Time
Landscaping
$22,033
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Avg. Annual Debt Service
$275,000
Total Estimated Capital Cost
$3,239,452
Subtotal:
$275,000
FUNDING SOURCE:
Maintenance Costs
W/WW CIP Fund Balance
$561,334
W/WW Operating Fund
$1,000,000
Revenue Bond Issue
$1,500,000
Reclaimed Water - WT0202
$143,663
Escrow Funds - ES0298 & ES1301
$34,455
Subtotal:
$0
Total Estimated Annual Cost
$275,000 1
Total Funding
$3,239,452
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (- +) %
EXPENDED
Engineering
$373,622
$373,622 $0
100%
Construction
$2,825,809
$2,825,809 $0
100%
Landscaping
$17,988
$17,988 $0
100%
Sidewalk/Curb Construction
$22,033
$22,033 $0
100%
*WT1201 has been split into two projects -
see WT1201 and WT1212. Future phases shown in unfunded.
FY2015 Total Project $6,650,000
Phase II (WT1212) ($3,129,300)
Budget Reduction ($281,248)
Phase I (WT1201) $3,239,452
TOTAL PROJECT
$3,239,452
$3,239,452 $0
100%
47
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15, 2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE II
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project CODE: WT1212 Priority: A
COUNCIL AUTHORIZATION:
January 14, 2014: Authorized the City Manager to execute an Engineering Services Contract with Alan Plummer and
Associates, Inc. for services in assisting the City with the Texas Water Development Board State Revolving Fund loan
applications.
August 12, 2014: Approved Resolution No. 14-1439, requesting financial assistance (low interest loan) by authorizing
an application to be filed with the Texas Water Development Board.
October 28, 2014: Approved Resolution No. 14-1446, amending a previously authorized request for financial assistance
(low interest loan) by authorizing an amended amount of financial assistance to be sought from the Texas Water
Development Board (TWDB). The amount of financial assistance approved and authorized to be sought from TWDB is not
to exceed $2,755,300. Additionally, $375,300 of the total project financial assistance is eligible for loan forgiveness.
February 10, 2015: Authorized the City Manager to negotiate and execute an Engineering Design Contract with
Alan Plummer and Associates, Inc. for the design of Phase II of the reclaimed water system extension project. The
estimated expenditure is $227,000.
June 23, 2015: Authorized the issuance of City of Euless, Texas, Waterworks and Sewer System Revenue Bonds,
Series 2015B.
June 23, 2015: Authorized the execution of a loan forgiveness agreement with the Texas Water Development Board and
an escrow agreement related thereto associated with the City of Euless, Texas, Waterworks and Sewer System Revenue
Bonds, Series 2015B.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear Creek
Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will ultimately provide
reclaimed water service to several multi -family properties from Harwood Road to Mid Cities Boulevard as well as the City's
Bear Creek Park. Phase II would extend the project to supply approximately 23MG annually to 6 additional properties.
Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
Begin Construction: November 2015
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
No
_1\
48
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE II PROJECT CODE: *WT1212
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Engineering $235,000
Direct Operating Cost Construction Administration $39,000
Personnel: Full Time Construction $2,755,300
Part Time Debt Issuance $100,000
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
2015E Rev Bond Avg. Debt Service $144,000
Total Estimated Capital Cost $3,129,300
Subtotal: $144,000
FUNDING SOURCE:
Maintenance Costs Transfer from WT1201:
W/WW CIP Fund Balance $188,665
Revenue Bond Issue $2,755,300
Transfer from:
W/WW CIP Fund Balance $185,335
Subtotal: $0
Total Estimated Annual Cost $144,000 1 Total Funding $3,129,300 I
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (- +)
% EXPENDED
Engineering
$235,000
$34,958
$200,042
15%
Construction Administration
$39,000
$0
$39,000
0%
Construction
$2,755,300
$0
$2,755,300
0%
Debt Issuance
$100,000
$0
$100,000
0%
*WT1201 has been split into two projects - see WT1201 and WT1212. Future phases shown in unfunded.
FY2015 Total Project $6,650,000
Phase II (WT1212) ($3,129,300)
Budget Reduction ($281,248)
Phase I (WT1201) $3,239,452
(TOTAL PROJECT $3,129,300 $34,958
49
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 25, 2013
Submitted By: RON YOUNG Date Completed:
Project Title: FIXED BASE METER READING & WATER METER CHANGEOUT
Project Type: WATER Sub -Type: METER
Project CODE: WT1402 Priority: A
COUNCIL AUTHORIZATION:
January 14, 2014: Alan Plummer and Associates, Inc. (APAI) will assist the City through the preparation of information
forms, application forms and follow-up administration of loan(s) for Texas Water Development Board (TWDB) funding and
with the preparation of a U.S. Bureau of Reclamation (USBR) WaterSMART grant application. The Engineering
Services Contract to APAI is authorized for project WT0803-Meters and Transponders and WT1201-Reclaimed Water Line
Extension. The funding requested from TWDB and USBR is for project WT1402.
June 23, 2015: Authorized the issuance of City of Euless, Texas, Waterworks and Sewer System Revenue Bonds,
Series 2015A.
June 23, 2015: Authorized the execution of a loan forgiveness agreement with the Texas Water Development Board and
an escrow agreement related thereto associated with the City of Euless, Texas, Waterworks and Sewer System Revenue
Bonds, Series 2015A.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Replacement of existing meter reading capital project of 1992.
PROJECT DESCRIPTION:
Replace existing drive by meter reading system to a fixed base reading system. Currently, City water meters are divided into
one of four reading cycles with each cycle being read on a monthly basis. The reading occurs as a City vehicle traverses
each street within the cycle that is being read for that week. By implementing a fixed base system, all City water meters can
be read at the same time with the readings transmitted to the Utility Billing Office utilizing current City infrastructure.
PROJECT SCHEDULE:
Begin Construction: October 2015
Anticipate Construction Complete: October 2016
JUSTIFICATION:
Implementing the new system will:
1. allow real time reading of approximately 15,000 meters,
2. allow for more timely billing to coincide with billings from TRA,
3. provide the ability to track water efficiency (billed vs produced and purchased) with greater accuracy,
4. replace the high percentage of meters nearing the point at which there is a loss of accuracy due to age and volume,
5. store consumption history allowing for pinpointing of consumption patterns for suspected leak resolution,
6. facilitate enforcement of time of day irrigation violations during times of drought and watering restrictions,
7. depending upon manufacturer chosen, offer system wide leak monitoring/detection as an option,
8. allow customer to access to water use patterns, and
9. replace meters with low/no lead brass meters to meet EPA requirements.
,-**N
W
50
M
PROJECT TITLE: FIXED BASE METER READING & WATER METER CHANGEOUT PROJECT CODE: WT140:
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Fixed Base Equipment
$4,750,000
Personnel: Full Time
Meter Installation
$450,000
Part Time
Contingency
$293,050
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
2015A Rev Bond Avg. Debt Service
$279,000
Total Estimated Capital Cost
$5,493,050
Subtotal: $279,000
FUNDING SOURCE:
Maintenance Costs
Revenue Bond Issue
$5,493,050
Subtotal:
$0
Total Estimated Annual Cost
$279,000
Total Funding
$5,493,050
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED BUDGET (- +) % EXPENDED
Fixed Base Equipment
Meter Installation
$4,750,000
$450,000
$0 $4,750,000
$0 $450,000
0%
0%
Contingencv
$293,050
$0 $293,050
0%
FY2015 Total Project $5,500,000
Budget Reduction ($6,950)
FY2016 Total Project $5,493,050
TOTAL PROJECT
$5,493,050
0%
51
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2013
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION DEBT PAYMENT
Project Type: WATER Sub -Type: IMPACT FEE
Project Code: WT1403 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water system extension was included in the impact fee study.
PROJECT DESCRIPTION:
This project includes the transfer of funds from the water impact fee to pay debt service (W/S System Revenue
Bonds, 2013) related to the extension of the reclaimed water system.
PROJECT SCHEDULE:
Last debt payment is scheduled for July 15, 2033.
JUSTIFICATION:
The project provides a non -potable water source for irrigation which will offset future potable water purchases by
the City and will serve to responsibly conserve potable water resources for the City and the region.
'1
52
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION DEBT PAYMENT PROJECT CODE: WT1403
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Debt Service FY2014-FY2015
$241,263
Personnel: Full Time
Debt Service FY2016
$119,694
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
Annual debt payment - water impact fee
$120,000
$0
Subtotal:
$120,000
Total Estimated Capital Cost
$360,957
Maintenance Costs
Funding Source:
Transfer from:
WT Impact Fee Fund Balance
$241,263
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
WT Impact Fee Fund Balance
$119,694
Total Estimated Annual Cost
$120,000
Total Funding
$360,957
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Transfer to Debt Service
$360,957 $200,969 $159,988
56%
TOTAL PROJECT
$360,957 $200,969 $159,988
56%
53
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 08,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: VALVE REPLACEMENT- CINNAMON, ANICE, FULLER -WISER
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: WT1501 Priority: A
COUNCIL AUTHORIZATION:
May 26, 2015: Awarded Bid No. 004-15 for a construction contract to Atkins Bros. Equipment Co., Inc. for the FY
2015 Gate Valve Replacement Project and authorized the City Manager to enter into a contract with Atkins Bros.
Equipment Co., Inc. The estimated expenditure is $141,800.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace three 24-inch gate valves on the 24-inch main line running between North Main Street
and Fuller -Wiser Road.
PROJECT SCHEDULE:
Begin Construction: July 2015
Anticipate Construction Complete: October 2015
JUSTIFICATION:
Old and deteriorated water valves prevent water lines from being isolated in the event of a line break. Not being
able to isolate as small a segment as possible during a line break increases the labor required to isolate the line,
as well as the number of residents and fire hydrants that would be affected by a line break. Systematic annual
replacement of old deteriorated water valves will increase efficiency, reduce maintenance costs, and ensure
maximum fire protection and water service availability.
No
64
PROJECT TITLE: VALVE REPLACEMENT- CINNAMON, ANICE, FULLER -WISER PROJECT CODE: WT1501
+NET EFFECTS ON OPERATING AND
I MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Engineering $20,000
Construction $160,000
Total Estimated Capital Cost $180,000
Funding Source:
transfer from:
N 1 W11 Operating Fund $220,000
Subtotal:
$0
Transfer to:
W/WW CIP Fund Balance
($40,000)
Total Estimated Annual Cost
$0
Total Funding
$180,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (- +)
% EXPENDED
Engineering
$20,000 $100
$19,900
1%
Construction
$160,000 $0
$160,000
0%
$180,000 $100 $179,900 0% I
55
T H E C I T Y O F
EULESS
I
56
N
4
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/14
Appropriation/
Amendment
Budget as of
5131/15
Expended as
of 5/31/15
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
OTHER
Texas Star sports Complex Phase IV
$
840,687
$
$
840,687
$
556,196
$
284,491
$
840,687
$
4
Ent Monument Sign Program
$
115,782
$
20,000
$
135,782
$
106,227
$
29,555
$
135,782
$
4
Redevelopment
$
974,300
$
400,122
$
1,374,422
$
1,053,006
$
321,416
$
1.374,422
$
8
Car Rental Contingency
$
-
$
700,000
$
700,000
$
-
$
700,000
$
700,000
$
9
Municipal Plaza Improvements Phase 1
$
$
100,000
$
100,000
$
$
100,000
$
158,500
$ 58,500
EDC Incentive Funds
$
500,854
$
25,000
$
525,854
$
450,853
$
75,001
$
550,854
$ 25,000
1
k20
PlanningConsultants
$
204,869
$
-
$
204,869
$
104,869
$
100,000
$
204,869
$ -
EDC Contingency
$
250,000
$
$
250,000
$
-
$
250,000
$
250,000
$ -
1
ADA/TAS Facility Improvements (min bal $75,000)
$
100,000
$
$
100,000
$
39,386
$
60,614
$
115,000
$ 15,000
0
Development/EngineeringBuilding Design
$
-
$
94,350
$
94,350
$
34,600
$
59,750
$
94,350
$ -
1
TSGC Misc. Improvements (min bal $150,000)
$
250,000
$
105,000
$
355,000
$
219,212
$
135,788
$
430,000
$ 75,000
Misc. Park Improvements (min bal $100,000)
$
575,000
$
10,500
$
585,500
$
519,569
$
65,931
$
665,500
$ 80,000
PRO804
Park Irrigation
$
175,000
$
25,000
$
200,000
$
87,116
$
112,884
$
225,000
$ 25,000
PR1401
Glade Parks Trail Connection
$
117,000
$
1,269,545
$
1,386,545
$
81,677
$
1,304,868
$
1,396,545
$ 10,000
FB9906
FB-EDC CIP
$
-
$
-
$
-
$
-
$
-
$
-
$ 418,130)
FB9908
FB-Texas Star Sports Complex CIP
$
$
$
$
$
$
$ 753,326
FB9909
FB-General CIP
$
$
$
$
$
$
$ 189,645
FB9913
FB-Car Rental CIP
$
$
$
$
$
$
$ (225,173)
Total Other Projects
$4,103,492
$2,749,517
$6,853,009
$3,252,711
$3,600,298
$7,141,509
($1,297,774)
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 01,2010
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE IV
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: AC1201 Priority: A
COUNCIL AUTHORIZATION:
January 24, 2012: Authorized the City Manager to negotiate and execute a Field Use and Lease Agreement with
Sting Soccer Group, LP and Texas Titans FC, LLC, (collectively "Sting") for the use of a portion of the property
located at 1501 South Pipeline Road Euless, Texas 76040 (The Parks at Texas Star Sports Complex) as a
practice and training facility for youth soccer. In consideration of its use of the property, Sting will construct
certain facility improvements on the property.
August 28, 2012: Ratified the Euless Development Corporation action taken on August 28, 2012, approving Bid
No. 015-12, to award a contract to Reliable Paving, Inc. in the amount of $494,823 for parking improvements at
the Parks at Texas Star.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Texas Star Sports Complex Phase IV incorporates the addition of a concession and rest room facility and parking
for 200 vehicles. This addition will ensure that the Texas Star Sports Complex is positioned as a premier facility
that serves the athletic and recreational programming needs of the City.
PROJECT DESCRIPTION:
The project scope includes the design and construction of a parking lot and a concession/rest room facility at the
Texas Star Sports Complex. Related support facilities such as electrical service, lighting, fencing, etc. are also
included in the scope of the project.
PROJECT SCHEDULE:
Began Construction: September 2012
Construction Complete: December 2013
JUSTIFICATION:
Since the completion of Phase III at the Texas Star Sports Complex, the facility has been severely under served
in parking, rest room facilities, and concessions. With the completion of Phase IV, the Texas Star Sports
Complex will be positioned to serve the ever-increasing athletic needs of the community and spur economic
opportunities for the City.
58
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE IV PROJECT CODE: AC1201
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Parking Lot
$412,000
Personnel: Full Time
$0
Concessions & Rest Room
$195,000
Part Time
$0
Lights/Electrical
$90,000
Total Salary
$0
Material storage bin
$15,600
Purchase of Services
$0
Entry walk
$35,000
Materials & Supplies
$7,500
Fencing
$18,000
Utilities
$3,500
Concession equipment
$16,000
Retaining Wall
$18,000
5% Contingency
$41,087
Subtotal: $11,000 Total Estimated Capital Cost $840,687
Maintenance Costs Funding Source:
$0 Transfer from:
EDC CIP Fund Balance $645,687
Contributed Capital $195,000
Subtotal: $
Total Estimated Annual Cost
$11,0001
Total Funding
$840,687
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Parking Improvements
$489,561 $489,561
$0
100%
Lighting
$33,000 $33,000
$0
100%
Remodel / Improvements
$8,030 $8,030
$0
100%
Land Betterments
$45,000 $7,260
$37,740
16%
Construction
$1,585 $1,584
$1
100%
Buildings
$195,000 $0
$195,000
0%
Contingencies
$12,111 $0
$12,111
0%
Special Services
$56,400 $16,760
$39,640
30%
TOTAL PROJECT $840,687 $556,196 $284,491 66%
59
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: July 11,2006
Submitted By: JOE HENNIG Date Completed:
Project Title: ENTRY MONUMENT SIGN PROGRAM
Project Type: MISCELLANEOUS Sub -Type: IMPROVEMENTS
Project Code: CM0304 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Continuation of the original City of Euless Entry Monument Sign Program.
PROJECT DESCRIPTION:
Continued construction of City of Euless entry monument signs at key high visibility points throughout the City
extending Euless beautification and branding efforts.
PROJECT SCHEDULE:
JUSTIFICATION:
To enable continuous efforts to identify, beautify, and brand the City of Euless.
wo
60
1-11
PROJECT TITLE: ENTRY MONUMENT SIGN PROGRAM
PROJECT CODE: CM0304
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Land Betterments $135,782
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $135,782
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $135,782
I Subtotal:
Total Estimated Annual Cost $01 Total Funding $135,782
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Land Betterments $135,782 $106,227 29,555 78%
AL PROJECT $135,782 $106,227 $29,555 78% I
61
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: July 11,2006
Submitted By: GARY MCKAMIE Date Completed:
Project Title: REDEVELOPMENT
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: CM0804 Priority: A
COUNCIL AUTHORIZATION:
Oct 23, 2007: Authorized the purchase of property on Lot 27, Block 2, Cresthaven Addn, 1010 Highland Dr
Nov 27, 2007: Authorized the purchase of property on Lot 24, Block 1, Cresthaven Addn, 1010 Cresthaven Dr
Dec 11, 2007: Authorized the purchase of property on Lots 17&18, Block 8, Cedar Hill Estates Addn, 710 S Main
Oct 28, 2008: Authorized the purchase of property on Lot 3, Block 2, Cresthaven Addn, 1007 Cresthaven Dr
Jan 13, 2009: Authorized the purchase of property on Lot 18, Block 1, Cresthaven Addn, 912 Cresthaven Dr; Lot
4, Block 2, Cresthaven Addn, 1005 Cresthaven Dr; and Lot 23, Block 2, Cresthaven Addn, 1002 Highland Dr
Mar 12, 2013: Authorized the purchase of property on N. Sheppard Drive (10 lots).
Nov 26, 2013: Authorized the purchase of property on 908 and 910 Cresthaven.
Feb 24, 2015: Authorized the purchase of property on 903 Cresthaven, 1447 W. Euless Blvd, and 901 and 904
Highland Drive.
Mar 24, 2015: Authorized the purchase of property on 215 E. Ash Lane.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding to allow the City to participate in redevelopment projects and other community
improvements or make acquisitions of property that will be of economic benefit to the City of Euless.
PROJECT DESCRIPTION:
Project includes City participation in community redevelopment projects and property acquisitions that will be of
economic benefit to the City.
PROJECT SCHEDULE:
Long-term on -going project for continuous improvement of the community.
JUSTIFICATION:
As the City ages, it is imperative that the economic vitality of the City remain strong. Reinvestment into the
community will protect property values from deterioration and keep commercial properties occupied and
vibrant.
ho
62
PROJECT TITLE: REDEVELOPMENT
PROJECT CODE: CM0804
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Land Acquisition $1,273,502
Personnel: Full Time Demolition $90,323
Part Time $0 Minor Apparatus $597
Total Salary $0 Incentives $10,000
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $1,374,422
Maintenance Costs Funding Source:
Transfer from:
General Fund $930,000
Interest Earnings $34,422
Drill Site Surface Damage $10,000
Subtotal: Car Rental Fund $400,000
Total Estimated Annual Cost
$01
Total Funding
$1,374,422
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Land Acquisition
$1,266,502 $319,594
$946,908
25%
Demolition
$90,323 $89,654
$669
99%
Minor Apparatus
$597 $167
$430
28%
Incentives
$10,000 $10,000
$0
100%
Other Professional Services
$7,000 $6,278
$722
90%
$1,374,422 $425,693 $948,729 31% I
63
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: July 22,2014
Submitted By: GARY MCKAMIE Date Completed:
Project Title: CAR RENTAL CONTINGENCY
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: CM1508 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
To provide funding for development opportunities that arise throughout the year.
PROJECT SCHEDULE:
JUSTIFICATION:
This project provides flexibility and enables the City to act quickly on development opportunities.
,-Is
64
Ow
PROJECT TITLE: CAR RENTAL CONTINGENCY
PROJECT CODE: CM1508
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Contingency $700,000
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $700,000
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $700,000
I Subtotal:
Total Estimated Annual Cost $01 Total Funding $700,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Contingency $700,000 $0 $700,000 0%
TOTAL PROJECT $700,000 $0 $700,000 0%
65
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MUNICIPAL PLAZA IMPROVEMENTS PHASE I
Project Type: FACILITIES Sub -Type: IMPROVEMENTS
Project Code: CM1509 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is the landscaping and irrigation related to the 40th CDBG ADA accessibility and infrastructure
improvements.
PROJECT DESCRIPTION:
Landscaping and irrigation improvements to the Municipal Plaza following the 40th CDBG ADA accessibility and
infrastructure improvements.
PROJECT SCHEDULE:
Begin Construction: March 2016
Anticipate Construction Complete: May 2016
JUSTIFICATION:
Beautification of the municipal plaza following the hardscape improvements.
66
PROJECT TITLE: MUNICIPAL PLAZA IMPROVEMENTS PHASE I
PROJECT CODE: CM1509
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Landscaping $158,500
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $158,500
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $100,000
Subtotal: $0 Additional Funding Needed:
Transfer from:
Car Rental CIP Fund Balance $58,500
Total Estimated Annual Cost $0 Total Funding $158,500
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Landscaping $158,500 $0 $158,500 0%
$158,500 $0 $158,500 0%
67
City of Euless
Capital Project Request
Department: ECONOMIC DEVELOPMENT Date Prepared: July 26,1999
Submitted By: BILL RIDGWAY Date Completed:
Project Title: EULESS DEVELOPMENT CORPORATION INCENTIVE
Project Type: EDC Sub -Type: DEVELOPMENT
Project Code: DV9901 Priority: A
COUNCIL AUTHORIZATION:
March 27, 2001: Approved transfer of $325,000 to North Main Street for right-of-way to free up funds for a sign
program.
May 30, 2006: Approved payment to Professional Turf Products, Inc. in the amount of $300,000 per agreement.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Euless Development Corporation funds that have been set aside to aid the City of Euless in attracting
development opportunities.
PROJECT SCHEDULE:
JUSTIFICATION:
Funding this project would enable the City to act quickly on development opportunities that arise throughout the
year.
68
M
PROJECT TITLE: EULESS DEVELOPMENT CORPORATION INCENTIVE PROJECT CODE: DV9901
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Will be based on the merits of
Personnel: Full Time
each opportunity.
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfers from:
EDC CIP Fund Balance
$913,454
EDC Operating Fund
$400,000
$0
Transfer to FS#2 SS0010
($432,600)
Subtotal:
$0
Transfer to N Main PS9901
($355,000)
Additional Funding Needed:
EDC Operating Fund
$25,000
Total Estimated Annual Cost
$0
Total Funding
$550,854
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Economic Development Incentives
$550,000 $450,000 $100,000
82%
Irrigation Supplies
$854 $853 $1
100%
TOTAL PROJECT
$550,854 $450,853 $100,001
82%
69
City of Euless
Capital Project Request
Department: ECONOMIC DEVELOPMENT Date Prepared: July 07,2000
Submitted By: BILL RIDGWAY Date Completed:
Project Title: PLANNING CONSULTANTS
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: ED0101 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding for evaluating various development opportunities.
PROJECT DESCRIPTION:
Commission a study to determine the highest and best use of valuable undeveloped commercial land.
PROJECT SCHEDULE:
JUSTIFICATION:
Poor planning can result in lower than desired tax revenue, hodge podge development activity, and less than
optimal development quality. The City needs to be proactive to guide the development of these vital tracts.
W
70
PROJECT TITLE: PLANNING CONSULTANTS
PROJECT CODE: ED0101
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Planning Study $204,869
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $204,
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $200,
Car Rental CIP Fund Balance $4,
$0
Subtotal: $0
Total Estimated Annual Cost $01 Total Fundina $204,869
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Planning Study $204,869 $104,869 100,000 51%
TOTAL PROJECT $204,869 $104,869 $100,000 51%
71
City of Euless
Capital Project Request
Department: ECONOMIC DEVELOPMENT Date Prepared: Sept 30,2010
Submitted By: GARY MCKAMIE Date Completed:
Project Title: EDC CONTINGENCY
Project Type: EDC Sub -Type: MISCELLANEOUS
Project Code: ED1002 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
To provide funding for emergencies or unforeseen projects that arise throughout the year.
PROJECT SCHEDULE:
JUSTIFICATION:
This would enable the City to act quickly on emergency or unforeseen projects. Without funding, these types of
projects would have to wait until the next budget cycle which could increase costs or impede economic
development opportunities.
."IN
W
72
PROJECT TITLE: EDC CONTINGENCY
PROJECT CODE: ED1002
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Contingency
$250,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
$250,000
Maintenance Costs
Funding Source:
Transfer from:
EDC CIP Fund Balance
$250,000
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Funding
$250,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Contingency
$250,000 $0 $250,000
0%
TOTAL PROJECT
$250,000 $0 $250,000
0%
73
City of Euless
Capital Project Request
Department: FACILITIES Date Prepared: April 11,2011
Submitted By: KYLE MCADAMS Date Completed:
Project Title: ADA/TAS FACILITY IMPROVEMENTS
Project Type: FACILITIES Sub -Type: IMPROVEMENTS
Proiect Code: FM1201 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for the continued improvements to various City facilities as required by Federal and State
mandated Americans with Disabilities Act/Texas Accessibility Standards ("ADA/TAS"). City facilities, entrances,
lifts, signage, speech and hearing aided devices, and other areas covered under both ADA and TAS
requirements will be part of these improvements. Project funds will be managed by the City Manager's Office and
will be allocated as identified projects are brought forth and approved.
PROJECT SCHEDULE:
JUSTIFICATION:
Some City facilities do not meet current ADAITAS standards. Updating accessibility on a continuing basis will
help keep the City in compliance with government standards and will address the growing needs of citizens with
accessibility issues.
74
PROJECT TITLE: ADA/TAS FACILITY IMPROVEMENTS
PROJECT CODE: FM1201
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Improvements
Personnel: Full Time (Minimum balance $75,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
Car Rental Fund
$50,000
General Fund
$50,000
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
Car Rental Fund
$15,000
Total Estimated Annual Cost
$01
Total Funding
$115,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Structural Maintenance
$112,000 $36,629 $75,371
33%
Trainina
$3,000 $2,758 $242
92%
PROJECT $115 000 $39,386 $75,614 34%
75
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 01,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: DEVELOPMENT/ENGINEERING BUILDING DESIGN
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: FM1510 Priority: A
COUNCIL AUTHORIZATION:
November 25, 2014: Authorized the City Manager to negotiate and execute an Architectural Services contract
pursuant to Request for Qualifications (RFQ) No. 015-14 with Oxley Williams Tharp Architects for the remodel of
the Development and Engineering building.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Development and Engineering Building is the final project planned as part of the City's 1999 Master
Construction plan.
PROJECT DESCRIPTION:
Planning and design phase for renovation of the Development and Engineering Building scheduled for FY2016.
Selected firm will conduct staff interviews, identify potential utilization of available space, complete design
process, create budget projections, and prepare plans and specifications for bid documents.
PROJECT SCHEDULE:
Planning / Design Work: December 2014 - March 2015
Bid Specifications: July 2015
Bid Project: August 2015
Receive Bids: September 2015
Council Approval: October 2015
Start Construction: December 2015
JUSTIFICATION:
The Development and Engineering Building received a major remodel in 1996 with renovation of the building's
interior. Due to limited funding at that time, certain elements could not be justified as part of the remodel.
76
PROJECT TITLE: DEVELOPMENT/ENGINEERING BUILDING DESIGN PROJECT CODE: FM1510
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating -Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Planning/Bid Specifications
Total Estimated 1
Funding Source:
Transfer from:
Car Rental Fund
I Cost
$94
$94,3501
$94,3501
Total Estimated Annual Cost $01 Total Funding $94,350
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Architectural Services $94,350 $34,600 $59,750 37%
'AL PROJECT
$94,350 $34,600 $59,750
37%
77
City of Euless
Capital Project Request
Department: TEXAS STAR GOLF COURSE Date Prepared: May 17,2011
Submitted By: GLENDA HARTSELL Date Completed:
Project Title: TSGC MISCELLANEOUS IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: TSGC IMPROVEMENTS
Project Code: GC1201 Priority: A
COUNCIL AUTHORIZATION:
September 23, 2014: Authorized the purchase of carpet for the Texas Star Golf Course Clubhouse and
Conference Centre from Vector Concepts through the BuyBoard Cooperative Purchasing Program. The
estimated expenditure is $60,878.14.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
To provide funding to address small capital projects that arise throughout the year at Texas Star Golf Course.
PROJECT SCHEDULE:
JUSTIFICATION:
Without funding for this project, the smaller items identified throughout the year could not be addressed in a
timely manner and would have to be postponed until the next budget cycle for funding consideration. Timely
response preserves the City's investment in a high -profile asset and maintains the quality service levels expected
from patrons.
78
PROJECT TITLE: TSGC MISCELLANEOUS IMPROVEMENTS
PROJECT CODE: GC1201
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost Improvements
Personnel: Full Time (Minimum balance $150,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
TSGC Reserve Fund
$315,000
Conf Center Imp. - GC1402
$40,000
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
TSGC Reserve Fund
$75,000
Total Estimated Annual Cost
$0
Total Fundina
$430,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Repair & Maintenance
$38,076 $38,076 $0
100%
Land Acquisition
$2,000 $2,000 $0
100%
Land Betterments
$40,105 $30,697 $9,408
77%
Improvements
$237,611 $76,233 $161,378
32%
Equipment
$112,208 $72,207 $40,001
64%
ITOTAL PROJECT $430 000 $219,212 $210,788 51%
79
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: March 23,2004
Submitted By: RAY MCDONALD Date Completed:
Project Title: MISCELLANEOUS PARK IMPROVEMENTS
Project Type: EDC Sub -Type: PARKS
Proiect Code: PR0720 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan recommends funding for system -wide park facilities and amenities upgrades.
PROJECT DESCRIPTION:
The project provides funding for the upgrade and modernization of City parks to include replacement of aged
structures such as pavilions, picnic tables, gazebos, signs, safety components, and other park amenities
including the addition of a gazebo on Main Street. Park infrastructure and structure painting are included in the
scope of the project. Additionally, the project encompasses the installation of trail lighting along the Trails of
Euless similar to the lighting installed along the trail through Midway Park. Trailwood Park, Bob Eden Trail, The
Preserve at McCormick Park, The Villages of Bear Creek Park and Heritage Park would also benefit from trail
lighting.
PROJECT SCHEDULE:
JUSTIFICATION:
Pursuant to the recommendations in the Parks Master Plan, park accessibility should be in compliance with the
Americans with Disabilities Act. The existing equipment in many park areas is becoming aged and will require
refurbishment or replacement in the near term. Additionally, park infrastructure should be maintained at a level
that meets citizen expectations. The popularity of the trails have necessitated the installation of lighting to extend
the hours of usage and to provide increased visibility in remote areas of the trail system.
80
PROJECT TITLE: MISCELLANEOUS PARK IMPROVEMENTS
PROJECT CODE: PR0721
INET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
uirect uperating Cost Fixtures, landscaping, lighting,
Personnel: Full Time & other park and infrastructure
Part Time $0 improvements
Total Salary $0
Purchase of Services (Minimum balance $100,000)
Materials & Supplies
Utilities
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
EDC Operating Fund
$575,000
Developer Contribution (TRA)
$10,500
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
Operating Fund
$80,000
Total Estimated Annual Cost
1EDC
$0
Total Funding
$665,500
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Park Furnishings
$474,848 $418,530 56,318
88%
Landscaping
$55,942 $40,167 15,775
72%
Contingency
$81,540 $57,702 23,838
71%
Park Lighting
$50,000 $0 50,000
0%
Equipment
$3,170 $3,170 0
100%
$665,500 $519,569 $145,931 78% 1
81
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: October 01,2007
Submitted By: RAY MCDONALD Date Completed:
Project Title: PARK IRRIGATION
Project Type: EDC Sub -Type: PARKS
Project Code: PR0804 Prioritv: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides annual funding to continue efforts to meet irrigation needs throughout the City's park
system.
IPROJECT SCHEDULE:
Projects will be identified and completed on an as needed basis.
JUSTIFICATION:
This project allows for maintenance and expansion of the irrigation systems throughout the parks system to
enhance the overall condition of the landscape and green space.
82
PROJECT TITLE: PARK IRRIGATION
PROJECT CODE: PR0804
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost (Annual Transfer $25,000)
Personnel: Full Time Irrigation $225,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $225,000
Maintenance Costs Funding Source:
Transfer from:
EDC Operating Fund $200,000
$0
Subtotal: $0 Additional Funding Needed:
Transfer from:
EDC Operating Fund $25,000
Total Estimated Annual Cost $0 Total Funding $225,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Irrigation $225,000 $87,116 137,884 39%
TOTAL PROJECT $225,000 $87,116 $137,884 39%
83
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 05,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: GLADE PARKS TRAIL CONNECTION
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Proiect Code: PR1401 Priori A
COUNCIL AUTHORIZATION:
March 25, 2014: Authorized the City Manager to execute an Engineering Design Contract with Mycoskie McInnis
Associates, Inc. for the design of the Glade Parks Trail Connection Project with an estimated expenditure of
$119,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
As identified in the Glade Parks development, this project proposes to connect the existing Trails of Euless to the
City of Colleyville trails through the Glade Parks Development.
PROJECT DESCRIPTION:
This phase of the project consists of the design, engineering, surveying, geotech and construction for a trail that
will connect to the existing trail at Creekwood Estates, run underneath the northbound service road, SH121, and
the southbound service road to the southeast corner of the Glade Parks Development. Future connectivity
through Glade Parks is planned within the overall development of that site.
PROJECT SCHEDULE:
Anticipate Design Complete: July 2015
Anticipate Construction Complete: June 2016
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development with
an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community as it
assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The development and maintenance of the trails system
continued to receive significant support from the citizens as indicated in the responses to the needs assessment
survey conducted as a part of the Parks Master Plan update.
84
PROJECT TITLE: GLADE PARKS TRAIL CONNECTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
PROJECT CODE: PR1401
TOTAL ESTIMATED CAPITAL COST:
Design
Engineering, Surveying and
Contingency
$55,000
$72,000
$1,237,045
$32,500
Subtotal:
$0
Total Estimated Capital Cost
$1,396,545
Maintenance Costs
Funding Source:
Transfer from:
Car Rental Fund
$474,545
Grant Award
$912,000
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
Car Rental Fund
$10,000
Total Estimated Annual Cost
$01
Total Funding
$1,396,545
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Design, Engineering, Surveying & Geotech
$127,000 $81,677 $45,323
64%
Construction
$1,237,045 $0 $1,237,045
0%
Continaencv
$32,500 $0 $32,500
0%
AL
$1,396,545 $81,677 $1,314,868
6%
85
T H E C I T Y O F
EULESS
'-'N
86
Go
4
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contributions
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
DRAINAGE PROJECTS
None Currently
A
$
Sub -Total Drainage Priority A -Proposed FY16
$
None Currently B
$
Sub -Total Drainage Priority B-Unfunded
$
Bell Hi Addition
C
TBD
XX
Blessing Branch -Main Street to SH 360
C
TBD
XX
Hollow Oak Channel Erosion
C
TBD
XX
Kynette Drive Culvert Modifications
C
TBD
XX
Little Bear Creek Drainage Improvements
C
TBD
XX
Marlene Drive Culvert Replacement
C
TBD
XX
Simmons Drive Culvert Improvements
C
TBD
XX
Sub -Total Drainage Priority C-Unfunded
$
DRAINAGE PROJECTS - TOTAL
STREET PROJECTS
East Harwood Road Extension
A
$ 100,000
XX
FY2016 41" CDBG-ADA/TAS Infrastructure Improvements
A
$ 59,301
XX
FY2016 Street Overlay
A
$ 600,000
XX
Sub -Total Street Priority A -Proposed FY16
$ 759,301
FY2017 42"d CDBG-ADA/TAS Infrastructure Improvements i'71
B
$ 91,000
XX
FY2017 Street Overlay (" )
B
$ 600,000
XX
XX
State Highway 183 East Improvements (17) _�
B
$ 250,000
XX
Traffic Signal -Harwood Road at Bear Creek Parkway (17) — --
B
$ 180,000
XX
FY2018 Street Overlay (19)
B
$ 600,000
XX
XX
Traffic Signal-Cheek-Sparger Road at Heritage Avenue (19)
B
$ 180,000
$ 50,000
$ 130,000
FY2019 44"' CDBG-ADA/TAS Infrastructure Improvements (19)
B
$ 110,000
XX
FY2019 Street Overlay (19)
B
$ 600,000
XX
XX
Bear Creek Parkway Reconstruction R0)
B
$ 1,290,000
XX
FY2020 Street Overlay I20i
B
$ 600,000
XX
XX
Vine Street Reconstruction-SH183 to SH10 (20)
B
$ 455,000
XX
XX
Sub -Total Street Priority B-Unfunded
$ 4,956,000
Cresthaven Drive Reconstruction
C
TBD
XX
E Alexander Lane Reconstruction
C
TBD
XX
Fuller -Wiser Road Reconstruction -Harwood Road to Mid Cities
Boulevard
C
TBD
XX
Fuller -Wiser Road Reconstruction-SH183 to Harwood Road
C
TBD
XX
Highland Drive Reconstruction
C
TBD
XX
Midway Drive Reconstruction
C
TBD
XX
Ross Avenue Extension
C
TBD
XX
South Pipeline Road Reconstruction
C
TBD
XX
Sub -Total Street Priority C-Unfunded
$
STREET PROJECTS - TOTAL
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contributions
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
WASTEWATER PROJECTS
LR: Glenn Drive
A
$ 253,000
XX
Sub -Total Wastewater Priority A -Proposed FY16
$ 253,000
LR: Cedar Hill Estates/Hollywood Boulevard
B
$ 129,000
XX
FY2017 42Id CDBG LR: Oakwood Terrace Phase I i"i
B
$ 209,000
XX
FY2018 43rd CDBG LR: Oakwood Terrace Phase II i'si
B
$ 472,000
$ 172,000
$ 300,000
LR: Ector Drive/Fayette Drive
B
$ 315,000
XX
LR: Milam Drive ('B)
B
$ 299,000
XX
SH183 Phase 11 Wastewater Relocation
B
$ 600,000
XX
LR: Kynette Drive/Wilshire Drive
B
$ 403,000
XX
Sub -Total Wastewater Priority B-Unfunded
$ 2,427,000
LR: Donley Drive/Shelmar Drive
C
TBD
XX
LR: Eastcliff Drive/Windlea Drive/Signet Drive
C
TBD
XX
LR: Ector Drive/Donley Drive/Crane Drive
C
TBD
XX
LR: Evans Drive/Canyon Ridge Drive/N Kynette Drive
C
TBD
XX
LR: Huntington/Koen/Atkerson/E Huitt/Slaughter/Martin
C
TBD
XX
LR: Janann StreettBrownstone/Shelmar Drive
C
TBD
XX
LR: Lakewood Boulevard/Dogwood Circle/Bocowood Circle
C
TBD
XX
LR: Live Oak Drive/Silver Creek Drive/Marlene Drive
C
TBD
XX
LR: Mary/Madene/Commerce/ Wilshire/Greenbriar
C
TBD
XX
LR: Northclrff/Toplea/Windlea/Signet/ Kynette/Westcliff
C
TBD
XX
LR: NW Midway Drive/Rusk Drive/Parker Drive/Rockwall Drive
C
TBD
XX
LR: S Main Street
C
TBD
XX
LR: Sagebrush/Toplea/Wilshire/Yorkshire/Tyler
C
TBD
XX
LR: Sierra Drive
C
TBD
XX
LR: W Donley/Private Drive/Mimosa/Magnolia/Redbud
C
TBD
XX
LR: W MidwayNictoria/Delta/ Lamar/Rockwall
C
TBD
XX
Sub-loral wastewarerPr—to—riTy—C-Un-fu-nVed
WASTEWATER PROJECTS - TOTAL
2,680,000
LH = Line Replacement
00
tp
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS -SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
fund
CIP Fund
Balance
Bond Sale
Grants/
Contributions
Impact
Fees
Escrow
funds
Car Rental
Tax
Other
EDC
To Be
Determined
WATER PROJECTS
LR: Donley Drive/Shelmar Drive
A
$ 212,000
XX
FY2016 41"CDBG LR: Ector Drive
A
$ 310,925
XX
Miscellaneous Valve Replacement
A
$ 120,000
XX
Reclaimed Water Line Extension Phase III
A
$ 1,280,000
XX
XX
Sub -Total Water Priority A -Proposed FYI 6
$ 1,922,925
Fort Worth Interconnect (") -
B
$ 300,000
XX
Reclaimed Water Line Extension Phase IV nel
B
$ 1,960,000
XX
FY2019 44' CDBG LR: Hollow Oak Drive ('9)
B
$ 190,000
XX
LR: Kynette Drive ('B)
B
$ 289,000
XX
SH183 Phase II Water Relocation i19i
B
$ 1,200,000
XX
FY2020 45' CDBG LR: S Main Street (South) (211
B
$ 300,000
XX
Reclaimed Water Line Extension Phase V r20)
B
$ 1,410,000
XX
Reclaimed Water Line Extension Phase VI r20I
B
$ 1,000,000
XX
LR: Sunset Drive (20)
B
$ 415,000
XX
Sub -Total Water Priority B-Unfunded
$ 7,064,000
LR: Blessing Creek/Stony Creek/Rock Creek
C
TBD
XX
LR: Collin Drive -Dallas Drive to Harwood Road
C
TBD
XX
LR: Collin Drive -Denton Drive to Dallas Drive
C
TBD
XX
LR: Denton Drive
C
TBD
XX
LR: Dickey Drive North
C
TBD
XX
LR: Dickey Drive South
C
TBD
XX
LR: Dunaway Drive
C
TBD
XX
LR: E Huitt Lane
C
TBD
XX
LR: Eastcliff Drive
C
TBD
XX
LR: Fuller Drive
C
TBD
XX
LR: Live Oak Court/Live Oak Drive
C
TBD
XX
LR: Midcreek/Rock Creek/Stony Creek
C
TBD
XX
LR: Midway Drive East
C
TBD
XX
LR: Midway Drive West
C
TBD
XX
LR: Needles Street
C
TBD
XX
LR: Paula Lane
C
TBD
XX
LR: S Main Street (North)
C
TBD
XX
LR: S Pipeline Road East
C
TBD
XX
LR: S Pipeline Road West
C
TBD
XX
SH360 Water Crossing
C
TBD
XX
LR Shady Creek Drive/Cliffwood Road
C
TBD
XX
LR: Springwood Court
C
TBD
XX
LR: Westwood Drive
C
TBD
XX
LR: Wildwood Street
C
TBD
XX
LR: Woodvine (East)
C
TBD
XX
LR: Woodvine (West)
C
T8D
XX
Sub -Total Water Priority C-Unfunded
$
WATER PROJECTS - TOTAL
8,986,92
tG
O
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contributions
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
OTHER PROJECTS
Development/Engineering Building Construction
A
$ 2,494,775
XX
Midtown Development
A
$ 16,748,583
XX
Texas Star Sports Complex Phase V
A
$ 2,307,767
$ 877,767
$ 730,000
$ 700,000
Sub -Total Other Priority A -Proposed FY16
$ 21,551,125
Municipal Plaza Improvements Phase II i"'
B
$ 150,000
XX
Texas Star Goff Course Maintenance Building ('r)
B
$ 110,000
XX
Texas Star Sports Complex Phase VI I"i
B
$ 926,573
XX
Blessing Branch Park Improvements
B
$ 267,120
XX
Texas Star Sports Complex Phase VII Design i1Bj
B
$ 810,930
XX
Library Remodel Design (19)
B
$ 147,630
XX
Texas Star Sports Complex Phase VII Construction i'sl
B
$ 5,946,821
XX
XX
Library Remodel Construction (20)
B
$ 2,000,000
XX
Trail Enhancements Phase 1 (21)
B
$ 184,523
XX
Sub -Total Other Priority 8-Unfunded
$ 10,543,597
Animal Shelter Expansion/Renovation
C
TBD
XX
Fire Station #2 Remodel
C
TBD
XX
Kiddie Carr Park Improvements
C
TBD
XX
South Euless Park Upgrades
C
TBD
XX
Trail Enhancements Phase 11
C
TBD
XX
Trail Enhancements Villages of Bear Creek
C
TBD
XX
Trailwood Park Improvements
C
TBD
XX
Wilshire Park Upgrades
C
TBD
XX
Sub -Total Other Priority C-Unfunded
OTHER PROJECTS - TOTAL
32,094,722
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED $ UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
DRAINAGE PROJECTS
None Currently
A
$
Sub -Total Drainage Priority A -Proposed FY16
$
None Currently B
$
Sub -Total Drainage Priority B-Unfunded
$
Bell Hi Addition
C
TBD
XX
Blessing Branch -Main Street to SH 360
C
TBD
XX
Hollow Oak Channel Erosion
C
TBD
XX
Kynette Drive Culvert Modifications
C
TBD
XX
Little Bear Creek Drainage Improvements
C
TBD
XX
Marlene Drive Culvert Replacement
C
TBD
XX
Simmons Drive Culvert Improvements
C
TBD
XX
Sub -Total Drainage Priority C-Unfunded
$
DRAINAGE PROJECTS -TOTAL
m
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: BELL HI ADDITION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005, the City commissioned and received a drainage plan from Freese and Nichols, Inc. In this plan, the
Bell Hi Addition was identified as an area in need of flood relief.
PROJECT DESCRIPTION:
The proposed project ties into an existing storm drainage system on Needles Street. A substantial portion of the
cost of this project is related to street repair which would indicate the need to combine this project with a street
reconstruction project.
PROJECT SCHEDULE:
JUSTIFICATION:
The construction of this project will prevent the flooding of Paula Lane, David Drive, and Needles Street during
the most intense rainfall events. The terrain in this location is very flat, which causes the streets to have a very
low capacity to remove storm water.
--N
W
W
92
PROJECT TITLE: BELL HI ADDITION
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
93
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: BLESSING BRANCH -MAIN STREET TO SH360
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Blessing Branch Drainage Master Plan included a conceptual plan to convey storm water through the creek
more efficiently.
PROJECT DESCRIPTION:
This project involves the channeling and lining of Blessing Branch in accordance with the Blessing Branch
Master Plan.
PROJECT SCHEDULE:
JUSTIFICATION:
The City expects to receive significant developer contributions toward this project. However, the City may be
required to fund a portion of this project.
t
94
PROJECT TITLE: BLESSING BRANCH -MAIN STREET TO SH360
NET
EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
°
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
°
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
95
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 03,2008
Submitted By: RON YOUNG Date Completed:
Project Title: HOLLOW OAK CHANNEL EROSION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In May 2008, the City authorized a drainage study for the creek area that runs at the rear of the lots fronting on
Hollow Oak Drive and Linkwood Drive. The completed drainage study was received in July 2008.
PROJECT DESCRIPTION:
The creek area along the rear of the lots on Hollow Oak Drive and Linkwood Drive exists in a natural state. The
creek bank along the south has experienced some slope failure. The drainage study recommends installation of
"bag wall" slope protection.
PROJECT SCHEDULE:
JUSTIFICATION:
The City has received complaints that fences and other improvements on private property will be threatened if
additional slope failures take place. Currently no residences are threatened.
96
OR
PROJECT TITLE: HOLLOW OAK CHANNEL EROSION
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
Due to the expected impact to the native conditions, this project would require broad support from all impacted
neighbors. Alternatives, such as possible assistance with removal or relocation of improvements on affected
properties, should also be considered.
97
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,1999
Submitted By: RON YOUNG Date Completed:
Project Title: KYNETTE DRIVE CULVERT MODIFICATIONS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Wilshire Village Addition was constructed prior to the adoption of the City's Uniform Development Code ("UDC").
The requirements prior to the UDC were lower than what the City now requires. The current construction
configuration of Wilshire Village causes more water to remain above ground than is acceptable under current
standards. The drainage system in the Wilshire Village Addition needs to be upgraded to meet the current
requirements.
PROJECT DESCRIPTION:
The project involves the installation of a small drainage system on Kynette Drive up to Sierra Drive. It is Project
No. 16 in the 1990 Knowlton, English, Flowers Drainage Utility System Study of Selected Improvement Projects.
PROJECT SCHEDULE:
JUSTIFICATION:
Surface water flow within Kynette Drive exceeds the City's current development standards. A large amount of
storm water drains to an existing culvert on Kynette Drive between Eastcliff and Westcliff Drives. The existing
drainage facilities collecting this storm water are inadequate according to current standards.
he
98
M
PROJECT TITLE: KYNETTE DRIVE CULVERT MODIFICATIONS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
99
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,1999
Submitted By: RON YOUNG Date Completed:
Project Title: LITTLE BEAR CREEK DRAINAGE IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The improvements proposed for Bob Eden Park are identified in the Little Bear Creek Watershed Master Plan.
The Little Bear Creek Park portion of this project was identified in the 1990 Knowlton, English and Flowers
Drainage Utility System Study of Selected Improvement Projects.
PROJECT DESCRIPTION:
Both parts of this drainage project involve erosion control and channelization improvements to Little Bear Creek.
The Bear Creek Park part is a portion of Project No. 11 in the above -referenced study. This project will be re-
evaluated to determine if the scope and proposed improvements should be modified. This part of the project will
be redefined and re -estimated.
PROJECT SCHEDULE:
JUSTIFICATION:
Continued erosion will eventually undermine the creek in both parks and cause damage to existing City facilities.
..N
100
PROJECT TITLE: LITTLE BEAR CREEK DRAINAGE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
101
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2008
Submitted By: RON YOUNG Date Completed:
Project Title: MARLENE DRIVE CULVERT REPLACEMENT
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Marlene Drive is noted as a collector street on the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The scope of the project includes construction of a new culvert at Cyclone Branch to meet current load and
drainage capacity standards. A portion of the concrete channel will also need to be reconstructed both
upstream and downstream to ensure a smooth transition.
PROJECT SCHEDULE:
JUSTIFICATION:
The existing culvert is load limited. The new culvert will be designed to convey sufficient drainage to comply
with current standards.
102
1.11
M
PROJECT TITLE: MARLENE DRIVE CULVERT REPLACEMENT
NEINT EFFECTS ON OPERATING AND
MATENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
103
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: SIMMONS DRIVE CULVERT IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005, the City commissioned and received a drainage plan from Freese and Nichols, Inc.
PROJECT DESCRIPTION:
An additional culvert will extend from the apartment complex on the east side of Simmons Drive and will outfall
into the creek area on the north side of Carr Park.
PROJECT SCHEDULE:
JUSTIFICATION:
In intense storms, the capacity of the existing culvert is exceeded. Additional culverts will be required to convey
the storm flows. The construction of this project will enable the safe use of Simmons Drive in intense storm
events.
104
PROJECT TITLE: SIMMONS DRIVE CULVERT IMPROVEMENTS
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
°
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
°
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
106
w
T H E C I T Y O F
EULESS
106
O
V
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
STREET PROJECTS
East Harwood Road Extension
A
$ 100,000
XX
FY2016 41s` CDBG-ADA/TAS Infrastructure Improvements
A
$ 59,301
XX
FY2016 Street Overlay
A
$ 600,000
XX
Sub -Total Street Priority A -Proposed FY16
$ 759,301
FY2017 42"d CDBG-ADA/TAS Infrastructure Improvements (")
B
$ 91,000
XX
FY2017 Street Overlay (17)
B
$ 600,000
XX
XX
State Highway 183 East Improvements (")
B
$ 250,000
XX
Traffic Signal -Harwood Road at Bear Creek Parkway i"i
B
$ 180,000
XX
FY2018 Street Overlay ('B)
B
$ 600,000
XX
XX
Traffic Signal-Cheek-Sparger Road at Heritage Avenue 11ei
B
$ 180,000
$ 50,000
$ 130,000
FY2019 44" CDBG-ADA/TAS Infrastructure Improvements (19)
B
$ 110,000
XX
FY2019 Street Overlay (19)
B
$ 600,000
XX
XX
Bear Creek Parkway Reconstruction (20)
B
$ 1,290,000
XX
FY2020 Street Overlay (20)
B
$ 600,000
XX
XX
Vine Street Reconstruction-SH183 to SH10 120i
B
$ 455,000
XX
XX
Sub -Total Street Priority B-Unfunded
$ 4,956,000
Cresthaven Drive Reconstruction
C
TBD
XX
E Alexander Lane Reconstruction
C
TBD
XX
Fuller -Wiser Road Reconstruction -Harwood Road to Mid
Cities Boulevard
C
TBD
XX
Fuller -Wiser Road Reconstruction-SH183 to Harwood Road
C
TBD
XX
Highland Drive Reconstruction
C
TBD
XX
Midway Drive Reconstruction
C
TBD
XX
Ross Avenue Extension
C
TBD
XX
South Pi eline Road Reconstruction
C
TBD
XX
Sub -Total Street Priority C-Unfunded
STREET PROJECTS - TOTAL
5,715,30
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 20,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: EAST HARWOOD ROAD EXTENSION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The Texas Department of Transportation and DFW Airport are combining efforts to extend East Harwood Road
through the airport to Rental Car Drive to provide additional access to airport properties. Euless has committed to
share in the cost of the extension in an amount not to exceed $100,000.
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
Participation in the project will provide Euless residents with an additional route to and through the airport properties.
108
PROJECT TITLE: EAST HARWOOD ROAD EXTENSION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Construction $100,000
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$100,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
n %
Conceptual Design
P 9
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
S P
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
109
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 17,2011
Submitted By: CHRIS BARKER Date Completed:
Project Title: FY2016 41 ST CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(41 st year CDBG project)
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
No
1-.11-1
110
PROJECT TITLE: FY2016 41 ST CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
TOTAL ESTIMATED CAPITAL COST:
Construction
$59,301 1
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$59,301
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Council Authorization:
February 24, 2015: Conduct a Public Hearing for the proposed 41 st year CDBG projects which include the
installation of sidewalk accessibility ramps along W. Harwood Road, and motion to approve a recommendation
regarding the selected CDBG projects.
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2016 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Anticipate Construction Beginning: May 2016
Anticipate Construction Complete: July 2016
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadways, and will enhance the appearance of the streets.
112
OR
M
PROJECT TITLE: FY2016 STREET OVERLAY
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$600,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
9
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
113
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 16,2012
Submitted By: CHRIS BARKER Date Completed:
Project Title: FY2017 42ND CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(42nd year CDBG project)
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
114
7
PROJECT TITLE: FY2017 42ND CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost
Construction
$91,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$91,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
115
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2017 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Anticipate Construction Beginning: May 2017
Anticipate Construction Complete: July 2017
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadways, and will enhance the appearance of the streets.
116
PROJECT TITLE: FY2017 STREET OVERLAY
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
L
117
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: STATE HIGHWAY 183 EAST IMPROVEMENTS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Various street improvements and realignments necessitated by the SH183 East expansion project.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
The expansion of 183 eastward may necessitate street improvements and the realignment of various City
streets. These improvements will help facilitate efficient traffic flow and property redevelopment.
wo
-IN
118
PROJECT TITLE: STATE HIGHWAY 183 EAST IMPROVEMENTS
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Improvements
$250,000
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $250,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
119
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: TRAFFIC SIGNAL-HARWOOD ROAD @ BEAR CREEK PARKWAY
Project Type: STREET Sub -Type: SIGNALIZATION
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic signals are located at the intersections of arterial and collector thoroughfares identified in the City's
Master Thoroughfare Plan adopted in 1999.
PROJECT DESCRIPTION:
The project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection, and signal controller for the intersection of Harwood Road and Bear
Creek Parkway.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Traffic volumes at this intersection will be monitored and signal warrant studies will be performed to justify signal
installation. This intersection will ultimately require a traffic signal.
.-IN
120
7
PROJECT TITLE: TRAFFIC SIGNAL-HARWOOD ROAD @ BEAR CREEK PARKWAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $30,000
Traffic Signals $150,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$180,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
121
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2018 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Anticipate Construction Beginning: May 2018
Anticipate Construction Complete: July 2018
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
._N
122
L
PROJECT TITLE: FY2018 STREET OVERLAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
123
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 0412812015
Submitted By: HAL CRANOR Date Completed:
Project Title: TRAFFIC SIGNAL-CHEEKSPARGER ROAD @ HERITAGE AVENUE
Project Type: STREET Sub -Type: SIGNALIZATION
Proiect Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic signals are located at the intersections of arterial and collector thoroughfares identified in the City's
Master Thoroughfare Plan adopted in 1999. The development of Glade Parks may produce a need for a traffic
signal at this intersection.
PROJECT DESCRIPTION:
The project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection, and signal controller for the intersection of Cheeksparger Road and
Heritage Avenue.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Traffic volumes at this intersection will be monitored and signal warrant studies will be performed to justify signal
installation. This intersection will ultimately require a traffic signal.
-14N
'-11\
124
PROJECT TITLE: TRAFFIC SIGNAL-CHEEKSPARGER ROAD @ HERITAGE AVENUE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $30,000
Personnel: Full Time Traffic Signals $150,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$180,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Other
$50,000
Supplemental Sales Tax
Car Rental Tax Fund
$130,000
To Be Determined
ADDITIONAL COMMENTS:
Escrow Funds will be used to finance a portion of this project
125
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: CHRIS BARKER Date Completed:
Project Title: FY2019 44TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(44th year CDBG project)
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
126
PROJECT TITLE: FY2019 44TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$110,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$110,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability.
127
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2019 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Proiect Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Anticipate Construction Beginning: May 2019
Anticipate Construction Complete: July 2019
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
128
PROJECT TITLE: FY2019 STREET OVERLAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
129
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 04/28/2015
Submitted By: HAL CRANOR Date Completed:
Project Title: BEAR CREEK PARKWAY RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Bear Creek Parkway is identified as a local collector thoroughfare in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the complete reconstruction of Bear Creek Parkway from Harwood Road to Ash Lane to
meet current City standards.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Bear Creek Parkway is an aging roadway nearing the end of its service life. Portions of the roadway are
beginning to deteriorate and require additional maintenance. As the pavement deteriorates and fails,
maintenance costs increase.
130
OR
L
PROJECT TITLE: BEAR CREEK PARKWAY RECONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $90,000
Construction $1,200,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,290,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
XX
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
131
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2020 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Anticipate Construction Beginning: May 2020
Anticipate Construction Complete: July 2020
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
132
PROJECT TITLE: FY2020 STREET OVERLAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
133
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 04/28/2015
Submitted By: HAL CRANOR Date Completed:
Project Title: VINE STREET RECONSTRUCTION-SH183 TO SH10
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Vine Street is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of the reconstruction of Vine Street from SH183 to SH10.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
The City has received street escrow funds from several developments along Vine Street. When development is
complete, it would be appropriate for the City to reconstruct the existing roadway.
MR
134
MIN
PROJECT TITLE: VINE STREET RECONSTRUCTION-SH183 TO SH10
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $55,000
Personnel: Full Time Construction $380,000
Part Time $0 ROW $20,000
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$455,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
XX
Revenue Bonds
Other
XX
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Escrow Funds will be used to finance a portion of this project
136
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: CRESTHAVEN DRIVE RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Cresthaven Drive is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project includes the reconstruction of Cresthaven Drive from a two-lane asphalt roadway to a 31' wide curb
and gutter concrete street from SH10 to S Pipeline Road.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade Cresthaven Drive to a standard City concrete curb and gutter street.
W
136
PROJECT TITLE: CRESTHAVEN DRIVE RECONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
137
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 23,1999
Submitted By: RON YOUNG Date Completed:
Project Title: E ALEXANDER LANE RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This minor street serves as a collector type street by conveying traffic to major roadways.
PROJECT DESCRIPTION:
E Alexander Lane will be reconstructed from Main Street to Cullum Drive. It will be reconstructed from a two-
lane county type road to a standard 31' wide residential street with underground drainage and sidewalks.
PROJECT SCHEDULE:
JUSTIFICATION:
Reconstruction of this street will decrease the annual maintenance and provide compliance with current City
standards.
138
\-..r
PROJECT TITLE: E ALEXANDER LANE RECONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To be Determined
Personnel: Full Time Construction - To be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Other
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
w
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
139
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 0412812015
Submitted By: HAL CRANOR Date Completed:
Project Title: FULLER -WISER ROAD RECONSTRUCTION-HARWOOD ROAD TO MID CITIES BLVD
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Fuller -Wiser Road is identified as a minor arterial in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the complete reconstruction of Fuller -Wiser Road to current City standards from
Harwood Road to Mid Cities Boulevard. The project includes the replacement of 6,775 linear feet of a 24 inch
water line.
PROJECT SCHEDULE:
JUSTIFICATION:
Fuller -Wiser Road is an aging roadway nearing the end of its service life. Portions of the roadway are beginning
to deteriorate and require additional maintenance. As the pavement deteriorates and fails, maintenance costs
increase.
W
140
MR
PROJECT TITLE: FULLER -WISER ROAD RECONSTRUCTION-HARWOOD ROAD TO MID CITIES BLVD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans ova
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
141
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 0412812015
Submitted By: HAL CRANOR Date Completed:
Project Title: FULLER -WISER ROAD RECONSTRUCTION-SH183 TO HARWOOD ROAD
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Fuller -Wiser Road is identified as a minor arterial in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of the complete reconstruction of Fuller -Wiser Road to current standards from SH183 to
Harwood Road. The project includes the replacement of 4,775 linear feet of a 16 inch water line.
PROJECT SCHEDULE:
JUSTIFICATION:
Fuller -Wiser Road is an aging roadway nearing the end of its service life. Portions of the roadway are beginning
to deteriorate and require additional maintenance. As the pavement deteriorates and fails, maintenance costs
increase.
142
M
PROJECT TITLE: FULLER -WISER ROAD RECONSTRUCTION-SH183 TO HARWOOD ROAD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
143
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: HIGHLAND DRIVE RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Highland Drive is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project includes the reconstruction of Highland Drive from SH10 to S Pipeline Road from a two-lane asphalt
roadway to a 31' wide curb and gutter concrete street.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade Highland Drive to a standard City concrete curb and gutter street.
144
PROJECT TITLE: HIGHLAND DRIVE RECONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
145
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 05/04/2015
Submitted By: HAL CRANOR Date Completed:
Project Title: MIDWAY DRIVE RECONSTRUCTION- BEAR CREEK TO WEST OF FULLER WISER
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Midway is identified as a Minor arterial in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the complete reconstruction of Midway from Bear Creek Parkway to just west of Fuller
Wiser (approximately 2200 LF).
PROJECT SCHEDULE:
JUSTIFICATION:
Midway is an aging road that is nearing its service life. As maintenance costs increase due to the increased
deterioration, complete reconstruction will become necessary.
146
L
PROJECT TITLE: MIDWAY DRIVE RECONSTRUCTION- BEAR CREEK TO WEST OF FULLER WISER
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To be Determined
Personnel: Full Time
Construction - To be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
147
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2005
Submitted By: RON YOUNG Date Completed:
Project Title: ROSS AVENUE EXTENSION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This extension of Ross Avenue from the recently completed section adjacent to the fire station will complete the
upgrading of this street.
PROJECT DESCRIPTION:
The construction of the remainder of Ross Avenue from the fire station to the west limit will be in accordance
with City standards which includes concrete pavement.
PROJECT SCHEDULE:
JUSTIFICATION:
This construction, in accordance with City standards, will allow the road a long service life and lower the annual
maintenance costs.
W
148
OR
PROJECT TITLE: ROSS AVENUE EXTENSION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Right -of -Way - To Be Determined
Part Time
$0
Construction - To Be Determined
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
149
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: SOUTH PIPELINE ROAD RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
South Pipeline Road is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of reconstruction of South Pipeline Road from a two-lane asphalt roadway to a 31' wide
curb and gutter concrete street from east of Royal Parkway to east of Highland Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade South Pipeline Road to a standard City concrete curb and gutter street.
150
PROJECT TITLE: SOUTH PIPELINE ROAD RECONSTRUCTION
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
IN ATENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
°
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
151
'1
T H E C I T Y O F
EULESS
152
Cn
W
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
good Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
WASTEWATER PROJECTS
LR: Glenn Drive
A
$ 253,000
XX
Sub -Total Wastewater Priority A -Proposed FY16
$ 253,000
LR: Cedar Hill Estates/Hollywood Boulevard
B
$ 129,000
XX
FY2017 42"' CDBG LR: Oakwood Terrace Phase 1 (171
B
$ 209,000
XX
FY2018 43rd CDBG LR: Oakwood Terrace Phase 11 i'9)
B
$ 472,000
$ 172,000
$ 300,000
LR: Ector Drive/Fayette Drive771
B
$ 315,000
XX
LR: Milam Drive (19)
B
$ 299,000
XX
SH183 Phase II Wastewater Relocation
B
$ 600,000
XX
LR: Kynette Drive/Wilshire Drive
B
$ 403,000
XX
Sub -Total Wastewater Priority B-Unfunded
$ 2,427,000
LR: Donley Drive/Shelmar Drive
C
TBD
XX
LR: Eastcliff DriveAAfindlea Drive/Signet Drive
C
TBD
XX
LR: Ector Drive/Donley Drive/Crane Drive
C
TBD
XX
LR: Evans Drive/Canyon Ridge Drive/N Kynette Drive
C
TBD
XX
LR: Huntington/Koen/Atkerson/E Huitt/Slaughter/Martin
C
TBD
XX
LR: Janann Street/Brownstone/Shelmar Drive
C
TBD
XX
LR: Lakewood Boulevard/Dogwood Circle/Bocowood Circle
C
TBD
XX
LR: Live Oak Drive/Silver Creek Drive/Marlene Drive
C
TBD
XX
LR: Mary/Marlene/Commerce/ Wilshire/Greenbriar
C
TBD
XX
LR: Northcliff/Toplea/Windlea/Signet/ Kynette/Westcliff
C
TBD
XX
LR: NW Midway Drive/Rusk Drive/Parker Drive/Rockwall Drive
C
TBD
XX
LR: S Main Street
C
TBD
XX
LR: Sagebrush/Toplea/WilshireNorkshire/Tyler
C
TBD
XX
LR: Sierra Drive
C
TBD
XX
LR: W Donley/Private Drive/Mimosa/Magnolia/Redbud
C
TBD
XX
LR: W MidwayNictoria/Delta/ Lamar/Rockwall
C
TBD
XX
Sub- Total Wastewater nonC-Unfunded
WASTEWATER PROJECTS - TOTAL
LR = Line Replacement
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-GLENN DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains located west of Glenn Drive from Aransas
Drive to Glenn Drive.
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
164
OR
PROJECT TITLE: LINE REPLACEMENT-GLENN DRIVE
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $33,000
Construction $220,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$253,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
155
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -CEDAR HILLS ESTATES/HOLLYWOOD BOULEVARD
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of wastewater mains in the Cedar Hill Addition along Hollywood
Boulevard from Vine Street to east of Cannon Drive.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
156
PROJECT TITLE: LINE REPLACEMENT -CEDAR HILLS ESTATES/HOLLYWOOD BOULEVARD
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$17,000
Personnel: Full Time
Construction
$112,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$129,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
157
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 20,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: 42ND CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE I
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Between Hollywood Boulevard and Reaves Court from Vine Street to the end of Reaves Court and
2. From Hollywood Boulevard to Reaves Court along 306 Hollywood Boulevard.
(42nd year CDBG project)
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
158
OR
PROJECT TITLE: 42ND CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE I
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $27,000
Personnel: Full Time Cosntruction $182,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$209,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
159
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: 43RD CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE II
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains..
1. Along 608 and 610 Martha Street,
2. Between Martha Street and Cannon Drive from Reaves Court to W Huitt Lane,
3. Between Jefflyn Court and W Huitt Lane from Martha Street to S Main Street, and
4. Between Henslee Drive and Cannon Drive from Reaves Court to Jefflyn Court.
(43rd year CDBG project)
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
160
PROJECT TITLE: 43RD CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE II
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$62,000
Personnel: Full Time
Construction
$410,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$472,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
$172,000
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
$300,000
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability.
161
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-ECTOR DRIVE/FAYETTE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains between Fayette Drive and Ector Drive from
Harwood Road to the end of the line.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
162
OR
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE/FAYETTE DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$41,000
Personnel: Full Time
Construction
$274,000
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$315,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
163
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-MILAM DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains located along Milam Drive from Blanco Drive to
south of Bell Drive.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
164
PROJECT TITLE: LINE REPLACEMENT-MILAM DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $39,000
Construction $260,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$299,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
165
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 06,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: SH183 PHASE II WASTEWATER RELOCATION
Project Type: WASTEWATER Sub -Type: LINE RELOCATION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Department of Transportation ("TxDoT") has planned for the expansion of SH183. The Phase II
construction will affect the City of Euless' utilities along and crossing SH183 between FM157 and the east city
limits.
PROJECT DESCRIPTION:
The City of Euless has wastewater mains and associated items located within the SH183 right-of-way. These
facilities must be relocated to accommodate Phase II of the SH183 expansion. It is anticipated that the City of
Euless will enter into a relocation agreement with the contractor selected by TxDoT to authorize them to design
and relocate wastewater lines. The City will be responsible for the cost of the relocation of the utilities.
PROJECT SCHEDULE:
Est. FY2019
JUSTIFICATION:
City of Euless wastewater facilities are located within TxDoT right-of-way. As such, the City must provide for
utility relocation to accommodate the roadway expansion.
166
PROJECT TITLE: SH183 PHASE II WASTEWATER RELOCATION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
WW Line Relocation Reimbursement
$600,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding schedule: FY2016 $150,000
W/WW Operating Fund
FY2017 $150,000
W/WW Operating Fund
FY2018 $150,000
W/WW Operating Fund
FY2019 $150,000
W/WW Operating Fund
167
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-KYNETTE DRIVE/WILSHIRE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Kynette Drive from Eastcliff Drive to Wilshire Drive and
2. Wilshire Drive from Kynette Drive extending 1000' north.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
W
168
Oq
PROJECT TITLE: LINE REPLACEMENT-KYNETTE DRIVE/WILSHIRE DRIVE
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $53,000
Construction $350,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$403,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
00 0
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
169
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-DONLEY DRIVE/SHELMAR DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater lines:
1. Donley Drive from Shelmar Drive to W Ash Lane,
2. Donley Drive from Harwood Road to Shelmar Drive, and
3. Shelmar Drive from Green Hill Street to the end of Shelmar Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
170
Lw_ 9
PROJECT TITLE: LINE REPLACEMENT-DONLEY DRIVE/SHELMAR DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
171
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-EASTCLIFF DRIVE/WINDLEA DRIVE/SIGNET DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project includes the replacement of the following wastewater mains:
1. Eastcliff Drive from Tyler Avenue to Signet Drive,
2. Windlea Drive from Eastcliff Drive to Wilshire Drive, and
3. Between Windlea Drive and Signet Drive from Eastcliff Drive to Wilshire Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
172
M
IM
PROJECT TITLE: LINE REPLACEMENT-EASTCLIFF DRIVE/WINDLEA DRIVE/SIGNET DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
173
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-ECTOR DRIVE/DONLEY DRIVE/CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Ector Drive and Donley Drive from Aransas Drive to Harwood Road and
2. Between Donley Drive and Crane Drive from Aransas Drive to Harwood Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
174
1...
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE/DONLEY DRIVE/CRANE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
175
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-EVANS DRIVE/CANYON RIDGE DRIVE/N KYNETTE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Evans Drive and Canyon Ridge Drive from Cyclone Branch to north of Kynette Drive and
2. North of Kynette Drive from Canyon Ridge Drive to Cyclone Branch.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
W
176
PROJECT TITLE: LINE REPLACEMENT-EVANS DRIVE/CANYON RIDGE DRIVE/N KYNETTE DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
o
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
177
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REP-HUNTINGTON/KOEN/ATKERSON/E HUITT/SLAUGHTER/MARTIN
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. East of Huntington Drive from S Atkerson Lane to E Alexander Lane,
2. Between Koen Lane and S Atkerson Lane from Huntington Drive to FAA Road,
3. Between S Atkerson Lane and N Atkerson Lane from Huntington Drive to FAA Road,
4. Between N Atkerson Lane and E Huitt Lane from Huntington Drive to FAA Road,
5. Between E Huitt Lane and Slaughter Lane from Huntington Drive to FAA Road,
6. Between Slaughter Lane and Martin Lane from Huntington to FAA Road, and
7. Between Martin Lane and E Alexander Lane from Huntington Drive to FAA Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
'1
W
178
OR
PROJECT TITLE: LINE REP-HUNTINGTON/KOEN/ATKERSON/E HUITT/SLAUGHTER/MARTIN
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
179
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-JANANN STREET/BROWNSTONE DRIVE/SHELMAR DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Janann Street from Aransas Drive to Donley Drive,
2. Brownstone Drive from Aransas Drive to Donley Drive,
3. Shelmar Drive from Greenhill Street to Aransas Drive, and
4. Aransas Drive from 500' south of Shelmar Drive to Janann Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
180
0101
PROJECT TITLE: LINE REPLACEMENT-JANANN STREET/BROWNSTONE DRIVE/SHELMAR DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost Engineering -To be Determined
Personnel: Full Time Construction - To be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
181
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-LAKEWOOD BLVD/DOGWOOD CIRCLE/BOCOWOOD CIRCLE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains..
1. Lakewood Boulevard from Dogwood Circle north to Private Drive and
2. Dogwood Circle, Cypress Circle, Bocowood Circle, and Aspenway Circle.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
.-1
182
M
IR
PROJECT TITLE: LINE REPLACEMENT-LAKEWOOD BLVD/DOGWOOD CIRCLE/BOCOWOOD CIRCLE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
183
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 16,2012
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP -LIVE OAK DRIVE/SILVER CREEK DRIVE/MARLENE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Live Oak Drive from Silver Creek Drive south to Hurricane Creek,
2. Mains in the cul-de-sacs on the east side of Live Oak Drive,
3. Silver Creek Drive between Westpark Way and Evans Drive, and
4. Marlene Drive between Live Oak and Marlene Court.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
',IN
184
1..._.
PROJECT TITLE: LINE REP -LIVE OAK DRIVE/SILVER CREEK DRIVE/MARLENE DRIVE
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
� Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
185
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-MARY/MARLENE/COMMERCE/WILSHI RE/GREENBRIAR
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Mary Drive and Marlene Drive from Cyclone Branch to Marlene Drive,
2. Between Commerce Street and Wilshire Drive from Marlene Drive to Sagebrush Trail,
3. South of Greenbriar Drive from Cyclone Branch to Debra Drive,
4. Between Greenbriar Drive and Mary Street from Eastcliff Drive to Debra Drive, and
5. East of Debra Drive and south of Mary Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
_,�N
186
M
PROJECT TITLE: LINE REPLACEMENT-MARY/MARLENE/COMMERCE/WILSHI RE/GREENBRIAR
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
187
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-NORTHCLIFF/TOPLEA/WINDLEA/SIGNET/KYNETTE/WESTCLIFF
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Northcliff Drive and Toplea Drive from Canyon Ridge to Cyclone Branch,
2. Between Toplea Drive and Windlea Drive from Canyon Ridge to Cyclone Branch,
3. Between Windlea Drive and Signet Drive from Canyon Ridge to Cyclone Branch,
4. Between Signet Drive and Kynette Drive from the church to Cyclone Branch, and
5. Westcliff Drive from Toplea Drive to north of Windlea Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
'-'IN
188
RON
00,
PROJECT TITLE: LINE REP-NORTHCLIFF/TOPLEA/WINDLEA/SIGNET/KYNETTE/WESTCLIFF
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
189
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -NW MIDWAY/RUSK/PARKER/ROCKWALL
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. North of West Midway Drive from FM157 to Parker Drive,
2. West Midway Drive from Parker Drive to Rusk Drive,
3. Rusk Drive from West Midway Drive to Parker Drive,
4. Parker Drive from West Midway Drive to Rockwall Drive, and
5. Rockwall Drive from west of Parker Drive to 400' west of Lamar Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
190
U
N'...
PROJECT TITLE: LINE REPLACEMENT -NW MIDWAY/RUSK/PARKER/ROCKWALL
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To be Determined
Personnel: Full Time
Construction - To be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
Subtotal:
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
191
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-S MAIN STREET
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater main along S Main Street from Jean Lane to W
Alexander Lane.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
192
OR
PROJECT TITLE: LINE REPLACEMENT-S MAIN STREET
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To be Determined
Personnel: Full Time Construction - To be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
193
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-SAGEBRUSH/TOPLEA/WILSHIRE/YORKSHIRE/TYLER
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Sagebrush Trail and Toplea Drive from Cyclone Branch to east of Wilshire Drive,
2. Between Wilshire Drive and Yorkshire Drive from Signet Drive to south of Toplea Drive,
3. Between Sagebrush Trail and Tyler Avenue from Cyclone Branch to Commerce Street,
4. Eastcliff Drive from Tyler Avenue to the apartments, and
5. Between Marlene Drive and Tyler Avenue from Eastcliff Drive to Commerce Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
194
PROJECT TITLE: LINE REPLACEMENT-SAGEBRUSH/TOPLEA/WILSHIRE/YORKSHIRE/TYLER
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
o
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
195
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 01,2011
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SIERRA DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of replacement of the following wastewater mains:
1. Between Sierra Drive and Eastcliff Drive from Kynette Drive to Signet Drive and
2. East of Sierra Drive from Wilshire Park to Signet Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
wo
196
PROJECT TITLE: LINE REPLACEMENT -SIERRA DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
197
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-W DONLEY/PRIVATE DRIVE/MIMOSA/MAGNOLIA/REDBUD
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. West of Donley Drive from West Ash Lane to Private Drive,
2. Private Drive from west of Redbud Drive to Lakewood Boulevard,
3. Mimosa Lane from Bocowood Drive to Private Drive,
4. Magnolia Lane from Bocowood Drive to Private Drive, and
5. Redbud Drive from Bocowood Drive to Private Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
W
198
PROJECT TITLE: LINE REPLACEMENT-W DONLEY/PRIVATE DRIVE/MIMOSA/MAGNOLIA/REDBUD
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
199
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-W MIDWAY/VICTORIA/DELTA/LAMAR/ROCKWALL
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay the wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. West Midway Drive from FM157 to Victoria Drive,
2. Victoria Drive from West Midway Drive north 700',
3. Delta Drive from West Midway Drive north 1000',
4. Lamar Drive from West Midway Drive north to Fayette Drive, and
5. Rockwall Drive from Lamar Drive west and north 800'.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
200
7
PROJECT TITLE: LINE REP-W MIDWAYVICTORIA/DELTA/LAMAR/ROCKWALL
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
201
T H E C I T Y 0 F
EULESS
i•
i•
202
N
O
W
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
WATER PROJECTS
LR: Donley Drive/Shelmar Drive
A
$ 212,000
XX
FY2016 41s1 CDBG LR: Ector Drive
A
$ 310,925
XX
Miscellaneous Valve Replacement
A
$ 120,000
XX
Reclaimed Water Line Extension Phase III
A
$ 1,280,000
XX
XX
Sub -Total Water Priority A -Proposed FYI
$ 1,922,926
Fort Worth Interconnect 1"I
B
$ 300,000
XX
Reclaimed Water Line Extension Phase IV (19)
B
$ 1,960,000
XX
FY2019 441" CDBG LR: Hollow Oak Drive (19)
B
$ 190,000
XX
LR: K nette Drive (19)
B
$ 289,000
XX
SH183 Phase II Water Relocation 19i
B
$ 1,200.000
XX
FY2020 451" CDBG LR: S Main Street (South) (211
B
$ 300,000
XX
Reclaimed Water Line Extension Phase V i20)
B
$ 1,410.000
XX
Reclaimed Water Line Extension Phase VI (20)
B
$ 1,000,000
XX
LR: Sunset Drive (20)
B
$ 415,000
XX
Sub -Total Water Priority B-Unfunded
$ 7,064,000
LR: Blessing Creek/Stony Creek/Rock Creek
C
TBD
XX
LR: Collin Drive -Dallas Drive to Harwood Road
C
TBD
XX
LR: Collin Drive -Denton Drive to Dallas Drive
C
TBD
XX
LR: Denton Drive
C
TBD
XX
LR: Dickey Drive North
C
TBD
XX
LR: Dickey Drive South
C
TBD
XX
LR: Dunaway Drive
C
TBD
XX
LR: E Huitt Lane
C
TBD
XX
LR: Eastcliff Drive
C
TBD
XX
LR: Fuller Drive
C
TBD
XX
LR: Live Oak Court/Live Oak Drive
C
TBD
XX
LR: Midcreek/Rock Creek/Stony Creek
C
TBD
XX
LR: Midway Drive East
C
TBD
XX
LR: Midway Drive West
C
TBD
XX
LR: Needles Street
C
TBD
XX
LR: Paula Lane
C
TBD
XX
LR: S Main Street (North)
C
TBD
XX
LR: S Pipeline Road East
C
TBD
XX
LR: S Pipeline Road West
C
TBD
XX
SH360 Water Crossing
C
TBD
XX
LR: Shady Creek Drive/Cliffwood Road
C
TBD
XX
LR Sprin wood Court
C
TBD
XX
LR: Westwood Drive
C
TBD
XX
LR: Wildwood Street
C
TBD
XX
LR: Woodvine (East)
C
TBD
XX
LR: Woodvine (West)
C
TBD
XX
Sub -Total Water Priority C-Unfunded
$
WATER PROJECTS - TOTAL
8,986, 25
arc = une mapiacerneni
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT- DONLEY & SHELMAR DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,212 feet of 6" cast iron main with an 8" PVC main along Donley
Drive from Glen Drive to Shelmar Drive and along Shelmar Drive from Donley Drive (E) to Donley Drive (W).
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
No
204
PROJECT TITLE: LINE REPLACEMENT- DONLEY & SHELMAR DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $25,000
Construction $187,000'
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$212,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
o
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
206
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 26,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2016 41 ST CDBG-LINE REPLACEMENT ECTOR DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,840 feet of 6" cast iron water main with an 8" PVC main on Ector
Drive from Trojan Trail to Midway Drive.
(41st year CDBG project)
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
Milk
206
PROJECT TITLE: FY2016 41ST CDBG-LINE REPLACEMENT ECTOR DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
TOTAL ESTIMATED CAPITAL COST:
Construction
$310,925
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$310,925
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Council Authorization. -
February 24, 2015: Conduct a Public Hearing for the proposed 41 st year CDBG projects which include the
replacement of a six (6") inch water main with an eight (8") inch waterline on N. Ector Road from Midway Drive to
Trojan Trail.
207
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: MISCELLANEOUS VALVE REPLACEMENT
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project will be a reoccurring on a biennial basis. Starting in 2016, two valves that operate on major
transmission lines will be replaced with butterfly valves.
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
Old and deteriorated water valves prevent water lines from being isolated in the event of a line break. Not being
able to isolate as small a segment as possible during a line break increases the labor required to isolate the line,
as well as the number of residents and fire hydrants that would be affected by a line break. Systematic annual
replacement of old deteriorated water valves will increase efficiency, reduce maintenance costs, and ensure
maximum fire protection and water service availability.
208
No
PROJECT TITLE: MISCELLANEOUS VALVE REPLACEMENT
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering
$10,000
Personnel: Full Time
Construction
$100,000
Part Time
$0
10% Contingency
$10,000
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$120,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
209
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE III
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase III would extend the project to supply approximately 17MG
annually to 5 additional properties. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
*Design: FY2016
*Construction: FY2017
*Subject to availability of funds.
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
210
LOW
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE III
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $230,000
$p Construction $1,050,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,280,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
211
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 06,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: FORT WORTH INTERCONNECT
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of a connection to the City of Fort Worth's 24-inch water main on Main Street and South
Pipeline Road. In the event of an emergency, the City will be able to receive water from the City of Forth Worth
water system. Costs include the physical water connection, a vault, meter, and valves.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
The City is dependent on the Trinity River Authority (TRA) water supply. In the event of an emergency, the City
owned wells can not produce a sufficient amount of water to sustain the City. The City of Fort Worth obtains
water from a source that is not interconnected with TRA and should be able to supply enough water to sustain
the City in emergency situations.
'.
212
PROJECT TITLE: FORT WORTH INTERCONNECT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering
Personnel: Full Time Construction
Part Time $0 10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$30,000
$240,000
$30,000
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$300,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
213
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE IV
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase IV would extend the project to supply approximately 22MG
annually to 4 additional properties. It is anticipated the Phase IV would also trigger the need for additional pumps to
be placed at the existing pump site to supply necessary pressure and capacity. Additional system expansion would be
possible in the future.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
214
L
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE IV
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $360,000
$0 Construction $1,600,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,960,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
215
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2019 44TH CDBG LINE REPLACEMENT -HOLLOW OAK DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Proiect Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,270 feet of 6" cast iron main with an 8" PVC main along Hollow
Oak Drive from Woodridge Circle to Pebble Creek Drive and Woodridge Circle south of Hollow Oak Drive.
(44th year CDBG project)
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
216
M
PROJECT TITLE: FY2019 44TH CDBG LINE REPLACEMENT -HOLLOW OAK DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $23,000
Personnel: Full Time Construction $167,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$190,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
217
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-KYNETTE DRIVE, CYCLONE CREEK TO WILSHIRE DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,500 feet of 6" cast iron water main with an 8" PVC main along
Kynette Drive from Cyclone Creek to Wilshire Drive.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
218
PROJECT TITLE: LINE REPLACEMENT-KYNETTE DRIVE, CYCLONE CREEK TO WILSHIRE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Engineering
Personnel: Full Time
Construction
Part Time $0
10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$32, 000
$236, 000
$21, 000
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$289,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
219
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 06,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: SH183 PHASE II WATER RELOCATION
Project Type: WATER Sub -Type: LINE RELOCATION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Department of Transportation ("TxDoT") has planned for the expansion of SH183. The Phase II
construction will affect the City of Euless' utilities along and crossing SH183 between FM157 and the east city
limits.
PROJECT DESCRIPTION:
The City of Euless has water mains and associated items located within the SH183 right-of-way. These facilities
must be relocated to accommodate Phase II of the SH183 expansion. It is anticipated that the City of Euless will
enter into a relocation agreement with the contractor selected by TxDoT to authorize them to design and
relocate water lines and associated infrastructure. The City will be responsible for the cost of relocating the
utilities.
PROJECT SCHEDULE:
Est. FY2019
JUSTIFICATION:
City of Euless water facilities are located within TxDoT right-of-way. As such, the City must provide for utility
relocation to accommodate the roadway expansion.
220
ON
PROJECT TITLE: SH183 PHASE II WATER RELOCATION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Water Relocation Reimbursement $1,200,000 1
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,200,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding schedule: FY2016
$155,000 W/WW Operating Fund
FY2017
$445,000 W/WW Operating Fund
FY2018
$300,000 W/WW Operating Fund
FY2019
$300,000 W/WW Operating Fund
221
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 08,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2020 45TH CDBG LINE REPLACEMENT-S MAIN STREET (SOUTH)
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along S Main Street from Hollywood Blvd to E Huitt Lane
from a 6" cast iron main to an 8" PVC.
(45th year CDBG project)
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
W
222
L
09
PROJECT TITLE: FY2020 45TH CDBG LINE REPLACEMENT-S MAIN STREET (SOUTH)
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $35,000
Personnel: Full Time Construction $265,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$300,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
223
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted Bv: CHRIS BARKER n.+e r.,.,,.,ie+ed.
Project Title: RECLAIMED WATER LINE EXTENSION PHASE V
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase V would extend the project to supply approximately 13MG
annually to 3 additional properties. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
224
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE V
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $260,000
$p I Construction $1,150,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,410,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
225
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE VI
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase VI would extend the project to supply approximately 8MG
annually to 4 additional properties. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
226
M
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE VI
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $200,000
$p Construction $800,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,000,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
227
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -SUNSET DRIVE, S PIPELINE ROAD TO S MAIN STREET
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan,
PROJECT DESCRIPTION:
The project will replace and upgrade 2,230 feet of water main along Sunset Drive from S Pipeline Road to S
Main Street from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
W
228
PROJECT TITLE: LINE REPLACEMENT -SUNSET DRIVE, S PIPELINE ROAD TO S MAIN STREET
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering
Personnel: Full Time Construction
Part Time $0 10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$50,000
$332,000
$33,000
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$415,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
229
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -BLESSING CREEK/STONY CREEK/ROCK CREEK
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains are included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace the 6" AC main with an 8" PVC main for Blessing Creek, Stony Creek, and Rock Creek.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
.�
230
PROJECT TITLE: LINE REPLACEMENT -BLESSING CREEK/STONY CREEK/ROCK CREEK
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering/Surveying - To be Det.
Personnel: Full Time Construction - To be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
231
City of Euless
--1
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-COLLIN DRIVE, DALLAS DRIVE TO HARWOOD ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main with an 8" PVC main along Collin Drive from Dallas Drive to Harwood
Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
232
ON 9
M
PROJECT TITLE: LINE REPLACEMENT-COLLIN DRIVE, DALLAS DRIVE TO HARWOOD ROAD
NET
EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct O erating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
°
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
°
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
/_\911]kNIs] ►/_\Wd0]i'di'iI=1ilk&-3
233
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-COLLIN DRIVE, DENTON DRIVE TO DALLAS DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main to an 8" PVC main along Collin Drive from Denton Drive to Dallas
Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
'-'IN
234
PROJECT TITLE: LINE REPLACEMENT-COLLIN DRIVE, DENTON DRIVE TO DALLAS DRIVE
NET
EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
00 0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
7
235
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-DENTON DRIVE, TARRANT DRIVE TO HARWOOD ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main along Denton Drive
from Tarrant Drive to Harwood Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
--IN
'_N
236
PROJECT TITLE: LINE REPLACEMENT-DENTON DRIVE, TARRANT DRIVE TO HARWOOD ROAD
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
237
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -DICKEY DRIVE NORTH, SH10 TO E HUITT LANE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project consists of replacing the 6" cast iron water main with an 8" PVC main along Dickey Drive north from
SH10 to E Huitt Lane.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
' N
238
111.1
PROJECT TITLE: LINE REPLACEMENT -DICKEY DRIVE NORTH, SH10 TO E HUITT LANE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
239
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT -DICKEY DRIVE SOUTH, E HUITT LANE TO HILTON DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project consists of the replacement of a 6" cast iron water main with an 8" PVC main along Dickey Drive
south from E Huitt Lane to Hilton Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
240
PROJECT TITLE: LINE REPLACEMENT -DICKEY DRIVE SOUTH, E HUITT LANE TO HILTON DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
241
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-DUNAWAY DRIVE, E ALEXANDER LANE TO E ASCOT DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" AC water main with an 8" PVC water main on
Dunaway Drive from E Alexander Lane to E Ascot Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
--*N
242
0q
OR
PROJECT TITLE: LINE REPLACEMENT-DUNAWAY DRIVE, E ALEXANDER LANE TO E ASCOT DRIVE
NET
EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct O erating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
243
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-E HUITT LANE, S MAIN STREET TO DUNAWAY DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" PVC water main with an 8" PVC water main along
E Huitt Lane from S Main Street to Dunaway Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
'"IN
2"
L
PROJECT TITLE: LINE REPLACEMENT-E HUITT LANE, S MAIN STREET TO DUNAWAY DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
246
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REPLACEMENT-EASTCLIFF DRIVE, TOPLEA DRIVE TO DEL PRADO APTS.
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" AC main to an 8" PVC main along Eastcliff Drive from Toplea
Drive to Del Prado Apartments.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
r
W
246
PROJECT TITLE: LINE REPLACEMENT-EASTCLIFF DRIVE, TOPLEA DRIVE TO DEL PRADO APTS.
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct ODerating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
L..
247
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -FULLER DRIVE, SALEM DRIVE TO CARTER DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of replacing a 6" cast iron water main with an 8" PVC water main along Fuller Drive from
Salem Drive to Carter Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
248
PROJECT TITLE: LINE REPLACEMENT -FULLER DRIVE, SALEM DRIVE TO CARTER DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
249
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -LIVE OAK CT/LIVE OAK DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 4" cast iron water main with an 8" PVC main along Live
Oak Drive from Cedar Court to the south end of Live Oak Court. Additionally, the replacement of the existing 8"
cast iron water main with an 8" PVC water main from Canyon Ridge to West Cliff Drive is also included in the
scope of the project.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
250
OR
PROJECT TITLE: LINE REPLACEMENT -LIVE OAK CT/LIVE OAK DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
251
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REP-MIDCREEK DRIVE/ROCK CREEK DRIVE/STONY CREEK DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project consists of the replacement of a 6" AC main with an 8" PVC main on Midcreek Drive, Rock Creek
Drive, and Stony Creek Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
'1
'1
252
PROJECT TITLE: LINE REP-MIDCREEK DRIVE/ROCK CREEK DRIVE/STONY CREEK DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
263
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -MIDWAY DRIVE EAST, N MAIN ST TO FREESTONE DR
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project replaces the 6" cast iron water main with an 8" PVC main on Midway Drive east from N Main Street
to Freestone Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
.-**N
@110
264
L
PROJECT TITLE: LINE REPLACEMENT -MIDWAY DRIVE EAST, N MAIN ST TO FREESTONE DR
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
i Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
255
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -MIDWAY DRIVE WEST, FREESTONE DRIVE TO ECTOR DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project replaces the 6" cast iron water main with an 8" PVC main along Midway Drive west from Freestone
Drive to Ector Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
256
M
00,
PROJECT TITLE: LINE REPLACEMENT -MIDWAY DRIVE WEST, FREESTONE DRIVE TO ECTOR DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
267
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -NEEDLES STREET, PAULA LANE TO RAIDER DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" cast iron water main with an 8" PVC water main along
Needles Street from Paula Lane to Raider Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
'-,*N
W
258
M
PROJECT TITLE: LINE REPLACEMENT -NEEDLES STREET, PAULA LANE TO RAIDER DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
259
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-PAULA LANE, NEEDLES STREET TO S PIPELINE ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main along Paula Lane
from Needles Street to S Pipeline Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
W7
260
PROJECT TITLE: LINE REPLACEMENT-PAULA LANE, NEEDLES STREET TO S PIPELINE ROAD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
261
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 08,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-S MAIN STREET (NORTH), E HUITT LANE TO SH10
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along S Main Street from E Huitt Lane to SH10 from a 6"
cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
262
PROJECT TITLE: LINE REPLACEMENT-S MAIN STREET (NORTH), E HUITT LANE TO SH10
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
263
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-S PIPELINE ROAD EAST, VINE STREET TO S MAIN STREET
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace the existing 6" cast iron water main with an 8" PVC water main along S Pipeline Road
east from Vine Street to S Main Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
1111110
264
M
PROJECT TITLE: LINE REPLACEMENT-S PIPELINE ROAD EAST, VINE STREET TO S MAIN STREET
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
265
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-S PIPELINE ROAD WEST
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,625 feet of existing 6" cast iron water main with an 8" PVC water
main along S Pipeline Road west from Simmons Drive to Vine Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
No
266
PROJECT TITLE: LINE REPLACEMENT-S PIPELINE ROAD WEST
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To be Determined
Personnel: Full Time Construction - To be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
267
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,2000
Submitted By: RON YOUNG Date Completed:
Project Title: SH360 WATER CROSSING
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is related to the DFW International Airport Master Plan for property in Euless.
PROJECT DESCRIPTION:
The project scope includes the extension of two (2) 12" diameter water mains through the SH360 right-of-way to
provide service to the southwest portion of the DFW Airport property. The water mains will be bored under
SH360 at the Midway Drive intersection and between Harwood Road and Ash Lane. The mains will be located
within the Texas Department of Transportation right-of-way. The mains will be plugged at the east right-of-way
of SH360 in anticipation of the likely extension into DFW Airport property to serve future development.
PROJECT SCHEDULE:
JUSTIFICATION:
Development on the airport property could potentially increase the City's tax revenues. Future development is
dependent upon the availability of water service to this area.
268
PROJECT TITLE: SH360 WATER CROSSING
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX _
ADDITIONAL COMMENTS:
269
City of Euless
bo
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SHADY CREEK DRIVE/CLIFFWOOD ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water mains along Shady Creek Drive and Cliffwood Road from the
existing 6" cast iron mains to 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
270
L
PROJECT TITLE: LINE REPLACEMENT -SHADY CREEK DRIVE/CLIFFWOOD ROAD
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
00 0
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
271
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-SPRINGWOOD COURT
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 4" water main with an 8" main on Springwood Court.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance cost. Substandard size water mains provide
a reduced flow of water. Systematic annual replacement of deteriorated and substandard size water mains will
reduce maintenance costs.
-111.1
272
PROJECT TITLE: LINE REPLACEMENT-SPRINGWOOD COURT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
273
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-WESTWOOD DRIVE, FULLER DRIVE TO CARTER DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main with an 8" PVC main along Westwood Drive from Fuller Drive to
Carter Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
W
274
L
q
PROJECT TITLE: LINE REPLACEMENT-WESTWOOD DRIVE, FULLER DRIVE TO CARTER DRIVE
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Orwatina Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
275
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-WILDWOOD STREET
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along Wildwood Street from a 6" cast iron main to an 8"
PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
276
PROJECT TITLE: LINE REPLACEMENT-WILDWOOD STREET
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
277
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-WOODVINE DRIVE (EAST), CLIFFWOOD ROAD TO EL CAMINO REAL
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along Woodvine Drive from Cliffwood Road to El Camino
Real from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
'1
278
M,
PROJECT TITLE: LINE REP-WOODVINE DRIVE (EAST), CLIFFWOOD ROAD TO EL CAMINO REAL
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
279
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-WOODVINE DRIVE (WEST), PEBBLE CREEK DR TO CLIFFWOOD RD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along Woodvine Drive from Pebble Creek to Cliffwood
Road from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance cost.
--IN
W
280
PROJECT TITLE: LINE REP-WOODVINE DRIVE (WEST), PEBBLE CREEK DR TO CLIFFWOOD RD
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
°
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
°
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
281
T H E C I T Y O F
EULESS
-'1
282
N
co
W
CAPITAL IMPROVEMENT PROGRAMS
FY16 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
OTHER PROJECTS
Development/Engineering Building Construction
A
$ 2,494,775
XX
Midtown Development
A
$ 16,748,583
XX
Texas Star Sports Complex Phase V
A
$ 2,307,767
$ 877,767
$ 730,000
$ 700,000
Sub -Total Other Priority A-ProposedFYI 6
$ 21,551,126
Municipal Plaza Improvements Phase III" I
B
$ 150,000
XX
Texas Star Golf Course Maintenance Building (17)
B
$ 110,000
XX
Texas Star Sports Complex Phase VI (" )
B
$ 926,573
XX
Blessing Branch Park Improvements
B
$ 267,120
XX
Texas Star Sports Complex Phase VII Design I'81
B
$ 810,930
XX
Libra Remodel Design (19)
B
$ 147,630
XX
Texas Star Sports Complex Phase VII Constructionl'BI
B
$ 5,946,821
XX
XX
Library Remodel Construction(20)
B
$ 2,000,000
XX
Trail Enhancements Phase 1 (21)
B
$ 184,523
XX
Sub -Total Other Priority B-Unfunded
$ 10,543,597
Animal Shelter Expansion/Renovation
C
TBD
XX
Fire Station #2 Remodel
C
TBD
XX
Kiddie Carr Park Improvements
C
TBD
XX
South Euless Park Upgrades
C
TBD
XX
Trail Enhancements Phase II
C
TBD
XX
Trail Enhancements Villages of Bear Creek
C
TBD
XX
Trailwood Park Improvements
C
TBD
XX
Wilshire Park Upgrades
C
TBD
XX
Sub -Total OtherPriority -Unfunded
OTHER PROJECTS - TOTAL
32,094,722
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: May 07,2007
Submitted By: KYLE MCADAMS Date Completed:
Project Title: DEVELOPMENT/ENGINEERING BUILDING CONSTRUCTION
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Development and Engineering Building is the final project planned as part of the City's 1999 Master
Construction plan.
PROJECT DESCRIPTION:
The project includes the construction of a new entrance facade to match the other campus structures. Security
issues pertaining to controlled access will be addressed as well as renovation of the Fuller Room into a
functional conference area. Public rest room facilities will be relocated to meet American with Disabilities Act/
Texas Accessibility Standards, the interior will be upgraded, and new carpet will be installed throughout the
facility.
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
The Development and Engineering Building received a major remodel in 1996 with renovation of the building's
interior. Due to limited funding at that time, certain elements could not be justified as part of the remodel.
W
284
OR
PROJECT TITLE: DEVELOPMENT/ENGINEERING BUILDING CONSTRUCTION
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Construction
Personnel: Full Time
Architect - Special Services
Part Time $0
Survey & Testing Fees
Total Salary $0
Furniture
Purchase of Services
Instruments & Apparatus
Materials & Supplies
Data & Telephone
Utilities $0
Alarm & Security Services
IT Fixtures
Subtotal: $0
Janitorial Service/Pest Control
PM & Minor Repairs
Unscheduled Maintenance
Renewal & Replacement
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
$2,000
$3,000
$2,000
$1,500
$8,500
$8,500 Total Estimated Capital Cost
F
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
$2,216,750
$50,000
$10, 000
$188,000
$9,150
$14,875
$3,000
$3,000
$2,494,775 1
100
100
100
50%
0%
285
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: June 16,2015
Submitted By: LORETTA GETCHELL Date Completed:
Project Title: MIDTOWN DEVELOPMENT
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding for City participation in a public/private development opportunity.
PROJECT DESCRIPTION:
Project includes City participation in a public/private community development project of approximately 56 acres
located in the A.J. Huitt Survey, Abstract 684. Project costs will include land, right-of-way, remediation, paving, storm
drainage, water, wastewater, landscaping, hardscaping, amenities, design and administrative costs.
PROJECT SCHEDULE:
Begin Demolition: Fall 2015
Begin Construction: Spring 2016
JUSTIFICATION:
This is a significant development opportunity within the heart of Euless. The development is projected to include
residential development including villas, townhomes and rowhouses, cluster housing, urban lofts, and assisted living
center; commercial development including retail and restaurant development; and landscaped bioswales and water
detention areas for stormwater management.
286
PROJECT TITLE: MIDTOWN DEVELOPMENT
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Public Improvements $16,582,755
Personnel: Full Time Bond Issuance Costs $165,828
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
$0
$0
$0
$0 1 Total Estimated Capital Cost $16,748,583
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
XX
Specifications %
0%
County, State, Federal Funding
Construction %
00 0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
June 23, 2015: Conducted a Public Hearing and approved Planned Development.
Debt funding to build public improvements is anticipated to be funded by Public Improvement District revenues and
Tax Increment Reinvestment Zone revenues generated from the District. Project cost and proposed funding method
is subject to final approval by the City Council, TIRZ Board, and other participating taxing entities. Figures reflected
represent qualifying public improvements estimated by the developer for budgetary purposes only. Final approval of a
formal Project and Financing Plan and creation of a PID and TIRZ will be required before the project commences.
287
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27,2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE V
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase V includes the design and construction for an additional 60/90 field with
turf infield and natural grass outfield, site amenities, and additional parking of approximately 190 spaces.
With the growing number of participants in youth baseball, particularly in this division, the new field will allow our
staff the opportunity to expand our league and tournament format ultimately resulting in additional revenue for
the park. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the design and construction of an additional 60/90 field with a synthetic turf infield and
natural grass outfield. Additionally, the project will include all amenities to support the new field such as lights,
parking, scoreboard, irrigation, landscaping, and electrical service.
PROJECT SCHEDULE:
FY2016
JUSTIFICATION:
With the completion of Phase V, the new field will serve the athletic needs of the fastest growing age group and
most sought after field that we have.
111111110
,.N,
288
�..
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE V
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Design
$277,000
Personnel: Full Time
General Items
$59,000',
Part Time
$0
Earth Work
$56,500
Total Salary
$0
Site Paving
$415,750
Purchase of Services
Baseball Field
$814,422
Materials & Supplies
General Site Amenities
$53,950
Utilities
$0
Irrigation
$36, 000
Water
$27,150
Electrical
$353,500-
General Landscape
$29,880
Subtotal:
$0
10% Contingency
$184,615
$0
Subtotal: $0
Total Estimated Annual Cost $0 Total Estimated Capital Cost $2,307,767
PROPOSED METHOD OF FINANCE: I CURRENT STATUS:
Operating Fund
$700,000
Conceptual Design %
0%
Fund Balance
$877,767
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Escrow Funds
Other
$730,000
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed financing is as follows:
Operating funds from EDC debt reduction.
Fund balance funds from TSSC CIP and TSSC Reserves
Other from EDC Debt Reserve reduction.
289
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MUNICIPAL PLAZA IMPROVEMENTS PHASE II
Project Type: FACILITIES Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is the landscaping and irrigation related to the 40th CDBG ADA accessibility and infrastructure
improvements.
PROJECT DESCRIPTION:
Landscaping and irrigation improvements to the Municipal Plaza following the 40th CDBG ADA accessibility and
infrastructure improvements.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Beautification of the municipal plaza following the hardscape improvements.
--411�
W
290
PROJECT TITLE: MUNICIPAL PLAZA IMPROVEMENTS PHASE II
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Landscaping
$150,000
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $150,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
L
291
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: 04/22/2015
Submitted By: KYLE MCADAMS Date Completed:
Project Title: TEXAS STAR GOLF COURSE MAINTENANCE BUILDING
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is not part of the City's five year master plan.
PROJECT DESCRIPTION:
The project consists of the renovation of the current maintenance facility constructed in 1997. The project scope
includes the remodel of existing office space, break room, maintenance, and storage rooms. Interior walls will be
repaired along with the installation of new counter tops, cabinets, bathroom fixtures, light fixtures, and
miscellaneous appliances. Concrete floors will be polished and seal coated, and both the interior and exterior of
the building will be repainted.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
The maintenance facility was constructed in 1997 and has not received any previous remodels or upgrades.
Wo
'1
292
11.1
PROJECT TITLE: TEXAS STAR GOLF COURSE MAINTENANCE BUILDING
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct O e
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Full Time
Part Time
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Remodel / Renovation $110,000 1
$0
$0
$0
$0
$0 Total Estimated Capital Cost $110,000
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
XX
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
293
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27, 2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE VI
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase VI includes renovating the infields of the existing 4-plex with turf infields.
With the growing number of participants in youth baseball, renovating the infields with synthetic turf will allow our
staff the opportunity to expand our existing leagues as well as programming for additional leagues in adult
softball. Synthetic turf infields will also substantially reduce the number of rain outs which results in lost
revenue. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the renovation of the infields in the existing 4-plex with synthetic turf.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
With the completion of Phase VI, the new infields will increase programming opportunities as well as
substantially reduce the number of rain outs.
11"N
294
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE VI
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
I Personnel
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Full Time
Part Time
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund _
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds _
Revenue Bonds
Escrow Funds _
Other _
Car Rental Tax Fund _
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding is from EDC debt drop-off.
OR
TOTAL ESTIMATED CAPITAL COST:
Design
General Items
$0 Earth Work
$0 Baseball Field
Contingency
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
XX Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
$102,953
$5,000
$16,800
$664, 550
$137,270
$926, 5731
0%
0%
0%
0%
0%
295
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 30,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: BLESSING BRANCH PARK IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a continuation of the overall trail system expansion and general park improvements as identified
in the Parks Master Plan.
PROJECT DESCRIPTION:
Blessing Branch Park is a 7.3 acre linear park located on the east side of Main Street across from Midway Park.
Currently, the park has only one swing set. This project includes construction of a trail connection from Main
Street to the west and Fuller -Wiser to the east. Additionally, the project includes a new playground, picnic
pads with grills, and some type of shade shelter/pavilion/gazebo. This area currently gets a high volume of foot
traffic. Constructing a trail in this linear greenbelt would not only provide a safe paved access for the residents
east of Main Street to Midway Park, Midway Park Elementary, and to Trinity High School, but also help create a
renewed sense of quality of life for the residents in that area by enhancing the recreational amenities available.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
The number one request from Euless citizens as it relates to trails, based on the responses to the needs
assessment survey as identified in the Parks Master Plan, was to construct trail connections between existing
and/or future park developments. This project not only satisfies that request, but also provides trail connections
to neighborhoods, schools, between major thoroughfares, and potentially to future commercial developments to
the southeast.
296
L
q
\..
PROJECT TITLE: BLESSING BRANCH PARK IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost
Approximately 28,000 square feet of
Personnel: Full Time
4"x8' concrete trail @ $4.25 square foot
$119,000
Part Time
$0
Playground/Border
$60,000
Total Salary
$0
Picnic pads w/grills
$20,000
Purchase of Services
Shade shelter/pavilion/gazebo
$30,000
Materials & Supplies
Trail Lighting
$20,000
Utilities
$0
Playground chips
$5,400
Contingency 5%
$12,720
Subtotal: $0
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance XX
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
The proposed financing is EDC CIP Fund Balance
$0
$0
$0 Total Estimated Capital Cost $267,120
CURRENT STATUS:
Conceptual Design % 00
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 00 0
297
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27,2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE VII DESIGN
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase VII includes additional multi -use fields to accommodate both softball and
baseball. Also included in the project is additional parking and a concession building to support the new phase
and the number of participants the activities hosted by the new phase will generate. With the growing number of
participants in youth baseball and adult softball, the new multi -use fields will allow our staff the opportunity to
expand our programming in both sports as well as creating new opportunities for future programs including girl's
fast pitch. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the design of four (4) multi -use playing fields that would accommodate adult slow pitch and
girl's fast pitch softball, as well as youth baseball. Phase VII will also feature synthetic sports turf in all the
infields, a concession and restroom building, a pavilion, playground and sufficient parking to accommodate the
additional patrons.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Softball World is an aging facility with many necessary upgrades looming in the short-term which would require
a significant capital investment. This phase would eliminate the upgrades with consolidation and movement of
this operation to the Parks at Texas Star, collectively known as the Texas Star Sports Complex. With the
completion of Phase VII, the new multi -use facility will serve the athletic needs of the community and spur
economic opportunities for the City.
W
298
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE VII DESIGN
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Design $810,930
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost $810,930
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Escrow Funds
Other
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Note: Operating currently under the TSSC umbrella, Softball World's proposed relocation to Parks At Texas
Star, under this phase, will cover all operating costs of the new operations. Accordingly, no additional baseline
expenses are anticipated.
Proposed funding is from EDC debt drop-off
299
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 01,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: LIBRARY REMODEL DESIGN
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This remodel planning is submitted as a new project and is not related to the City's Master Plan.
PROJECT DESCRIPTION:
Planning and design phase for remodel of the Library.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
The Library was constructed in 1996 and interior furnishings and design layout are in need of updating.
--*N
300
PROJECT TITLE: LIBRARY REMODEL DESIGN
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Insurance
I Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Planning/Bid Specifications $147,630 1
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$147,630
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
301
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27,2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE VII CONSTRUCTION
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Pro'ect Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase VII includes additional multi -use fields to accommodate both softball and
baseball. Also included in the project is additional parking and a concession building to support the new phase
and the number of participants the activities hosted by the new phase will generate. With the growing number of
participants in youth baseball and adult softball, the new multi -use fields will allow our staff the opportunity to
expand our programming in both sports as well as creating new opportunities for future programs including girl's
fast pitch. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the construction of four (4) multi -use playing fields that would accommodate adult slow
pitch and girl's fast pitch softball, as well as youth baseball. Phase VII will also feature synthetic sports turf in all
the infields, a concession and restroom building, a pavilion, playground and sufficient parking to accommodate
the additional patrons.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Softball World is an aging facility with many necessary upgrades looming in the short-term which would require
a significant capital investment. This phase would eliminate the upgrades with consolidation and movement of
this operation to the Parks at Texas Star, collectively known as the Texas Star Sports Complex. With the
completion of Phase VII, the new multi -use facility will serve the athletic needs of the community and spur
economic opportunities for the City.
NO
302
M
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE VII CONSTRUCTION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost
General Items
$61,000
Personnel: Full Time
Earth Work
$110,500
Part Time
$0
Site Paving
$1,029,150
Total Salary
$0
Softball Fields (four - plex)
$1,909,120
Purchase of Services
General Site Amenities
$96,666
Materials & Supplies
Playground
$200,000
Utilities
$0
Concession/Restroom Bldg
$585,000
Irrigation/Landscaping
$267,520
Water
$152,425
Sanitary Sewer
$42,000
Subtotal:
$0
Storm Drain
$498,420
Maintenance Costs
Electrical
$454,400
$0
10% Contingency
$540,620
Subtotal: $0
Total Estimated Annual Cost $0 Total Estimated Capital Cost $5,946,821
PROPOSED METHOD OF FINANCE: I CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Escrow Funds
Other
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Note: Operating currently under the TSSC umbrella, Softball World's proposed relocation to Parks At Texas
Star, under this phase, will cover all operating costs of the new operations. Accordingly, no additional baseline
expenses are anticipated.
303
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 01,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: LIBRARY REMODEL CONSTRUCTION
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This remodel is submitted as a new project and is not related to the City Master Plan.
PROJECT DESCRIPTION:
The library facility remodel project scope includes reconfiguration of the general interior layout, replacement of
the chilled water HVAC system, replacement of furnishings, updating overall facility decor, lighting upgrades,
and electrical work.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
The Library was constructed in 1996, pre-internet and pre -digital age. Electrical plugs and data ports are
currently in limited areas but are needed throughout the building to provide increased access to computers and
technology. Patrons are requesting more space for quiet study, group study, and collaboration. The Young
Adult/Teen collection is one of the highest circulation and this group needs a space in the Library.
W
304
PROJECT TITLE: LIBRARY REMODEL CONSTRUCTION
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $2,000,000 1
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$2,000,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
00 0
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
305
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 12,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS PHASE I
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment and Identification section of the adopted Parks Master Plan are a number of
trail related improvements.
PROJECT DESCRIPTION:
This project consists of the first phase of implementation of park improvements identified in the adopted Parks
Master Plan which includes additional water fountains, additional benches, construction of shaded seating areas
along the trail, addition and/or installation of new exercise equipment along the trails, picnic stations, and
construction of additional pedestrian bridges in high water areas. Also identified, is the need to address various
areas in our trails system that might need to be converted from unpaved to paved trails.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The development and maintenance of the trails system
continued to receive significant support from the citizens as indicated in the responses to the needs assessment
survey conducted as a part of the Parks Master Plan update.
.."IN
306
LIM
PROJECT TITLE: TRAIL ENHANCEMENTS PHASE I
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost
Stopping Stations:
Personnel: Full Time
8'x8' w/bench (2) Bob Eden
Part Time $0
Health Trail:
Total Salary $0
Fitness Course - Bob Eden
Purchase of Services
Freight for fitness equipment
Materials & Supplies
Installation of fitness equipment
Utilities $0
32' Gazebo shade shelter
Freight for gazebo
Installation of gazebo
New fitness trail surface
Subtotal: $0
(4527 sq. ft @ $4.25 sq. ft)
Maintenance Costs
Gazebo slab (805 sq. ft @ $4.25 sq.ft)
$0
Safety surface for fitness stations
Contingency (10%)
Other (5%)
Subtotal: $0
Total Estimated Annual Cost $0 Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE: I CURRENT STATUS:
Operating Fund
Fund Balance XX
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
The proposed method of finance is EDC CIP Fund Balance
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
$8,200 1
$9,678
$1,635
$4, 090
$44, 552
$2,050
$17, 820
$19,240
$3,421
$50, 000
$15,892
$7,945
$184, 5231
0%
0%
0%
0%
0%
307
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: May 07,2007
Submitted By: KYLE MCADAMS Date Completed:
Project Title: ANIMAL SHELTER-EXPANSION/RENOVATION
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the City's five year master plan.
PROJECT DESCRIPTION:
The project consists of the expansion of the current animal shelter facility to better accommodate visitors,
adoptions, and animal services. The project scope includes the addition of ten (10) enclosed dog runs, six (6)
quarantine runs, an adoption room, additional room for cat containment, and an area for animal washing. Office
space expansion will be included in the renovation as well as updates to the public/employee rest rooms.
PROJECT SCHEDULE:
JUSTIFICATION:
The current animal control facility has insufficient space to meet current and future demands.
'1
308
M
PROJECT TITLE: ANIMAL SHELTER-EXPANSION/RENOVATION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Engineering - To Be Determined
Personnel: Full Time
Construction - To Be Determined
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
Subtotal:
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
25 /o
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
XX
ADDITIONAL COMMENTS:
309
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: March 13,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: FIRE STATION #2 REMODEL
Project Type: CONSTRUCTION Sub -Type: REMODEL
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This structure was the former vehicle service center built in 1977 and was reconstructed for the relocation of Fire
Station #2 from 1100 Westpark Way. The remodel was completed in 1997.
PROJECT DESCRIPTION:
The project scope includes interior enhancements, reconfiguration of the bathrooms and shower facilities,
kitchen improvements, and general remodel of interior structures including updates required by the Americans
with Disabilities Act.
PROJECT SCHEDULE:
JUSTIFICATION:
310
L
PROJECT TITLE: FIRE STATION #2 REMODEL
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
311
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: KIDDIE CARR PARK IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan recommends funding for system -wide park facilities and amenities upgrades.
PROJECT DESCRIPTION:
This project includes the construction or installation of a pavilion, a concrete trail connection to Carr Park, bank
stabilization along Boyd Branch Creek which runs through the park, a playground, park lighting, picnic stations,
an irrigation system, new perimeter fencing, a drinking fountain, benches, and a dedicated parking lot at Kiddie
Carr Park.
PROJECT SCHEDULE:
JUSTIFICATION:
As identified in the adopted Parks Master Plan, the municipal park is the foundation of any solid parks and
recreation system. The City of Euless parks and recreation system provides residents and visitors with
significant personal, social, environmental, and economic benefits. The revitalization efforts that the Euless City
Council has focused on over the years has increased the sense of community pride. Kiddie Carr Park is a four
acre park located adjacent to Carr Park off Pauline. The current amenities at this park include the Parks
Department's in -ground tree farm, a greenhouse, and an outdoor basketball court. The park is located in a
section of town that needs something to stimulate community pride. The proposed project will continue the City
Council's revitalization efforts by creating an area that will serve both the passive and active leisure needs of the
residents in this area.
312
PROJECT TITLE: KIDDIE CARR PARK IMPROVEMENTS
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
313
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 02,2013
Submitted By: RAY MCDONALD Date Completed:
Project Title: SOUTH EULESS PARK UPGRADES
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan calls for general upgrades and improvements in the overall quality of parks in
the City and to develop a high quality parks system that provides for all age and interest groups and enhances
the adjoining neighborhoods.
PROJECT DESCRIPTION:
Overall park enhancements and improvements that might include amenities such as new playground equipment,
park redevelopment, improved lighting, water features, upgrades to existing splashpad, expansion of existing
splashpad, and additional landscaping.
PROJECT SCHEDULE:
JUSTIFICATION:
This has been documented in the adopted Parks Master Plan.
314
L
PROJECT TITLE: SOUTH EULESS PARK UPGRADES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
315
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS PHASE II
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This enhancement was identified in the Needs Assessment and Identification section of the adopted Parks
Master Plan.
PROJECT DESCRIPTION:
This project is Phase II of the trail enhancements that continues implementation of park improvements identified
in the adopted Parks Master Plan which includes additional water fountains, additional benches, construction of
shaded seating areas along the trail, addition and/or installation of new exercise equipment along the trails,
picnic stations, and construction of additional pedestrian bridges in high water areas. Also identified, is the need
to address various areas along the trail that need to be converted from unpaved to paved trails.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The development and maintenance of the trails system
continued to receive significant support from the citizens as indicated in the responses to the needs assessment
survey conducted as a part of the Parks Master Plan update.
.-,
s,
316
PROJECT TITLE: TRAIL ENHANCEMENTS PHASE II
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering - To Be Determined
Personnel: Full Time Construction - To Be Determined
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
317
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: March 23,2004
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS VILLAGES OF BEAR CREEK
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project includes infrastructure improvements which were identified as a high priority in the adopted Parks
Master Plan.
PROJECT DESCRIPTION:
This project includes the redevelopment/redesign and improvement of the trail at the Villages of Bear Creek
Park to offer multiple uses for the citizens of Euless.
PROJECT SCHEDULE:
JUSTIFICATION:
Trail development and enhancement opportunities will be consistent with available land, funding and time
variables. This Master Plan recommendation will be part of a city-wide comprehensive trail enhancement
project. Due to the continual erosion of the existing trail, a redevelopment/redesign of the trail system at Villages
of Bear Creek will be a high priority.
318
L
L
PROJECT TITLE: TRAIL ENHANCEMENTS VILLAGES OF BEAR CREEK
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0 I Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
319
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAILWOOD PARK IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a continuation of the overall park improvement plan as identified in the Parks Master Plan.
PROJECT DESCRIPTION:
Trailwood Park is an eleven acre site that currently has a playground and a half -mile hike/bike trail. This project
includes the installation of a new pavilion, a parking lot, upgraded playground to meet American with Disabilities
Act standards, park lighting, new park signs, benches along the trail, and trail lighting.
PROJECT SCHEDULE:
JUSTIFICATION:
As identified in the adopted Parks Master Plan, the municipal park is the foundation of any solid parks and
recreation system. The City of Euless parks and recreation system provides the residents and visitors with
significant personal, social, environmental and economic benefits. The revitalization efforts that the Euless City
Council has focused on over the years has increased the sense of community pride. This proposed project will
continue those efforts by creating an area that will serve both the passive and active leisure needs of the
residents in the vicinity.
320
M
M
PROJECT TITLE: TRAILWOOD PARK IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To be Determined
Construction - To be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
321
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 03,2013
Submitted By: RAY MCDONALD Date Completed:
Project Title: WILSHIRE PARK UPGRADES
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan calls for general upgrades and improvements in the overall quality of parks in
the city and to develop a high quality parks system that provides for all age and interest groups and enhances
the adjoining neighborhoods.
PROJECT DESCRIPTION:
Overall park enhancements and improvements that might include amenities such as new playground equipment,
park/trail lighting, pavilion, additional water features, parking improvements, additional landscaping and shade
structures for existing picnic pads.
PROJECT SCHEDULE:
JUSTIFICATION:
Documented in the adopted Parks Master Plan.
W
wo
322
L
PROJECT TITLE: WILSHIRE PARK UPGRADES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
XX
TOTAL ESTIMATED CAPITAL COST:
Engineering - To Be Determined
Construction - To Be Determined
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
0%
0%
0%
0%
0%
323
T H
EU
C I T Y O F
LESS
324
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
DRAINAGE PROJECTS
DR9901
JSulphurBranch Phase II
08/01/99
$ 123,404
$ 120,128
$ 3,276
DR9902
Wiridlea & WestCliff
08/01/99
$ 4,396
$ 1,159
$ 3,237
DR9904
Hurricane Creek
04/30/02
$ 257,500
$ 69,906
$ 187,594
DR0302
Flooding Mitigation
Cancelled
$ 250,000
$ -
$ 250,000
DR0303
Aransas Q Glenn
12/31/04
$ 250000
$ 250,000
$
DR0304
Live Oak Drainage
04/15/05
$ 218,000
$ 175,958
$ 42,042
DR0305
Sierra Drive Drainage
04/15/05
$ 40,738
$ 40,738
$ 0
DR0306
Flood Mitigation Plan FEMA
04/15/05
$ 32,000
$ 7,750
$ 24,250
DR0307
Simmons Drainage
04/15/05
$ 22,995
$ 22,995
$ -
DR0301
Fuller Branch Channel Stabilization
05/31/07
$ 279,136
$ 232,176
$ 46,960
DR0401
Channel Stabilization Tributary WFA
05/31/07
$ 437,462
$ 438,070
$ 608
DR0402
Drainage Project Stud
05/31/07
$ 60,000
$ 51,000
$ 9,000
DR0601
Little Bear Creek Study Update
04/25/08
$ 50,000
$ 49,000
$ 1,000
DR0602
McCormick Park
04125/08
$ 250,000
$ 247,925
$ 2,075
DR0701
Eastcliff Drive/Greenbriar Drive Drainage Imp.
04/17/10
$ 340,000
$ 246,584
$ 93,416
DR0801
Rockwall Drive/Lamar Drive Drainage Imp.
04/17/10
$ 430,000
$ 272,554
$ 157,446
DR0901
Bear Creek Parkway Erosion Repair
02/17/11
$ 530,000
$ 464,465
$ 65,535
DR0802
Hurricane Creek & Bridge at Marlene
]Improvements
04/14/11
1 $ 378,500
1 $ 344,574
1 $ 33,926
Drainage Projects - Prior Years
1 $ 3,954,131
$ 3,034,982
$ 919,149
DR0000 JBoyd Branch improvements Cancelled
$ 10.000,000
$ -
$ 10,000,000
Drainage Projects - Current Year
$ 10,000,000
$ -
$ 10,000,000
Total Drainage Projects
$ 13,954,131
$ 3,034,982
$ 10,919,149
326
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 17,2009
Submitted By: RON YOUNG Date Completed: Cancelled
Project Title: BOYD BRANCH IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Proiect Code: DR0000 Priority: A
COUNCIL AUTHORIZATION:
Authorized in the FY2011 Capital Improvement Plan.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Drainage improvements are included in the Boyd Branch Watershed Study.
PROJECT DESCRIPTION:
This project includes the portion of Boyd Branch from S Pipeline Road to SH183 and may include structural and
non-structural activities to reduce or minimize the effects of large stormwater events. A large portion of this
project occurs on a section of Boyd Branch that lies in a platted private drainage easement which also shows the
maintenance responsibility to rest on the property owner(s). Since the City of Euless has no easement rights
along these sections of Boyd Branch, the City is of the opinion that improving the capacity of Boyd Branch to
handle large stormwater events is the responsibility of the property owner(s). The City of Euless may have some
expenses related to improvements made to Boyd Branch.
PROJECT SCHEDULE:
Project is deemed unnecessary at this time.
JUSTIFICATION:
Large stormwater events result in runoff exceeding the capacity of Boyd Branch. This project is intended to
reduce or minimize property losses associated with stormwater runoff exceeding the capacity of Boyd Branch.
1-111
we
326
PROJECT TITLE: BOYD BRANCH IMPROVEMENTS
PROJECT CODE: DR0000
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Construction $10,000
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $10,000
Maintenance Costs Funding Source:
Subtotal: $0 Additional Funding Needed:
Developer Contribution $6,000,000
Future Revenue Bond Issue $4,000,000
Total Estimated Annual Cost $0 Total Funding $10,000,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Construction $10,000,000 $0 $10,000,000 0%
TOTAL PROJECT $10,000,000 $0 $10,000,000 0% I
327
..N
T H E C I T Y O F
EU-LESS
1
328
00,
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Com leted Total Budget Costs Budget
STREET PROJECTS
PS9911
Overlay Projects
03/30/00
$ 294,687
$ 294,687
$ -
PS9912
Harwood -Main Intersection
04/30/00
$ 1,126 935
$ 1,077,303
$ 49,632
PS9907
Wes ark W - SH10 to SH183
09/30/00
$ 605,542
$ 479,915
$ 125,627
PS9902
Mid Cities Blvd.
05/02/02
$ 1,075,074
$ 963635
$ 111,439
PS9910
Sidewalks
06/30/03
$ 200,000
$ 200,000
$ -
PS0001
FM 157 S Pipeline to SH10(Utility Relocation
04/30/04
$ 378,207
$ 371,318
$ 5,889
PS0003
Glade from Henta a to SH121
04/30/04
$ 1,866,612
$ 1,866 612
$ -
PS0004 IGIade
Rd East - SH121 to Champagne
04/30/04
$ 1,210 014
$ 1,162,009
$ 48,005
PS0201[Gateway
Blvd - Southern Portion
04/30/04
$ 510,000
$ 473,817
$ 36,183
PS0301 110id
Cities Roadway Illuminabon
04/15/05
$ 160,000
$ 148,115
$ 11,885
PS0302 I
Driftwood Pipeline Traffic Signal
04/15/05
$ 100,000
$ 68,665
$ 31,335
PS0303
Aransas/Harwood Traffic Signal
04/15/05
$ 120,000
$ 89,118
$ 30,882
PSO402
South Pipeline Road Bride
04/30/05
$ 28.208
$ 28,208
$ -
PS9908
Si nalization
05131MB
$ 168,055
$ 168055
$ -
PSO401
West Pipeline - Raider to City Limits
05/31/06
$ 223,000
$ 104,859
$ 118,141
PSO403
Raider Or-SH10to South Pipeline
05/31/06
$ 330,000
$ 293,435
$ 36,565
PS0501
Ross Avenue/S.Main 300' W
05/31/06
$ 95,688
$ 95,638
$ 50
PS0502 11ndustnal
Signal Timin
05/31/06
$ 50 000
$ 50,000
$ -
PS0503
Overla-Hanvood157/Main
05/31/06
$ 137,000
$ 119816
$ 17,184
PS0604
Overla S.Main, SH1D/S.PI eline
05/31/06
$ 137,000
$ 140,211
$ 3,211
PS0601
Overlay -East Midway
05/31/07
$ 83,000
$ 73,550
$ 9,450
PS0602
Overlay -Midway, N Main /FM157
05/31/07
$ 105,000
$ 67,632
$ 37,368
PS0603
Overlay -Fuller Wiser, Midway/Harwood
05/31/07
$ 40,000
$ 28,695
$ 11,305
PS9906
Traffic Safe /Si nalizabon
05/31/08
$ 128,027
$ 127,939
$ 88
PSO404
South Pipeline Road Overlay
05131108
$ 114.750
$ 85,062
$ 29.688
PS0701
Oveda -Dicke Drive
05/31/08
$ 122,200
$ 48,435
$ 73,765
PS0702
Overlay -East Hutt
05/31/08
$ 89,000
$ 64,895
$ 24,105
PS0703
Overlay -Huntington Drive
05/31/08
$ 69,500
$ 42,884
$ 26,616
PS0706
Gateway Blvd Screening Wall
05/31/08
$ 135,800
$ 138,862
$ 3,062
PS0705
Signal ateway Blvd 0 Glade
10/28/08
$ 98,000
$ 98,000
$ -
PS0002
West Pipeline Road-Rarder/H 10
12/01/08
$ 6,082,621
$ 6,081,392
$ 1,229
PS0801
Oveda -North Main/Cullum Drive
12/31/08
$ 290,000
$ 211,130
$ 78.870
PS9905
Traffic Studies
05/30/09
$ 27,286
$ 27,197
$ 89
PS0704 I
Disability Access Stud
05/31/09
$ 30,000
$ 13,950
$ 16,050
PS0901
Ash/Denton/FairOaks Overlay
09/30/09
$ 320,000
$ 231,984
$ 88,016
PS0902
JVine Street Design
Cancelled
$ 100,000
$ -
$ 100,000
PS9903
I HWY 183 Service Road
Cancelled
$
$ -
$ -
PS0304
lGlade Road
04/16/10
$ 3,077,977
$ 2 905,205
$ 172,772
PS9909
JFM157 North - SH183 to SH121
04/16/10
$ 267,519
$ 129,215
$ 138,304
PS0903
IMid Cities A Gateway & Baze Traffic Si nals
04/16/10
$ 320,000
$ 250,702
$ 69,298
PS0802
I Fuller -Wiser Connector
02/17/11
$ 495,000
$ 441,491
$ 53,509
PS1002
FY10 County Overlay - Wilshire/Marlene
05/17/11
$ 288,000
$ 200,890
$ 87,110
PS9901
North Main Street
05/31/12
$ 6,745,047
$ 6,698,149
$ 46,898
PS9904
Harwood Road
05/31/12
$ 5770,211
$ 5,686.556
$ 83,655
PS1001
Baze Road
05/31/12
$ 1,830,000
$ 1,558,401
$ 271,599
PS1101
FY2011 County Overlay -Bear Creek
Drive/Lakewood Blvd/Ash Lane
05/31/12
$ 300,000
$ 265,887
$ 34,113
PS0605
IScuth Pi line Road Bridge Replacement
05/31/13
$ 157,000
$ 157,000
$ -
PS1003
Ash Lane -Aransas Drrve to N. Main Street
05/31/13
$ 1.959 230
$ 1,597,270
$ 361,960
PS12D1
FY2012 County Overlay -Aransas Dnve/Slaughter
I Lane
05131/13
$ 300,D00
$ 228,759
$ 71 241
PS1301
FY2013 38th CDBG-ADA/TAS Infrastructure
Im rovements
05/31/14
$ 450,000
$ 284,581
$ 165419
PS1302
FY2013 County Overlay-Trailwood/Summit
I Rid e/West ark/Baze
05/31/14
$ 280,000
$ 273,995
$ 6,005
PS1402
FY2014 County Overlay-Ector Drive/Midway
DnverrroanTrail
05/31/14
$ 300000
$ 300,000
$ -
Street Projects - Prior Years
$ 39,191,190
1 $ 36 515,123
1 $ 2,676 067
PS1401
FY2014 39th CDBG-ADA/TAS Infrastructure
Im rovements
02/26/15
$ 300 000
$ 272.057
$ 27,943
PS1303
lCullurn Drive Improvements
1 03/31/15
$ 11296,738
1 $ 1,210,748
$ 84,990
SteetPro'ects- current Year
$ 1,595,738
$ 1,482,805
$ 112,933
Tota/Street Pro' $ 40,786,928 1 $ 37,997,928 $ 2,789,000
329
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 17,2011
Submitted By: CHRIS BARKER Date Completed: Feb 28, 2015
Project Title: 39TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Proiect Code: PS1401 Priority: A
COUNCIL AUTHORIZATION:
February 12, 2013: Conduct a Public Hearing for the proposed 39th Year CDBG project, for the installation of
sidewalk accessibility ramps located along North Main Street, Midway Drive, and within several neighborhoods
and motion to approve a recommendation regarding the selected CDBG project.
May 13, 2014: Approved Resolution No. 14-1433, recommending award of a construction contract for the 39th
Year Community Development Block Grant (CDBG) Project (No. B13-UC-48-0001-22-30) to Reliable Paving,
Inc., 1903 Peyco Drive N., Arlington, Texas, for the replacement of sidewalk accessibility ramps. The estimated
expenditure is $265,598.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(39th year CDBG project)
PROJECT SCHEDULE:
Began Construction: August 2014
Construction Complete: February 2015
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
--1
'_*N
.—,*N
330
Im
PROJECT TITLE: 39TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS PROJECT CODE: PS1401
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $45,000
Personnel: Full Time Construction $255,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total. Estimated Capital Cost $300,000
Maintenance Costs Funding Source:
CDBG Award $300,000
$0
Subtotal: $0
Unused 39th CDBG Funding ($27,943)
Total Estimated Annual Cost $0 Total Fundin-q $272,057
CURRENT STATUS
OVERIUNDER
PHASEIFUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Construction $300,000 $272,057 $27,943 91%
TOTAL PROJECT $300,000 $272,057 $27,943 91%
331
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed: Mar 31, 2015
Project Title: CULLUM DRIVE IMPROVEMENTS-SH10 TO HUITT LANE
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: PS1303 Priority: A
COUNCIL AUTHORIZATION:
January 22, 2013: Authorized the City Manager to execute an engineering design contract with Neel -Schaffer,
Inc. consulting engineers with an amount not to exceed $137,000 for the design of Cullum Drive from SH10 to
East Huitt Lane.
November 12, 2013: Authorized the City Manager to enter into a construction contract with McClendon
Construction in the amount of $1,138,738, which includes a $50,000 contingency, for the construction of street
improvements to Cullum Drive from SH10 to East Huitt Lane.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Cullum Drive is a roadway that connects an arterial thoroughfare (SH10) and a residential collector thoroughfare
(Huitt Lane) both of which are identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of the engineering, required right-of-way acquisition and construction for a 31' wide concrete
roadway to replace an existing deteriorating asphalt roadway from SH10 to Huitt Lane. The project scope
includes underground storm drainage, sidewalks and wastewater main replacement.
PROJECT SCHEDULE:
Design Complete: September 2013
Construction Began: January 2014
Construction Complete: March 2015
JUSTIFICATION:
Reconstruction of this street will decrease the annual maintenance and provide compliance with current City
standards.
r
332
N01111M
PROJECT TITLE: CULLUM DRIVE IMPROVEMENTS-SH10 TO HUITT LANE PROJECT CODE: PS1303
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost Engineering $137,000
Personnel: Full Time Right -of -Way $20,000
Part Time $0 Construction $1,138,738
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
Total Estimated Capital Cost
$1,295,738
Maintenance Costs
Funding Source:
Transfer from:
Street CIP Fund Balance
$992,610
Car Rental Fund
$189,786
$0
Car Rental CIP Fund Balance
$46,128
Subtotal:
$0
Escrow Funds
$67,214
Transfer to:
Street CIP Fund Balance
($84,990)
Total Estimated Annual Cost
$01
Total Funding
$1,210,748
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Engineering
$137,000 $142,599 ($5,599)
104%
Right -of -Way
$20,000 $0 $20,000
0%
Construction
$1,138,738 $1,068,148 $70,590
94%
(TOTAL PROJECT $1 295,738 $1 210,748 $84,990 93%
333
334
11",
OR
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WASTEWATER PROJECTS
VWV9902
Impact Fee Stud
09/30/99
$ 13,000
$ 12,238
$ 762
WW9903
Misc Sewer Rehab FY99
09/30/99
$ 50,000
$ 12,987
$ 37,013
WW9904
Hydraulic Analsis
06/30/00
$ 27,000
$ 27,000
$
WW9901
CDBG B/98-UC-48-0001/B95-22-50
08/19/00
$ 150,000
$ 72,927
$ 77,073
WW0003
TRA Debt Payment
05/31/01
$ 822,037
$ 822,037
$
WW0001
CDBG B/99-UC-48-0001
09/30/01
$ 150,000
$ 121,682
$ 28,318
01010101
CDBG B00-UC480001-2250
02/20/02
$ 251,485
$ 247,790
$ 3,695
WWO102
Manhole Rehab. Program
03/31/03
$ 250,000
$ 184,520
$ 65,480
WW0201
CDBG - B01-UC-48-0001-22-50
03/31/03
$ 237,086
$ 172,948
$ 64,138
WW0202
Line Replacement -Dunawa
02/28/05
$ 140,000
$ 139,955
$ 45
WW0203
Line Replacement - E. Alexander
02/28/05
$ 20,000
$ 20,000
$ -
W W0204
Line Replacement - Paula Lane
02/28/05
$ 79,000
$ 79,000
$ -
WW0103
Line replacement-S. Pi eline,Heather-Vine
04/15/05
$ 489,759
$ 464,504
$ 25,255
WW0205
Line Replacement - Midway Park
04/30/05
$ 366,000
$ 318,149
$ 47,851
WW0401
CDBG B03-UC-48-0001-22-50
04/30/05
$ 217,000
$ 161,170
$ 55,830
WW0301
CDBG B02-UC-48-0001-22-50
07/26/05
$ 271,455
$ 271,454
$ 1
WW0302
Inflow & Infiltration
Cancelled
$ 200,000
$ -
$ 200,000
WW0303
Line Replacement, Canyon Ride
08/31/06
$ 196,200
$ 173,516
$ 22,684
VVVV0304
Line Replacement, Sagebrush
08/31/06
$ 160,900
$ 136,470
$ 24,430
WW0305
Line Replacement, Short
08/31/06
$ 251,400
$ 219,932
$ 31,468
WW0306
Line Replacement, E. Fuller
08/31/06
$ 231,372
$ 180.089
$ 51,283
WW0501
Line Replacement, Pebble Creek
08/31/06
$ 172,600
$ 145,655
$ 26,945
WWO604
Line Replacement, CDBG-Oakwood Terrace
05/31/07
$ 293,723
$ 232,274
$ 61,449
WW0402
Line Replacement, Carr Park/SH10
05/31/08
$ 588,000
$ 528,302
$ 59,698
WW0403
Line Replacement, Ector Drive
05/31/08
$ 373,000
$ 328,309
$ 44,691
WVV0601
Line Replacement, Cedar Hills Estate
05/31/08
$ 319,000
$ 200,201
$ 118,799
WW0602
Line Replacement, Ector Drive
05/31108
$ 425,000
$ 285,758
$ 139,242
WW0603
Little Bear Creek Collection Line
05/31/08
$ 575,000
$ 464,293
$ 110,707
VVW0701
Line Replacement, McCormick & Co her
02/05/09
$ 243,000
$ 194,254
$ 48,746
WW0702
Line Replacement, Arnett Addition
02/05109
$ 313,322
$ 229,006
$ 84,316
WW0703
Line Replacement, Jean Lane
02/05/09
$ 111,000
$ 70,603
$ 40,397
WW0704
Line Replacement, W. Fuller
02/05/09
$ 132,000
$ 82,708
$ 49,292
WWO902
Line Replacement, West Mills Drive-34th CDBG
04/16/10
$ 46,855
$ 46,855
$ -
WW0802
Line Replacement South Mills Drive CDBG-R
11/01/10
Is 253,710
$ 165,867
$ 87,843
WWO901
Line Replacement Woodridge Circle/Koen Lane
11/01/10
$ 407,000
$ 309,410
$ 97,590
VWJ0801
Line Replacement Fayette Drive
04114111
$ 357,000
$ 325,676
$ 31,324
WW1001
Line Re - W Alexander Ln/Norman Dr/Franklin Dr
05/31/12
$ 420,000
$ 331,614
$ 88,386
WW1101
Line Re - Bayless/Pauline/Jones CDBG
05/31/12
$ 350,000
$ 208,903
$ 141,097
VVW1103
Line Re - Bayless/Pauline/Jones Outfall
05/31/92
$ 57,000
$ 37,544
$ 19,456
WW1202
Line Re -Collin Drive 37thCDBG
05/31/12
$ 300,000
$ 231,173
$ 68,827
WWI 102
Line Re - E Huit Lane/Ascot Drive/Dunaway Drive
05/31/13
$ 560,000
$ 468,932
$ 91,068
WW1201
Line Re-Blanco/Aransas/Crane
05/31/13
$ 327,000
$ 284,321
$ 42,679
WW1301
Line Re - Ross/Slaughter/East & West Huitt
05/31/14
$ 670,000
$ 566,640
$ 103,360
WastewaterPro'ects - Prior Years
$ 11,867,904
$ 9,576,666
$ 2,291,238
WW1203
ISH183 Phase I Wastewater Relocation
10/31/14
$ 372,243
Is 372,243
$
WW1401
Line Re -Denton Drive
06/01/15
$ 629,000
$ 506,466
$ 122,534
Wastewater Projects-CurrentYear
Is 1,001,243
$ 878,709
$ 122,534
Total Wastewater Projects $ 12,869,147 $ 10,455,375 $ 2,413,772
335
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 10, 2010
Submitted By: RON YOUNG Date Completed: Oct 31, 2014
Project Title: SH183 PHASE I WASTEWATER RELOCATION
Project Type: WASTEWATER Sub -Type: LINE RELOCATION
Project Code: WW1203 Priority: A
COUNCIL AUTHORIZATION:
October 14, 2014: Authorized the Mayor to execute a Quitclaim Deed regarding Property Interests included in
Master Utility Adjustment Agreement No. 183-U-0504 for the North Tarrant Express (NTE) Project. Bluebonnet
Contractors, LLC, has offered the City $221,243.02 for its property interests stretching from Westpark Way to Nita
Lane, situated along the south right-of-way line of SH 183.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Department of Transportation ("TxDoT') has entered into a developer agreement with North Tarrant
Express Mobility Partners ("NTEMP") for the expansion of SH183. A portion of the Phase I construction will affect
the City of Euless utilities along SH183 between Westpark Way and FM157.
PROJECT DESCRIPTION:
The City of Euless has approximately 2,400 linear feet of wastewater mains and several manholes located within
the SH183 right-of-way. These facilities must be relocated to accommodate the SH183 expansion. It is
anticipated that the City will enter into a relocation agreement with NTEMP to authorize them to design and
relocate the wastewater lines. The City will be responsible for 50% of the cost of the line relocation.
PROJECT SCHEDULE:
Construction Complete: October 2014
JUSTIFICATION:
City of Euless wastewater facilities are located within TxDoT right-of-way. As such, the City must provide for
utility relocation to accommodate the roadway expansion.
-"*N
''IN
_ 1
336
PROJECT TITLE: SH183 PHASE I WASTEWATER RELOCATION
PROJECT CODE: WW1203
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODeratina Cost Construction $372,243
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $372,243
Maintenance Costs Funding Source:
Transfer from:
W/WW Operating Fund $151,000
R-O-W Proceeds $221,243
$0
Subtotal: $0
Total Estimated Annual Cost $()I Total Funding $372,243
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Construction $372,243 $372,243 $0 100%
$372,243 $372,243 $0 100%
337
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: HAL CRANOR Date Completed: Jun 1, 2015
Project Title: LINE REPLACEMENT-DENTON DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Pro'ect Code: WW1401 Priority: A
COUNCIL AUTHORIZATION:
December 10, 2013: Authorized the City Manager to execute an engineering design contract with Elliott and
Hughes, Inc. for the design of Fiscal Year 2014 Sanitary Sewer Rehabilitation Project. The estimated
expenditure is $60,000.
August 26, 2014: Awarded Bid No. 012-14 to William J. Schultz, Inc. dba Circle C Construction for the
replacement of sanitary sewer mains in portions of the Midway Park Addition. The estimated expenditure is
$492,335.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The project
is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Denton Drive between Collin Drive and Harwood Drive to include a portion of Bell Drive,
2. Dallas Drive between Denton Drive and Irion Drive, and
3. Trion Drive between Dallas Drive and Harwood Drive.
PROJECT SCHEDULE:
Began Construction: October 2014
Construction Complete: June 2015
JUSTIFICATION:
Many wastewater mains throughout the city are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
338
PROJECT TITLE: LINE REPLACEMENT-DENTON DRIVE
PROJECT CODE: WW1401
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct ODerating Cost Engineering $62
Personnel: Full Time Construction $567
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $01 Total Estimated Capital Cost $629,
Maintenance Costs Funding Source:
Transfer from:
W/VWV Operating Fund $539,
WMIW CIP Fund Balance $90,
$0
Subtotal: $0
Transfer to:
W(WW CIP Fund Balance ($122,534)
Total Estimated Annual Cost $0 Total Funding $506,466
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $62,000 $61,004 $996 98%
Construction $567,000 $445,462 $121,538 79%
ITOTAL PROJECT $629,000 $506,466 $122,534 81%
339
T H E C I T Y U f
EULESS
--IN
340
00
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WATER PROJECTS
WT9903
Master Plan
08/30/99
$ 42,000
$ 5,445
$ 36,555
WT9904
Well Repairs
09/30/99
$ 66,921
$ 66,921
$ -
WT9907
Impact Fee Study
09/30199
$ 13,000
$ 12,238
$ 762
WT9911
Water Distribution - Master Plan
09/30/99
$ 25,600
$ 24,000
$ 1,600
WT9901
Meter Change Out Program
10/30/99
$ 101,917
$ 98,365
$ 3,552
WT0002
Emergency Repair - H10
11/30199
$ 15,450
$ 14,214
$ 1,236
WT9906
Hwy 10 Water Line
01/30/00
$ 150,000
$ 138,883
$ 11,117
WT0006
Central Drive Water Mains
03/31/00
$ 92,814
$ 90,742
$ 2,072
WT9905
Misc Water Rehab
06/30/00
$ 50,000
$ 43,749
$ 6,251
WT0004
Water Line Milam - Eclor/Midwa
06/30/00
$ 18,248
$ 13,743
$ 4,505
WT0102
SCADA Upgrade
04/09/01
$ 93,400
$ 93,400
$ -
WT0003
Waterline Replacement - Aransas
06/30/01
$ 12,057
$ 7,089
$ 4,968
WT0005
Waterline Replacement - Milam- Denton/Mid
04/30/02
$ 26,988
$ 26,988
$ -
WT9910
Water Line for Elevated Tank
05/31/02
$ 1,608,386
$ 1,201,698
$ 406,688
WT9909
2MG Water Tank
03/31/03
$ 2,430,881
$ 2,289,571
$ 141,310
WT0103
Fire Hydrant Replacement Program
03/31/03
$ 50,000
$ 49,626
$ 374
WT9908
Mid Cities Blvd. IT' Line
04/30104
$ 342,080
$ 313,354
$ 28,726
W1-0401
Line Replacement, West Pipeline Main
05/31/06
$ 1,215,663
$ 1,215,663
$ -
WT0403
Waterline Replacement - Fairlawn Court
Cancelled
$ 35,000
$ -
$ 35,000
WT0404
Waterline Replacement - Atkerson Lane
Cancelled
$ 104,000
$ -
$ 104,000
WT0405
Line Replacement, West Ash Lane
08/31/06
$ 30,000
$ 11,626
$ 18,374
WT0406
Line Replacement, Westport/Newport/Asbury
08/31/06
$ 67,000
$ 9,866
$ 57,134
WT0502
FY'2005 CDBG
08/31/06
$ 69,300
$ 29,549
$ 39,751
WT0503
Line Replacement, S. Atkerson Lane
08/31106
$ 79,000
$ 51,294
$ 27,706
WT0504
Line Replacement, Blanco Drive
08131/06
$ 112,620
$ 112,620
$ -
WT0505
Line Replacement, Henslee
08/31/06
$ 183,000
$ 123.859
$ 59,141
WT0506
Line Replacement, Vemon/Slau hter
08/31/06
$ 161,000
$ 113,052
$ 47,948
WT9902
Tank Painting
05131t07
$ 1,317,763
$ 957542
$ 360,221
WT0501
System Security Upgrade
05/31/08
$ 40,000
$ 28,319
$ 11,681
W1-0601
Wtr Sys Security Perimeter Fence Upgrade
05/31/08
$ 75,000
$ 49,567
$ 25,433
WTO602
Line Replacement, Cannon Drive
05/31/08
$ 250,000
$ 223,055
$ 26,945
WT0701
Line Replacement, Canyon Ride
05/31/08
$ 116,000
$ 78,136
$ 37,864
W1-0702
CDBG FY07 - 32nd Oakwood Terrace
05/31/08
$ 334,481
$ 296,223
$ 38,258
WT0802
CDBG-33rd Oakwood Terrace -Simmons
12/31/08
$ 451,639
$ 384,173
$ 67,466
W1-0402
Water & Wastewater Impact Fee Update
05/31109
$ 30,000
$ 17,729
$ 12,271
WT0801
Line Replacement, Signet/Mesa
05/31/09
$ 255,000
$ 218,663
$ 36,337
W1-0201
Well Rehabilitation/Disinfection
04/17/10
$ 600,000
$ 522,308
$ 77,692
WT0202
Reclaimed Water Main
05/31/13
$ 1,750,000
$ 1,606,337
$ 143,663
WT1202
Stand i e Stora a Tank & Building Demolition
05/31/13
is 134,640
$ 70,089
$ 64,551
WT1203
lWater & Wastewater Impact Fee Update
05/31/13
Is 34,575
$ 34,575
$ -
water Projects - Prior Years
$ 12,585,423
$ 10,644,271
$ 1,941,152
WT1401 EI Caminio Real 02/28/15
$ 460,000
1 $ 420,462
$ 39,538
Water Projects- Current Year
Is 460,000
$ 420 462
$ 39,538
Total Water Mfects
$ 13,045,423
$ 711064,733
1 $ 1,980,690
341
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed: Feb 28, 2015
Project Title: LINE REPLACEMENT -EL CAMINO REAL
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Prolect Code: WT1401 Priority: A
COUNCIL AUTHORIZATION:
January 28, 2014: Authorized the City Manager to execute an Engineering Design Contract to Wier and
Associates, Inc. for the design of El Camino Real waterline. The estimated expenditure is $63,595.
June 24, 2014: Awarded Bid No. 009-14 for a construction contract to A&M Construction and Utilities, Inc., for
the El Camino Real waterline replacement project. The estimated expenditure is $329,423.90.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of an existing 8" AC water main with a 10" PVC water main on El Camino
Real from W Pipeline Road to the south City limits. The project scope includes approximately 3200 linear feet of
10" PVC, 20 valves, and 8 fire hydrants. New water service connections to the apartments and townhomes will
also be included in the project.
PROJECT SCHEDULE:
Began Construction: August 2014
Construction Complete: February 2015
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic replacement of old deteriorated or substandard size water mains will
reduce maintenance costs. The water main on El Camino Real has experienced several breaks within the last
two years.
--4N
342
PROJECT TITLE: LINE REPLACEMENT -EL CAMINO REAL
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
PROJECT CODE: WT1401
TOTAL ESTIMATED CAPITAL COST:
Engineering $65,
Construction $395,
Total Estimated Capital Cost $460,000
Funding Source:
Transfer from:
W/WW Operating Fund $515,000
Subtotal: $0 Transfer to:
W/WW CIP Fund Balance ($55,000)
W/WW CIP Fund Balance ($39,538)
Total Estimated Annual Cost $0 Total Funding $420,462
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $65,000 $61,744 $3,256 95%
Cnnstruction $395,000 $358,719 $36,281 91 %
$460,000 $420,462 $39,538 91%
343
T H E C I T Y O F
EULESS
344
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
OTHER PROJECTS
AC9901
Athletic Complex Phase II
06/30/02
$ 123,654
$ 75,047
$ 48,607
ACO202
Athletic Complex Phase III
05/31/06
$ 1,252,221
$ 1,251,915
$ 306
AC1001
Texas Star Sports Complex Lighting Improvements
05/31/12
$ 504,200
$ 475,246
$ 28 954
ED0102
Bell Ranch Terrace
Cancelled
$ 200,000
$ -
$ 200,000
FM0209
Midway Recreation Upgrade
06/30/02
$ 557,125
$ 557,125
$
FMO101
Buildin D
09/30/02
$ 930,610
$ 930,608
$ 2
FM0308
Building A Remodel
05/31/07
$ 1,663,238
$ 1,651,325
$ 11,913
FM0309
Fire Station #3
05/31/07
$ 2,286,798
$ 2,286,229
$ 569
FM0601
Public Works Facility
05/31/08
$ 2,210,956
$ 2,213,507
$ 2,551
FM0802
Senior Citizen Center Design
cancelled
$ 250,000
$ -
$ 250,000
FMO804
Library -Shell Expansion
12/31/08
$ 307,034
$ 305,664
$ 1,370
FM0803
Midway Recreation Improvements
03/31/09
$ 293,500
$ 75,976
$ 217,524
FM0504
Building "B" Remodel
05/31/09
$ 1,322,490
$ 1,315,697
$ 6,793
FM0801
TX Star Golf Course & Conference Ctr Expand
05/31/09
$ 3,630,079
$ 3,630,079
$
PR0015
Purchase of Dallas Stars Center
05/31/00
$ 10,327,978
$ 10,327,978
$
PR0016
Wilshire Park Improvements
06/30/02
$ 150,000
$ 149,926
$ 74
PR0110
Sloe Protection/Screening Wall
03/31/03
$ 1,275,203
$ 1,273,923
$ 1,280
PR0409
Parking Improvements, Simmons
07/29/04
$ 6,960
$ 6,960
$
PR0410
Parking Improvements, Villages Bear Creek
07/29/04
$ 33,666
$ 33,666
$
PR0302
Bob Eden Parkin
04/30/05
$ 75,000
$ 74,854
$ 146
PR0303
Youth Ballpark
04/30/05
$ 600,000
$ 600,000
$
PR9901
Hike/Bike Trail
04/30/05
$ 237,714
$ 237,714
$
PR9902
Senior Citizen Remodel
04/30/05
$ 16,130
$ 16,130
$
PR0407
Parkin Improvements, MidwayCancelled
$ 11,000
$ -
$ 11,000
PR0408
Parkin Improvements, S. Euless Park
05/31/06
$ 55,000
$ 20,991
$ 34,009
PR0411
Preserve at McCormick Park
05/31/06
$ 1,168,427
$ 1,168,427
$
PR0412
Splash Pool
05/31/06
$ 125,000
$ 124,477
$ 523
PR9903-
PR9918
Various EDC Park Projects
09/30/06
$ 259,566
$ 248,891
$ 10,675
PR0602
Mid Cities Landscaping
05/31/09
$ 40,000
$ 33,199
$ 6,801
PR0719
Midway Park Trail
05/31/09
$ 210,000
$ 190,473
$ 19,527
PR0601
Park Amenities Upgrade
04/17/10
$ 150,000
$ 145,316
$ 4,684
PR0901
Trail Enhancements - Bob Eden Park
04/17/10
$ 135,000
$ 101,673
$ 33,327
PR0902
Senior Citizen Center at Midway Park
05/31/11
$ 4,763,661
$ 3,888,892
$ 874,769
PR0907
Euless Family Life Center Phase I
05/31/11
$ 2,105 000
$ 2,099,281
$ 5,719
PR9922
Teas Remodel
11 /30/01
$ 430,000
$ 455,885
$ (25,885
PR9927
Park Improvements - Texas Star
09/30/01
$ 1,036,500
$ 1,025,298
$ 11,202
SS9901
Fire Station II
03/30/00
$ 49,688
$ 49,688
$
SS9919
Fire Station #3 - Structural Repairs
03/30/00
$ 30,000
$ 17,344
$ 12,656
SS9902
Libra Books
08/15/00
$ 3,302
$ 3,302
$
SS0010
Former Fire Station #2
06/30/02
$ 599,600
$ 595,257
$ 4,343
SS0113
Park Building
06/30/02
$ 1,492,400
$ 1,492,100
$ 300
OtherPro'ects- PriorYears
$ 40,918,700
$ 39,150,063
$ 1,768,637
GR1401
Golf Course Up2rades
09/30/14
$ 587,000
$ 581,296
$ 5,704
PR1201 JEuless
Family Life Center Aquatics
09/30/14
$ 7,504,972
$ 7,319 299
$ 185,673
PD9901 1pouce
and Courts Facility
05/31/15
$ 11,718,304
$ 11,718,304
$
OtherPro'ects- Current Year
$ 19,810,27S
$ 19,618,899
$ 191,377
Total Other Projects
$ 60,728,976
$ 58,768,962
$ 1,960,014
345
City of Euless
Capital Project Request
Department: TEXAS STAR GOLF COURSE Date Prepared: March 18, 2013
Submitted By: GLENDA HARTSELL Date Completed: September 30, 2014
Project Title: GOLF COURSE UPGRADES
Project Type: PARK/RECREATION Sub -Type: TSGC IMPROVEMENTS
Project CODE: GC1401 Priority: A
COUNCIL AUTHORIZATION:
December 10, 2013: Awarded Bid No. 005-14 for the fumigation of putting greens at Texas Star Golf Course to Francis
and Francis, Highland Village, Texas. The estimated expenditure is $68,850.
March 25, 2014: Authorized the purchase of bunker sand with Turf Materials, Inc., P.O. Box 2213, Rockwall, Texas, for
Texas Star Golf Course bunker renovation. The estimated expenditure is $72,150.
March 25, 2014: Authorized the City Manager to execute a contract with King Ranch Turfgrass, LP, 106 North Dennis
Street, Wharton, Texas, for the purchase of MiniVerde Ultra -Dwarf Bermuda grass sprigs on 19 greens and certified
Tifway 419 Bermuda grass on collars around the greens. The estimated expenditure is $64,028.
April 22, 2014: Awarded Bid No. 006-14 for a construction contract to Fleetwood Services, LLC, 4558 Steeple Chase
Lane, Rockwall, Texas, for miscellaneous golf course improvements to Texas Star Golf Course. The estimated
expenditure is $235,788.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Resurface the 18 Bentgrass greens on the course and the green nursery. Strip and prepare putting surface and collars for
new turf, fumigate greens and collars to kill all plants, weed seeds, diseases, nematodes, and insects present in the soil. Sprig
putting surface with Mini Verde Ultra Dwarf Bermuda and re -sod collars with 419 Bermuda. Reconstruct all sand bunkers to
consistent standards and specifications including the removal of existing sand material and drainage, reshape the bunkers as
needed, install new drainage and bunker liner material, and refill with premier crushed quartz bunker sand material to a
uniform depth. The existing sand will be used for agronomic practices around the course and practice areas. Tee leveling,
cart path improvements, expansion of the tee boxes and various miscellaneous improvements are included in the project
scope.
PROJECT SCHEDULE:
Began Construction: June 2014
Construction Complete: September 2014
JUSTIFICATION:
Texas Star is a championship daily fee golf facility known for its high level of service and excellent course conditions. At this
point in the life of the greens, it has become increasing more difficult to maintain the Bentgrass greens in an acceptable
condition during the summer months. This is due in large part to a reduction in drainage capabilities of the greens
themselves, weed and surrounding turf encroachment, the utilization of fans for air circulation, and the use of reclaimed water
containing higher salt levels. The proposed Ultra Dwarf Bermuda greens are much better suited to withstand the heat of North
Texas summers and are much more forgiving of drainage issues, poor air circulation, and the use of reclaimed water.
Additionally, the sand bunkers have been a consistent area of concern which staff has addressed on a limited number of
bunkers each year by repair or replacement of both the bunker sand and underlying drainage. Simultaneous reconstruction of
all sand bunkers to consistent standards and specifications would result in not only an aesthetically pleasing look, but optimal
playing conditions as well.
"t
346
M,
PROJECT TITLE: GOLF COURSE UPGRADES
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Maintenance Costs
Subtotal:
Total Estimated Annual Cost
PHASE/FUNDING SOURCE
Golf Course Greens Improvement
Golf Course Bunker Improvement
Contingencies
TOTAL PROJECT
PROJECT CODE: GC1401
TOTAL ESTIMATED CAPITAL COST
Greens Replacement
Bunker Replacement
Contingency
$0
Total Estimated Capital Cost
$0
FUNDING SOURCE:
Transfer from:
Golf Course Reserves
Car Rental Fund
$0
Transfer to:
TSGC Reserve Fund ($5,704)
$0 Total Funding $581,296
CURRENT STATUS
OVERIUNDER
BUDGET EXPENDED BUDGET (-+) % EXPENDED
$213,225 $207,497 $5,728 97%
$325,154 $325,179 ($25) 100%
$48,621 $48,620 $1 100%
$270,000
$242,000
$75,000
g l
$512000 I
$75:000
$587,000 $581
704 99%
347
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: February 11, 2009
Submitted By: RAY MCDONALD Date Completed: September 30, 2014
Project Title: EULESS FAMILY LIFE CENTER AQUATICS
Project Type: PARK/RECREATION Sub -Type: AQUATICS
Project CODE: PR1201 Priority: A
COUNCIL AUTHORIZATION:
April 10, 2012: Authorized the City Manager to negotiate and execute an architectural contract for certain components of the
Euless Family Life Center ("FLC") aquatics facilities to John Kirksey Associates, Architects, Inc. d/b/a Kirksey, Houston, TX.
Fee is anticipated at 8% of construction costs of the buildings.
April 10, 2012: Authorized the City Manager to solicit statements of qualifications for Design/Build Services related to the
Euless FLC Indoor and Outdoor Aquatics Facilities.
August 14, 2012: Authorized the City Manager to negotiate and execute a Design/Build contract with Progressive
Commercial Aquatics in the approximate amount of $3,200,000, which includes construction administration and general
contracting services for certain components of the Euless Family Life Aquatics Center.
January 8, 2013: Authorized the City Manager to negotiate and execute a contract with Modern Contractors in the amount
of $3,658,000 for the construction of an Indoor Pool Structure and Outdoor Building Features. Authorized a contingency in
the amount of $150,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless has for many years recognized the importance of planning for parks, recreation, and open space based on
the needs as expressed by the citizens. For the update to the Parks Master Plan and as part of the City's five year master
plan, a survey of park, recreation, and open space needs was conducted from a sample of randomly selected citizens in
Euless. The survey identified a new aquatic center as a top priority of the citizens. Project approval requires revision of the
master planning of Midway Park as the aquatics center eliminates the current ball fields and requires the relocation of the
existing tennis courts in order to provide support facilities and amenities for the FLC.
PROJECT DESCRIPTION:
The project consists of the design of indoor and outdoor family aquatic facilities. The indoor facility includes a lap/leisure pool,
current channel, slide, and therapy pool. This multi -purpose facility will be attached to the senior center and will offer aquatic
programs for the senior population and the general public. The outdoor aquatics center will include various play components
such as a leisure pool, slides, aqua play features, shade structures, a bath house, and all the necessary filtration systems. The
project scope also includes redevelopment and improvement of the entire site such as relocating the tennis courts and the
construction of various trails, a group pavilion, an amphitheater, multi -use sport courts, additional picnic stations with grills, a
nature area, a botanical garden, and public art display(s).
PROJECT SCHEDULE:
Outdoor Complete: May 2013
Indoor Complete: December 2013
JUSTIFICATION:
The City's population is sufficient to support a family aquatic center. The City's existing aquatic facilities have aged and
maintaining the pools and support facilities has been an ongoing issue and concern. The operating expenses continue to
increase, far exceeding the revenue generated by the pools. Continuing in repair mode is no longer possible at the Wilshire
and South Euless Pools and a long-term plan is necessary. Given the fact that two of the neighborhood pools are over thirty
years old and the cost to renovate, repair, or replace them is estimated at over one million dollars each, it is recommended that
the City concentrate efforts and resources toward the family aquatic facility to serve the citizens of Euless.
_ 1
348
PROJECT TITLE: EULESS FAMILY LIFE CENTER AQUATICS PROJECT CODE: PR1201
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST
MAINTENANCE COST (+ OR -) ANNUAL
Direct Overatinq Cost
Architectural - Design
Personnel: Full Time
Architectural - Reimbursables
Part Time $198,903
Architectural - Consulting
Total Salary $198,903
Surveying
Purchase of Services
Engineering Services
Materials & Supplies
Contingencies
Utilities
Construction - Aquatic Element
Construction - Buildings
Owner Equipment
Total Estimated Capital Cost
Subtotal: $198,903
FUNDING SOURCE:
Maintenance Costs
Transfer from:
Car Rental Fund
Car Rental CIP Fund Balance
General CIP Fund Balance
Subtotal:
Estimated Annual Cos*
PHASE/FUNDING SOURCE
Surveying
Architectural Services
Engineering
Contingencies
Construction
Owner Equipment
Furniture
(TOTAL PROJECT
$0
Transfer to:
Car Rental CIP Fund Balance
$198,903 Total Funding
RRENT STATUS
BUDGET
$14,000
$380,277
$55,000
$114,130
$6,897,370
$38,000
$6,195
$7
EXPENDED
$13,973
$343,385
$54,999
$0
$6,855,743
$45,004
$6,195
L
$292,640
$21,000
$72,832
$13,500
$30,000
$147,630
$3,239,370
$3,658,000
$30,000
$7,504,972 1
$1,763,500
$4,236,500
$1,504,972
($185,673)`
$7,319,299 I
OVER/UNDER
BUDGET (- +) % EXPENDED
$28
100%
$36,892
90%
$1
100%
$114,130
0%
$41,627
99%
($7,004)
118%
$0
100%
185
98%
349
City of Euless
Capital Project Request
Department: POLICE DEPARTMENT Date Prepared: July 15, 1999
Submitted By: GARY MCKAMIE Date Completed: May 31, 2015
Project Title: POLICE & COURTS FACILITY
Project Type: BUILDINGS/FACILITIES Sub -Type: CONSTRUCTION
Project No.: PD9901 Priority: A
COUNCIL AUTHORIZATION:
January 13, 1998 - Authorized contract with Phillips Swager for architectural services.
April 14, 1998 - Authorized the acquisition of the Western Hills Inn and Western Hills Annex.
June 9, 1998 - Awarded Bid No. 98-13 for demolition services.
October 9, 1998 - Awarded change order to West Excavation for abatement of asbestos.
February 23, 1999 - Authorized additional funds for demolition.
June 22, 1999 - Declared expectation to reimburse expenditures with proceeds of future debt.
June 22, 1999 - Authorized City Manager to request qualifications for construction management service.
February 22, 2000 - Public Hearing and approval of Special Use Permit.
February 22, 2000 - Approval of request for site plan.
May 9, 2000 - Approval of Ordinance No. 1426 authorizing sale of Cert. Of Obligation Series 2000A.
May 9, 2000 - Awarded bid for construction to Ratcliff Construction.
November 14, 2000 - Authorized execution of contract for Project Management Services
January 9, 2001 - Granted City Manager approval to authorize change orders not to exceed $25,000.
January 23, 2001 - Ratified contract for inspection services to increase limit to $65,000
January 23, 2001 - Approved Change Order #1 to credit contract $152,391.
January 23, 2001 - Approved Change Order #3 for payment of $48,372.79 on new piers & removal.
March 27, 2001 - Approved Change Order #4 to credit contract $42,871.41.
May 22, 2001 - Awarded bid #044-01 for furniture in the amount of $332,400.70.
June 12, 2001 - Authorized City Manager to execute contract with DataTex not to exceed $74,257.86.
August 28, 2001 - Awarded contract to DFW Communication in the amount of $33,009 for relocating and
installing police and public works radio system.
April 22, 2014: Authorized the purchase of a security control system to upgrade and replace various existing
system components from ISI Security/MCS, 12903 Delivery Drive, San Antonio, Texas, at the Euless Police,
Jail, and Municipal Court Facility. The estimated expenditure is $149,480 and a portion of this amount is
authorized for project PD 1401 -SecuritySystem Upgrade.
PROJECT DESCRIPTION AND RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This 53,000 square foot facility will accommodate police, jail and courts.
PROJECT SCHEDULE:
JUSTIFICATION:
Current facility space is grossly inadequate for these areas.
,-"It
350
\I-
PROJECT TITLE: POLICE & COURTS FACILITY
Don ict it 41• Dnnnni
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Bond Issuance Cost
$76,000
Direct Operating Cost
Construction
$9,071,257
Personnel: Full Time
$128,000
Contingency
$128,313
Part Time
Demolition
$606,709
Architectural/ Surveying/ Geotech
$826,439
Other Professional Services
$36,310
Utilities
$106,000
Equipment
$67,912
Furnishings
$350,000
Land Purchase
$43,592
Planning Services
$70,428
Subtotal:
$234,000
Owner Equipment
$441,344
Total Estimated Capital Cost
$11,718,304
Maintenance Costs
HVAC Maintenance
$18,084
FUNDING SOURCE:
Maintenance
$24,850
Transfers from:
Janitorial Services & Supplies
$37,500
General Fund
$394,890
Elect. Supplies
$8,000
W/S Operating Fund
$175,000
Pest Control
$1,500
CCPD Operating Fund
$2,160,000
Subtotal:
$89,934
DEA Funds
$450,000
Bond Proceeds
$8,600,000
Other
Interest Income
$577,217
Average Annual Debt Service
$750,815
Less Inter -project Transfer to:
Building D FM0101
($638,803)
Total Estimated Annual Cost
$1,074,749
Total Funding
$11,718,304
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (- +)
% EXPENDED
Bond Issuance Cost
$76,000
$76,000
$0
100%
Construction
$9,071,257
$9,071,257
$0
100%
Contingency plus interest earnings
$96,527
$96,527
$0
100%
Demolition
$606,709
$606,709
$0
100%
Architectural Services
$745,369
$745,369
$0
100%
Surveying Services
$6,070
$6,070
$0
100%
Geo-Technical Services
$72,511
$72,511
$0
100%
Other Professional Services
$36,310
$36,310
$0
100%
Equipment
$141,392
$141,392
$0
100%
Furnishings
$348,347
$348,347
$0
100%
Land Purchase
$43,592
$43,592
$0
100%
Off -Site Utilities
$0
$0
$0
0%
Owner Equipment
$403,792
$403,792
$0
100%
Planning Services
$70,428
$70,428
$0
100%
" - This project transferred $638,803 to FM0101.
'AL PROJECT $11,718,304 $11,718,304 $0 100%
351
T H E C I T Y O F
EU-LESS
'"*N
352