- CITY OF EULESS
FISCAL YEAR 2016-2017
LINDA MARTIN, MAYOR
Tim Stinneford, Council Member - Place One
Jeremy Tompkins, Council Member - Place Two
Eddie Price, Council Member - Place Three
Linda Eilenfeldt, Council Member - Place Four
Harry Zimmer, Council Member - Place Five
Perry Bynum, Council Member - Place Six, Mayor Pro Tem
Loretta Getchell, City Manager
Bob Freeman, Deputy City Manager
Chris Barker, Assistant City Manager
M
M,
TABLE OF CONTENTS
PRELIMINARY CAPITAL IMPROVEMENTS PROGRAM
City Officials
Table of Contents i-v
Letter vi-vii
FUNDED PROJECTS
Summary of Funded Projects 1
FY16 Amendments 3
Drainaae Proiects
Summary of Funded Drainage Projects
5
DR9903 Miscellaneous Drainage Improvements
6
DR1101 Flooding Mitigation
8
DR1201 Miscellaneous Creek Maintenance
10
Street Projects
Summary of Funded Street Projects
13
PS1102 Glade Parks Improvements
14
PS1203 Miscellaneous Street Repairs
16
PS1501 FY2015 40th CDBG — ADA/TAS Infrastructure Improvements
18
PS1601 East Harwood Road Extension
20
PS1602 FY2016 Street Overlay
24
PS1603 FY2016 41st CDBG — ADA/TAS Infrastructure Improvements
26
Wastewater Projects
Summary of Funded Wastewater Projects
29
WW0002 Miscellaneous Wastewater Rehabilitation
30
WW0605 TRA Wastewater Payments — Impact
32
WW1601 Line Replacement — Glenn Drive
34
Water Projects
Summary of Funded Water Projects
39
WT0001 Miscellaneous Water Rehabilitation
40
WT0101 Water Tank Debt Payment —Impact
42
WT0104 Well Repairs
44
WT0803 Meters and Transponders
46
WT1212 Reclaimed Water Line Extension Phase II
48
WT1402 Fixed Base Meter Reading and Water Meter Changeout
50
WT1403 Reclaimed Water Line Extension Debt Payment — Impact
52
WT1602 FY2016 41 st CDBG Line Replacement — Ector Drive
54
W71603 Miscellaneous Valve Replacement
58
WT1604 Reclaimed Water Line Extension Phase III
60
Other Projects
Summary of Funded Other Projects
63
.-,
AC1601 Texas Star Sports Complex Phase V
64
CM0304 Entry Monument Sign Program
66
CM0804 Redevelopment
68
CM1509 Municipal Plaza Improvements Phase 1
70
DV9901 EDC Incentive Funds
72
ED0101 Planning Consultants
74
ED1002 EDC Contingency
76
ED1601 Midtown Development
78
FM1201 ADA/TAS Facility Improvements
80
FM1510 Development/Engineering Building Improvements
82
GC1201 TSGC Miscellaneous Improvements
84
PR0720 Miscellaneous Park Improvements
86
PR0804 Park Irrigation
88
PR1401 Glade Parks Trail Connection
90
PROPOSED & UNFUNDED PROJECTS
Summary of FY17 Proposed & Unfunded Projects — Sorted by Type 93
Drainaae Proiects
Summary of FY17 Proposed & Unfunded Drainage Projects
97
Bell Hi Addition
98
Blessing Branch — Main Street to SH360
99
Hollow Oak Channel Erosion
100
Kynette Drive Culvert Modifications
101
Little Bear Creek Drainage Improvements
102
Marlene Drive Culvert Replacement
103
Simmons Drive Culvert Improvements
104
Street Projects
Summary of FY17 Proposed & Unfunded Street Projects
105
FY2017 42nd CDBG — ADA/TAS Infrastructure Improvements
106
FY2017 Street Improvements
108
Traffic Signal — Harwood Road at Bear Creek Parkway
110
Ash Lane Reconstruction — Village Drive to West of SH360
114
Bear Creek Parkway Reconstruction — Harwood Road to Mid -Cities Boulevard
116
Fuller -Wiser Road Reconstruction — SH183 to Midway Drive
118
Midway Drive & Fuller -Wiser Road Intersection Reconstruction
120
FY2018 Street Improvements
122
FY2019 44th CDGB — ADA/TAS Infrastructure Improvements
124
FY2019 Street Improvements
126
Traffic Signal — Cheek Sparger Road at Heritage Avenue
128
FY2020 Street Improvements
130
FY2021 Street Improvements
132
Vine Street Reconstruction — SH183 to SH10
134
Cresthaven Drive Reconstruction
136
E Alexander Lane Reconstruction
137
Highland Drive Reconstruction
138
Ross Avenue Extension
139
South Pipeline Road Reconstruction
140
Wastewater Projects
Summary of FY17 Proposed & Unfunded Wastewater Projects
141
Line Replacement — Cedar Hills Estates/Hollywood Boulevard
142
FY2017 42nd CDBG LR: Oakwood Terrace Phase 1
146
FY2018 43rd CDBG LR: Oakwood Terrace Phase 11
150
Line Replacement — Ector Drive/Fayette Drive
152
Line Replacement — Milam Drive
154
SH183 Phase II Wastewater Relocation
156
Line Replacement — Kynette Drive/Wilshire Drive
158
Line Replacement — Eastcliff Drive/Windlea Drive/Signet Drive
160
Line Replacement — Ector Drive/Donley Drive/Crane Drive
162
Line Replacement — Donley Drive/Shelmar Drive
164
Line Replacement — Evans Drive/Canyon Ridge Drive/N Kynette Drive
165
Line Replacement — Huntington/Koen/Atkerson/E Huitt/Slaughter/Martin
166
Line Replacement — Janann Street/Brownstone Drive/Shelmar Drive
167
Line Replacement — Lakewood Boulevard/Dogwood Circle/Bocowood Circle
168
Line Replacement — Live Oak Drive/Silver Creek Drive/Marlene Drive
169
Line Replacement — Mary/Marlene/Commerce/Wilsh ire/Green briar
170
Line Replacement — Northcliff/Toplea/VVindlea/Signet/Kynette/Westcliff
171
Line Replacement — NW Midway/Rusk/Parker/Rockwall
172
Line Replacement — S Main Street
173
Line Replacement — Sagebrush/TopleanVilshire/YorkshirelTyler
174
Line Replacement — Sierra Drive
175
Line Replacement — W Don ley/Private/Mimosa/Magnolia/Red bud
176
Line Replacement — W Midway/Victoria/Delta/Lamar/Rockwall
177
Water Projects
Summary of FY17 Proposed & Unfunded Water Projects
179
Fort Worth Interconnect
180
Reclaimed Water Line Extension Phase IV
182
FY2019 44th CDBG Line Replacement — Hollow Oak Drive
184
Line Replacement — Kynette Drive, Cyclone Creek to Wilshire Drive
186
SH183 Phase II Water Relocation
188
FY2020 45th CDBG Line Replacement — S Main (South)
190
Line Replacement — Springwood Court
192
Line Replacement — Sunset Drive, S Pipeline Road to S Main Street
194
Reclaimed Water Line Extension Phase V
196
Reclaimed Water Line Extension Phase VI
198
FY2021 46th CDBG Line Replacement — S Main Street (North)
200
1 Mil Well Replacement
202
Far North Well Replacement
203
Fuller Well Replacement
204
M
Line Replacement — Blessing Creek/Stony Creek/Rock Creek
205
Line Replacement — Collin Drive, Dallas Drive to Harwood Road
206
Line Replacement — Collin Drive, Denton Drive to Dallas Drive
207
Line Replacement — Cresthaven Drive
208
Line Replacement — Denton Drive, Tarrant Drive to Harwood Road
209
Line Replacement — Dickey Drive North, SH10 to E Huitt Lane
210
Line Replacement — Dickey Drive South, E Huitt Lane to Hilton Drive
211
Line Replacement — Dunaway Drive, E Alexander Lane to E Ascot Drive
212
Line Replacement — E Huitt Lane, S Main Street to Dunaway Drive
213
Line Replacement — Eastcliff Drive, Toplea Drive to Del Prado Apts
214
Line Replacement — Fuller Drive, Salem Drive to Carter Drive
215
Line Replacement — Highland Drive
216
Line Replacement — Live Oak Court/Live Oak Drive
217
Line Replacement — Midcreek Drive/Rock Creek Drive/Stony Creek Drive
218
Line Replacement — Midway Drive East, N Main Street to Freestone Drive
219
Line Replacement — Midway Drive West, Freestone Drive to Ector Drive
220
Line Replacement — Needles Street, Paula Lane to Raider Drive
221
Line Replacement — Paula Lane, Needles Street to S Pipeline Road
222
Line Replacement — S Pipeline Road East, Vine Street to S Main Street
223
Line Replacement — S Pipeline Road West, Simmons Drive to Vine Street
224
SH360 Water Crossing
225
Line Replacement — Shady Creek Drive/Cliffwood Road
226
Line Replacement — Westwood Drive, Fuller Drive to Carter Drive
227
Line Replacement — Wildwood Street
228
Line Replacement — Woodvine Drive (East), Cliffwood Road to El Camino Real
229
Line Replacement — Woodvine Drive (West), Pebble Creek Drive to Cliffwood Rd
230
Other Projects
Summary of FYI Proposed & Unfunded Other Projects
231
Library Remodel Design
232
Municipal Plaza Improvements Phase II
234
Public Works Yard Improvements
236
Texas Star Maintenance Building
238
Texas Star Sports Complex Phase VI
240
Texas Star Sports Complex Phase VII Design
242
Library Remodel Construction
244
Texas Star Sports Complex Phase VII Construction
246
Blessing Branch Park Improvements
248
Trail Enhancements Phase 1
250
Animal Shelter Expansion/Renovation
252
Fire Station #2 Remodel
253
Kiddie Carr Park Improvements
254
South Euless Park Upgrades
255
Trail Enhancements Phase II
256
Trail Enhancements Villages of Bear Creek
257
Trailwood Park Improvements
258
'1
iv
OR
Wilshire Park Upgrades 259
COMPLETED PROJECTS
Drainage Proiects
Summary of Completed Drainage Projects
261
Street Projects
Summary of Completed Street Projects
263
PS1202 ADA/TAS Infrastructure Improvements
264
PS1502 FY2015 Street Overlay
266
Wastewater Proiects
Summary of Completed Wastewater Projects
269
WW1501 Line Replacement —Crane Drive
270
WW1502 Line Replacement —Town Creek Drive
272
Water Proiects
Summary of Completed Water Projects
275
WT0901 Trinity River Authority Water Payment — Impact
276
WT1201 Reclaimed Water Line Extension Phase 1
278
WT1501 24-Inch Valve Replacement Cinnamon, Anice, Fuller -Wiser
280
WT1601 Line Replacement —Donley Drive/Shelmar Drive
282
Other Proiects
Summary of Completed Other Projects
285
AC1201 Texas Star Sports Complex Phase IV
286
CM1508 Car Rental Contingency
288
v
T H E C I T Y O f
SS
July 27, 2016
Honorable Mayor Linda Martin
Honorable City Councilmembers:
Tim Stinneford, Place One
Jeremy Tompkins, Place Two
Eddie Price, Place Three
Linda Eilenfeldt, Place Four
Harry Zimmer, Place Five
Perry Bynum, Place Six, Mayor Pro Tern
INTRODUCTION
The City of Euless' Capital Improvements Program is a comprehensive document
detailing all projects that have been identified to date. Emphasis has been placed on
organizing this data in a manner that will facilitate decision -making processes, assist in
long-range planning, and provide the citizens of Euless with information regarding
planned projects. This document meets the requirements of the City Charter. Article
VII, Section 2 (5) requires, "A statement proposing any capital expenditures deemed
necessary for undertaking during the next budget year and recommended provisions for
financing." Section 2 (6) further requires, "A list of capital projects which should be
undertaken within the five (5) next succeeding years."
We extend special appreciation to the directors and the finance staff for their outstanding
performance in creating this document.
UNDERSTANDING THIS BOOK
Although this book contains a large volume of information, the summaries should make it
easy to understand at a glance. The book is divided into three sections: Funded
Projects, FY2017 Proposed and Unfunded Projects, and Completed Projects. Each
section begins with a summary and is followed by detailed data for those wishing to
research individual projects.
The detail provided includes the project's relationship to City master plans, the project
description and justification, the effect on future maintenance and operating costs, and
the estimated total cost. Within each section, you will find the detailed descriptions
sorted by type. There are five basic project types: Drainage, Streets, Wastewater,
Water, and Other.
201 N. Ector Drive, Euless, Texas 76039-3595
817/685-1400 • Metro 817/267-4403 . Fax 817/685-1416
www.eutesstx.gov
V1
The Funded Projects section includes all projects that the City Council has previously
authorized_ Many of these projects are on -going and require additional funding from
time to time. For each project, a detailed description has been provided that includes
any City Council authorization, the current status of the project, and a financial summary
detailing funding sources and total project budget. Any amendments or additional
appropriations requested are also identified.
Any project that has been authorized by the City Council that is not fully funded will
include a clear explanation as to how the remainder of the project is expected to be
funded.
The FY2017 Proposed and Unfunded Projects section has been classified into three
categories of priority. Priority A indicates the item is recommended and funding has
been identified in the proposed FY2017 budget. Staff recommends City Council
authorization for these projects. Priority B projects should be presented to Council
within two to five years for consideration. Projects that will not begin for at least five
years have been assigned a Priority C. This system has been used to allow the Council
to evaluate and shift priorities, when necessary, and to provide a means of budgeting
capital projects for at least five years. Recommended funding sources have been
indicated if known.
The Completed Projects section provides a summary for each project type indicating
total project budget, actual expenditure, and variance. Funds remaining have been
returned to the appropriate fund balance account for re -appropriation. Details of projects
closed during the prior year have also been included.
'%� FY2017 PROJECTS:
Funding has been identified for all proposed FY2017 projects which are reflected on the
FY2017 Proposed and Unfunded Projects Summary as Priority A. These include:
• FY2017 42"d Year CDBG - ADA/TAS Infrastructure Improvements
• FY2017 Street Improvements
• Traffic Signal - Harwood Road at Bear Creek Parkway
• Cedar Hill Estates/Hollywood Boulevard Wastewater Line Replacement
• FY2017 42"d Year CDBG - Oakwood Terrace Phase I Line Replacement
• Library Remodel Design
• Municipal Plaza Improvements Phase II
• Public Works Yard Improvements
• Texas Star Golf Course Maintenance Building
• Texas Star Sports Complex Phase VI
CLOSING COMMENTS
This document is prepared as a comprehensive summary of capital needs that have
been identified throughout the City of Euless. This document will be updated annually to
aid the City Council in allocating resources and determining priorities.
Sinc ely;,�
_ t7
L etta Getch II
City Manager
vii
T H E C I T Y O F
EUL''ESS
viii
CITY OF EIILEss
CAPITAL IMPROVEMENT PROGRAM
AMENDMENTS — FuxDED PROJECT8
PROJECT#
PROJECT DESCRIPTION
DATE
AMENDMENTS 8s ACTIONS
AC1201
Texas Star Sports Complex Phase IV
05/31/2016
To close project and transfer excess funding of $70,034 to EDC CIP
Fund Balance.
AC1601
Texas Star Sports Complex Phase V
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $2,307,767
from TSSC CIP, TSSC Reserves, EDC debt reduction and EDC Debt
Reserve.
AC1601
Texas Star Sports Complex Phase V
06/28/2016
To provide additional funding of $295,110 from TSSC Reserves.
CM0804
Redevelopment
05/31/2016
To provide additional funding of $100,000 from Gardner Capital
Texas, LLC and Bloomfield Homes Fund, LP for contributions to a
Community Revitalization Fund.
CM0804
Redevelopment
05/31/2016
Increase funding for additional earned interest of $387.
CM1508
Car Rental Contingency
05/31/2016
To close project.
CM1509
Municipal Plaza Improvements Phase 1
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan
$58,500 from Car Rental CIP Fund Balance.
DR1201
Miscellaneous Creek Maintenance
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$60,000 from Drainage Operating Fund.
DR9903
Miscellaneous Drainage Improvements
05/31/2016
To provide additional funding of $68,113 from FEMA
reimbursement for drainage channel improvements along
Hurricane Creek.
DV9901
EDC Incentive Funds
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$25,000 from EDC Operating Fund.
ED1601
Midtown Development
10/01/2015
To establish budget per FY2016 Approved CIP Plan - $16,748,583
(Future Bond Issue).
ED1601
Midtown Development
05/31/2016
Reduce budget in the amount of $330,603 per the 2016 bond sale
and development agreement.
FM1201
ADA/TAS Facility Improvements
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$15,000 from Car Rental Fund.
FM1510
Development/Engineering Building Improvements
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $2,494,775
from Car Rental Fund.
GC1201
TSGC Miscellaneous Improvements
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$75,000 from TSGC Reserve Fund.
PR0720
Miscellaneous Park Improvements
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$80,000 from EDC Operating Fund.
PRO804
Park Irrigation
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$25,000 from EDC Operating Fund.
PR1401
Glade Parks Trail Connection Construction
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan
$10,000 from Car Rental Fund.
PS1102
Glade Parks Improvements
10/01/2015
To increase budget per FY2016 Approved CIP Plan - $3,268,910
(Future Bond Issue).
PS1202
ADA/TAS Infrastructure Improvements
05/31/2016
To close project and transfer excess funding of $2,804 to Street CIP
Fund Balance.
PS1203
Miscellaneous Street Repairs
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$106,000 from Street CIP Fund Balance.
PS1501
FY2015 40th CDBG-ADA Infrastructure
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
Improvements
$24,000 from Car Rental Fund.
PS1502
FY2015 Street Overlay
05/31/2016
To close project and transfer excess funding of $82,818 to Street
CIP Fund Balance.
PS1601
East Harwood Road Extension
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $100,000 from
Car Rental Fund.
PS1602
FY2016 Street Overlay
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $600,000 from
General Fund.
PS1603
FY2016 41st CDBG-ADA/TAS Infrastructure
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $59,301 from
Improvements
Community Development Block Grant.
WT0001
Miscellaneous Water Rehabilitation
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan
$110,000 from W/WW CIP Operating Fund.
WT0101
Water Tank Debt Payment -Impact
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan
1$245,482 from Water Impact Fee Fund Balance.
CTTY OF EmEss
CAPITAL IMPROVEMENT PROGRAM
AMENDMENTS -- FaNDED PROJECTS
PROJECT#
PROJECT DESCRIPTION
DATE
AxENDMENTS & ACTIONS
WT0803
Meters/Transponders
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$158,000 from W/WW Operating Fund.
WT0901
Trinity River Authority Water Payment -Impact
05/31/2016
To close project.
WT1201
Reclaimed Water Line Extension Phase 1
05/31/2016
To close project.
WT1403
Reclaimed Water Line Extension Debt Payment-
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
Impact
$119,694 from Water Impact Fee Fund Balance.
WT1501
24-Inch Valve Replacement Cinnamon, Anice, Fuller
05/31/2016
To close project and transfer excess funding of $48,630 to W/WW
Wiser
CIP Fund Balance.
WT1601
Line Rep - Donley Drive/Shelmar Drive
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $212,000 from
W/WW Operating Fund.
WT1601
Line Rep - Donley Drive/Shelmar Drive
05/31/2016
To close project and transfer excess funding of $59,010 to W/WW
CIP Fund Balance.
WT1602
Line Rep - Ector Drive FY2016 41st CDBG
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $310,925 from
Community Development Block Grant.
WT1603
Miscellaneous Valve Replacement
10/01/2015
To provide funding per FY2016 Approved CIP Plan - $120,000 from
W/WW Operating Fund.
WT1604
Reclaimed Water Line Extension Phase III
10/01/2015
To establish budget per FY2016 Approved CIP Plan - $1,280,000
(Future Bond Issue).
WW0002
Miscellaneous Water Rehabilitation
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$100,000 from W/WW CIP Fund Balance.
WW0605
TRA Wastewater Payments -Impact
10/01/2015
To provide additional funding per FY2016 Approved CIP Plan -
$100,000 from WW Impact Fee Fund Balance.
WW1501
Line Rep - Crane Drive
05/31/2016
To provide additional funding of $17,154 from W/WW CIP Fund
Balance.
WW1501
Line Rep - Crane Drive
05/31/2016
To close project.
WW1502 Line Rep - Town Creek Drive 05/31/2016 To close project and transfer excess funding of $44,769 to W/WW
CIP Fund Balance.
WW1601 Line Rep - Glenn Drive 10/01/2015 To provide funding per FY2016 Approved CIP Plan - $253,000 from
W/WW Operating Fund.
WW1601 Line Rep - Glenn Drive 06/28/2016 To provide additional funding of $40,000 from W/WW CIP Fund
Balance.
4
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/15
Appropriation/
Amendment
Budget as of
5131/16
Expended as
of 5/31/16
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
DRAINAGE PROJECTS
DR9903
Misc. Drainage Improvements
$ 932,833
$ 68,113
$ 1,000,946
$ 439,768
$ 561,178
$ 1,000,946
$
DR1101
Flooding Mitigation
$ 500,000
$ -
$ 500,000
$ 18,334
$ 481,666
$ 500,000
$
DR1201
Misc. Creek Maintenance (min bal $100,000)
$ 135,000
$ 60,000
$ 195,000
$ 116,316
$ 78,684
$ 270,000
$ 75,000
FB9902
Fund Balance - Drainage CIP
$ -
$ -
$ -
$ -
$ -
$ -
$ 8,406)
Sub -Total Drainage Projects
$ 1,567,833
$ 128,113
$ 1.695,946
$ 574.418
$ 1,121,528
$ 1,770.946
$ 66,594
0n
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 23,1999
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS DRAINAGE IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: DR9903 Priority: A
COUNCIL AUTHORIZATION:
May 27, 2014: Awarded Bid No. 007-14 for a construction contract to Knight Erosion Control, Inc. for Drainage
Channel Improvements along Hurricane Creek and authorized the City Manager to enter into a contract with
Knight Erosion Control, Inc. The estimated expenditure is $135,487.82.
June 23, 2015: Ratified City Manager action to proceed with emergency repairs to City property located along
Hurricane Creek. The estimated expenditure is $74,602.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project provides funding for various drainage projects or emergency repairs identified throughout the year.
Often correction of these problems requires design services and other improvements such as bank stabilization.
As major projects are identified, they will be tracked separately and assigned a different project number.
PROJECT SCHEDULE:
JUSTIFICATION:
Failure to correct these problems often causes damage to existing infrastructure.
1-111
PROJECT TITLE: MISCELLANEOUS DRAINAGE IMPROVEMENTS PROJECT CODE: DR990
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
mprovements $1,000
$0
$0
$0
Total Estimated Capital Cost $1,000,946
Funding Source:
Transfer from:
Drainage Operating Fund $749,609
Drainage CIP Fund Balance $183,224
$0
FEMA Reimbursement $68,113
$0
Total Estimated Annual Cost
$()I
Total Funding
$1,000,946
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (- +)
% EXPENDED
Fence
$559 $559
0
100%
Storm Drain
$1,000,192 $439,014
561,178
44%
Meters & Setting
$195 $195
0
100%
TOTAL PROJECT
$1,000,946 $439, 768 $561,178 44% I
7
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 30,2010
Submitted By: RON YOUNG Date Completed:
Project Title: FLOODING MITIGATION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Proiect Code: DR1101 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project consists of identifying chronic flooding locations within the City of Euless and determining the
cost/benefit of property acquisition and protection compared to extensive drainage relief projects. Property
acquisition will be recommended after consideration of flooding history, appraisals, and feasible alternative
drainage solutions have been evaluated. It is recommended that this be established as an ongoing project.
PROJECT SCHEDULE:
JUSTIFICATION:
Properties throughout the City of Euless situated adjacent to creeks have experienced drainage problems for
several years. The cost for implementing drainage improvement projects to mitigate flooding at isolated locations
may be much greater than the cost of property acquisition. Chronic flooding lowers the property values and this
program will offer a means of relief for affected property owners.
PROJECT TITLE: FLOODING MITIGATION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
PROJECT CODE: DR1101
TOTAL ESTIMATED CAPITAL COST:
Flooding Mitigation $500,000
$0
$0
$01 Total Estimated Caoital Cost $500
$0
Funding Source:
Transfer from:
Drainage CIP Fund Balance $350
Drainage Operating Fund $150
Total Estimated Annual Cost $01 Total Funding $500,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Storm Sewer $500,000 $18,334 $481,666 4%
'AL PROJECT
$500,000 $18,334 $481,666
4%
9
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 22,2011
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS CREEK MAINTENANCE
Project Type: DRAINAGE Sub -Type: CREEK MAINTENANCE
Project Code: DR1201 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The City of Euless completed drainage master plan studies for the major creeks that traverse the City. They
include Little Bear Creek, Hurricane Creek, Boyd Branch and Blessing Branch.
PROJECT DESCRIPTION:
The project provides for maintenance in the creeks described above including removal of fallen trees that impede
the flow of creek water in the natural creek channels, clearing brush and debris at major bridge crossings, and
preventative maintenance. This project does not address items that are deemed cosmetic enhancements.
PROJECT SCHEDULE:
JUSTIFICATION:
Natural creek erosion undermines the root systems of trees adjacent to creek banks which results in trees falling
into or across creek channels. These fallen trees together with accumulated brush and debris can impede the
flow of storm water in the natural creek channels resulting in a rise in the normal water surface elevation. Fallen
trees that are conveyed down stream in the natural creek channels may cause damage to the substructure of
bridges spanning the creek channels.
t
10
PROJECT TITLE: MISCELLANEOUS CREEK MAINTENANCE
PROJECT CODE: DR1201
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Improvements
Personnel: Full Time (Minimum balance $100,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
Drainage CIP Fund Balance $105,000
Drainage Operating Fund $90,000
$0
Subtotal: $0 Additional Funding Needed:
Transfer from:
Drainage Operating Fund $75,000
Total Estimated Annual Cost $01 Total Funding $270,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Storm Sewers $270,000 $116,316 $153,684 43%
$270,000 $116,316 $153,684 43% 1
11
W
ONN
Y
A
'-IN
12
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5131115
Appropriation/
Amendment
Budget as of
6/31/16
Expended as
of 6/31/16
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
STREET PROJECTS
PS1102
Glade Parks Improvements
$ 12,100,604
$ 3,268,910
$ 15,369,514
$ 12,100,604
$ 3,268,910
$ 15,369,514
$
PS1203
Misc. Street Repairs (min bal $160,000)
$ 405,000
$ 106,000
$ 511,000
$ 508,585
$ 2,415
$ 661,000
$ 150,000
PS1501
FY2015 40t' CDBG-ADA/TAS Infrastructure Improvements
$ 495,600
$ 24,000
$ 519,600
$ 102,125
$ 417,475
$ 519,600
$ -
PS1601
East Harwood Road Extension
$ -
$ 100,000
$ 100,000
$ -
$ 100,000
$ 100,000
$
PS1602
FY2016 Street Overlay
$
$ 600,000
$ 600,000
$ 225,541
$ 374,459
$ 600,000
$
PS1603
I FY2016 41st CDBG-ADA/TAS Infrastructure Improvements
$
$ 59,301
$ 59,301
$ -
$ 59,301
$ 79,301
$ 20,000
FB9907
I Fund Balance - Street CIP
$
$ -
$ -
$ -
$ -
$ -
$ 90,493
Total Street Projects
$ 13,001,204
$ 4,158,211
$ 17,159,415
$ 12,936,855
$ 4,222,560
$ 17,329,415
$ 79,507
1 Portion of debt not yet issued.
W
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27, 2014
Submitted By: HAL CRANOR Date Completed:
Project Title: GLADE PARKS IMPROVEMENTS
Project Type: STREET Sub -Type: CONSTRUCTION
Project CODE: PS1102 Priority: A
COUNCIL AUTHORIZATION:
December 14, 2010: Approval of Resolution #10-1352 authorizing the publication of intention to issue COs.
January 25, 2011: Consider all matters incident and related to the issuance of and sale of up to $3.1 M in COs.
January 25, 2011: Consider acceptance of ROW and easements necessary for public improvements.
January 25, 2011: Awarded Bid #001-11 for a construction contract to McMahon Contracting LP in the amount of
$1,973,615.95 for the construction of Rio Grande Boulevard, Heritage Avenue, and widening of the SH121 service road.
February 24, 2011: Issued COs for funding of first segment of public improvements at Glade Parks.
February 14, 2012: Authorized the City Manager to enter into a contract with Jackson Construction, LTD in the amount
of $1,696,277.25 for the construction of Glade Parks Phase II streets (Brazos Drive, Red River Drive, and Heritage Avenue).
October 23, 2012: Authorized the City Manager to enter into a contract with All Around Lawn Care, Inc. in the amount
of $213,925.65 for the construction of the Glade Parks Phase II Streetscape project.
August 13, 2013: Authorized the City Manager to execute an Engineering Design Contract with Mycoskie, McInnis &
Associates for the design of portions of the Glade Parks Infrastructure. The estimated expenditure is $114,800, plus
reimbursable expenses and additional services.
August 24, 2014: Approved Ordinance No. 2015, considering all matters incident and related to the issuance and sale
of "City of Euless, Texas, Tax and Waterworks and Sewer System (Limited Pledge) Revenue Certificates of Obligation,
Series 2014," and authorizing the issuance of such certificates.
August 11, 2015: Approved Ordinance No. 2079 approving the Amended Project and Financing Plan for Tax Increment
Reinvestment Zone Number Three. The amended Project and Financing Plan increased total project costs by $3,268,910.
September 8, 2015: Authorized the Mayor to negotiate and execute a public parking deck and park easement agreement
with Glade Lifestyle, LLC.
October 27, 2015: Approved Ordinance No. 2092, considering all matters incident and related to the issuance and sale
of "City of Euless, Texas, Tax and Waterworks and Sewer System (Limited Pledge) Revenue Certificates of Obligation,
Series 2015," and authorizing the issuance of such certificates.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The infrastructure located in the Glade Parks development is included in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project represents the funding required for the infrastructure improvements at the Glade Parks Development per the
Project and Financing Plan. The project scope includes the construction of Rio Grande Blvd., portions of Heritage Ave., the
Little Bear Creek bridge, SH121 improvements, landscaping, wetland mitigation, Brazos Blvd. and remaining streets, main
entrance and medians, underground drainage and associated utility installations, parking garage, park and amenities, as well
as administrative and financing costs.
PROJECT SCHEDULE:
Design: Winter 2010 Phase If Complete: August 2012
ROW: Winter 2010 Phase III Complete: April 2015
Begin Construction: Spring 2011 Phase IV Construction: FY2016-FY2017
Phase I Complete: FY2012
JUSTIFICATION:
The construction of public infrastructure at Glade Parks will spur economic development in the area and complete an access
route to existing Euless businesses.
W
14
2ROJECT TITLE: GLADE PARKS IMPROVEMENTS PRAJFcr cnnF- Pc11nq
EFFECTS ON OPERATING AND
ITENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Rio Grande Blvd.
Little Bear Creek Bridge
Heritage Ave.
$0 Highway 121 Improvements
$0 Landscaping
Wetland Mitigation
Brazos and Remaining Streets
Main Entrance and Median
Parking Garage
Park and Park Amenities
Administrative Costs
$0 Total Estimated Capital Cost
$0
FUNDING SOURCE:
2011 Certificates of Obligation
Street CIP Fund Balance
2014 Certs. of Ob. Proceeds
2015 Certs. of Ob. Proceeds
$0
$3,911,023
$1,016,065
$231, 767
$1,297,164
$517,029
$296,000
$3,494,309
$587,247
$1,901,793
$1,287,387
$829,730
15,369,514
$2,854,870
$180,130
$6,000,000
$3,065,604
Additional Funding Needed:
Future Bond Issue #4
$3,268,910
Total Estimated Annual Cost
$0
Total Funding
$15,369,514
CURRENT
STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (-+)
% EXPENDED
Design
$226,292
$226,292
$0
100%
Construction/Administrative Costs
$11,834,589
$11,834,589
$0
100%
Other Professional Services
$119,453
$39,723
$79,730
33%
Land Betterments
$1,287,387
$0
$1,287,387
0%
Parking Garage
$1,901,793
$0
$1,901,793
0%
AL PROJECT
5,369,514 $12,1
910
15
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MISCELLANEOUS STREET REPAIRS
Project Type: STREET Sub -Type: IMPROVEMENTS
Pro'ect Code: PS1203 Priority: A
COUNCIL AUTHORIZATION:
April 24, 2012: Authorized the City Manager to enter into a contract with Estrada Concrete Co. LLC for concrete
road repairs at various locations on North Main Street, Fuller -Wiser Road and Bear Creek Parkway in the amount
of $93,390.
March 11, 2014: Authorized the City Manager to negotiate and execute a contract for a citywide pavement
management analysis and asset management inventory with Infrastructure Management Services (IMS). The
estimated expenditure is $82,155.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Master Thoroughfare Plan identifies the various street types within the City of Euless. These street types
include residential streets through regional arterial streets.
PROJECT DESCRIPTION:
This project includes the removal and replacement of deteriorated sections of pavement along identified
roadways.
PROJECT SCHEDULE:
JUSTIFICATION:
Continuing repair of the existing street pavement will maintain safe driving conditions and will extend the overall
life of the City streets.
''\
16
PROJECT TITLE: MISCELLANEOUS STREET REPAIRS
PROJECT CODE: PS1203
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Construction
Personnel: Full Time (Minimum balance $150,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
Street CIP Fund Balance
$436,000
Car Rental Fund
$75,000
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
eC3efSera Fund <..t?
rZ� 50,000
Total Estimated Annual Cost
$0
Total Funding
$661,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Other Professional Services
$83,156 $82,331 $825
99%
Construction
$577,844 $426,254 $151,590
74%
ECT $661,000 $508,585 $152,415 77%
17
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: 40TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET/FACILITIES Sub -Type: CDBG
Proiect Code: PS1501 Priority: A
COUNCIL AUTHORIZATION:
February 25, 2014: Conducted a Public Hearing for the proposed 40th Year CDBG projects and approved the
recommendation regarding the selected CDBG projects.
April 28, 2015: Approved Resolution No. 15-1460 recommending award of a construction contract for the 40th
Year Community Development Block Grant (CDBG) Project No. B-14-UC-48-0001-22-30-B to Reliable Paving,
Inc. for the replacement of sidewalk accessibility ramps in the amount of $116,010.
March 22, 2016: Approved Resolution No. 16-1490, recommending award of a construction contract for the 40th
Year Community Development Block Grant (CDBG) Project to RJM Contractors in the amount of $220,765.25.
CDBG construction funds will pay $207,282.47 and the City of Euless will pay the remaining $13,482.78.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides for continued improvements to accessibility by removing architectural barriers to
accessibility as required by the Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards (ADA/TAS). This project includes identification of architectural barriers to accessibility that meet
CDBG eligibility guidelines and the subsequent replacement thereof.
PROJECT DESCRIPTION:
The 40th Year CDBG project consists of two separate scopes of work. The first is the replacement of twenty (20)
sidewalk ramp locations identified by the Engineering Department. These areas are primarily located along W.
Pipeline Road, Kynette Drive, and Signet Drive. Sidewalk accessibility ramp installations are eligible for CDBG
funding regardless of their location within the community. Secondly, staff has also identified an accessibility
project which affects citizen access to municipal buildings within the City Municipal Complex. This portion of the
project also focuses on the reconstruction of pathways for ADA compliance.
PROJECT SCHEDULE:
Ramps
Began Construction: August 2015
Construction Complete: September 2015
Municipal Complex
Began Construction: May 2016
Anticipate Construction Complete: August 2016
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
18
1-11
PROJECT TITLE:40TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS PROJECT CODE: PS1501
INET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $67,
Personnel: Full Time Construction $451,
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost $519,600
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $134,572
CDBG Award $385,028
$0
Subtotal: $0
Total Estimated Annual Cost $01 Total Funding $519,600
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Construction $519,600 $102,125 $417,475 20%
$519,600 $102,125 $417,475 20% I
19
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 20,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: EAST HARWOOD ROAD EXTENSION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: PS1601 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The Texas Department of Transportation and DFW Airport are combining efforts to extend East Harwood Road
through the airport to Rental Car Drive to provide additional access to airport properties. Euless has committed to
share in the cost of the extension in an amount not to exceed $100,000.
PROJECT SCHEDULE:
Anticipate Begin Construction: FY2017
JUSTIFICATION:
Participation in the project will provide Euless residents with an additional route to and through the airport
properties.
.-,*N
20
`....
PROJECT TITLE: EAST HARWOOD ROAD EXTENSION
PROJECT CODE: PS160
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Construction $100
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $100,000
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $100,000
Subtotal: $0
Total Estimated Annual Cost $01 Total Funding $100,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Construction $100,000 $0 $100,000 0%
TOTAL PROJECT $100,000 $0 $100,000 0% I
21
roo
T H E C I T Y O F
'-*N
22
EAST HARWOOD ROAD EXTENSION
IN
... ........ — - -----
0 625 1,250 2,500
Feet LENGTH: 6714 FT
23
Legend
— Proposed Project
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2016 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Pro'ect Code: PS1602 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Began Construction: October 2015
Anticipate Construction Complete: October 2016
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadways, and will enhance the appearance of the streets.
24
L
PROJECT TITLE: FY2016 STREET OVERLAY
PROJECT CODE: PS160,
INET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
$600, 000 1
Subtotal: $0 Total Estimated Capital Cost $600,000
Maintenance Costs Funding Source:
Transfer from:
General Fund $600,000
$0
Subtotal: $0
Total Estimated Annual Cost $01 Total Funding $600,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Construction $600,000 $225,541 $374,459 38%
$600,000 $225,541 $374,459 38% I
25
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 17,2011
Submitted By: CHRIS BARKER Date Completed:
Project Title: 41ST CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Pro'ect Code: PS1603 Priority: A
COUNCIL AUTHORIZATION:
February 24, 2015: Conducted a Public Hearing for the proposed 41 st year CDBG projects and approved the
recommendation which includes the installation of sidewalk accessibility ramps along W. Harwood Road.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(41st year CDBG project)
PROJECT SCHEDULE:
Begin Construction: July 2016
Anticipate Construction Complete: July 2016
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
--1
W
26
PROJECT TITLE: 41 ST CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS PROJECT CODE: PS160,'
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Construction
$0
$0
$0
$0 Total Estimated Capital C
Funding Source:
CDBG Award
$0
$79,301 1
$79,301 1
$59,301 1
Subtotal: $0 Additional Funding Needed. -
Transfer from:
Street CIP Fund Balance . $20,000
Total Estimated Annual Cost $0 Total Funding $79,301
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Construction $79,301 $0 $79,301 0%
TOTAL PROJECT
$79,301 $0 $79,301
0%
27
AO-1*,
28
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/15
Appropriation/
Amendment
Budget as of
5/31/16
Expended as
of 5/31/16
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
WASTEWATER PROJECTS
WW0002
Misc. Wastewater Rehab (min bal $100,000)
$ 506.086
$ 100,000
$ 606.086
$ 541,760
$ 64,326
$ 706,086
$ 100,000
WW0605
TRA Wastewater Payments - Impact
$ 680,000
$ 100,000
$ 780,000
$ 680,000
$ 100,000
$ 880,000
$ 100,000
WW1601
Line Re -Glenn Drive
$ -
$ 293,000
$ 293,000
$ 29,827
$ 263,173
$ 293,000
$ -
FB9911
FB - Wastewater Impact (Restricted)
$ -
$ -
$ -
$ -
$ -
$ -
$ (466,056
Total Wastewater Projects
$ 1,186,086
$ 493,000
$ 1,679,086
$ 1,251,587
$ 427,499
$ 1,879,086
N
t0
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: MISCELLANEOUS WASTEWATER REHABILITATION
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: WW0002 Priority: A
COUNCIL AUTHORIZATION:
March 8, 2005: Awarded contract to Hall -Albert Construction Company for the replacement of various
wastewater lines in the amount of $977,857.50. (This award was only partially for the WW0002 project.)
March 28, 2006: Authorized the city manager to proceed with emergency repair by GRA-TEX Utilities to the
aerial wastewater main crossing Hurricane Creek at a cost of $55,000.
November 10, 2015: Awarded Bid No. 008-15 for a construction contract to William J. Schultz, Inc. dba Circle C
Construction for the replacement of sanitary sewer mains in portions of the Westwood Village Addition and the
Green Hills Park Addition and authorized the City Manager to enter into a contract including add alternate #1 if
required. The estimated expenditure is $577,357 and will be paid from WW1501, WW1502 and WW0002.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project is for funding of small wastewater main projects identified throughout the fiscal year. Larger projects
will be determined on an "as needed" basis and presented for funding under a new project number.
PROJECT SCHEDULE:
JUSTIFICATION:
Most of these lines are clay tile and are seriously deteriorated.
..ON
30
11.
PROJECT TITLE: MISCELLANEOUS WASTEWATER REHABILITATION PROJECT CODE: WW0002
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Wastewater Mains
(Minimum balance $100,000)
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
W/WW Operating Fund
$165,000
WW9903
$37,013
$0
W/WW CIP Fund Balance
$404,073
Subtotal:
$0
Additional Funding Needed:
Transfer from:
W/WW CIP Fund Balance
$100,000
Total Estimated Annual Cost
$0
Total Funding
$766,086
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Engineering
$17,939 $12,621 5,318
70%
Contingency
$30,580 $30,580 0
100%
Wastewater Mains
$657,567 $498,559 159,008
76%
$706,086 $541,760 $164,326 77% I
31
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 03,2006
Submitted By: RON YOUNG Date Completed:
Project Title: TRINITY RIVER AUTHORITY WASTEWATER PAYMENT
Project Type: WASTEWATER Sub -Type: IMPACT FEE
Project Code: WW0605 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Based on a review by Birkhoff, Hendricks, and Conway of the water and wastewater impact fees, it was
determined that a substantial portion of the wastewater impact fee is attributed to Trinity River Authority ("TRA")
capital projects. Therefore, these fees should be used to pay a portion of the annual TRA expense, as these
funds are directly attributed to the expansion of TRA. Based on the available fund balance, a systematic
drawdown over a ten year period has been developed.
PROJECT SCHEDULE:
JUSTIFICATION:
The expansion at TRA provides additional capacity and it was determined through the wastewater impact fee
study that these funds could be used to pay a portion of TRA wastewater payments. It was determined a ten
year drawdown would approximate the Capital Improvement Plan Review time frame, as well as provide for a
systematic drawdown that would not impact the annual budget.
-"N
W
32
1-11
PROJECT TITLE: TRINITY RIVER AUTHORITY WASTEWATER PAYMENT PROJECT CODE: WW0605
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
$0
($100,
TOTAL ESTIMATED CAPITAL COST:
TRA Wastewater Payments $880,000
($100,000) Total Estimated Capital Cost $880,000
Funding Source:
Transfer from:
WW Impact Fee Fund Balance $780,000
$0
Subtotal: $0 Additional Funding Needed:
Transfer from:
WW Impact Fee Fund Balance $100,000
Total Estimated Annual Cost ($100,000) Total Funding $880,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Wastewater - TRA Service $880,000 $680,000 $200,000 77%
$880,000 $680,000 $200,000 77% I
33
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-GLENN DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Proiect Code: WW1601 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The project
is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains located west of Glenn Drive from Aransas Drive
to Glenn Drive.
PROJECT SCHEDULE:
Anticipate Begin Construction: August 2016
Anticipate Construction Complete: October 2016
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
-,*N
34
PROJECT TITLE: LINE REPLACEMENT-GLENN DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
PROJECT CODE: WW1601
TOTAL ESTIMATED CAPITAL COST:
$33,000
$260,000
Total Estimated Capital Cost $293,000
Funding Source:
Transfer from:
VV/WW Operating Fund $253,000
NI W1l CIP Fund Balance $40,000
Total Estimated Annual Cost
$01
Total Funding
$293,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Engineering
$33,000 $29,277
$3,723
89%
Construction
$260,000 $550
$259,450
0%
$293,000 $29,827 $263,173 10%
35
T H E C I T Y O
36
WW LINE REPLACEMENT
GLENN DRIVE
GLENN DR
MIDLAND ST
0
tQn
0
-1
0
-1
0
<
O
DOUGLAS ST
W HARWOOD RD
O
z
.0
O.
m
z
0
m
m
0
x
0 125 250 500
-- OW019 Feet LENGTH: 1984 FT
Legend
� Proposed Project
37
T H E C I T Y O F
E-u-
ss
wo
38
W
t0
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
6131115
Appropriation/
Amendment
Budget as of
5131/16
Expended as
of 5/31/16
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
WATER PROJECTS
WT0001
Misc. Water Rehab (min bal $150,000)
$
593,511
$
110,000
$
703,511
$
636,145
$
67,366
$ 853,511
$ 150,000
WT0101
Water Tank Debt Payment -impact
$
3.978,720
$
245.482
$
4,224,202
$
4,142,376
$
81,826
$ 4,474,226
$ 250,024
WT0104
Well Repairs (min bal $200,000)
$
1,613,992
$
-
$
1,613,992
$
1,298,606
$
315,386
$ 1,613,992
$ -
WT0803
Meters/Transponders annual transfer$168,000
$
1,511,750
$
158,000
$
1,669,750
$
1203,652
$
466,099
$ 1,827,750
$ 158,000
WT1212
Reclaimed Water Line Extension Phase 11
$
3,129,300
$
-
$
3,129,300
$
964,302
$
2,164,998
$ 3,129,300
$
WT1402
Fixed Base Meter Reading and Water Meter Chan eout
$
5,493,050
$
-
$
5,493,050
$
852,893
$
4,640,157
$ 5,493,050
$ -
WT1403
I Reclaimed Water Line Extension Debt Payment -Impact
$
241,263
$
119.694
$
360,957
$
321,055
$
39,902
$ 479,451
$ 118,494
WT1602
Line Re - Ector Drive FY2016 41 st CDBG
$
-
$
310,925
$
310,925
$
$
310,925
$ 310,925
$ -
WT1603
Misc. Valve Replacement min bal $150,000
$
$
120,000
$
120,000
$
4,509
$
115,491
$ 160,000
$ 40,000
WT1604
Reclaimed Water Line Extension Phase III
$
$
1,280,000
$
1,280,000
$
$
1,280,000
$ 1,280,000
$
FB9910
FB - Water Impact Restricted
$
$
$
-
$
$
-
$
$ 1,376,048
FB9901
FB - Water & Wastewater CIP
$
$
$
$
$
$
$ 184,981
FB9915
JFB - Water & Wastewater CIP Restricted
$
-
$
$
$
$
$
$ 534,344
Total Water Projects
$16.561,586
$2.344,101
$18,905,687
$9,423,538
$9,482,149
$19,622,205
$ (1,378,855)
ueot not yet issuea.
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MISCELLANEOUS WATER REHABILITATION
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: WT0001 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides funding for small water main projects identified throughout the fiscal year. Large projects
that are identified will be presented for funding under a new project number.
PROJECT SCHEDULE:
JUSTIFICATION:
Some of the City's older water mains have deteriorated and need replacement or repair.
W
40
PROJECT TITLE: MISCELLANEOUS WATER REHABILITATION
PROJECT CODE: WT000'
[NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
I MAINTENANCE COST (+ OR -) ANNUAL:
Uirect Uperating Cost Water Mains
Personnel: Full Time (Minimum balance $150,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfers from:
W/WW CIP Fund Balance
$390,000
WNWV Operating Fund
$460,000
$0
Project Transfers
($146,489)
Subtotal:
$0
Additional Funding Needed:
Transfer from:
W/WW Operating Fund
$150,000
Total Estimated Annual Cost
$0
Total Funding
$853,511
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Contingency
$49,231 $33,734 $15,498
69%
Water Mains
$804,280 $602,411 $201,869
75%
$853,511 $636,145 $217,366 75% 1
41
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 01,2001
Submitted By: RON YOUNG Date Completed:
Project Title: WATER TANK DEBT PAYMENT - IMPACT
Project Type: WATER Sub -Type: IMPACT FEE
Proiect Code: WT0101 Priority: A
COUNCIL AUTHORIZATION:
Approved in the annual budget.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water tower was included in the water impact fee study.
PROJECT DESCRIPTION:
This project includes the transfer of funds from the water impact fee to pay debt service (W/S System Revenue
Refunding Bonds, Series 2012) related to the construction of the new water tower (Heritage Park).
PROJECT SCHEDULE:
Last debt payment for the water tower is scheduled for July 15, 2020,
JUSTIFICATION:
The water tower provides additional capacity and was included in the water impact fee study.
1-11N
42
PROJECT TITLE: WATER TANK DEBT PAYMENT - IMPACT
PROJECT CODE: WT0101
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Debt Service FY2001-FY2016
$4,224,202
Personnel: Full Time
Debt Service FY2017
$250,024
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Annual debt payment - water impact fee
$250,000
$0
Subtotal:
$250,000
Total Estimated Capital Cost
$4,474,226
Maintenance Costs
Funding Source:
WT Impact Fee Fund Balance
$4,224,202
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
WT Impact Fee Fund Balance
$250,024
Total Estimated Annual Cost
$250,000
Total Funding
$4,474,226
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (- +)
% EXPENDED
Transfer to Debt Service
$4,474,226 $4,142,376 331,850
93%
PROJECT $4,474,226 $4,142,376 $331,850 93%
43
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: WELL REPAIRS
Project Type: WATER Sub -Type: WELL REPAIR
Project Code: WT0104 Priority: A
COUNCIL AUTHORIZATION:
April 22, 2003: Awarded bid 018-03 for Far North Well pump repair to Layne -Texas for $32,790.
February 14, 2006: Awarded bid 011-06 to Millican Well Service, LLC for rehabilitation and installation of the new
Centrilift submersible motor and pump for the Far North Well in the amount of $250,035.
January 25, 2011: Authorized Millican Well Service, LLC to repair Fuller Well in an amount not to exceed
$117,000, budget increase and additional funding of $117,000 required.
July 20, 2011: Transferred $95,000 from FB9901 to WT0104 for emergency well repairs.
August 9, 2011: Ratified City Manager action to proceed with emergency repairs to the Far North Well site, by
Millican Well Service, LLC in an amount not to exceed $95,000.
June 26, 2012: Ratified City Manager action to proceed with emergency repairs to the well located at 1400 North
Main Street, by Millican Well Service, LLC for an estimated amount of $64,950.
May 14, 2013: Authorized well repairs to the well located at 118 W. Fuller Drive (Fuller Well Site) by Millican Well
Service, LLC for an estimated amount of $120,000.
August 13, 2013: Ratified the City Manager action to proceed with emergency repairs to the City owned and
operated water well located at 1400 North Main Street, by Millican Well Service, LLC. The estimated expenditure
is $75,178.02.
October 27, 2015: Ratified City Manager action to proceed with emergency repairs to the well located at 2591
North Main Street, by Millican Well Service, LLC. The estimated expenditure is $54,128.23.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The funding is being utilized to repair well pumps and for other unexpected well repairs.
PROJECT SCHEDULE:
JUSTIFICATION:
Maintaining the City's wells results in the ability to produce water at a substantial reduction in cost.
44
PROJECT TITLE: WELL REPAIRS
PROJECT CODE: WT0104
INET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Well Rehabilitation
Personnel: Full Time (Minimum balance $200,000)
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal: I Total Estimated Capital
Maintenance Costs Funding Source:
Transfer from:
WT0001 - Misc Water Rehab $145,720
W/WW CIP Fund Balance $893,272
W/WW Operating Fund $575,000
Subtotal:
Total Estimated Annual Cost Total Funding $1,613,992
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Well Rehabilitation $1,613,992 $1,298,606 $315,386 80%
$1,613,992 $1,298,606 $315,386 80%
46
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: METERS AND TRANSPONDERS
Project Type: WATER Sub -Type: METERS/TRANSPONDERS
Project Code: WT0803 Priority: A
COUNCIL AUTHORIZATION:
November 13, 2007: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Supply Company in the amount of
$383,875. Amount for project not to exceed $331,875.
November 11, 2008: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Supply Company in the amount of
$356,875. Amount for project not to exceed $331,875.
February 14, 2012: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Company in the amount of $200,000.
January 14, 2014: Authorized the City Manager to execute an Engineering Services Contract with Alan Plummer
and Associates, Inc. for services in assisting the City with the Texas Water Development Board State Revolving
Fund loan applications and the United States Bureau of Reclamation WaterSMART grant application. The
estimated amount is $78,000 and a portion of this amount is also authorized for project WT1 201 -Reclaimed
Water Line Extension.
February 10, 2015: Awarded the annual contract for the purchase of water meters and transponders, and
authorized the City Manager to enter into an agreement with Atlas Utility Supply Company.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides funding for the systematic replacement of meters and transponders on an as needed basis
as well as the accumulation of funds for future system -wide replacements.
PROJECT SCHEDULE:
On -going
JUSTIFICATION:
This project provides funding for the systematic replacement of meters and transponders on a regular schedule at
or near end of asset life.
'"\
46
1-11
PROJECT TITLE: METERS AND TRANSPONDERS
PROJECT CODE: WT0803
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost (Annual Funding $158,000)
Personnel: Full Time Transponders/Meters
Part Time $0 FY2008 through FY2016 $1,669,750
Total Salary $0 Transponders/Meters FY2017 $158,000
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
$1,827,750
Maintenance Costs
Funding Source:
Transfer from:
W/WW CIP Fund Balance
$347,750
W/WW Operating Fund
$1,422,000
$0
Transfer to: CIP Fund Balance
($100,000)
Subtotal:
$0
Additional Funding Needed:
Transfer from:
W/WW Operating Fund
$158,000
Total Estimated Annual Cost
$0
Total Funding
$1,827,750
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Meters/Transponders
$1,665,593 $1,048,958 $616,635
63%
Debt Issuance
$162,157 $154,693 $7,464
95%
AL PROJECT $1,827,750 $1,203,652 $624,099 66% I
47
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15, 2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE II
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project CODE: WT1212 Priority: A
COUNCIL AUTHORIZATION:
January 14, 2014: Authorized the City Manager to execute an Engineering Services Contract with Alan Plummer and
Associates, Inc. for services in assisting the City with the Texas Water Development Board State Revolving Fund loan
applications.
August 12, 2014: Approved Resolution No. 14-1439, requesting financial assistance (low interest loan) by authorizing
an application to be filed with the Texas Water Development Board.
October 28, 2014: Approved Resolution No. 14-1446, amending a previously authorized request for financial assistance
(low interest loan) by authorizing an amended amount of financial assistance to be sought from the Texas Water
Development Board (TWDB). The amount of financial assistance approved and authorized to be sought from TWDB is not
to exceed $2,755,300. Additionally, $375,300 of the total project financial assistance is eligible for loan forgiveness.
February 10, 2015: Authorized the City Manager to negotiate and execute an Engineering Design Contract with
Alan Plummer and Associates, Inc. for the design of Phase II of the reclaimed water system extension project. The
estimated expenditure is $227,000.
June 23, 2015: Authorized the issuance of City of Euless, Texas, Waterworks and Sewer System Revenue Bonds,
Series 2015B.
June 23, 2015: Authorized the execution of a loan forgiveness agreement with the Texas Water Development Board and
an escrow agreement related thereto associated with the City of Euless, Texas, Waterworks and Sewer System Revenue
Bonds, Series 2015B.
November 24, 2015: Awarded Bid No. 009-15 for a construction contract to William J. Schultz, Inc dba Circle C
Construction for the construction of the Reclaimed Water Line Extension Phase II and authorized the City Manager
to enter into a contract. The estimated expenditure is $1,785,750.
RELATIONSHIP TO OTHER PROJECTS ANDIOR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear Creek
Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will ultimately provide
reclaimed water service to several multi -family properties from Harwood Road to Mid Cities Boulevard as well as the City's
Bear Creek Park. Phase II would extend the project to supply approximately 23MG annually to 6 additional properties.
Additional system expansion would be possible in the future. Scope also includes engineering services for future phases of
the extension project.
PROJECT SCHEDULE:
Began Construction: January 2016
Anticipate Construction Complete: October 2016
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
._N
48
OR
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE II PROJECT CODE- *WT1219
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Ooeratino Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
2015B Rev Bond Avg. Debt Service
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering
Construction Administration
Construction
Debt Issuance
$0
$144,000
[Total Estimated Capital Cost
$144,000
FUNDING SOURCE:
Transfer from WT1201:
W/WW CIP Fund Balance
Revenue Bond Issue
Transfer from:
W/WW CIP Fund Balance
$235,000
$39,000
$2, 755,300
$100,000
$3,129,300 1
$188,665
$2,755,300
$185, 335
Subtotal: $0
Total Estimated Annual Cost $144,000 Total Funding $3,129,300
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (-+)
% EXPENDED
Engineering
$235,000
$273,913
($38,913)
117%
Construction/Administrative Costs
$2,794,300
$611,694
$2,182,607
22%
Debt Issuance
$100,000
$78,695
$21,305
79%
*WT1201 has been split into two projects - see WT1201 and WT1212. Future phases shown in unfunded.
FY2015 Total Project $6,650,000
Phase II (WT1212) ($3,129,300)
Budget Reduction ($281,248)
Phase I (WT1201) $3,239,452
TOTAL PROJECT $3,129,300 $964,302 $2,164,998
49
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 25, 2013
Submitted By: RON YOUNG Date Completed:
Project Title: FIXED BASE METER READING & WATER METER CHANGEOUT
Project Type: WATER Sub -Type: METER
Project CODE: WT1402 Priority: A
COUNCIL AUTHORIZATION:
January 14, 2014: Alan Plummer and Associates, Inc. (APAI) will assist the City through the preparation of information
forms, application forms and follow-up administration of loan(s) for Texas Water Development Board (TWDB) funding and
with the preparation of a U.S. Bureau of Reclamation (USBR) WaterSMART grant application. The Engineering
Services Contract to APAI is authorized for project WT0803-Meters and Transponders and WT1201-Reclaimed Water Line
Extension. The funding requested from TWDB and USBR is for project WT1402.
June 23, 2015: Authorized the issuance of City of Euless, Texas, Waterworks and Sewer System Revenue Bonds,
Series 2015A.
June 23, 2015: Authorized the execution of a loan forgiveness agreement with the Texas Water Development Board and
an escrow agreement related thereto associated with the City of Euless, Texas, Waterworks and Sewer System Revenue
Bonds, Series 2015A.
August 25, 2015: Awarded RFP No. 006-15 to Aqua Metric Sales Company for Advanced Metering Infrastructure,
System Water Meter Replacement and Leak Detection System and authorized the City Manager to negotiate and
execute a contract. The estimated expenditure is $5,493,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Replacement of existing meter reading capital project of 1992.
PROJECT DESCRIPTION:
Replace existing drive by meter reading system to a fixed base reading system. Currently, City water meters are divided into
one of four reading cycles with each cycle being read on a monthly basis. The reading occurs as a City vehicle traverses
each street within the cycle that is being read for that week. By implementing a fixed base system, all City water meters can
be read at the same time with the readings transmitted to the Utility Billing Office utilizing current City infrastructure.
PROJECT SCHEDULE:
Began Construction: March 2016
Anticipate Construction Complete: January 2017
JUSTIFICATION:
Implementing the new system will:
1. allow real time reading of approximately 15,000 meters,
2. allow for more timely billing to coincide with billings from TRA,
3. provide the ability to track water efficiency (billed vs produced and purchased) with greater accuracy,
4. replace the high percentage of meters nearing the point at which there is a loss of accuracy due to age and volume,
5. provide system wide leak monitoring/detection,
6. allow customer access to water use patterns, and
7. replace meters with low/no lead brass meters to meet EPA requirements.
he
50
ROJECT TITLE: FIXED BASE METER READING & WATFR MFTFR r_HANr,Grni IT Dorn IPI T cnnc- %Arrl An)
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST;
MAINTENANCE COST (+ OR -) ANNUAL
Direct Operating Cost
Fixed Base Equipment
$4,750,000
Personnel: Full Time
Meter Installation
$450,000
Part Time
Contingency
$293,050
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
2015A Rev Bond Avg. Debt Service
$279,000
Total Estimated Capital Cost
$5,493,050
Subtotal:
$279,000
FUNDING SOURCE:
Maintenance Costs
Revenue Bond Issue
$5,493,050
Subtotal: $0
Total Estimated Annual Cost $279,OOOITotal Funding $5,493,050
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Fixed Base Equip. & Meter Installation $5,200,000 $852,893 $4,347,107 16%
Contigency $293,050 $0 $293,050 0%
*FY2015 Total Project $5,500,000
Budget Reduction ($6,950)
FY2016 Total Project $5,493,050
TOTAL PROJECT
493,050 $852,893 $4,640,157
51
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2013
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION DEBT PAYMENT
Project Type: WATER Sub -Type: IMPACT FEE
Pro'ect Code: WT1403 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water system extension was included in the impact fee study.
PROJECT DESCRIPTION:
This project includes the transfer of funds from the water impact fee to pay debt service (W/S System Revenue
Bonds, 2013) related to the extension of the reclaimed water system.
PROJECT SCHEDULE:
Last debt payment is scheduled for July 15, 2033.
JUSTIFICATION:
The project provides a non -potable water source for irrigation which will offset future potable water purchases by
the City and will serve to responsibly conserve potable water resources for the City and the region.
._*N
t
'_1*_1
52
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION DEBT PAYMENT PROJECT CODE: WT1403
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Debt Service FY2014-FY2016 $360,957
Personnel: Full Time Debt Service FY2017 $118,494
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Annual debt payment - water impact fee $120,000
Subtotal: $120,000 Total Estimated Capital Cost $479,451
Maintenance Costs Funding Source:
Transfer from:
WT Impact Fee Fund Balance $360,957
Subtotal: $0 Additional Funding Needed:
Transfer from:
WT Impact Fee Fund Balance $118,494
Total Estimated Annual Cost $120,000 Total Funding $479,451
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Transfer to Debt Service $479,451 $321,055 $158,396 67%
TOTAL PROJECT $479,451 $321,055 $158,396 67% I
53
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 26,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2016 41 ST CDBG LINE REPLACEMENT-ECTOR DRIVE
Project Type: WATER Sub -Type: CDBG
Pro'ect Code: WT1602 Priority: A
COUNCIL AUTHORIZATION:
February 24, 2015: Conducted a Public Hearing for the proposed 41 st year CDBG projects and approved the
recommendation which includes the replacement of a six (6") inch water main with an eight (8") inch waterline on
N. Ector Road from Midway Drive to Trojan Trail.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,840 feet of 6" cast iron water main with an 8" PVC main on Ector
Drive from Trojan Trail to Midway Drive.
(41 st year CDBG project)
PROJECT SCHEDULE:
Begin Construction: July 2016
Anticipate Construction Complete: August 2016
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
.-111N
64
0M
11.1
PROJECT TITLE: FY2016 41ST CDBG LINE REPLACEMENT-ECTOR DRIVE PROJECT CODE: WT1602
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Construction $310,925
$0 Total Estimated i
Funding Source:
CDBG Award
$0
ital Cost
$310,925
$310,925
Total Estimated Annual Cost $01 Total Funding $310,925
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Construction $310,925 $0 $310,925 0%
PROJECT
$310,925 $0 $310,925
0%
55
,�
T H E C I T Y 0 F
ss
w
56
WT LINE REPLACEMENT -
ECTOR DRIVE
w GRA-W DR � IW
I _ o R
z
CLINIC DR
o
Q A¢
m
_..,__._.
4Y
x
m
- -
A7 ;
b�
h
It
O
O
d
W
T
U)
0 250 500 1,000
Feet LENGTH: 1840 FT
_ ?OF FWY N`
Nj gIRPORT WY NS W P\,
Legend
Proposed Project
67
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: MISCELLANEOUS VALVE REPLACEMENT
Project Type: WATER Sub -Type: VALVE REPLACEMENT
Project Code: WT1603 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project will allow for the systematic replacement of valves on an as needed basis.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water valves prevent water lines from being isolated in the event of a line break. Not being
able to isolate as small a segment as possible during a line break increases the labor required to isolate the line,
as well as the number of residents and fire hydrants that would be affected by a line break. Systematic annual
replacement of old deteriorated water valves will increase efficiency, reduce maintenance costs, and ensure
maximum fire protection and water service availability.
W
58
a
PROJECT TITLE: MISCELLANEOUS VALVE REPLACEMENT
PROJECT CODE: WT1603
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Water Valves
Personnel: Full Time (Minimum balance $150,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
W/WW Operating Fund $120,
Subtotal: $0 Additional Funding Needed:
Transfer from:
W/WW Operating Fund $40,000
Total Estimated Annual Cost $0 Total Funding $160,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Engineering $10,000 $0 $10,000 0%
Contingency $10,000 $0 $10,000 0%
Construction $140,000 $4,509 $135,491 3%
ECT $160,000 $4,509 $155,491 3% I
59
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE III
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: WT1604 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility
study completed in FY2012 recommends breaking the project into six phases with the first phase beginning in
FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of
Bear Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system
will ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase III would extend the project to supply approximately
17MG annually to 5 additional properties. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
*Design: FY2017
*Construction: FY2018
*Subject to availability of funds.
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable
water purchases by the City and will serve to responsibly conserve potable water resources for the City and the
region.
`1
60
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE III PROJECT CODE: WT1604
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering
$0
$0 Total Estimated Ca
Funding Source:
Revenue Bond Issue
$0
$0
I Cost
$230,000
$1,050,000
$1,280,000
$1,280,000
Total Estimated Annual Cost
$01
Total Funding
$1,280,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Engineering
$230,000 $0
$230,000
0%
Construction
$1,050,000 $0
$1,050,000
0%
TOTAL PROJECT
$1,280,000 $0 $1,280,000
0%
61
Y
4 F
�vs
62
4M
4f
( ( C
CAPITAL IMPROVEMENTS PROGRAM
FUNDED PROJECTS SUMMARY
Project
Number
Project Description
Budget as of
5/31/15
Appropriation/
Amendment
Budget as of
5/31/16
Expended as
of 5/31/16
Remaining
Funds
Revised
Project Cost
Estimates
Unfunded/
(Excess
Funding)
OTHER
AC1601
Texas Star Sports Complex Phase V
$
-
$
2,602,877
$
2,602,877
$
190,858
$
2,412,019
$
2,602,877
$
CM0304
Entry Monument
$
135,782
$
-
$
135,782
$
106,227
$
29,555
$
135,782
$
CM0804
Redevelopment
$
1,374,422
$
100,387
$
1,474,809
$
1,270,558
$
204,251
$
1.474,809
$
CM1509
Municipal Plaza Improvements Phase 1
$
100,000
$
58.500
$
158,500
$
-
$
158,500
$
158,500
$
DV9901
EDC Incentive Funds
$
525,854
$
25,000
$
550,854
$
450,853
$
100,001
$
575,854
$ 25,000
ED0101
Planning Consultants
$
204,869
$
-
$
204,869
$
104,869
$
100,000
$
204,869
$
ED1002
EDC Contingency
$
250,000
$
-
$
250,000
$
-
$
250,000
$
250,000
$
ED1601
IMidtown Development
$
-
$
16,417,980
$ 16,417,980
$
3,262,866
$ 13,155,114
$
16,417,980
$
FM1201
ADA/TAS Facility Improvements (min bal $75,000)
$
100,000
$
15,000
$
115,000
$
42,129
$
72,871
$
115,000
$
FM1510
Development/EngineeringDevelopment/Engineering Building Improvements
$
94,350
$
2,494,775
$
2,589,125
$
1,174,115
$
1,415,010
$
2,589,125
$
GC1201
TSGC Misc. Improvements (min bal $150,000)
$
355,000
$
75,000
$
430,000
$
231,923
$
198,077
$
430,000
$
PR0720
Misc. Park Improvements (min bal $100,000)
$
585,500
$
80,000
$
665,500
$
566,830
$
98,670
$
745,500
$ 80,000
PR0804
Park Irrigation
$
200,000
$
25,000
$
225,000
$
138,763
$
86,237
$
250,000
$ 25.000
PR1401
JGlade Parks Trail Connection
$
1,386,545
$
10,000
$
1,396,545
$
133,075
$
1,263,470
$
1,396,545
$ -
FB9906
FB-EDC CIP
$
-
$
-
$
-
$
-
$
-
$
-
$ (490,070)
FB9908
FB-Texas Star Sports Complex CIP
$
$
$
$
$
$
$ 303,935
FB9909
FB-General CIP
$
$
$
$
$
$
$ 191,713)
FB9913
FB-Car Rental CIP
$
$
$
$
$
$
$ 172,958
Total Other Projects
$
5,312,322
$
21,904,519
$27,216,841
$7,673,066
$ 19,543,775
$27,346,841
$ (1,028,676)
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27,2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE V
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Proiect Code: AC1601 Priority: A
COUNCIL AUTHORIZATION:
November 24, 2015: Authorized the City Manager to negotiate and execute an engineering design contract with
David McCaskill Design Group for the design of Phase V of the Parks at Texas Star.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase V includes the design and construction for an additional 60/90 field with
turf infield, natural grass outfield, and site amenities.
With the growing number of participants in youth baseball, particularly in this division, the new field will allow our
staff the opportunity to expand our league and tournament format ultimately resulting in additional revenue for the
park. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the design and construction of an additional 60/90 field with a synthetic turf infield and
natural grass outfield. Additionally, the project will include all amenities to support the new field such as lights,
scoreboard, irrigation, landscaping, and electrical service.
PROJECT SCHEDULE:
Anticipate Begin Construction: July 2016
Anticipate Construction Complete: October 2016
JUSTIFICATION:
With the completion of Phase V, the new field will serve the athletic needs of the fastest growing age group and
most sought after field that we have.
_1\
.-N
64
IN.,
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE V PROJECT CODE: AC1601
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Design
$220,000
Personnel: Full Time
Field Construction
$1,614,121
Part Time
$0
Site Paving
$54,000
Total Salary
$0
Equipment
$165,756
Purchase of Services
Synthetic Turf Field
$287,000
Materials & Supplies
Lighting
$237,000
Utilities
Contingency
$25,000
Subtotal: $0
Maintenance Costs
Total Estimated Capital Cost $2,602,877
Funding Source:
Transfer from:
TSSC Fund Balance $452,767
EDC Debt Reduction $700,000
$0
TSSC Reserves $720,110
Subtotal: $0
EDC Reserves $730,000
Total Estimated Annual Cost
$01
Total Funding
$2,602,877
CURRENT STATUS
OVEWUNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Engineering
$220,000 $190,858
$29,142
87%
Contingencies
$25,000 $0
$25,000
0%
Construction
$1,614,121 $0
$1,614,121
0%
Equipment
$165,756 $0
$165,756
0%
Lighting
$237,000 $0
$237,000
0%
Land Betterments
$341,000 $0
$341,000
0%
AL PROJECT $2,602,877 $190,858 $2,412,019 7% 1
65
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: July 11,2006
Submitted By: JOE HENNIG Date Completed:
Project Title: ENTRY MONUMENT SIGN PROGRAM
Project Type: MISCELLANEOUS Sub -Type: IMPROVEMENTS
Pro'ect Code: CM0304 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Continuation of the original City of Euless Entry Monument Sign Program.
PROJECT DESCRIPTION:
Continued construction of City of Euless entry monument signs at key high visibility points throughout the City
extending Euless beautification and branding efforts.
PROJECT SCHEDULE:
JUSTIFICATION:
To enable continuous efforts to identify, beautify, and brand the City of Euless.
, -"*N
'"1
66
L
PROJECT TITLE: ENTRY MONUMENT SIGN PROGRAM
PROJECT CODE: CM0304
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Land Betterments $135,782
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $135,782
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $135,782
$0
Subtotal: $0
Total Estimated Annual Cost $01 Total Funding $135,782
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Land Betterments $135,782 $106,227 29,555 78%
TOTAL PROJECT $135,782 $106,227 $29,555 78% I
67
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: July 11,2006
Submitted By: GARY MCKAMIE Date Completed:
Project Title: REDEVELOPMENT
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Pro'ect Code: CM0804 Priority: A
COUNCIL AUTHORIZATION:
Oct 23, 2007: Authorized the purchase of property on Lot 27, Block 2, Cresthaven Addn, 1010 Highland Dr.
Nov 27, 2007: Authorized the purchase of property on Lot 24, Block 1, Cresthaven Addn, 1010 Cresthaven Dr.
Dec 11, 2007: Authorized the purchase of property on Lots 17&18, Block 8, Cedar Hill Estates Addn, 710 S
Main.
Oct 28, 2008: Authorized the purchase of property on Lot 3, Block 2, Cresthaven Addn, 1007 Cresthaven Dr.
Jan 13, 2009: Authorized the purchase of property on Lot 18, Block 1, Cresthaven Addn, 912 Cresthaven Dr; Lot
4, Block 2, Cresthaven Addn, 1005 Cresthaven Dr; and Lot 23, Block 2, Cresthaven Addn, 1002 Highland Dr.
Mar 12, 2013: Authorized the purchase of property on N. Sheppard Drive (10 lots).
Nov 26, 2013: Authorized the purchase of property on 908 and 910 Cresthaven.
Feb 24, 2015: Authorized the purchase of property on 903 Cresthaven, 1447 W. Euless Blvd, and 901 and 904
Highland Drive.
Mar 24, 2015: Authorized the purchase of property on 215 E. Ash Lane.
November 10, 2015: Authorized the City Manager to execute an agreement to accept contributions from Gardner
Capital Texas, LLC and Bloomfield Homes Fund, LP to a Community Revitalization Fund in the amount of
$100, 000.
April 26, 2016: Authorized the purchase of property on 905 Cresthaven.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding to allow the City to participate in redevelopment projects and other community
improvements or make acquisitions of property that will be of economic benefit to the City of Euless.
PROJECT DESCRIPTION:
Project includes City participation in community redevelopment projects and property acquisitions that will be of
economic benefit to the City.
PROJECT SCHEDULE:
Long-term on -going project for continuous improvement of the community.
JUSTIFICATION:
As the City ages, it is imperative that the economic vitality of the City remain strong. Reinvestment into the
community will protect property values from deterioration and keep commercial properties occupied and
vibrant.
No
68
PROJECT TITLE: REDEVELOPMENT
PROJECT CODE: CM0804
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Land Acquisition $1,273,889
Personnel: Full Time Demolition $90,323
Part Time $0 Minor Apparatus $597
Total Salary $0 Incentives $10,000
Purchase of Services Revitalization Target Area #1 $100,000
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
$1,474,809
Maintenance Costs
Funding Source:
Transfer from:
General Fund
$930,000
Interest Earnings
$34,809
Drill Site Surface Damage
$10,000
Subtotal:
Car Rental Fund
$400,000
Developer Contributions
$100,000
Total Estimated Annual Cost
$0
Total Funding
$1,474,809
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Land Acquisition
$1,237,005 $1,133,206 $103,799
92%
Demolition
$109,194 $109,172 $22
100%
Minor Apparatus
$597 $167 $430
28%
Incentives
$10,000 $10,000 $0
100%
Other Professional Services
$18,013 $18,013 $0
100%
Redevelopment
$100,000 $0 $100,000
0%
TOTAL PROJECT $1,474,809 $1,270,558 $204,251 86% I
69
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: .tune 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MUNICIPAL PLAZA IMPROVEMENTS PHASE I
Project Type: FACILITIES Sub -Type: IMPROVEMENTS
Proiect Code: CM1509 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is the landscaping and irrigation related to the 40th CDBG ADA accessibility and infrastructure
improvements.
PROJECT DESCRIPTION:
Landscaping and irrigation improvements to the Municipal Plaza following the 40th CDBG ADA accessibility and
infrastructure improvements.
PROJECT SCHEDULE:
Began Construction: March 2016
Anticipate Construction Complete: Fall 2016
JUSTIFICATION:
Beautification of the municipal plaza following the hardscape improvements.
-*N
.-IN
70
PROJECT TITLE: MUNICIPAL PLAZA IMPROVEMENTS PHASE I
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
$0
PROJECT CODE: CM1509
TOTAL ESTIMATED CAPITAL COST:
Landscaping $158,500
$0 Total Estimated Capital Cost $158,500
Funding Source:
Transfer from:
Car Rental Fund $100,000
Car Rental CIP Fund Balance $58,500
$0
$0
Total Estimated Annual Cost $01 Total Funding $158,500
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Landscaping $158,500 $0 $158,500 0%
$158,500 $0 $158,500 0%
71
City of Euless
Capital Project Request
Department: ECONOMIC DEVELOPMENT Date Prepared: July 26,1999
Submitted By: BILL RIDGWAY Date Completed:
Project Title: EULESS DEVELOPMENT CORPORATION INCENTIVE
Project Type: EDC Sub -Type: DEVELOPMENT
Project Code: DV9901 Priority: A
COUNCIL AUTHORIZATION:
March 27, 2001: Approved transfer of $325,000 to North Main Street for right-of-way to free up funds for a sign
program.
May 30, 2006: Approved payment to Professional Turf Products, Inc. in the amount of $300,000 per agreement.
April 24, 2012: Ratified Euless Development Corporation (EDC) action taken on April 23, 2012, to approve the
first amendment to the lease and incentive agreement by and between the EDC, the City of Euless and U.S.
Concrete, Inc. and its subsidiary Redi-Mix, L.L.C., and authorizing the President to make the modification and
execute such amendment. The agreement called for a $150,000 incentive payment upon the successful
relocation of the US Concrete corporate headquarters to Euless.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Euless Development Corporation funds that have been set aside to aid the City of Euless in attracting
development opportunities.
PROJECT SCHEDULE:
JUSTIFICATION:
Funding this project would enable the City to act quickly on development opportunities that arise throughout the
year.
.IN
W
-IN
72
Ow
PROJECT TITLE: EULESS DEVELOPMENT CORPORATION INCENTIVE PROJECT CODE: DV9901
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Will be based on the merits of
Personnel: Full Time each opportunity.
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Maintenance Costs Funding Source:
Transfers from:
EDC CIP Fund Balance $913,454
EDC Operating Fund $425,000
$0 Transfer to FS#2 SS0010 ($432,600)
Subtotal: $0 Transfer to N Main PS9901 ($355,000)
Additional Funding Needed:
EDC Operating Fund $25,000
Total Estimated Annual Cost $0 Total Funding $575,854
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Economic Development Incentives $575,000 $450,000 $125,000 78%
Irrigation Supplies $854 $853 $1 100%
ITOTAL PROJECT $575 854 $450,853 $125,001 78%
73
City of Euless
Capital Project Request
Department: ECONOMIC DEVELOPMENT Date Prepared: July 07,2000
Submitted By: BILL RIDGWAY Date Completed:
Project Title: PLANNING CONSULTANTS
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: ED0101 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding for evaluating various development opportunities.
PROJECT DESCRIPTION:
Commission a study to determine the highest and best use of valuable undeveloped commercial land.
PROJECT SCHEDULE:
JUSTIFICATION:
Poor planning can result in lower than desired tax revenue, hodge podge development activity, and less than
optimal development quality. The City needs to be proactive to guide the development of these vital tracts.
74
`.
PROJECT TITLE: PLANNING CONSULTANTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
PROJECT CODE: ED0101
TOTAL ESTIMATED CAPITAL COST:
Planning Study $204,869
$0
$0
$0 Total Estimated Capital Cost $204,869
Funding Source:
Transfer from:
Car Rental Fund $200,000
Car Rental CIP Fund Balance $4,869
Total Estimated Annual Cost $01 Total Funding $204,869
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) %, EXPENDED
Planning Study $204,869 $104,869 100,000 51 %
AL PROJ
$204,869 $104,869 $100,000
75
City of Euless
Capital Project Request
Department: ECONOMIC DEVELOPMENT Date Prepared: Sept 30,2010
Submitted By: GARY MCKAMIE Date Completed:
Project Title: EDC CONTINGENCY
Project Type: EDC Sub -Type: MISCELLANEOUS
Project Code: ED1002 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
To provide funding for emergencies or unforeseen projects that arise throughout the year.
PROJECT SCHEDULE:
JUSTIFICATION:
This would enable the City to act quickly on emergency or unforeseen projects. Without funding, these types of
projects would have to wait until the next budget cycle which could increase costs or impede economic
development opportunities.
W
76
L
0�
PROJECT TITLE: EDC CONTINGENCY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
PROJECT CODE: ED1002
TOTAL ESTIMATED CAPITAL COST:
$250
$0 Total Estimated Capital Cost $250,000
Funding Source:
Transfer from:
EDC CIP Fund Balance $250,000
$0
Total Estimated Annual Cost $01 Total Funding $250,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Contingency $250,000 $0 $250,000 0%
$250,000 $0 $250,000 0%
77
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: June 16,2015
Submitted By: LORETTA GETCHELL Date Completed:
Project Title: MIDTOWN DEVELOPMENT
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: ED1601 Priority: A
COUNCIL AUTHORIZATION:
June 23, 2015: Conducted a Public Hearing and approved Planned Development.
August 25, 2015: Approved Resolution No. 15-1471 creating, authorizing, and establishing the Euless Midtown
Public Improvement District.
December 8, 2015: Approved Resolution No. 15-1479 authorizing publication of notice of intention to issue
certificates of obligation to fund public infrastructure improvements including streets, drainage, and water and
wastewater in the Euless Midtown Zone.
December 8, 2015: Approved Ordinance No. 2096 approving the Project and Financing Plan for Tax Increment
Reinvestment Zone Number Four.
January 12, 2016: Approved Ordinance No. 2098 authorizing the issuance and sale of "City of Euless, Texas,
Tax and Waterworks and Sewer System (Limited Pledge) Revenue Certificates of Obligation, Series 2016."
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project provides funding for City participation in a public/private development opportunity.
PROJECT DESCRIPTION:
Project includes City participation in a public/private community development project of approximately 56 acres
located in the A.J. Huitt Survey, Abstract 684. Project costs will include land, right-of-way, remediation, paving,
storm drainage, water, wastewater, landscaping, hardscaping, amenities, design and administrative costs.
PROJECT SCHEDULE:
Began Demolition: Spring 2016
Anticipate Begin Construction: Summer 2016
JUSTIFICATION:
This is a significant development opportunity within the heart of Euless. The development is projected to include
residential development including villas, townhomes and rowhouses, cluster housing, and urban lofts; commercial
development including retail and restaurant development; and landscaped bioswales and water detention areas
for stormwater management.
78
I"...
PROJECT TITLE: MIDTOWN DEVELOPMENT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
i Utilities
I Subtotal:
Subtotal:
I Total
PROJECT CODE: ED1601
TOTAL ESTIMATED CAPITAL COST:
Public Improvements $16,417
Total Estimated Capital Cost $16,417,980
Funding Source:
Certificates of Obligation $16,417,980
$16,417,
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Public Improvements $16,417,980 $3,262,866 $13,155,114 20%
TOTAL
$16,417,980 $3,262,866 $13,155,114
209%
79
City of Euless
Capital Project Request
Department: FACILITIES
Date Prepared: April 11,2011
Submitted By: KYLE MCADAMS Date Completed:
Project Title: ADA/TAS FACILITY IMPROVEMENTS
Project Type: FACILITIES Sub -Type: IMPROVEMENTS
Prolect Code: FM1201 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for the continued improvements to various City facilities as required by Federal and State
mandated Americans with Disabilities Act/Texas Accessibility Standards ("ADA/TAS"). City facilities, entrances,
lifts, signage, speech and hearing aided devices, and other areas covered under both ADA and TAS
requirements will be part of these improvements. Project funds will be managed by the City Manager's Office and
will be allocated as identified projects are brought forth and approved.
PROJECT SCHEDULE:
JUSTIFICATION:
Some City facilities do not meet current ADA/TAS standards. Updating accessibility on a continuing basis will
help keep the City in compliance with government standards and will address the growing needs of citizens with
accessibility issues.
W
'IN
80
PROJECT TITLE: ADA/TAS FACILITY IMPROVEMENTS
PROJECT CODE: FM1201
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Improvements
Personnel: Full Time (Minimum balance $75,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $01 Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $65,000
General Fund $50,000
$0
Subtotal: $0
Total Estimated Annual Cost $01 Total Funding $115,000
CURRENT STATUS
OVER/UNDER
,PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Structural Maintenance $109,000 $38,623 $70,377 35%
Training $6,000 $3,506 $2,494 58%
PROJECT $115,000 $42,129 $72,871 37%
81
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 01,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: DEVELOPMENT/ENGINEERING BUILDING IMPROVEMENTS
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: FM1510 Priority: A
COUNCIL AUTHORIZATION:
November 25, 2014: Authorized the City Manager to negotiate and execute an Architectural Services contract
pursuant to Request for Qualifications (RFQ) No. 015-14 with Oxley Williams Tharp Architects for the remodel of
the Development and Engineering building.
October 27, 2015: Awarded Bid No. 010-15 for the remodel of the Development/Engineering building to RJM
Contractors in the amount of $2,215,922 and authorized the City Manager to enter into a contract with RJM
Contractors.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Development and Engineering Building is the final project planned as part of the City's 1999 Master
Construction plan.
PROJECT DESCRIPTION:
The project includes the design and construction of a new entrance facade to match the other campus structures.
Security issues pertaining to controlled access will be addressed as well as renovation of the Fuller Room into a
functional conference area. Public rest room facilities will be relocated to meet American with Disabilities Act/
Texas Accessibility Standards, the interior will be upgraded, and new carpet will be installed throughout the
facility.
PROJECT SCHEDULE:
Planning / Design Work: December 2014 - March 2015
Bid Specifications: July 2015
Bid Project: August 2015
Receive Bids: September 2015
Council Approval: October 2015
Start Construction: December 2015
Anticipate Construction Complete: September 2016
JUSTIFICATION:
The Development and Engineering Building needs significant interior renovation to better utilize the space along
with updates to the roof and exterior entry.
82
PROJECT TITLE: DEVELOPMENT/ENGINEERING BUILDING IMPROVEMENTS PROJECT CODE: FM1510
NET EFFECTS ON OPERATING AND I TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Planning/Bid Specifications
$94,350
Personnel: Full Time
Construction
$2,216,750
Part Time
$0
Architect - Special Services
$50,000
Total Salary
$0
Survey & Testing Fees
$10,000
Purchase of Services
Furniture
$188,000
Materials & Supplies
Instruments & Apparatus
$9,150
Utilities
Data & Telephone
$14,875
Alarm & Security Services
$3,000
IT Fixtures
$3,000
$0
Subtotal: $0 Total Estimated Capital Cost $2,589,125
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $2,589,125
Subtotal. -
Total Estimated Annual Cost
$01
Total Funding
$2,589,125
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (- +)
% EXPENDED
Architectural Services
$141,350 $116,121
$25,229
82%
Surveying Services
$13,000 $12,951
$49
100%
Construction
$2,216,750 $1,045,043
$1,171,707
47%
Equipment
$30,025 $0
$30,025
0%
Furniture
$188,000 $0
$188,000
0%
$2,589,125 $1,174,115 $1,415,010 45% 1
83
City of Euless
Capital Project Request
Department: TEXAS STAR GOLF COURSE Date Prepared: May 17,2011
Submitted By: GLENDA HARTSELL Date Completed:
Project Title: TSGC MISCELLANEOUS IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: TSGC IMPROVEMENTS
Project Code: GC1201 Priority: A
COUNCIL AUTHORIZATION:
September 23, 2014: Authorized the purchase of carpet for the Texas Star Golf Course Clubhouse and
Conference Centre from Vector Concepts through the BuyBoard Cooperative Purchasing Program. The
estimated expenditure is $60,878.14.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
To provide funding to address small capital projects that arise throughout the year at Texas Star Golf Course.
PROJECT SCHEDULE:
JUSTIFICATION:
Without funding for this project, the smaller items identified throughout the year could not be addressed in a
timely manner and would have to be postponed until the next budget cycle for funding consideration. Timely
response preserves the City's investment in a high -profile asset and maintains the quality service levels expected
from patrons.
'1
84
PROJECT TITLE: TSGC MISCELLANEOUS IMPROVEMENTS
PROJECT CODE: GC1201
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Improvements
Personnel: Full Time (Minimum balance $150,000)
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Subtotal: $0 Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
TSGC Reserve Fund $390,
Conf Center Imp. - GC1402 $40,
Subtotal:
Total Estimated Annual Cost
$01
Total Funding
$430,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Repair & Maintenance
$51,393 $43,084
$8,309
84%
Land Acquisition
$2,000 $2,000
$0
100%
Land Betterments
$40,105 $30,697
$9,408
77%
Improvements
$224,294 $76,233
$148,061
34%
Equipment
$112,208 $79,909
$32,299
71%
'AL PROJECT $430,000 $231,923 $198,077 54%
85
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: March 23,2004
Submitted By: RAY MCDONALD Date Completed:
Project Title: MISCELLANEOUS PARK IMPROVEMENTS
Project Type: EDC Sub -Type: PARKS
Proiect Code: PR0720 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan recommends funding for system -wide park facilities and amenities upgrades.
PROJECT DESCRIPTION:
The project provides funding for the upgrade and modernization of City parks to include replacement of aged
structures such as pavilions, picnic tables, gazebos, signs, safety components, and other park amenities
including the addition of a gazebo on Main Street. Park infrastructure and structure painting are included in the
scope of the project. Additionally, the project encompasses the installation of trail lighting along the Trails of
Euless similar to the lighting installed along the trail through Midway Park. Trailwood Park, Bob Eden Trail, The
Preserve at McCormick Park, The Villages of Bear Creek Park and Heritage Park would also benefit from trail
lighting.
PROJECT SCHEDULE:
JUSTIFICATION:
Pursuant to the recommendations in the Parks Master Plan, park accessibility should be in compliance with the
Americans with Disabilities Act. The existing equipment in many park areas is becoming aged and will require
refurbishment or replacement in the near term. Additionally, park infrastructure should be maintained at a level
that meets citizen expectations.
--N
'1
No
86
OR
PROJECT TITLE: MISCELLANEOUS PARK IMPROVEMENTS PROJECT CODE: PR0720
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost
Fixtures, landscaping, lighting,
Personnel: Full Time
& other park and infrastructure
Part Time
$0
improvements
Total Salary
$0
Purchase of Services
(Minimum balance $100,000)
Materials & Supplies
Utilities
$0
Subtotal:
$0
Total Estimated Capital Cost
Maintenance Costs
Funding Source:
Transfer from:
EDC Operating Fund
$655,000
Developer Contribution (TRA)
$10,500
$0
Subtotal:
$0
Additional Funding Needed:
Transfer from:
EDC Operating Fund
$80,000
Total Estimated Annual Cost
$0
Total Funding
$745,500
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED BUDGET (-+)
% EXPENDED
Park Furnishings
$554,848 $465,791 89,057
84%
Landscaping
$55,942 $40,167 15,775
72%
Contingency
$81,540 $57,702 23,838
71%
Park Lighting
$50,000 $0 50,000
0%
Equipment
$3,170 $3,170 0
100%
TOTAL PROJECT
$745,500 $566,830 $178,670
76%
87
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: October 01,2007
Submitted By: RAY MCDONALD Date Completed:
Project Title: PARK IRRIGATION
Project Type: EDC Sub -Type: PARKS
Project Code: PR0804 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides annual funding to continue efforts to meet irrigation needs throughout the City's park
system.
PROJECT SCHEDULE:
Projects will be identified and completed on an as needed basis.
JUSTIFICATION:
This project allows for maintenance and expansion of the irrigation systems throughout the parks system to
enhance the overall condition of the landscape and green space.
W
88
"I','
PROJECT TITLE: PARK IRRIGATION
PROJECT CODE: PR0804
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost (Annual Transfer $25,000)
Personnel: Full Time Irrigation $250,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $250,000
Maintenance Costs Funding Source:
Transfer from:
EDC Operating Fund $225,000
Subtotal: $0 Additional Funding Needed:
Transfer from:
EDC Operating Fund $25,000
Total Estimated Annual Cost $0 Total Fundin-ci $250,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Irrigation $250,000 $138,763 111,237 56%
TOTAL PROJECT $250,000 $138,763 $111,237 56%
89
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 05,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: GLADE PARKS TRAIL CONNECTION
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: PR1401 Priority: A
COUNCIL AUTHORIZATION:
March 25, 2014: Authorized the City Manager to execute an Engineering Design Contract with Mycoskie McInnis
Associates, Inc. for the design of the Glade Parks Trail Connection Project with an estimated expenditure of
$119,000.
August 11, 2015: Approved Resolution No. 15-1465 which allows the City of Euless to enter into a Local Project
Advance Funding Agreement for the Trails of Euless — Western Extension project, CSJ # 0902-90-023. The City
was awarded $912,000 to complete the Trails of Euless — Western Extension project.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
As identified in the Glade Parks development, this project proposes to connect the existing Trails of Euless to the
City of Colleyville trails through the Glade Parks Development.
PROJECT DESCRIPTION:
This phase of the project consists of the design, engineering, surveying, geotech and construction for a trail that
will connect to the existing trail at Creekwood Estates, run underneath the northbound service road, SH121, and
the southbound service road to the southeast corner of the Glade Parks Development. Future connectivity
through Glade Parks is planned within the overall development of that site.
PROJECT SCHEDULE:
Anticipate Design Complete: July 2016
Anticipate Construction Complete: January 2017
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development with
an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community as it
assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The development and maintenance of the trails system
continued to receive significant support from the citizens as indicated in the responses to the needs assessment
survey conducted as a part of the Parks Master Plan update.
'.1
90
PROJECT TITLE: GLADE PARKS TRAIL CONNECTION
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
I Subtotal:
Total
PROJECT CODE: PR1401
TOTAL ESTIMATED CAPITAL COST:
Design
Engineering, Surveying and
$0 Geotech
$0 Construction
Contingency
$0
$0
Total Estimated I
Funding Source:
Transfer from:
Car Rental Fund
3rant Award
C•:
$55,000
$72,000
$1,237,045
$32,500
$1, 396,
$484, 545I
$912,000
$1,396
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+) % EXPENDED
Design, Engineering, Surveying & Geotech
$129,135 $121,705
$7,430 94%
Construction
$1,237,045 $11,370
$1,225,675 1%
Contingency
$30,365 $0
$30,365 0%
AL PROJECT
$1,396,545 $133,075 $1,263,470
91
E
of
SS
92
CAPITAL IMPROVEMENT PROGRAMS
FY2017 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Cont rib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
DRAINAGE PROJECTS
None Currently
A
$ -
Sub -Total Drainage Priority A -Proposed FY17
$
None Currently B
$
Sub -Total Drainage Priority 8-Unfunded
$
Bell Hi Addition
C
TBD
XX
Blessing Branch -Main Street to SH360
C
TBD
XX
Hollow Oak Channel Erosion
C
TBD
XX
K nette Drive Culvert Modifications
C
TBD
XX
Little Bear Creek Drainage Improvements
C
TBD
XX
Marlene Drive Culvert Replacement
C
TBD
XX
Simmons Drive Culvert Improvements
C
TBD
XX
Sub -Total Drainage Priority C-Unfunded
$
DRAINAGE PROJECTS - TOTAL
m
v
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: BELL HI ADDITION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005, the City commissioned and received a drainage plan from Freese and Nichols, Inc. In this plan, the
Bell Hi Addition was identified as an area in need of flood relief.
PROJECT DESCRIPTION:
The proposed project ties into an existing storm drainage system on Needles Street. A substantial portion of the
cost of this project is related to street repair which would indicate the need to combine this project with a street
reconstruction project.
PROJECT SCHEDULE:
JUSTIFICATION:
The construction of this project will prevent the flooding of Paula Lane, David Drive, and Needles Street during
the most intense rainfall events. The terrain in this location is very flat, which causes the streets to have a very
low capacity to remove storm water.
98
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 26,1999
Submitted By: RON YOUNG Date Completed:
Project Title: BLESSING BRANCH -MAIN STREET TO SH360
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Blessing Branch Drainage Master Plan included a conceptual plan to convey storm water through the creek
more efficiently.
PROJECT DESCRIPTION:
This project involves the channeling and lining of Blessing Branch in accordance with the Blessing Branch
Master Plan.
PROJECT SCHEDULE:
JUSTIFICATION:
Continued erosion will eventually undermine the creek.
99
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 03,2008
Submitted By: RON YOUNG Date Completed:
Project Title: HOLLOW OAK CHANNEL EROSION
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In May 2008, the City authorized a drainage study for the creek area that runs at the rear of the lots fronting on
Hollow Oak Drive and Linkwood Drive. The completed drainage study was received in July 2008.
PROJECT DESCRIPTION:
The creek area along the rear of the lots on Hollow Oak Drive and Linkwood Drive exists in a natural state. The
creek bank along the south has experienced some slope failure. The drainage study recommends installation of
"bag wall" slope protection.
PROJECT SCHEDULE:
JUSTIFICATION:
The City has received complaints that fences and other improvements will be threatened if additional slope
failures take place. Currently no residences are threatened. This drainage area is located completely on
private property. However, due to the scope of the recommended project, a public/private partnership project
may be necessary requiring participation and support from property owners.
No
100
1-11
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,1999
Submitted By: RON YOUNG Date Completed:
Project Title: KYNETTE DRIVE CULVERT MODIFICATIONS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Wilshire Village Addition was constructed prior to the adoption of the City's Uniform Development Code ("UDC").
The requirements prior to the UDC were lower than what the City now requires. The current construction
configuration of Wilshire Village causes more water to remain above ground than is acceptable under current
standards. The drainage system in the Wilshire Village Addition needs to be upgraded to meet the current
requirements.
PROJECT DESCRIPTION:
The project involves the installation of a small drainage system on Kynette Drive up to Sierra Drive. It is Project
No. 16 in the 1990 Knowlton, English, Flowers Drainage Utility System Study of Selected Improvement Projects.
PROJECT SCHEDULE:
JUSTIFICATION:
Surface water flow within Kynette Drive exceeds the City's current development standards. A large amount of
storm water drains to an existing culvert on Kynette Drive between Eastcliff and Westcliff Drives. The existing
drainage facilities collecting this storm water are inadequate according to current standards.
101
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,1999
Submitted By: RON YOUNG Date Completed:
Project Title: LITTLE BEAR CREEK DRAINAGE IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The improvements proposed for Bob Eden Park are identified in the Little Bear Creek Watershed Master Plan.
The Little Bear Creek Park portion of this project was identified in the 1990 Knowlton, English and Flowers
Drainage Utility System Study of Selected Improvement Projects.
PROJECT DESCRIPTION:
Both parts of this drainage project involve erosion control and channelization improvements to Little Bear Creek.
The Bear Creek Park part is a portion of Project No. 11 in the above -referenced study. This project will be re-
evaluated to determine if the scope and proposed improvements should be modified. This part of the project will
be redefined and re -estimated.
PROJECT SCHEDULE:
JUSTIFICATION:
Continued erosion will eventually undermine the creek in both parks and cause damage to existing City facilities.
be
W
102
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 10,2008
Submitted By: RON YOUNG Date Completed:
Project Title: MARLENE DRIVE CULVERT REPLACEMENT
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Marlene Drive is noted as a collector street on the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The scope of the project includes construction of a new culvert at Cyclone Branch to meet current load and
drainage capacity standards. A portion of the concrete channel will also need to be reconstructed both
upstream and downstream to ensure a smooth transition.
PROJECT SCHEDULE:
JUSTIFICATION:
The existing culvert is load limited. The new culvert will be designed to convey sufficient drainage to comply
with current standards.
103
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: SIMMONS DRIVE CULVERT IMPROVEMENTS
Project Type: DRAINAGE Sub -Type: IMPROVEMENTS
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
In 2005, the City commissioned and received a drainage plan from Freese and Nichols, Inc.
PROJECT DESCRIPTION:
An additional culvert will extend from the apartment complex on the east side of Simmons Drive and will outfall
into the creek area on the north side of Carr Park.
PROJECT SCHEDULE:
JUSTIFICATION:
In intense storms, the capacity of the existing culvert is exceeded. Additional culverts will be required to convey
the storm flows. The construction of this project will enable the safe use of Simmons Drive in intense storm
events.
INO
104
O
Ch
CAPITAL IMPROVEMENT PROGRAMS
FY2017 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
STREET PROJECTS
FY2017 42nd CDBG-ADA/TAS Infrastructure Improvements
A
$ 91,000
XX
FY2017 Street Improvements
A
$ 600,000
XX
Traffic Signal -Harwood Road at Bear Creek Parkway
A
$ 180,000
XX
Sub -Total Street Priority A -Proposed FYI
$ 871,000
Ash Lane Reconstruction -Villa a Drive to West of SH360 (18)
B
$ 880,400
XX
Bear Creek Parkway Reconstruction -Harwood Road to Mid Cities Blvd(")
B
$ 2,100,000
XX
Fuller -Wiser Road Reconstruction-SH183 to Midway Driveil8i
B
$ 2,024,550
XX
Midway Drive & Fuller -Wiser Road Intersection Reconstruction(18)
B
$ 184,500
XX
FY2018 Street Improvements(")
B
$ 600,000
XX
XX
FY2019 441h CDBG-ADA/TAS Infrastructure Improvements ('8)
B
$ 110,000
XX
FY2019 Street Improvements (19)
B
$ 600,000
XX
XX
Traffic Signal -Cheek S ar er Road at Heritage Avenue (19)
B
$ 180,000
$ 50,000
$ 130,000
FY2020 Street Improvements (20)
B
$ 600,000
XX
XX
FY2021 Street Improvements (21)
B
$ 600,000
XX
XX
Vine Street Reconstruction-SH183 to SH10 (21)
B
$ 455,000
XX
XX
Sub -Total Street Priority B-Unfunded
8,334,450
Cresthaven Drive Reconstruction
C
TBD
XX
E Alexander Lane Reconstruction
C
TBD
XX
Highland Drive Reconstruction
C
TBD
XX
Ross Avenue Extension
C
TBD
XX
South Pipeline Road Reconstruction
C
TBD
XX
ub-Total Street Priority C-Unfunded
$
STREET PROJECTS - TOTAL
9,205,450
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 16,2012
Submitted By: CHRIS BARKER Date Completed:
Project Title: FY2017 42ND CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Project Code: Priori : A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(42nd year CDBG project)
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
.,N
..,*N
W
106
M
PROJECT TITLE: FY2017 42ND CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
TOTAL ESTIMATED CAPITAL COST:
Construction
$91,000 1
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $91,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design % 0%
Fund Balance
Preliminary Design % 0%
Special Project Fund
Final Plans % 0%
Certificate of Obligation
Specifications % 0%
County, State, Federal Funding
XX
Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Council Authorization:
February 23, 2016: Conducted a Public Hearing for the proposed 42nd year CDBG projects and approved the
recommendation which includes the installation of accessible sidewalks located along Fuller -Wiser Road.
107
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2017 STREET IMPROVEMENTS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadways, and will enhance the appearance of the streets.
.-*N
W
108
PROJECT TITLE: FY2017 STREET IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$600,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
109
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: TRAFFIC SIGNAL-HARWOOD ROAD @ BEAR CREEK PARKWAY
Project Type: STREET Sub -Type: SIGNALIZATION
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic signals are located at the intersections of arterial and collector thoroughfares identified in the City's
Master Thoroughfare Plan adopted in 1999.
PROJECT DESCRIPTION:
The project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection, and signal controller for the intersection of Harwood Road and Bear
Creek Parkway.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
A traffic signal warrant study was performed in June 2016 that indicates this intersection warrants a traffic signal.
110
M
on
PROJECT TITLE: TRAFFIC SIGNAL-HARWOOD ROAD @ BEAR CREEK PARKWAY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $30,000
Traffic Signals $150,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$180,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
ill
.-*N
T H E C I T Y O f
ll- E ss
'IN
112
TRAFFIC SIGNAL - HARWOOD RD AT BEAR CREEK PKWY
_ Y
--AY pR
--
0 250 500 1,000
Feet
W
O
O
O
W
a
a
_
U
U
of
W
H
Z
2
Legend
Proposed Project
113
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 22,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: ASH LANE RECONSTRUCTION- VILLAGE DRIVE TO WEST OF SH360
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Ash Lane is identified as a Minor arterial in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the complete reconstruction of Ash Lane from Village Drive to just West of SH360.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
This segment of Ash Ln is an aging road that is deteriorating and is nearing its service life. As maintenance
costs increase due to the increased deterioration, complete reconstruction will become necessary.
114
PROJECT TITLE: ASH LANE RECONSTRUCTION- VILLAGE DRIVE TO WEST OF SH360
NET EFFECTS ON OPERATING AND
MAINTENANCE COST 1+ OR -j ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction
$880,400 1
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $880,400
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
XX
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
115
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 22,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: BEAR CREEK PARKWAY RECONSTRUCTION - HARWOOD RD TO MID -CITIES BLVD
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Bear Creek Parkway is identified as a local collector thoroughfare in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the complete reconstruction of Bear Creek Parkway from Harwood Road to Mid -Cities
Boulevard to meet current City standards.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Bear Creek Parkway is an aging roadway nearing the end of its service life. Portions of the roadway are
beginning to deteriorate and require major reconstruction. As the pavement deteriorates and fails, maintenance
costs increase.
116
PROJECT TITLE: BEAR CREEK PARKWAY RECONSTRUCTION - HARWOOD RD TO MID -CITIES BLVD
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$2,100,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$2,100,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
XX
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
117
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 22,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: FULLER -WISER ROAD RECONSTRUCTION-SH183 TO MIDWAY DRIVE
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Fuller -Wiser Road is identified as a minor arterial in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of the complete reconstruction of Fuller -Wiser Road to current standards from SH183 to
Midway Drive.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Fuller -Wiser Road is an aging roadway nearing the end of its service life. Portions of the roadway are beginning
to deteriorate and require major reconstruction. As the pavement deteriorates and fails, maintenance costs
increase.
'_11\
118
PROJECT TITLE: FULLER -WISER ROAD RECONSTRUCTION-SH183 TO MIDWAY DRIVE
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$2,024,550
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$2,024,550
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
XX
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
119
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 22,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: MIDWAY DRIVE & FULLER -WISER ROAD INTERSECTION RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Midway is identified as a Minor arterial in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project consists of the complete reconstruction of the Midway Drive & Fuller -Wiser Road Intersection.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
The Midway Drive & Fuller -Wiser Road Intersection is aging and is nearing its service life. As maintenance costs
increase due to the increased deterioration, complete reconstruction will become necessary.
"IN
.—,*N
120
PROJECT TITLE: MIDWAY DRIVE & FULLER -WISER ROAD INTERSECTION RECONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction
$184,500 j
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $184,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
XX
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
121
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2018 STREET IMPROVEMENTS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
-IN
122
M
PROJECT TITLE: FY2018 STREET IMPROVEMENTS
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
123
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: CHRIS BARKER Date Completed:
Project Title: FY2019 44TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREET Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project provides for continued improvements to accessibility ramps by removing architectural barriers to
accessibility as required by Federal and State mandated Americans with Disabilities Act/Texas Accessibility
Standards ("ADA/TAS"). The project scope includes identification of architectural barriers to accessibility that
meet CDBG eligibility guidelines and the subsequent replacement thereof.
(44th year CDBG project)
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Removing architectural barriers to accessibility is an eligible CDBG activity and will assist in the City's efforts to
maintain compliance with applicable Federal and State ADA/TAS codes.
'.1
h
124
PROJECT TITLE: FY2019 44TH CDBG-ADA/TAS INFRASTRUCTURE IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost
Construction
$110,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$110,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
125
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2019 STREET IMPROVEMENTS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
_4 �
126
1-11
M
OR
PROJECT TITLE: FY2019 STREET IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
127
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 0412812015
Submitted By: HAL CRANOR Date Completed:
Project Title: TRAFFIC SIGNAL -CHEEK SPARGER ROAD @ HERITAGE AVENUE
Project Type: STREET Sub -Type: SIGNALIZATION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Traffic signals are located at the intersections of arterial and collector thoroughfares identified in the City's
Master Thoroughfare Plan adopted in 1999. The development of Glade Parks may produce a need for a traffic
signal at this intersection.
PROJECT DESCRIPTION:
The project consists of the installation of traffic signal poles, mast arms, signal heads, pedestrian indicators,
underground conduit, vehicle detection, and signal controller for the intersection of Cheek Sparger Road and
Heritage Avenue.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Traffic volumes at this intersection will be monitored and signal warrant studies will be performed to justify signal
installation. This intersection will ultimately require a traffic signal.
128
OR
L.,.
PROJECT TITLE: TRAFFIC SIGNAL -CHEEK SPARGER ROAD @ HERITAGE AVENUE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $30,000
Personnel: Full Time Traffic Signals $150,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$180,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Other
$60,000
Supplemental Sales Tax
Car Rental Tax Fund
$130,000
To Be Determined
ADDITIONAL COMMENTS:
Escrow Funds will be used to finance a portion of this project.
129
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted B : HAL CRANOR Date Completed:
Project Title: FY2020 STREET IMPROVEMENTS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
'"ON
130
Or -
PROJECT TITLE: FY2020 STREET IMPROVEMENTS
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design ova
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
131
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2021 STREET IMPROVEMENTS
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadway, and will enhance the appearance of the streets.
132
PROJECT TITLE: FY2021 STREET IMPROVEMENTS
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Construction $600,000
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$600,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
133
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: 04/28/2015
Submitted By: HAL CRANOR Date Completed:
Project Title: VINE STREET RECONSTRUCTION-SH183 TO SH10
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Vine Street is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of the reconstruction of Vine Street from SH183 to SH10.
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
The City has received street escrow funds from several developments along Vine Street. When development is
complete, it would be appropriate for the City to reconstruct the existing roadway.
L
134
PROJECT TITLE: VINE STREET RECONSTRUCTION-SH183 TO SH10
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $55,000
Personnel: Full Time Construction $380,000
Part Time $0 ROW $20,000
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$455,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Other
XX
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
Escrow Funds will be used to finance a portion of this project.
135
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: CRESTHAVEN DRIVE RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Cresthaven Drive is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
This project includes the reconstruction of Cresthaven Drive from a two-lane asphalt roadway to a 31' wide curb
and gutter concrete street from SH10 to S Pipeline Road.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade Cresthaven Drive to a standard City concrete curb and gutter street.
136
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 23,1999
Submitted By: RON YOUNG Date Completed:
Project Title: E ALEXANDER LANE RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This minor street serves as a collector type street by conveying traffic to major roadways.
PROJECT DESCRIPTION:
E Alexander Lane will be reconstructed from Main Street to Cullum Drive. It will be reconstructed from a two-
lane county type road to a standard 31' wide residential street with underground drainage and sidewalks.
PROJECT SCHEDULE:
JUSTIFICATION:
Reconstruction of this street will decrease the annual maintenance and provide compliance with current City
standards.
137
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: HIGHLAND DRIVE RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Highland Drive is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project includes the reconstruction of Highland Drive from SH10 to S Pipeline Road from a two-lane asphalt
roadway to a 31' wide curb and gutter concrete street.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade Highland Drive to a standard City concrete curb and gutter street.
138
NO
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2005
Submitted By: RON YOUNG Date Completed:
Project Title: ROSS AVENUE EXTENSION
Project Type: STREET Sub -Type: CONSTRUCTION
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This extension of Ross Avenue from the recently completed section adjacent to the fire station will complete the
upgrading of this street.
PROJECT DESCRIPTION:
The construction of the remainder of Ross Avenue from the fire station to the west limit will be in accordance
with City standards which includes concrete pavement.
PROJECT SCHEDULE:
JUSTIFICATION:
This construction, in accordance with City standards, will allow the road a long service life and lower the annual
maintenance costs.
139
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 13,2007
Submitted By: RON YOUNG Date Completed:
Project Title: SOUTH PIPELINE ROAD RECONSTRUCTION
Project Type: STREET Sub -Type: IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
South Pipeline Road is not identified in the City's Master Thoroughfare Plan.
PROJECT DESCRIPTION:
The project consists of reconstruction of South Pipeline Road from a two-lane asphalt roadway to a 31' wide
curb and gutter concrete street from east of Royal Parkway to east of Highland Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
To upgrade South Pipeline Road to a standard City concrete curb and gutter street.
W
140
CAPITAL IMPROVEMENT PROGRAMS
FY2017 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
WASTEWATER PROJECTS
LR: Cedar Hill Estates/Hollywood Boulevard
A
$ 129,000
XX
FY2017 42ntl CDBG LR: Oakwood Terrace Phase I
A
$ 242,000
XX
Sub -Total Wastewater Priority A -Proposed FYI
$ 371,000
FY2018 43`d CDBG LR: Oakwood Terrace Phase II I'BI
B
$ 547,000
$ 297,000
$ 250,000
LR: Ector Drive/Fayette Drive
B
$ 443,000
XX
LR Milam Drive (")
B
$ 299,000
XX
SH183 Phase II Wastewater Relocation(19)
B
$ 700,672
XX
LR: Kynette Drive/Wilshire Drive
B
$ 464,000
XX
LR: Eastcliff Drive/Windlea Drive/Signet Drive
B
$ 637,000
XX
LR: Ector Drive/Donley Drive/Crane Drive
B
$ 219,000
XX
Sub -Total Wastewater Priority B-Unfunded
$ 3,309,672
LR: Donley Drive/Shelmar Drive
C
TBD
XX
LR: Evans Drive/Canyon Ridge Drive/N Kynette Drive
C
TBD
XX
LR: Huntington/Koen/Atkerson/E Huitt/Slaughter/Martin
C
TBD
XX
LR: Janann Street/Brownstone/Shelmar Drive
C
TBD
XX
LR: Lakewood Boulevard/Dogwood Circle/Bocowood Circle
C
TBD
XX
LR: Live Oak Drive/Silver Creek Drive/Marlene Drive
C
TBD
XX
LR: Mary/Marlene/Commerce/ Wilshire/Greenbrier
C
TBD
XX
LR: Northcliff/Toplea/Windlea/Signet/ Kynette/Westcliff
C
TBD
XX
LR: NW Midway Drive/Rusk Drive/Parker Drive/Rockwall Drive
C
TBD
XX
LR: S Main Street
C
TBD
XX
LR: SagebrushlToplea/WilshireNorkshire/Tyler
C
TBD
XX
LR: Sierra Drive
C
TBD
XX
LR: W Donley/Private Drive/Mimosa/Magnolia/Redbud
C
TBD
XX
LR: W MidwayNictoria/Delta/ Lamar/Rockwall
C
TBD
XX
Sub -Total as ewe er Priority C-Unfunded
WASTEWATER PROJECTS - TOTAL
LR = Line nepiacemeni
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -CEDAR HILLS ESTATES/HOLLYWOOD BOULEVARD
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of wastewater mains in the Cedar Hill Addition along Hollywood
Boulevard from Vine Street to east of Cannon Drive.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
-1
W
142
OR
"I,
PROJECT TITLE: LINE REPLACEMENT -CEDAR HILLS ESTATES/HOLLYWOOD BOULEVARD
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $17,000
Construction $112,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$129,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
143
T H E C I T Y O F
ss
144
WW LINE REPLACEMENT -
CEDAR HILL ESTATES/HOLLYWOOD BOULEVARD
JEFFLYN CT
rn
LL)
to
BAYLESS DV 0
z
U)
JEAN LN
REAVES CT
❑
z
z
U)
i W
>
0
❑
03
0
0
0 WHITENER RD
0 125 250 500 Legend
Feet LENGTH: 799 FT - Proposed Project
145
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: 42ND CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE I
Project Type: WASTEWATER Sub -Type: CDBG
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. Between Hollywood Boulevard and Reaves Court from Vine Street to the end of Reaves Court and
2. From Hollywood Boulevard to Reaves Court along 306 Hollywood Boulevard.
(42nd year CDBG project)
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
W
146
M
PROJECT TITLE: 42ND CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE I
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
TOTAL ESTIMATED CAPITAL COST:
Engineering
Construction
$0
$0
$0
$0
$0
$0
$0 Total Estimated Capital Cost
CURRENT STATUS:
$32,000
$210, 000
$242,000 1
Operating Fund Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
County, State, Federal Funding XX Construction % 0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Council Authorization:
February 23, 2016: Conducted a Public Hearing for the proposed 42nd year CDBG projects and approved the
recommendation which includes replacing a wastewater line that is approximately 1,580 feet in length and is
located along the rear property line of homes facing onto Hollywood Boulevard and surrounding Reaves Court.
147
.-IN
T H E C I T Y O F
ss
148
BAYLESS DR
FY 2017 CDBG WW LINE REPLACEMENT -
OAKWOOD TERRACE PHASE 1
W HUITT LN
EHU LN
G)
JEFFLYN CT
O
(n
ui
K
J
>
z
U)
Z
0
u) MAIN PL
z
JEAN LN
REAVES CT
HOLLYWOOD BLVD
LU
0
z
z
0 125 250 500
Fm Mm Feet LENGTH: 1558 FT
Cn
z
Legend
- Proposed Project
149
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: 43RD CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE II
Project Type: WASTEWATER Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Along 608 and 610 Martha Street,
2. Between Martha Street and Cannon Drive from Reaves Court to W Huitt Lane,
3. Between Jefflyn Court and W Huitt Lane from Martha Street to S Main Street, and
4. Between Henslee Drive and Cannon Drive from Reaves Court to Jefflyn Court.
(43rd year CDBG project)
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
150
PROJECT TITLE: 43RD CDBG LINE REPLACEMENT-OAKWOOD TERRACE ADDITION PHASE II
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
AINTENANCE COST (+ OR -) ANNUAL:
Direct O eratin Cost Engineering $71,000
Personnel: Full Time Construction $476,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$547,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
$297,000
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
$250,000
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
151
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-ECTOR DRIVEIFAYETTE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains between Fayette Drive and Ector Drive from
Harwood Road to the end of the line.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
152
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE/FAYETTE DRIVE
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $58,000
Construction $385,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$443,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
153
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-MILAM DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater mains located along Milam Drive from Blanco Drive to
south of Bell Drive.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
154
M
PROJECT TITLE: LINE REPLACEMENT-MILAM DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $39,000
Construction $260,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$299,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
155
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 06,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: SH183 PHASE II WASTEWATER RELOCATION
Project Type: WASTEWATER Sub -Type: LINE RELOCATION
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Department of Transportation ("TxDoT") is expanding SH183. The Phase II construction will affect
the City of Euless' utilities along and crossing SH183 between FM157 and the east city limits.
PROJECT DESCRIPTION:
The City of Euless has wastewater mains and associated items located within the SH183 right-of-way. These
facilities must be relocated to accommodate Phase II of the SH183 expansion. The City of Euless has entered
into a relocation agreement with Southgate, the TxDoT contractor, authorizing them to design and relocate
wastewater lines. The City will be responsible for the cost of the relocation of the utilities.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
City of Euless wastewater facilities are located within TxDoT right-of-way. As such, the City must provide for
utility relocation to accommodate the roadway expansion.
'-IN
156
L
PROJECT TITLE: SH183 PHASE II WASTEWATER RELOCATION
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
WW Line Relocation Reimbursement $700,672 1
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
I Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost $0
Total Estimated Capital Cost
$700,672
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding schedule: *FY2016 $114,672 Right -of -Way Proceeds
*FY2016 $150,000 W/WW Operating Fund
FY2017 $280,000 W/WW Operating Fund
FY2018 $156,000 W/WW Operating Fund
*Collected in FY2016 (FB9915)
157
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 2016
Submitted By: HAL CRANOR Date Completed:
Project Title. LINE REPLACEMENT-KYNETTE DRIVE/WILSHIRE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Kynette Drive from Eastcliff Drive to Wilshire Drive and
2. Wilshire Drive from Kynette Drive extending 1000' north.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
--I
158
PROJECT TITLE: LINE REPLACEMENT-KYNETTE DRIVE/WILSHIRE DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $61,000
Construction $403,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$464,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
159
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-EASTCLIFF DRIVE/WINDLEA DRIVE/SIGNET DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project includes the replacement of the following wastewater mains:
1. Eastcliff Drive from Tyler Avenue to Signet Drive,
2. Windlea Drive from Eastcliff Drive to Wilshire Drive, and
3. Between Windlea Drive and Signet Drive from Eastcliff Drive to Wilshire Drive.
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
W
W
160
M
PROJECT TITLE: LINE REPLACEMENT-EASTCLIFF DRIVE/WINDLEA DRIVE/SIGNET DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $83,000
Construction $554,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$637,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
161
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-ECTOR DRIVE/DONLEY DRIVE/CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Ector Drive and Donley Drive from Aransas Drive to Harwood Road and
2. Between Donley Drive and Crane Drive from Aransas Drive to Harwood Road.
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
.-*N
162
PROJECT TITLE: LINE REPLACEMENT-ECTOR DRIVE/DONLEY DRIVE/CRANE DRIVE
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $29,000
Construction $190,000
$0
$0
$0
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$219,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
11".1
163
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-DONLEY DRIVE/SHELMAR DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater lines:
1. Donley Drive from Shelmar Drive to W Ash Lane,
2. Donley Drive from Harwood Road to Shelmar Drive, and
3. Shelmar Drive from Green Hill Street to the end of Shelmar Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
.-N
.-'11\
164
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-EVANS DRIVE/CANYON RIDGE DRIVE/N KYNETTE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Evans Drive and Canyon Ridge Drive from Cyclone Branch to north of Kynette Drive and
2. North of Kynette Drive from Canyon Ridge Drive to Cyclone Branch.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
165
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title. LINE REP-HUNTINGTON/KOEN/ATKERSON/E HUITT/SLAUGHTER/MARTIN
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
This project consists of the replacement of the following wastewater mains:
1. East of Huntington Drive from S Atkerson Lane to E Alexander Lane,
2. Between Koen Lane and S Atkerson Lane from Huntington Drive to FAA Road,
3. Between S Atkerson Lane and N Atkerson Lane from Huntington Drive to FAA Road,
4. Between N Atkerson Lane and E Huitt Lane from Huntington Drive to FAA Road,
5. Between E Huitt Lane and Slaughter Lane from Huntington Drive to FAA Road,
6. Between Slaughter Lane and Martin Lane from Huntington to FAA Road, and
7. Between Martin Lane and E Alexander Lane from Huntington Drive to FAA Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay the and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
--1
166
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-JANANN STREET/BROWNSTONE DRIVE/SHELMAR DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Janann Street from Aransas Drive to Donley Drive,
2. Brownstone Drive from Aransas Drive to Donley Drive,
3. Shelmar Drive from Greenhill Street to Aransas Drive, and
4. Aransas Drive from 500' south of Shelmar Drive to Janann Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
167
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title. LINE REPLACEMENT-LAKEWOOD BLVD/DOGWOOD CIRCLE/BOCOWOOD CIRCLE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Lakewood Boulevard from Dogwood Circle north to Private Drive and
2. Dogwood Circle, Cypress Circle, Bocowood Circle, and Aspenway Circle.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
knO
168
11.1
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 16,2012
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP -LIVE OAK DRIVE/SILVER CREEK DRIVE/MARLENE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Live Oak Drive from Silver Creek Drive south to Hurricane Creek,
2. Mains in the cul-de-sacs on the east side of Live Oak Drive,
3. Silver Creek Drive between Westpark Way and Evans Drive, and
4. Marlene Drive between Live Oak and Marlene Court.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
169
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-MARY/MARLENE/COMMERCE/WILSHI RE/GREENBRIAR
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Mary Drive and Marlene Drive from Cyclone Branch to Marlene Drive,
2. Between Commerce Street and Wilshire Drive from Marlene Drive to Sagebrush Trail,
3. South of Greenbriar Drive from Cyclone Branch to Debra Drive,
4. Between Greenbriar Drive and Mary Street from Eastcliff Drive to Debra Drive, and
5. East of Debra Drive and south of Mary Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
5111110
170
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-NORTHCLIFFITOPLEA/WINDLEA/SIGNET/KYNETTE/WESTCLIFF
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Northcliff Drive and Toplea Drive from Canyon Ridge to Cyclone Branch,
2. Between Toplea Drive and Windlea Drive from Canyon Ridge to Cyclone Branch,
3. Between Windlea Drive and Signet Drive from Canyon Ridge to Cyclone Branch,
4. Between Signet Drive and Kynette Drive from the church to Cyclone Branch, and
5. Westcliff Drive from Toplea Drive to north of Windlea Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
171
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -NW MIDWAY/RUSK/PARKER/ROCKWALL
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Pro'ect Code: Priori C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. North of West Midway Drive from FM157 to Parker Drive,
2. West Midway Drive from Parker Drive to Rusk Drive,
3. Rusk Drive from West Midway Drive to Parker Drive,
4. Parker Drive from West Midway Drive to Rockwall Drive, and
5. Rockwall Drive from west of Parker Drive to 400' west of Lamar Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
172
M
IM
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 13,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-S MAIN STREET
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the wastewater main along S Main Street from Jean Lane to W
Alexander Lane.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
173
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-SAG EBRUSH/TOPLEA/WILSHIRENORKSHIRE/TYLER
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Between Sagebrush Trail and Toplea Drive from Cyclone Branch to east of Wilshire Drive,
2. Between Wilshire Drive and Yorkshire Drive from Signet Drive to south of Toplea Drive,
3. Between Sagebrush Trail and Tyler Avenue from Cyclone Branch to Commerce Street,
4. Eastcliff Drive from Tyler Avenue to the apartments, and
5. Between Marlene Drive and Tyler Avenue from Eastcliff Drive to Commerce Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
IW
174
111.1
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 01,2011
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SIERRA DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
This project consists of replacement of the following wastewater mains:
1. Between Sierra Drive and Eastcliff Drive from Kynette Drive to Signet Drive and
2. East of Sierra Drive from Wilshire Park to Signet Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
175
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-W DONLEY/PRIVATE DRIVE/MIMOSA/MAGNOLIA/REDBUD
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. West of Donley Drive from West Ash Lane to Private Drive,
2. Private Drive from west of Redbud Drive to Lakewood Boulevard,
3. Mimosa Lane from Bocowood Drive to Private Drive,
4. Magnolia Lane from Bocowood Drive to Private Drive, and
5. Redbud Drive from Bocowood Drive to Private Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
--1
''1
176
LIM
04-11111
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: February 16,2009
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-W MIDWAY/VICTORIA/DELTA/LAMAR/ROCKWALL
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The
project is part of the systematic replacement of deteriorating vitrified clay tile wastewater mains.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. West Midway Drive from FM157 to Victoria Drive,
2. Victoria Drive from West Midway Drive north 700',
3. Delta Drive from West Midway Drive north 1000',
4. Lamar Drive from West Midway Drive north to Fayette Drive, and
5. Rockwall Drive from Lamar Drive west and north 800'.
PROJECT SCHEDULE:
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
177
T HE C I T Y O F
ss
178
V
t0
CAPITAL IMPROVEMENT PROGRAMS
FY2017 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
Determined
WATER PROJECTS
None Currently
A
$
Sub -Total Water Priority A -Proposed FY17
$
Fort Worth Interconnect I'sl
B
$ 300,000
XX
Reclaimed Water Line Extension Phase IV I'sl
B
$ 1,960,000
XX
FY2019 441" CDBG LR: Hollow Oak Drive (79)
B
$ 238,500
XX
LR: Kynette Drive (")
B
$ 318,750
XX
SH183 Phase II Water Relocation I19I
B
$ 780,672
XX
FY2020 45" CDBG LR: S Main Street (South) (20)
B
$ 272,500
XX
LR: Springwood Court (20)
B
$ 130,500
XX
LR: Sunset Drive (2°)
B
$ 418,000
XX
Reclaimed Water Line Extension Phase V (20)
B
$ 1,410,000
XX
Reclaimed Water Line Extension Phase VI (20)
B
$ 1,000,000
XX
FY2021 46" CDBG LR: S Main Street (North) (21)
B
$ 384,500
$ 84,500
$ 300,000
Sub -Total Water Priority B-Unfunded
$ 7,213,422
1 Mil Well Replacement
C
TBD
XX
Far North Well Replacement
C
TBD
XX
Fuller Well Replacement
C
TBD
XX
LR: Blessing Creek/Stony Creek/Rock Creek
C
TBD
XX
LR: Collin Drive -Dallas Drive to Harwood Road
C
TBD
XX
LR: Collin Drive -Denton Drive to Dallas Drive
C
TBD
XX
LR: Cresthaven Drive
C
TBD
XX
LR: Denton Drive
C
TBD
XX
LR: Dickey Drive North
C
TBD
XX
LR: Dickey Drive South
C
TBD
XX
LR: Dunaway Drive
C
TBD
XX
LR: E Huitt Lane
C
TBD
XX
LR: Eastcliff Drive
C
TBD
XX
LR: Fuller Drive
C
TBD
XX
LR: Highland Drive
C
TBD
XX
LR: Live Oak Court/Live Oak Drive
C
TBD
XX
LR: Midcreek/Rock Creek/Stony Creek
C
TBD
XX
LR: Midway Drive East
C
TBD
XX
LR: Midway Drive West
C
TBD
XX
LR: Needles Street
C
TBD
XX
LR: Paula Lane
C
TBD
XX
LR: S Pipeline Road East
C
TBD
XX
LR: S Pipeline Road West
C
TBD
XX
SH360 Water Crossing
C
TBD
XX
LR: Shady Creek Drive/Cliffwood Road
C
TBD
XX
LR: Westwood Drive
C
TBD
XX
LR: Wildwood Street
C
TBD
XX
LR: Woodvine (East)
C
TBD
XX
LR: Woodvine (West)
C
TBD
XX
Sub -Total Water Priority C-Unfunded
WATER PROJECTS -TOTAL
7,21 2
LR = Line Replacement
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 06,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: FORT WORTH INTERCONNECT
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of a connection to the City of Fort Worth's 24-inch water main on Main Street and South
Pipeline Road. In the event of an emergency, the City will be able to receive water from the City of Forth Worth
water system. Costs include the physical water connection, a vault, meter, and valves.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
The City is dependent on the Trinity River Authority (TRA) water supply. In the event of an emergency, the City
owned wells can not produce a sufficient amount of water to sustain the City. The City of Fort Worth obtains
water from a source that is not interconnected with TRA and should be able to supply enough water to sustain
the City in emergency situations.
"-,IN
180
M
L
PROJECT TITLE: FORT WORTH INTERCONNECT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering
Personnel: Full Time Construction
Part Time $0 10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$30, 000
$240,000
$30,000
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$300,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
00 0
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
181
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE IV
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase IV would extend the project to supply approximately 22MG
annually to 4 additional properties. It is anticipated the Phase IV would also trigger the need for additional pumps to
be placed at the existing pump site to supply necessary pressure and capacity. Additional system expansion would be
possible in the future.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
..1
.-IN
182
NO
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE IV
NET
EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $360,000
$0 I Construction $1,600,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,960,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
00 0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
00 0
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
183
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2019 44TH CDBG LINE REPLACEMENT -HOLLOW OAK DRIVE
Project Type: WATER Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,270 feet of 6" cast iron main with an 8" PVC main along Hollow
Oak Drive from Woodridge Circle to Pebble Creek Drive and Woodridge Circle south of Hollow Oak Drive.
(44th year CDBG project)
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
111110
'IN
184
M
M
PROJECT TITLE: FY2019 44TH CDBG LINE REPLACEMENT -HOLLOW OAK DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $29,000
Personnel: Full Time Construction $190,500
Part Time $0 10% Contingency $19,000
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$238,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
185
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-KYNETTE DRIVE, CYCLONE CREEK TO WILSHIRE DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,700 feet of 6" cast iron water main with an 8" PVC main along
Kynette Drive from Cyclone Creek to Wilshire Drive.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
--*N
186
M
PROJECT TITLE: LINE REPLACEMENT-KYNETTE DRIVE, CYCLONE CREEK TO WILSHIRE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering
Personnel: Full Time Construction
Part Time $0 10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$38,250
$255,000
$25, 500
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$318,750
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
187
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 06,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: SH183 PHASE II WATER RELOCATION
Project Type: WATER Sub -Type: LINE RELOCATION
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Department of Transportation ("TxDoT") is expanding SH183. The Phase II construction will affect
the City of Euless' utilities along and crossing SH183 between FM157 and the east city limits.
PROJECT DESCRIPTION:
The City of Euless has water mains and associated items located within the SH183 right-of-way. These facilities
must be relocated to accommodate Phase II of the SH183 expansion. The City of Euless had entered into a
relocation agreement with Southgate, the TxDoT contractor, authorizing them to design and relocate water lines
and associated infrastructure. The City will be responsible for the cost of relocating the utilities.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
City of Euless water facilities are located within TxDoT right-of-way. As such, the City must provide for utility
relocation to accommodate the roadway expansion.
188
PROJECT TITLE: SH183 PHASE II WATER RELOCATION
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Relocation Reimbursement
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
I Subtotal: $0
$0
$780,672
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$780,672
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding schedule: *FY2016 $114,672
Right -of -Way Proceeds
*FY2016 $155,000
WNWV Operating Fund
FY2017 $315,000
W/WW Operating Fund
FY2018 $196,000
W/WW Operating Fund
*Collected in FY2016
(FB9915)
189
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 2016
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2020 45TH CDBG LINE REPLACEMENT-S MAIN STREET (SOUTH)
Project Type: WATER Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along S Main Street from Hollywood Blvd to E Huitt Lane
from a 6" cast iron main to an 8" PVC.
(45th year CDBG project)
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
'-*N
190
PROJECT TITLE: FY2020 45TH CDBG LINE REPLACEMENT-S MAIN STREET (SOUTH)
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $32,000
Personnel: Full Time Construction $218,500
Part Time $0 10% Contingency $22,000
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$272,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
XX
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding
availability.
191
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-SPRINGWOOD COURT
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 700 feet of 4" water main with an 8" main on Springwood Court.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance cost. Substandard size water mains provide
a reduced flow of water. Systematic annual replacement of deteriorated and substandard size water mains will
reduce maintenance costs.
192
OR
PROJECT TITLE: LINE REPLACEMENT-SPRINGWOOD COURT
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering
Personnel: Full Time Construction
Part Time $0 10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$15, 000
$105,000
$10, 500
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$130,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
193
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -SUNSET DRIVE, S PIPELINE ROAD TO S MAIN STREET
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade 2,230 feet of water main along Sunset Drive from S Pipeline Road to S
Main Street from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
W
194
PROJECT TITLE: LINE REPLACEMENT -SUNSET DRIVE, S PIPELINE ROAD TO S MAIN STREET
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Direct Operating Cost Engineering
Personnel: Full Time Construction
Part Time $0 10% Contingency
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$50,000
$334,500
$33,500
Subtotal:
Total Estimated Annual Cost
$0
$0
Total Estimated Capital Cost
$418,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
196
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE V
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase V would extend the project to supply approximately 13MG
annually to 3 additional properties. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
W
196
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE V
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $260,000
$p Construction $1,150,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,410,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
197
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 15,2015
Submitted By: CHRIS BARKER Date Completed:
Project Title: RECLAIMED WATER LINE EXTENSION PHASE VI
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear
Creek Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will
ultimately provide reclaimed water service to several multi -family properties from Harwood Road to Mid Cities
Boulevard as well as the City's Bear Creek Park. Phase VI would extend the project to supply approximately 8MG
annually to 4 additional properties. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water
purchases by the City and will serve to responsibly conserve potable water resources for the City and the region.
IW
198
PROJECT TITLE: RECLAIMED WATER LINE EXTENSION PHASE VI
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering $200,000
$0 Construction $800,000
$0
$0
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,000,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
XX
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
199
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 08,2015
Submitted By: HAL CRANOR Date Completed:
Project Title: FY2021 46TH CDBG LINE REPLACEMENT-S MAIN STREET (NORTH)
Project Type: WATER Sub -Type: CDBG
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along S Main Street from E Huitt Lane to SH10 from a 6"
cast iron main to an 8" PVC main.
(46th year CDBG project)
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
bo
200
PROJECT TITLE: FY2021 46TH CDBG LINE REPLACEMENT-S MAIN STREET (NORTH)
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $46,000
Personnel: Full Time Construction $307,500
Part Time $0 10% Contingency $31,000
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
Subtotal: $0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$384,500
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
$84, 500
Conceptual Design %
o
0 %
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0
°
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
$300,000
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project funding is subject to actual CDBG funding availability
201
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 14,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: 1 MIL WELL REPLACEMENT
Project Type: WATER Sub -Type: WELLS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project funds the drilling of a new well to replace the 1 Mil Well. In addition, an ammonia feed system is
proposed to upgrade the current chlorine feed system to state standards.
PROJECT SCHEDULE:
JUSTIFICATION:
The 1 Mil well is approximately 45 years old and has a deteriorating casing. To continue to supply quality water
to the citizens of Euless, a new well is proposed. An ammonia feed facility is required by state of Texas
Commission of Environmental Quality to match the TRA supplied water and disinfectant.
202
M,
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 25,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: FAR NORTH WELL REPLACEMENT
Project Type: WATER Sub -Type: WELLS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project funds the drilling of a new well to replace the Far North Well. In addition, an ammonia feed system
is proposed to upgrade the current chlorine feed system to state standards.
PROJECT SCHEDULE:
JUSTIFICATION:
The Far North well is approximately 45 years old and has a deteriorating casing. To continue to supply quality
water to the citizens of Euless, a new well is proposed. An ammonia feed facility is required by state of Texas
Commission of Environmental Quality to match the TRA supplied water and disinfectant.
203
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 25,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: FULLER WELL REPLACEMENT
Project Type: WATER Sub -Type: WELLS
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project funds the drilling of a new well to replace the Fuller Well. In addition, an ammonia feed system is
proposed to upgrade the current chlorine feed system to state standards.
PROJECT SCHEDULE:
JUSTIFICATION:
The Fuller well is approximately 50 years old and has a deteriorating casing. To continue to supply quality water
to the citizens of Euless, a new well is proposed. An ammonia feed facility is required by state of Texas
Commission of Environmental Quality to match the TRA supplied water and disinfectant.
FRO
-IN
204
M
City of Euless
Capital Project Request
pDepartment: PUBLIC WORKS Date Prepared: March 11,2015
: HALCRANOR Date Com leted:
LINE REPLACEMENT -BLESSING CREEK/STONY CREEK/ROCK CREEK
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains are included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace the 6" AC main with an 8" PVC main for Blessing Creek, Stony Creek, and Rock Creek.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
206
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-COLLIN DRIVE, DALLAS DRIVE TO HARWOOD ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main with an 8" PVC main along Collin Drive from Dallas Drive to Harwood
Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
206
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-COLLIN DRIVE, DENTON DRIVE TO DALLAS DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main to an 8" PVC main along Collin Drive from Denton Drive to Dallas
Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
207
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT - CRESTHAVEN DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,478 feet of 6" water main with an 8" main on Cresthaven Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
W
208
OR
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-DENTON DRIVE, TARRANT DRIVE TO HARWOOD ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: PrioriC
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main along Denton Drive
from Tarrant Drive to Harwood Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
209
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -DICKEY DRIVE NORTH, SH10 TO E HUITT LANE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project consists of replacing the 6" cast iron water main with an 8" PVC main along Dickey Drive north from
SH10 to E Huitt Lane.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
_1*\
210
M
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -DICKEY DRIVE SOUTH, E HUITT LANE TO HILTON DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project consists of the replacement of a 6" cast iron water main with an 8" PVC main along Dickey Drive
south from E Huitt Lane to Hilton Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
211
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-DUNAWAY DRIVE, E ALEXANDER LANE TO E ASCOT DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" AC water main with an 8" PVC water main on
Dunaway Drive from E Alexander Lane to E Ascot Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
"1
212
OR
M
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-E HUITT LANE, S MAIN STREET TO DUNAWAY DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" PVC water main with an 8" PVC water main along
E Huitt Lane from S Main Street to Dunaway Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
213
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP LACEMENT-EASTCL I FF DRIVE, TOPLEA DRIVE TO DEL PRADO APTS.
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" AC main to an 8" PVC main along Eastcliff Drive from Toplea
Drive to Del Prado Apartments.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
214
NO
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -FULLER DRIVE, SALEM DRIVE TO CARTER DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of replacing a 6" cast iron water main with an 8" PVC water main along Fuller Drive from
Salem Drive to Carter Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
216
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT -HIGHLAND DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,144 feet of 2" water main with an 8" main on Highland Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
216
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -LIVE OAK CT/LIVE OAK DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 4" cast iron water main with an 8" PVC main along Live
Oak Drive from Cedar Court to the south end of Live Oak Court. Additionally, the replacement of the existing 8"
cast iron water main with an 8" PVC water main from Canyon Ridge to West Cliff Drive is also included in the
scope of the project.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
217
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 05,2007
Submitted By: RON YOUNG Date Completed:
Project Title. LINE REP-MIDCREEK DRIVE/ROCK CREEK DRIVE/STONY CREEK DRIVE
Project Type. WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project consists of the replacement of a 6" AC main with an 8" PVC main on Midcreek Drive, Rock Creek
Drive, and Stony Creek Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
218
M
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -MIDWAY DRIVE EAST, N MAIN ST TO FREESTONE DR
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project replaces the 6" cast iron water main with an 8" PVC main on Midway Drive east from N Main Street
to Freestone Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
219
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -MIDWAY DRIVE WEST, FREESTONE DRIVE TO ECTOR DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project replaces the 6" cast iron water main with an 8" PVC main along Midway Drive west from Freestone
Drive to Ector Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
220
L
`,,
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 15,2005
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -NEEDLES STREET, PAULA LANE TO RAIDER DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the existing 6" cast iron water main with an 8" PVC water main along
Needles Street from Paula Lane to Raider Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
221
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-PAULA LANE, NEEDLES STREET TO S PIPELINE ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of the 6" cast iron water main with an 8" PVC main along Paula Lane
from Needles Street to S Pipeline Road.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
r
"1
222
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-S PIPELINE ROAD EAST, VINE STREET TO S MAIN STREET
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace 1,563 feet of existing 6" cast iron water main with an 8" PVC water main along
S. Pipeline Road east from Vine Street to S. Main Street.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
223
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 01,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: LINE REPLACEMENT-S PIPELINE ROAD WEST
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,343 feet of existing 6" cast iron water main with an 8" PVC water
main along S Pipeline Road west from Simmons Drive to Vine Street
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
MO
224
1141-11
N.,
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: July 21,2000
Submitted By: RON YOUNG Date Completed:
Project Title: SH360 WATER CROSSING
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is related to the DFW International Airport Master Plan for property in Euless.
PROJECT DESCRIPTION:
The project scope includes the extension of two (2) 12" diameter water mains through the SH360 right-of-way to
provide service to the southwest portion of the DFW Airport property. The water mains will be bored under
SH360 at the Midway Drive intersection and between Harwood Road and Ash Lane. The mains will be located
within the Texas Department of Transportation right-of-way. The mains will be plugged at the east right-of-way
of SH360 in anticipation of the likely extension into DFW Airport property to serve future development.
PROJECT SCHEDULE:
JUSTIFICATION:
Development on the airport property could potentially increase the City's tax revenues. Future development is
dependent upon the availability of water service to this area.
225
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT -SHADY CREEK DRIVE/CLIFFWOOD ROAD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water mains along Shady Creek Drive and Cliffwood Road from the
existing 6" cast iron mains to 8" PVC.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
226
MR
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 28,2003
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-WESTWOOD DRIVE, FULLER DRIVE TO CARTER DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace a 6" cast iron main with an 8" PVC main along Westwood Drive from Fuller Drive to
Carter Drive.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
227
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REPLACEMENT-WILDWOOD STREET
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along Wildwood Street from a 6" cast iron main to an 8"
PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
-_N
—"N
228
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-WOODVINE DRIVE (EAST), CLIFFWOOD ROAD TO EL CAMINO REAL
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace and upgrade the water main along Woodvine Drive from Cliffwood Road to El Camino
Real from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
229
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 12,2004
Submitted By: RON YOUNG Date Completed:
Project Title: LINE REP-WOODVINE DRIVE (WEST), PEBBLE CREEK DR TO CLIFFWOOD RD
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
This project will replace and upgrade the water main along Woodvine Drive from Pebble Creek to Cliffwood
Road from a 6" cast iron main to an 8" PVC main.
PROJECT SCHEDULE:
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
230
N
W
CAPITAL IMPROVEMENT PROGRAMS
FY2017 PROPOSED & UNFUNDED PROJECTS - SORTED BY TYPE
PROPOSED METHOD OF FINANCING
Project Description
Priority
Estimated Cost
Operating
Fund
CIP Fund
Balance
Bond Sale
Grants/
Contrib
Impact
Fees
Escrow
Funds
Car Rental
Tax
Other
EDC
To Be
ermined
OTHER PROJECTS
Library Remodel Design
A
$ 147,630
XX
Municipal Plaza Improvements Phase II
A
$ 150,000
XX
Public Works Yard Improvements
A
$ 100,000
XX
Texas Star Golf Course Maintenance Building
A
$ 100,000
XX
Texas Star Sports Complex Phase VI
A
$ 1,258,892
XX
XX
Sub -Total Other Priority A -Proposed FY17
$ 1,756,522
Texas Star Sports Complex Phase VII Design (1a)
B
$ 810,930
XX
Library Remodel Construction (is)
B
$ 2,000.000
XX
XX
Texas Star Sports Complex Phase VII Construction(20)
B
$ 5,946,821
XX
XX
XX
XX
Blessing Branch Park Improvements
B
$ 326,667
XX
Trail Enhancements Phase 1 (21)
B
$ 203,266
XX
Sub Total Other Priority S-Unfunded
$ 9,287,684
Animal Shelter Ex ansion/Renovation
C
TBD
XX
Fire Station #2 Remodel
C
TBD
XX
Kiddie Carr Park Improvements
C
TBD
XX
South Euless Park Upgrades
C
TBD
XX
Trail Enhancements Phase 11
C
TBD
XX
Trail Enhancements Villages of Bear Creek
C
TBD
XX
Trailwood Park Improvements
C
TBD
XX
Wilshire Park U rades
C
TBD
XX
Sub Ifni Other Priority C-Unfunded
OTHER PROJECTS - TOTAL
11, 444,206
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 01,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: LIBRARY REMODEL DESIGN
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This remodel planning is submitted as a new project and is not related to the City's Master Plan.
PROJECT DESCRIPTION:
Planning and design phase for remodel of the Library.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
The Library was constructed in 1996 and interior furnishings and design layout are in need of updating.
No
232
OR
PROJECT TITLE: LIBRARY REMODEL DESIGN
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Planning/Bid Specifications
$147,630
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Insurance
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$147,630
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
233
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: June 03,2014
Submitted By: HAL CRANOR Date Completed:
Project Title: MUNICIPAL PLAZA IMPROVEMENTS PHASE II
Project Type: FACILITIES Sub -Type: IMPROVEMENTS
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is the landscaping and irrigation related to the 40th CDBG ADA accessibility and infrastructure
improvements.
PROJECT DESCRIPTION:
Landscaping and irrigation improvements to the Municipal Plaza following the 40th CDBG ADA accessibility and
infrastructure improvements.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
Beautification of the municipal plaza following the hardscape improvements.
-.,*N
I-N
234
PROJECT TITLE: MUNICIPAL PLAZA IMPROVEMENTS PHASE II
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Landscaping
$150,000 1
Total Estimated Annual Cost
$0
Total Estimated Capital Cost $150,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
Fund Balance
Preliminary Design %
Special Project Fund
Final Plans %
Certificate of Obligation
Specifications %
County, State, Federal Funding
Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
235
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 25,2016
Submitted By: HAL CRANOR Date Completed:
Project Title: PUBLIC WORKS YARD IMPROVEMENTS
Project Type: OTHER Sub -Type: PARKING SURFACE IMPROVEMENT
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
This project funds the paving of a driveway constructed to firelane standards and an extension of the existing parking
lot within the multi -use yard located at the Public Works Building. The driveway will connect the rear gate and parking
area utilized for parking dump trucks and trailers. A paved surface will reduce ponding, mud, and tracking of
sediments onto the street and into the drainage system.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
This project addresses BPM # GH1 Good Housekeeping for Municipal Operations, of the Euless Storm Water
Management Plan. The Texas Commission on Environmental Quality requires the proper storage of materials, and
controls that keep sediment and pollutants from entering the storm sewer system. The Public Works yard is used to
store clean sand, soil and asphalt as well as construction related material such as dirt, pipe debris, mud and asphalt
milling's.
'--IN
--*IN
236
4
PROJECT TITLE: PUBLIC WORKS YARD IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Construction
$100,000
Personnel: Full Time
Part Time
$0
Total Salary
$0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal:
$0
Maintenance Costs
$0
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$100,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
Other -plan review/inspection fees
ADDITIONAL COMMENTS:
237
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 22,2015
Submitted By: KYLE MCADAMS Date Completed:
Project Title: TEXAS STAR GOLF COURSE MAINTENANCE BUILDING
Project Type: FACILITIES Sub -Type: REMODEL
Pro'ect Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is not part of the City's five year master plan.
PROJECT DESCRIPTION:
The project consists of the renovation of the current maintenance facility constructed in 1997. The project scope
includes the remodel of existing office space, break room, maintenance, and storage rooms. Interior walls will be
repaired along with the installation of new counter tops, cabinets, bathroom fixtures, light fixtures, and
miscellaneous appliances. Concrete floors will be polished and seal coated, and both the interior and exterior of
the building will be repainted.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
The maintenance facility was constructed in 1997 and has not received any previous remodels or upgrades.
ko
N
238
PROJECT TITLE: TEXAS STAR GOLF COURSE MAINTENANCE BUILDING
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Remodel / Renovation $100,000 1
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$100,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Escrow Funds
Other
XX
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding is from TSGC Reserves.
239
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27, 2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE VI
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: Priority: A
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase VI includes renovating the existing infields with synthetic turf and
construction of additional parking.
With the growing number of participants in youth baseball, renovating the existing infields with synthetic turf will
allow staff the opportunity to expand existing leagues as well as programming for additional leagues in adult
softball. Synthetic turf infields will also substantially reduce the number of rain outs which results in lost
revenue. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the renovation of the existing infields with synthetic turf and construction of additional
parking.
PROJECT SCHEDULE:
FY2017
JUSTIFICATION:
With the completion of Phase VI, the new infields will increase programming opportunities as well as
substantially reduce the number of rain outs.
W
240
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE VI
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel:
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Full Time
Part Time
TOTAL ESTIMATED CAPITAL COST:
Construction
Parking Lot
$0 Contingency
$0
$0
$0
$0
$960,850
$250,000
$48, 042
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$1,258,892
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
$958,892
Conceptual Design %
0%
Fund Balance
$300,000
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Escrow Funds
Other
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding is from EDC Operating Fund
Additional funding is from CIP fund balance.
241
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27,2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE VII DESIGN
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase VII includes additional multi -use fields to accommodate both softball and
baseball. Also included in the project is additional parking and a concession building to support the new phase
and the number of participants the activities hosted by the new phase will generate. With the growing number of
participants in youth baseball and adult softball, the new multi -use fields will allow our staff the opportunity to
expand our programming in both sports as well as creating new opportunities for future programs including girl's
fast pitch. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the design of four (4) multi -use playing fields that would accommodate adult slow pitch and
girl's fast pitch softball, as well as youth baseball. Phase VII will also feature synthetic sports turf in all the
infields, a concession and restroom building, a pavilion, playground and sufficient parking to accommodate the
additional patrons.
PROJECT SCHEDULE:
FY2018
JUSTIFICATION:
Softball World is an aging facility with many necessary upgrades looming in the short-term which would require
a significant capital investment. This phase would eliminate the upgrades with consolidation and movement of
this operation to the Parks at Texas Star, collectively known as the Texas Star Sports Complex. With the
completion of Phase VII, the new multi -use facility will serve the athletic needs of the community and spur
economic opportunities for the City.
242
11�
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE VII DESIGN
NET EFFECTS ON OPERATING AND
AINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
$0
$0
$0
$0
$0
TOTAL ESTIMATED CAPITAL COST:
Design $810,930
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$810,930
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Escrow Funds
Other
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Note: Operating currently under the TSSC umbrella, Softball World's proposed relocation to Parks At Texas
Star, under this phase, will cover all operating costs of the new operations. Accordingly, no additional baseline
expenses are anticipated.
Proposed funding is from EDC Operating Fund.
243
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: April 01,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: LIBRARY REMODEL CONSTRUCTION
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This remodel is submitted as a new project and is not related to the City Master Plan.
PROJECT DESCRIPTION:
The library facility remodel project scope includes reconfiguration of the general interior layout, replacement of
the chilled water HVAC system, replacement of furnishings, updating overall facility decor, lighting upgrades,
and electrical work.
PROJECT SCHEDULE:
FY2019
JUSTIFICATION:
The Library was constructed in 1996, pre-internet and pre -digital age. Electrical plugs and data ports are
currently in limited areas but are needed throughout the building to provide increased access to computers and
technology. Patrons are requesting more space for quiet study, group study, and collaboration. The Young
Adult/Teen collection is one of the highest circulation and this group needs a space in the Library.
2"
PROJECT TITLE: LIBRARY REMODEL CONSTRUCTION
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
TOTAL ESTIMATED CAPITAL COST:
Construction
Personnel: Full Time
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities $0
Subtotal: $0
$0
$2,000,000 1
Subtotal:
$0
Total Estimated Annual Cost
$0
Total Estimated Capital Cost
$2,000,000
PROPOSED METHOD OF FINANCE:
CURRENT STATUS:
Operating Fund
XX
Conceptual Design %
0%
Fund Balance
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
XX
To Be Determined
ADDITIONAL COMMENTS:
Proposed funding is a loan from Car Rental to be repaid from EDC
245
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 27,2015
Submitted By: RAY MCDONALD Date Completed:
Project Title: TEXAS STAR SPORTS COMPLEX PHASE VII CONSTRUCTION
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Texas Star Sports Complex Phase VII includes additional multi -use fields to accommodate both softball and
baseball. Also included in the project is additional parking End a concession building to support the new phase
and the number of participants the activities hosted by the new phase will generate. With the growing number of
participants in youth baseball and adult softball, the new multi -use fields will allow our staff the opportunity to
expand our programming in both sports as well as creating new opportunities for future programs including girl's
fast pitch. The addition of this phase will ensure that the Texas Star Sports Complex remains the premier sports
facility for amateur athletics for many years to come.
PROJECT DESCRIPTION:
The project includes the construction of four (4) multi -use playing fields that would accommodate adult slow
pitch and girl's fast pitch softball, as well as youth baseball. Phase VII will also feature synthetic sports turf in all
the infields, a concession and restroom building, a pavilion, playground and sufficient parking to accommodate
the additional patrons.
PROJECT SCHEDULE:
FY2020
JUSTIFICATION:
Softball World is an aging facility with many necessary upgrades looming in the short-term which would require
a significant capital investment. This phase would eliminate the upgrades with consolidation and movement of
this operation to the Parks at Texas Star, collectively known as the Texas Star Sports Complex. With the
completion of Phase VII, the new multi -use facility will serve the athletic needs of the community and spur
economic opportunities for the City.
900
bo
W
246
`..
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE VII CONSTRUCTION
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
General Items
$61,000
Personnel: Full Time
Earth Work
$110,500
Part Time
$0
Site Paving
$1,029,150
Total Salary
$0
Softball Fields (four - plex)
$1,909,120
Purchase of Services
General Site Amenities
$96,666
Materials & Supplies
Playground
$200,000
Utilities
$0
Concession/Restroom Bldg
$585,000
Irrigation/Landscaping
$267,520
Water
$152,425
Sanitary Sewer
$42,000
Subtotal:
$0
Storm Drain
$498,420
Maintenance Costs
Electrical
$454,400
$0
10% Contingency
$540,620
Subtotal:
$0
Total Estimated Annual Cost $0 Total Estimated Capital Cost $5,946,821
PROPOSED METHOD OF FINANCE: I CURRENT STATUS:
Operating Fund XX
Conceptual Design %
0%
Fund Balance XX
Preliminary Design %
0%
Special Project Fund
Final Plans %
0%
Certificate of Obligation
Specifications %
0%
County, State, Federal Funding
Construction %
0%
General Obligation Bonds
Revenue Bonds
Escrow Funds
Other XX
Car Rental Tax Fund XX
To Be Determined
ADDITIONAL COMMENTS:
Note: Operating currently under the TSSC umbrella, Softball World's proposed relocation
to Parks At Texas
Star, under this phase, will cover all operating costs of the new operations. Accordingly,
no additional baseline
expenses are anticipated.
Proposed financing includes operations, reserves, CIP fund balance and a loan from Car Rental to be repaid
from EDC.
247
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 30,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: BLESSING BRANCH PARK IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a continuation of the overall trail system expansion and general park improvements as identified
in the Parks Master Plan.
PROJECT DESCRIPTION:
Blessing Branch Park is a 7.3 acre linear park located on the east side of Main Street across from Midway Park.
Currently, the park has only one swing set. This project includes construction of a trail connection from Main
Street to the west and Fuller -Wiser to the east. Additionally, the project includes a new playground, picnic
pads with grills, and some type of shade shelter/pavilion/gazebo. This area currently gets a high volume of foot
traffic. Constructing a trail in this linear greenbelt would not only provide a safe paved access for the residents
east of Main Street to Midway Park, Midway Park Elementary, and to Trinity High School, but also help create a
renewed sense of quality of life for the residents in that area by enhancing the recreational amenities available.
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
The number one request from Euless citizens as it relates to trails, based on the responses to the needs
assessment survey as identified in the Parks Master Plan, was to construct trail connections between existing
and/or future park developments. This project not only satisfies that request, but also provides trail connections
to neighborhoods, schools, between major thoroughfares, and potentially to future commercial developments to
the southeast.
1111111-16
W
248
M
PROJECT TITLE: BLESSING BRANCH PARK IMPROVEMENTS
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Approximately 28,000 square feet of
Personnel: Full Time
4"x8' concrete trail @ $4.25 square foot
$119,000
Part Time
$0
Playground/Border
$60,000
Total Salary
$0
Picnic pads w/grills
$20,000
Purchase of Services
Shade shelter/pavilion/gazebo
$30,000
Materials & Supplies
Trail Lighting
$50,000
Utilities
$0
Playground chips
$5,400
Design/Survey/Engineering (10%)
$26,712
Contingency 5%
$15,555
Subtotal: $0
Subtotal:
Total Estimated Annual Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
$0
$0
$0 Total Estimated Capital Cost $326,667
CURRENT STATUS:
XX Conceptual Design % 0%
Preliminary Design % 0%
Final Plans % 0%
Specifications % 0%
Construction % 0%
249
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 12,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS PHASE I
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: Priority: B
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Identified in the Needs Assessment and Identification section of the adopted Parks Master Plan are a number of
trail related improvements.
PROJECT DESCRIPTION:
This project consists of the first phase of implementation of park improvements identified in the adopted Parks
Master Plan which includes additional water fountains, additional benches, construction of shaded seating areas
along the trail, addition and/or installation of new exercise equipment along the trails, picnic stations, and
construction of additional pedestrian bridges in high water areas. Also identified, is the need to address various
areas in our trails system that might need to be converted from unpaved to paved trails.
PROJECT SCHEDULE:
FY2021
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The development and maintenance of the trails system
continued to receive significant support from the citizens as indicated in the responses to the needs assessment
survey conducted as a part of the Parks Master Plan update.
W
-IN
250
PROJECT TITLE: TRAIL ENHANCEMENTS PHASE I
NET EFFECTS ON OPERATING AND
TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Stopping Stations:
Personnel: Full Time
8'x8' w/bench (2) Bob Eden
Part Time $0
Health Trail:
Total Salary $0
Fitness Course - Bob Eden
Purchase of Services
Freight for fitness equipment
Materials & Supplies
Installation of fitness equipment
Utilities $0
32' Gazebo shade shelter
Freight for gazebo
Installation of gazebo
New fitness trail surface
Subtotal: $0
(4527 sq. ft @ $4.25 sq. ft)
Maintenance Costs
Gazebo slab (805 sq. ft @ $4.25 sq.ft)
$0
Safety surface for fitness stations
Other (5%)
Design/Engineering (10% of proj. cost)
Contingency (10% of total proj)
Subtotal: $0
Total Estimated Annual Cost $0
Total Estimated Capital Cost
PROPOSED METHOD OF FINANCE:
Operating Fund
Fund Balance
Special Project Fund
Certificate of Obligation
County, State, Federal Funding
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
CURRENT STATUS:
XX Conceptual Design %
Preliminary Design %
Final Plans %
Specifications %
Construction %
$8,200 1
$9,678
$1,635
$4, 090
$44, 552
$2,050
$17,820
$19,240
$3,421
$50, 000
$8,034
$16,068
$18,478
$203,266 1
0%
0%
0%
0%
0%
251
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: May 07,2007
Submitted By: KYLE MCADAMS Date Completed:
Project Title: ANIMAL SHELTER-EXPANSION/RENOVATION
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is part of the City's five year master plan.
PROJECT DESCRIPTION:
The project consists of the expansion of the current animal shelter facility to better accommodate visitors,
adoptions, and animal services. The project scope includes the addition of ten (10) enclosed dog runs, six (6)
quarantine runs, an adoption room, additional room for cat containment, and an area for animal washing. Office
space expansion will be included in the renovation as well as updates to the public/employee rest rooms.
PROJECT SCHEDULE:
JUSTIFICATION:
The current animal control facility has insufficient space to meet current and future demands.
W
252
OR
\I -
City of Euless
Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: March 13,2013
Submitted By: KYLE MCADAMS Date Completed:
Project Title: FIRE STATION #2 REMODEL
Project Type: CONSTRUCTION Sub -Type: REMODEL
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This structure was the former vehicle service center built in 1977 and was reconstructed for the relocation of Fire
Station #2 from 1100 Westpark Way. The remodel was completed in 1997.
PROJECT DESCRIPTION:
The project scope includes interior enhancements, reconfiguration of the bathrooms and shower facilities,
kitchen improvements, and general remodel of interior structures including updates required by the Americans
with Disabilities Act.
PROJECT SCHEDULE:
JUSTIFICATION:
Interior enhancements, reconfiguration of the bathrooms and shower facilities, kitchen, and general remodel of
interior structures are needed.
253
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: KIDDIE CARR PARK IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan recommends funding for system -wide park facilities and amenities upgrades.
PROJECT DESCRIPTION:
This project includes the construction or installation of a pavilion, a concrete trail connection to Carr Park, bank
stabilization along Boyd Branch Creek which runs through the park, a playground, park lighting, picnic stations,
an irrigation system, new perimeter fencing, a drinking fountain, benches, and a dedicated parking lot at Kiddie
Carr Park.
PROJECT SCHEDULE:
JUSTIFICATION:
As identified in the adopted Parks Master Plan, the municipal park is the foundation of any solid parks and
recreation system. The City of Euless parks and recreation system provides residents and visitors with
significant personal, social, environmental, and economic benefits. The revitalization efforts that the Euless City
Council has focused on over the years has increased the sense of community pride. Kiddie Carr Park is a four
acre park located adjacent to Carr Park off Pauline. The current amenities at this park include the Parks
Department's in -ground tree farm, a greenhouse, and an outdoor basketball court. The park is located in a
section of town that needs something to stimulate community pride. The proposed project will continue the City
Council's revitalization efforts by creating an area that will serve both the passive and active leisure needs of the
residents in this area.
254
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 02,2013
Submitted By: RAY MCDONALD Date Completed:
Project Title: SOUTH EULESS PARK UPGRADES
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan calls for general upgrades and improvements in the overall quality of parks in
the City and to develop a high quality parks system that provides for all age and interest groups and enhances
the adjoining neighborhoods.
PROJECT DESCRIPTION:
Overall park enhancements and improvements that might include amenities such as new playground equipment,
park redevelopment, improved lighting, water features, upgrades to existing splashpad, expansion of existing
splashpad, and additional landscaping.
PROJECT SCHEDULE:
JUSTIFICATION:
This has been documented in the adopted Parks Master Plan.
265
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS PHASE II
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This enhancement was identified in the Needs Assessment and Identification section of the adopted Parks
Master Plan.
PROJECT DESCRIPTION:
This project is Phase II of the trail enhancements that continues implementation of park improvements identified
in the adopted Parks Master Plan which includes additional water fountains, additional benches, construction of
shaded seating areas along the trail, addition and/or installation of new exercise equipment along the trails,
picnic stations, and construction of additional pedestrian bridges in high water areas. Also identified, is the need
to address various areas along the trail that need to be converted from unpaved to paved trails.
PROJECT SCHEDULE:
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development
with an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community
as it assists not only in providing a safe means for non -vehicular travel, but also in providing an opportunity for a
variety of unstructured, low -impact recreational pursuits. The development and maintenance of the trails system
continued to receive significant support from the citizens as indicated in the responses to the needs assessment
survey conducted as a part of the Parks Master Plan update.
'-IN
256
OR
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: March 23,2004
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAIL ENHANCEMENTS VILLAGES OF BEAR CREEK
Project Type: PARK/RECREATION Sub -Type: TRAIL SYSTEM
Project Code: Priori C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project includes infrastructure improvements which were identified as a high priority in the adopted Parks
Master Plan.
PROJECT DESCRIPTION:
This project includes the redevelopment/redesign and improvement of the trail at the Villages of Bear Creek
Park to offer multiple uses for the citizens of Euless.
PROJECT SCHEDULE:
JUSTIFICATION:
Trail development and enhancement opportunities will be consistent with available land, funding and time
variables. This Master Plan recommendation will be part of a city-wide comprehensive trail enhancement
project. Due to the continual erosion of the existing trail, a redevelopment/redesign of the trail system at Villages
of Bear Creek will be a high priority.
257
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 13,2008
Submitted By: RAY MCDONALD Date Completed:
Project Title: TRAILWOOD PARK IMPROVEMENTS
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priority: C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This project is a continuation of the overall park improvement plan as identified in the Parks Master Plan.
PROJECT DESCRIPTION:
Trailwood Park is an eleven acre site that currently has a playground and a half -mile hike/bike trail. This project
includes the installation of a new pavilion, a parking lot, upgraded playground to meet American with Disabilities
Act standards, park lighting, new park signs, benches along the trail, and trail lighting.
PROJECT SCHEDULE:
JUSTIFICATION:
As identified in the adopted Parks Master Plan, the municipal park is the foundation of any solid parks and
recreation system. The City of Euless parks and recreation system provides the residents and visitors with
significant personal, social, environmental and economic benefits. The revitalization efforts that the Euless City
Council has focused on over the years has increased the sense of community pride. This proposed project will
continue those efforts by creating an area that will serve both the passive and active leisure needs of the
residents in the vicinity.
258
ME
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: April 03,2013
Submitted By: RAY MCDONALD Date Completed:
Project Title: WILSHIRE PARK UPGRADES
Project Type: PARK/RECREATION Sub -Type: PARK IMPROVEMENTS
Project Code: Priori : C
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The adopted Parks Master Plan calls for general upgrades and improvements in the overall quality of parks in
the city and to develop a high quality parks system that provides for all age and interest groups and enhances
the adjoining neighborhoods.
PROJECT DESCRIPTION:
Overall park enhancements and improvements that might include amenities such as new playground equipment,
park/trail lighting, pavilion, additional water features, parking improvements, additional landscaping and shade
structures for existing picnic pads.
PROJECT SCHEDULE:
JUSTIFICATION:
Documented in the adopted Parks Master Plan.
259
T H E C I T Y O F
ss
'-IN
260
M
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
DRAINAGE PROJECTS
DR9901
JSulphurBranch Phase II
08/01/99
$ 123,404
$ 120,128
$ 3,276
DR9902
JWindlea & WestCliff
08/01/99
$ 4,396
$ 1,159
$ 3,237
DR9904
Hurricane Creek
04/30/02
$ 257,500
$ 69,906
$ 187,594
DR0302
Flooding Mitigation
Cancelled
$ 250,000
$ -
$ 250,000
DR0303
Aransas Q Glenn
12/31/04
$ 250,000
$ 250000
$
DR0304
Live Oak Drainage
04/15/05
$ 218,000
$ 175,958
$ 42,042
DR0305
Sierra Drive Drainage
04/15/05
$ 40,738
$ 40,738
$ 0
DR0306
Flood Mitigation Plan FEMA
04/15/05
$ 32,000
$ 7,750
$ 24,250
DR0307
Simmons Drainage
04/15/05
$ 22,995
$ 22,995
$
DR0301
Fuller Branch Channel Stabilization
05/31/07
$ 279,136
$ 232,176
$ 46,960
DR0401
Channel Stabilization Tributary WFA
05/31/07
$ 437,462
$ 438,070
$ 608
DR0402
Drainage Project Stud
05/31/07
$ 60,000
$ 51,000
$ 9,000
DR0601
Little Bear Creek Study Update
04/25/08
$ 50,000
$ 49,000
$ 1,000
DR0602
McCormick Park
04/25/08
$ 250,000
$ 247,925
$ 2,075
DR0701
Eastcliff Drive/Greenbriar Drive Drainage Imp.
04/17/10
$ 340,000
$ 246,584
$ 93,416
DR0801
Rockwall Drive/Lamar Drive Drainage Imp.
04/17/10
$ 430,000
$ 272,554
$ 157,446
DR0901
Bear Creek Parkway Erosion Repair
02/17111
$ 530,000
$ 464,465
$ 65,535
DR0802
Hurricane Creek & Bridge at Marlene
Improvements
04/14/11
$ 378,500
$ 344,574
$ 33,926
DR0000
lBoyd Branch Improvements i
Cancelled
1 $ 10,000,000
$ -
$ 10,000,000
Drainage Projects - Prior Years
$ 13,954,131
$ 3,034982
$ 10,919,149
Drainage Projects - Current Year
$ -
$ -
$
Total Drainage Projects
$ 13,954,131
$ 3,034,982
$ 10,919,149
261
l''N
T H E C I T Y O F
ss
'-1
'-"N
262
`-,
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
STREET PROJECTS
PS9911
Overlay Pro acts
03/30/00
$ 294,687
$ 294.6
77 $
PS9912
Harwood -Main intersection
04/30/00
$ 1,126935
$ 1,077303
$ 49632
PS9907
Westpark Way - SH10 to SH183
09/30/00
$ 605,542
$ 479,915
$ 125,627
PS9902
Mid Cities Blvd.
05/02/02
$ 1.075074
$ 963635
$ 111,439
PS9910
Sidewalks
06/30/03
$ 200,000
$ 200,000
$
PS0001
FM 157 S Pipeline to SH10(Utility Relocation
04/30/04
$ 378,207
$ 371,318
$ 6,889
PS0003
Glade from Heritage to SH121
04/30/04
$ 1,866612
$ 1 866,612
$
PS0004
Glade Rd East-SH121toChampagne
04/30/04
$ 1210,014
$ 1162,009
1 $ 48.005
PS0201
Gateway Blvd - Southern Portion
04/30/04
$ 510,000
$ 473,817
$ 36,183
PS0301
Mid Cities Roadway Illumination
04/15/05
$ 160,000
$ 148,115
$ 11,885
PS0302
Dnftwood Pipeline Traffic Signal
04/15/05
$ 100,000
$ 68,665
$ 31,335
PS0303
Aransas/Harwood Traffic Signal
04/15/05
$ 120,000
$ 89,118
$ 30,882
PSO402
South Pipeline Road Bride
04/30/05
$ 28,208
$ 28,208
$
PS9908
Si nalization
05/31/06
$ 168,055
$ 168,055
$
PSO401
West Pipeline - Raider to City Limits
05/31/06
$ 223,000
$ 104,859
$ 118,141
PSO403
Raider Or - SH10 to South Pipeline
05/31/06
$ 330,000
$ 293,435
$ 36,565
PS0501
Ross Avenue/S.Main 300' W
05/31/06
$ 95,688
$ 95,638
$ 50
PS0502
Industnal Signal Timm
05/31/06
$ 50,000
$ 50,000
$
PS0503
Oveda -Harwood 157/Main
05/31/06
$ 137,000
$ 119,816
$ 17,184
PS0604
Ovena S Main SH10/S Pipeline
05/31/06
$ 137,000
$ 140,211
$ (3,211)
PS0601
Oveda -East Midway
05/31/07
$ 83,000
$ 73,550
$ 9,450
PS0602
Ovena -Midwa N Mam,/FM157
05/31/07
$ 105,000
$ 67,632
$ 37,368
PS0603
Oveda -Fuller Wiser, Midway/Harwood
05/31/07
$ 40,000
$ 28,695
$ 11,305
PS9906
Traffic Safe /Si nalization
05/31/08
$ 128,027
$ 127,939
$ 88
PSO404
South Pipeline Road Overlay
05/31/08
$ 114,750
$ 85,062
$ 29,688
PS0701
Oveda -Dicke Drive
05/31/08
$ 122,200
$ 48,435
$ 73.765.
PS0702
Overlay -East Huitt
05/31/08
$ 89,000
$ 64,895
$ 24.105
PS0703
Overlay -Huntington Drive
05/31/08
$ 69,500
$ 42,884
$ 26,616
PS0706
Gateway Blvd Screening Wall
05/31/08
$ 135,800
$ 138,862
$ (3,062)
PS0705
Signal Gateway Blvd Glade
1028108
$ 98,000
$ 98,000
$
PS0002
West Pipeline Road-Raider/H 10
12/01/08
$ 6,082621
1 $ 6,081,392
$ 1,229
PS0801
Overlay -North Main/Cullum Drive
12/31/08
$ 290,000
$ 211,130
$ 78,870
PS9905
Traffic Studies
05/30/09
$ 27,286
$ 27,197
$ 89
PS0704
Disability Access Stud
05/31/09
$ 30,000
$ 13,950
$ 16,050
PS0901
Ash/Denton/Fair Oaks Overlay
09/30/09
$ 320,000
$ 231,984
$ 88,016
PS0902
Vine Street Design
Cancelled
$ 100,000
$ -
$ 100,000
PS9903
HWY 183 Service Road
Cancelled
$ -
$ -
$
PS0304
Glade Road
04/16/10
$ 3,077.977
$ 2,905,205
$ 172,772
PS9909
FM157 North - SH183 to SH121
04/16/10
$ 267,519
$ 129,215
$ 138.304
PS0903
Mid Cities 0 Gateway & Baze Traffic Signals
04/16/10
$ 320,000
$ 250,702
$ 69,298
PS0802
Fuller -Wiser Connector
02/17/11
$ 495,000
$ 441,491
$ 53,509
PS1002
FY10 County Overlay - Wishire/Madene
05/17/11
$ 288,000
$ 200,890
$ 87,110
PS9901
North Main Street
05/31/12
$ 6 745,047
$ 6,698,149
$ 46,898
PS9904
Harwood Road
05/31/12
$ 5,770,211
$ 5,686,556
$ 63.655
PS1001
Baze Road
05/31/12
$ 1830000
$ 1558,401
$ 271599
PS1101
FY2011 County Overlay -Bear Creek
Drive/Lakewood Blvd/Ash Lane
05/31/12
$ 300,000
$ 265,887
$ 34,113
PS0605
South Pipeline Road Bridge Replacement
05/31/13
$ 157,000
$ 157,000
$
PS1003
Ash Lane -Aransas Drive to N. Main Street
05/31/13
$ 1,959,230
$ 1,597,270
$ 361,960
PS1201
FY2012 County Overlay -Aransas Dnve/Slaughter
Lane
05/31/13
$ 300,000
$ 228,759
$ 71.241
PS1301 Improvements
FY2013 38th CDBG-ADA/TAS Infrastructure
05/31/14
$ 450,000
$ 284,581
$ 165,419
PS1302
FY2013 County Overlay-Trailwood/Summit
Rid e/Wes ark/Baze
05/31/14
$ 280,000
$ 273,995
$ 6,005
PS1402
FY2014 County Overlay-Ector Drive/Midway
Drive/Troan Trail
05/31/14
$ 300 000
$ 300 000
$
PS1401 Improvements
FY2014 39th CDBG-ADA/TAS Infrastructure
0228/15
$ 300,000
$ 272,057
$ 27943
PS1303
Cullum Drive Improvements
03/31/15
$ 1,295738
$ 1,210748
$ 84,990
Street Projects - Prior Years
$ 40,786 928
$ 37,997,928
$ 2,789,000
PS1202 1ADAfTAS
Infrastructure Improvements
05/31/16
$ 463,800 1
$ 460,996
$ 2,804
PS1502 I FY2015
Street Overlay
05/31/16 1
$ 300,000 1
$ 217,182
$ 82,818
Street Projects - Current Year
$ 763,800
$ 678 178
$ 85,622
Total Street Projects $ 41,550,728 $ W,676,106 1 $ 2.874.622
263
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 27,2014
Submitted By: HAL CRANOR Date Completed: May 31, 2016
Project Title: ADA/TAS INFRASTRUCTURE IMPROVEMENTS
Project Type: STREETS Sub -Type: SIDEWALKS
Proiect Code: PS1202 Priority: A
COUNCIL AUTHORIZATION:
October 23, 2012: Authorized the City Manager to enter into a contract with Estrada Concrete, LLC in the
amount of $111,026 for the construction of ADA ramp improvements.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The Master Thoroughfare Plan includes and addresses sidewalks, crosswalks, and curb ramps for City streets.
PROJECT DESCRIPTION:
This project provides for the continued improvements to City infrastructure as required by Federal and State
mandated Americans with Disabilities Act/Texas Accessibility Standards ("ADA/TAS"). City sidewalks,
crosswalks, curb ramps, and other areas covered under both ADA and TAS requirements will be part of these
improvements.
PROJECT SCHEDULE:
JUSTIFICATION:
Many sidewalks, curb ramps, and other similar items are outdated and do not meet current ADA/TAS standards.
Updating accessibility on a continuing basis will help keep the City in compliance with government standards and
will address the growing needs of citizens with accessibility issues.
'11\
'-IN
264
PROJECT TITLE: ADA/TAS INFRASTRUCTURE IMPROVEMENTS PROJECT CODE: PS120
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
TOTAL ESTIMATED CAPITAL COST:
Improvements
$0
$0
$463
Subtotal: $0 Total Estimated Capital Cost $463,800
Maintenance Costs Funding Source:
Transfer from:
Car Rental Fund $300,000
Harwood Road - PS9904 $83,655
$0 Escrow Funds $80,145
Subtotal: $0
Transfer to:
Street CIP Fund Balance ($2,804)
Total Estimated Annual Cost $0 Total Funding $460,996
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Sidewalks/Curbs $380,145 $379,991 $154 100%
Utility Relocation $83,655 $81,005 $2,650 97%
ECT
$463,800 $460,996 $2,804
265
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2014
Submitted By: HAL CRANOR Date Completed: May 31, 2016
Project Title: FY2015 STREET OVERLAY
Project Type: STREET Sub -Type: OVERLAY
Proiect Code: PS1502 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of edge milling, asphalt overlay, and restriping on various streets prioritized by their
pavement condition index.
PROJECT SCHEDULE:
Begin Construction: June 2015
Construction Complete: May 2016
JUSTIFICATION:
The existing asphalt pavement is deteriorating. The asphalt overlay will provide an improved riding surface, will
extend the life of the roadways, and will enhance the appearance of the streets.
RIO
266
Ow
PROJECT TITLE: FY2015 STREET OVERLAY
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
PROJECT CODE: PS1502
TOTAL ESTIMATED CAPITAL COST:
$0
$0 Total Estimated I
Funding Source:
Transfer from:
Car Rental Fund
Cost
$300
$300
$300, 000 1
Transfer to:
Street CIP Fund Balance ($82,818)
Total Estimated Annual Cost $0 Total Funding $217,182
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Construction $300,000 $217,182 $82,818 72%
$300,000 $217,182 $82,818
72%
267
Ro
T H E C I T Y O F
268
OR
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WASTEWATER PROJECTS
WW9902
Impact Fee Stud
09/30/99
$ 13,000
$ 12,238
$ 762
WW9903
Misc Sewer Rehab FY99
09/30/99
$ 50,000
$ 12,987
$ 37,013
WW9904
Hydraulic Analsis
06/30/00
$ 27,000
$ 27,000
$
WW9901
CDBG B/98-UC-48-0001/B95-22-50
08/19/00
$ 150,000
$ 72,927
$ 77,073
WW0003
TRA Debt Payment
05/31/01
$ 822,037
$ 822,037
$
WW0001
CDBG B/99-UC-48-0001
09/30/01
$ 150,000
$ 121,682
$ 28,318
W010101
CDBG B00-UC480001-2250
02/20/02
$ 251,485
$ 247,790
$ 3,695
WWO102
Manhole Rehab. Program
03/31/03
$ 250,000
$ 184,520
$ 65480
WW0201
CDBG - B01-UC-48-0001-22-50
03/31/03
$ 237,086
$ 172,948
$ 64,138
WW0202
Line Replacement -Dunawa
02/28/05
$ 140,000
$ 139955
$ 45
WW0203
Line Replacement - E. Alexander
02/28/05
$ 20,000
$ 20,000
$
WW0204
Line Replacement - Paula Lane
02/28/05
$ 79,000
$ 79,000
$
WWO103
Line replacement-S. Pi eline,Heather-Vine
04/15/05
$ 489,759
$ 464,504
$ 25,255
WW0205
Line Replacement - MidwaPark
04/30/05
$ 366,000
$ 318,149
$ 47,851
WW0401
CDBG B03-UC-48-0001-22-50
04/30/05
$ 217,000
$ 161,170
$ 55,830
WVV0301
CDBG B02-UC-48-0001-22-50
07/26/05
$ 271,455
$ 271,454
$ 1
WW0302
Inflow & Infiltration
Cancelled
$ 200,000
$ -
$ 200,000
WW0303
Line Replacement, Canyon Ride
08/31/06
$ 196,200
$ 173,516
$ 22,684
WW0304
Line Replacement, Sagebrush
08/31/06
$ 160,900
$ 136,470
$ 24,430
VWV0305
Line Replacement, Short
08/31/06
$ 251,400
$ 219,932
$ 31,468
WW0306
Line Replacement, E. Fuller
08/31/06
$ 231,372
$ 180,089
$ 51,283
WW0501
Line Replacement, Pebble Creek
08/31/06
$ 172,600
$ 145,655
$ 26,945
WW0604
Line Replacement, CDBG-Oakwood Terrace
05/31/07
$ 293,723 1
$ 232,274
$ 61,449
WW0402
Line Replacement, Carr Park/SH10
05/31/08
$ 588,000
$ 528,302
$ 59,698
WW0403
Line Replacement, Ector Drive
05/31/08
$ 373,000
$ 328,309
$ 44,691
WW0601
Line Replacement, Cedar Hills Estate
05/31/08
$ 319,000
$ 200,201
$ 118,799
WW0602
Line Replacement, Ector Drive
05/31/08
$ 425,000
$ 285,758
$ 139,242
WW0603
Little Bear Creek Collection Line
05/31/08
$ 575,000
$ 464,293
$ 110,707
WW0701
Line Replacement, McCormick & Co her
02/05/09
$ 243,000
$ 194,254
$ 48,746
WW0702
Line Replacement, Amett Addition
02/05/09
$ 313,322
$ 229,006
$ 84,316
WW0703
Line Replacement, Jean Lane
02/05/09
$ 111,000
$ 70,603
$ 40,397
WW0704
Line Replacement, W. Fuller
02/05/09
$ 132,000
$ 82,708
$ 49,292
WW0902
Line Replacement, West Mills Drive-34th CDBG
04/16/10
$ 46,855
$ 46,855
$ -
WW0802
Line Replacement South Mills Drive CDBG-R
11/01/10
$ 253,710
$ 165,867
$ 87,843
WWO901
Line Replacement Woodridge Circle/Koen Lane
11/01/10
$ 407,000
$ 309,410
$ 97,590
WWO801
Line Replacement Fayette Drive
04/14/11
$ 357,000
$ 325,676
$ 31,324
WW1001
Line Re - W Alexander Ln/Norman Dr/Franklin Dr
05/31/12
$ 420,000 1
$ 331,614
$ 88,386
WW1101
Line Re -Ba less/Pauline/Jones CDBG
05/31/12
$ 350,000
$ 208,903
$ 141,097
WW1103
Line Re - Bayless/Pauline/Jones Outfall
05/31/12
$ 57,000
$ 37,544
$ 19,456
WW1202
Line Re - Collin Drive 37th CDBG
05/31/12
$ 300,000
$ 231,173
$ 68,827
VWV1102
Line Re - E Huit Lane/Ascot Drive/Dunaway Drive
05/31/13
$ 560,000
$ 468,932
$ 91,068
WW1201
Line Re -Blanco/Aransas/Crane
05/31/13
$ 327,000
$ 284,321
$ 42,679
WW1301
Line Re - Ross/Slaughter/East & West Huitt
05/31/14
$ 670,000
$ 566,640
I $ 103,360
WW1203
SH183 Phase I Wastewater Relocation
10/31/14
$ 372,243
$ 372,243
$
WVV1401
Line Re - Denton Drive
06/01/15
$ 629,000
$ 506,466
$ 122,534
WastewaterPro"ects - Prior Years
$ 12,869,147
$ 10,455,375
$ 2,413,772
WW1501
ILine Re - Crane Drive
05/31/16
$ 264,823
$ 264,823
$ -
WW1502
Line Re - Town Creek Drive
05/31/16
$ 440,665
$ 395,896
$ 44,769
Wastewater Projects- CurrentYear
Is 705.488
$ 660,719
$ 44,769
Total Wastewater Projects $ 13,574,635 $ 11,116,094 $ 2,458,541
269
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 26,2014
Submitted By: HAL CRANOR Date Completed: May 31, 2016
Project Title: LINE REPLACEMENT -CRANE DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Project Code: WW1501 Priority: A
COUNCIL AUTHORIZATION:
December 9, 2014: Authorized the City Manager to execute an Engineering Design contract with Elliott and
Hughes, Inc. for the design of the FY2015 Sanitary Sewer Rehabilitation Project. The estimated expenditure is
$74,513 and will be paid from WW1501 and WW1502.
November 10, 2015: Awarded Bid No. 008-15 for a construction contract to William J. Schultz, Inc. dba Circle C
Construction for the replacement of sanitary sewer mains in portions of the Westwood Village Addition and the
Green Hills Park Addition and authorized the City Manager to enter into a contract including add alternate #1 if
required. The estimated expenditure is $577,357 and will be paid from WW1501, WW1502 and WW0002.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The project
is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of wastewater mains between Crane Drive and Donley Drive north of
Harwood Road to the upper end of the main north of Glenn Drive.
PROJECT SCHEDULE:
Began Construction: January 2016
Construction Complete: May 2016
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
W
270
PROJECT TITLE: LINE REPLACEMENT -CRANE DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
$0
$0
$0
$0
PROJECT CODE: WW1501
TOTAL ESTIMATED CAPITAL COST:
Engineering
Total Estimated Capital 1
Funding Source:
Transfer from:
W/WW Operating Fund
WIWW CIP Fund Balance
$74, 513
$190,310
$264,
$185
$79
Total Estimated Annual Cost
$01
Total Fundina
$264,823
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (- +)
% EXPENDED
Engineering
$74,513 $30,422
$44,091
41%
Construction
$190,310 $234,401
($44,091)
123%
ECT
$264,823 $264,823 $0 100%
271
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 26,2014
Submitted By: HAL CRANOR Date Completed: May 31, 2016
Project Title: LINE REPLACEMENT -TOWN CREEK DRIVE
Project Type: WASTEWATER Sub -Type: MAIN REPLACEMENT
Proiect Code: WWI 502 Priority: A
COUNCIL AUTHORIZATION:
December 9, 2014: Authorized the City Manager to execute an Engineering Design contract with Elliott and
Hughes, Inc. for the design of the FY2015 Sanitary Sewer Rehabilitation Project. The estimated expenditure is
$74,513 and will be paid from WWI 501 and WWI 502.
November 10, 2015: Awarded Bid No. 008-15 for a construction contract to William J. Schultz, Inc. dba Circle C
Construction for the replacement of sanitary sewer mains in portions of the Westwood Village Addition and the
Green Hills Park Addition and authorized the City Manager to enter into a contract including add alternate #1 if
required. The estimated expenditure is $577,357 and will be paid from WW1501, WW1502 and WW0002.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The wastewater mains included in this project are part of the City's Wastewater System Master Plan. The project
is part of the systematic replacement of wastewater mains using a worst first approach.
PROJECT DESCRIPTION:
The project consists of the replacement of the following wastewater mains:
1. Town Creek Drive from Salem Drive to Carter Drive,
2. Carter Drive south of Town Creek Drive,
3. Westport Circle,
4. Newport Circle,
5. Asbury Circle, and
5. the outfall between Westport Circle and Newport Circle.
PROJECT SCHEDULE:
Began Construction: January 2016
Construction Complete: May 2016
JUSTIFICATION:
Many wastewater mains throughout the City are 40+ years old. Most of these lines are clay tile and are
susceptible to ground movement, pulled joints, root infiltration, and deterioration from hydrogen sulfide gas.
Many are substandard in size and have inflow/infiltration problems. This project is part of the systematic
replacement of wastewater mains using a worst first approach to reduce maintenance costs and customer
problems.
"�
272
L
PROJECT TITLE: LINE REPLACEMENT -TOWN CREEK DRIVE
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
Subtotal:
PROJECT CODE: WW1502
TOTAL ESTIMATED CAPITAL COST:
Engineering
Construction
$0
$0
$01 Total Estimated Caoital Cost
Funding Source:
Transfer from:
W/WW Operating Fund
W/WW CIP Fund Balance
$0
$0
$57,000
$383,665
$440,
$437,
$3,
Transfer to:
W/WW CIP Fund Balance
($44,769)
Total Estimated Annual Cost
$0
Total Funding
$395,896
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (- +)
% EXPENDED
Engineering
$57,000 $44,191
$12,809
78%
Construction
$383,665 $351,705
$31,961
92%
TOTAL
$440,665 $395,896 $44,769
90%
273
T H E C I T Y O
'1
274
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
WATER PROJECTS
WT9903
Master Plan
08/30/99
$ 42,000
$ 5,445
$ 36,555
WT9904
Well Repairs
09/30/99
$ 66,921
$ 66,921
$
WT9907
Impact Fee Stud
09/30/99
$ 13,000
$ 12,238
$ 752
WT9911
Water Distribution - Master Plan
09/30/99
$ 25,600
$ 24,000
$ 1,600
WT9901
Meter Change Out Program
10/30/99
$ 101,917
$ 98,365
$ 3,552
WT0002
E merqencv Repair - Hw10
11/30/99
$ 15,450
$ 14,214
$ 1,236
WT9906
Hwy 10 Water Line
01/30/00
$ 150,000
$ 138,883
$ 11,117
Wl-0006
Central Drive Water Mains
03/31/00
$ 92,814
$ 90,742
$ 2,072
WT9905
Misc Water Rehab
06/30/00
$ 50,000
$ 43,749
$ 6,251
WT0004
Water Line Milam - Ector/Midwa
06/30/00
$ 18,248
$ 13,743
$ 4,505
WT0102
SCADA Upgrade
04/09/01
$ 93,400
$ 93,400
$ -
WT0003
Waterline Replacement - Aransas
06/30/01
$ 12,057
$ 7,089
$ 4,968
WT0005
Waterline Replacement - Milam- Denton/Mid
04/30/02
$ 26,988
$ 26,988
$ -
WT9910
Water Line for Elevated Tank
05/31/02
$ 1,608,386
$ 1,201,698
$ 406,688
WT9909
2MG Water Tank
03/31/03
$ 2,430,881
$ 2,289,571
$ 141,310
WT0103
Fire Hydrant Replacement Program
03/31/03
$ 50,000
$ 49,626
$ 374
WT9908
Mid Cities Blvd. 12" Line
04/30/04
$ 342,080
$ 313,354
$ 28,726
WT0401
Line Replacement, West Pipeline Main
05/31/06
$ 1,215,663
$ 1,215.663
$
WT0403
Waterline Replacement - Fairlawn Court
Cancelled
$ 35,000
$ -
$ 35,000
WT0404
Waterline Replacement - Atkerson Lane
Cancelled
$ 104,000
$ -
$ 104,000
WT0405
Line Replacement, West Ash Lane
08131t06
$ 30,000
$ 11,626
$ 18,374
WT0406
Line Replacement, West orttNew ort/Asbu
08/31/06
$ 67,000
$ 9,866
$ 57,134
WT0502
FY'2005 CDBG
08/31/06
$ 69,300
$ 29,549
$ 39,751
WT0503
Line Replacement, S. Atkerson Lane
08/31/06
$ 79,000
$ 51,294
$ 27,706
WT0504
Line Replacement, Blanco Drive
08/31/06
$ 112,620
$ 112,620
$
WT0505
Line Replacement, Henslee
08/31/06
$ 183,000
$ 123,859
$ 59,141
WT0506 ILine
Replacement, Vemon/Slau hter
08/31/06
$ 161,000
$ 113,052
$ 47,948
WT9902
Tank Painting
05/31/07
$ 1,317,763
$ 957,542
$ 360,221
WT0501
System Security Upgrade
05/31/08
$ 40,000
$ 28,319
$ 11,681
WT0601
Wtr Sys Security Perimeter Fence Upgrade
05/31/08
$ 75,000
$ 49,567
$ 25,433
WT0602
Line Replacement, Cannon Drive
05/31/08
$ 250,000
$ 223,055
$ 26,945
WT0701
Line Replacement, Canyon Ride
05/31/08
$ 116,000
$ 78,136
$ 37,864
WT0702
CDBG FY07 - 32nd Oakwood Terrace
05/31/08
$ 334,481
$ 296,223
$ 38,258
WT0802
CDBG-33rd Oakwood Terrace -Simmons
12/31/08
Is 451,639
$ 384,173
$ 67,466
WTO402
Water & Wastewater Impact Fee Update
05/31/09
$ 30,000
$ 17,729
$ 12,271
WT0801
Line Replacement, Signet/Mesa
05/31/09
$ 255,000
$ 218,663
$ 36,337
WT0201
Well Rehabilitation/Disinfection
04/17/10
$ 600,000
$ 522,308
$ 77,692
WT0202
Reclaimed Water Main
05/31/13
$ 1,750,000
$ 1,606,337
$ 143,663
WT1202
Standpipe Storage Tank & Building Demolition
05/31113
$ 134,640
$ 70,089
$ 64,551
WT1203
Water &Wastewater Impact Fee Update
05/31/13
$ 34,575
$ 34,575
$ -
WT1401
JEI Camino Real
02/28/15
$ 460,000
$ 420,462
$ 39,538
Water Projects - Prior Years
$ 13,045,423
$ 11 064,733
$ 1,980,690
WT0901
Trinity River Authority Water Payment -Impact
05/31/16
$ 750,000
$ 750,000
1 $ -
WT1201
Reclaimed Water Line Extension Phase 1
05/31/16
$ 3,239,452
$ 3,239,452
$ -
WT1501
244nch Valve Replacement
05/31/16
$ 180,000
$ 131,370
$ 48,630
WT1601
Line Re - Donley Drive/Shelmar Drive
05/31/16
$ 212,000
$ 152,990
$ 59,010
Water projects- Current Year
$ 4,381,452
$ 4,273,812
$ 107,640
Total Water Projects
$ 17,425,875
$ 15,338,545
$ 2,088,330
275
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: May 31,2008
Submitted By: RON YOUNG Date Completed: May 31, 2016
Project Title: TRINITY RIVER AUTHORITY WATER PAYMENT -IMPACT
Project Type: WATER Sub -Type: IMPACT FEE
Project Code: WT0901 Priority: A
COUNCIL AUTHORIZATION:
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
Based on a review by Birkhoff, Hendricks, and Conway of the water and wastewater impact fees, it was
determined that a substantial portion of the water impact fee is attributed to Trinity River Authority ("TRA") capital
projects. Therefore, these fees should be used to pay a portion of the annual TRA expense, as these funds are
directly attributed to the expansion of TRA. Based on the available fund balance, a systematic drawdown over a
ten year period has been developed.
PROJECT SCHEDULE:
Annual payment FY2009: $100,000
Annual payments FY2010-2013: $150,000
Annual payment FY2014: $50,000
JUSTIFICATION:
The expansion at TRA provides additional capacity and it was determined through the water impact fee study that
these funds could be used to pay a portion of TRA water payments. It was determined a ten year drawdown
would approximate the Capital Improvement Plan Review time frame, as well as provide for a systematic
drawdown that would not impact the annual budget.
.*N
276
PROJECT TITLE: TRINITY RIVER AUTHORITY WATER PAYMENT -IMPACT PROJECT CODE: WT0901
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
$0
($50,000)
TOTAL ESTIMATED CAPITAL COST:
TRA Water Pmts FY2009-2013 $700,000
TRA Water Payments FY2014 $50,000
Subtotal: ($50,000) Total Estimated Capital Cost
Maintenance Costs Funding Source:
Transfer from:
WT Impact Fee Fund Balance
I Subtotal:
$750,0001
$750,0001
Total Estimated Annual Cost ($50,0001 Total Funding $750,000
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (- +) % EXPENDED
Water - TRA Service $750,000 $750,000 $0 100%
AL PROJECT $750,000 $750,000 $0 100%
277
City of Euless
Capital Project Request
--1
Department: PUBLIC WORKS Date Prepared: May 17, 2011
Submitted By: CHRIS BARKER Date Completed: May 31, 2016
Project Title: RECLAIMED WATER LINE EXTENSION PHASE I
Project Type: WATER Sub -Type: RECLAIMED WATER SYSTEM
Project CODE: WT1201 Priority: A
COUNCIL AUTHORIZATION:
January 22, 2013: Authorized the City Manager to execute an engineering design contract with Alan Plummer and
Associates, Inc. (APAI) with an amount not to exceed $294,678 for the design of a reclaimed water system line
extension project.
May 14, 2013: Authorized the City Manager to seek bids for Phase I of the extended reclaimed water distribution system.
June 25, 2013: Authorized the City Manager to execute a construction contract to Crescent Constructors, Inc. for the
Reclaimed Water Delivery System Extension, Phase I. The estimated expenditure is $3,110,758 which includes a
contingency of $150,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The reclaimed water line extension is a continuation of the City's Reclaimed Water Utility System. The feasibility study
completed in FY2012 recommends breaking the project into six phases with the first phase beginning in FY2013.
PROJECT DESCRIPTION:
The overall project will extend the City's Reclaimed Water Utility System from a point near the northeast corner of Bear Creek
Parkway and Midway Drive, northward to a point near Mid Cities Boulevard. Extension of this system will ultimately provide
reclaimed water service to several multi -family properties from Harwood Road to Mid Cities Boulevard as well as the City's
Bear Creek Park. Additional system expansion would be possible in the future.
PROJECT SCHEDULE:
Feasibility Study Complete: July 2012
Phase I Construction Began: July 2013
Phase I Construction Complete: September 2014
JUSTIFICATION:
Construction of the project will provide a non -potable water source for irrigation which will offset future potable water purchases
by the City and will serve to responsibly conserve potable water resources for the City and the region.
278
L-
NIP
PROJECT TITLE: RECLAIMED WA TEK LINE EX I EN510N F'HASt I PKUJtG I GUM: -VV 11ZU1
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Engineering $373,622
Direct Operatinq Cost Construction $2,825,809
Personnel: Full Time Sidewalk/Curb Construction $17,988
Part Time Landscaping $22,033
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
Avq. Annual Debt Service
$275,000
Total Estimated Capital Cost $3,239,452
FUNDING SOURCE:
W/WW CIP Fund Balance $561,334
W/WW Operating Fund $1,000,000
Revenue Bond Issue $1,500,000
Reclaimed Water - W70202 $143,663
Escrow Funds - ES0298 & ES1301 $34,455
{Subtotal: $0
(Total Estimated Annual Cost $275,0001Total Funding $3,239,452 I
f CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET (-+)
% EXPENDED
Engineering
$373,622
$373,622
$0
100%
Construction
$2,825,809
$2,825,809
$0
100%
Landscaping
$17,988
$17,988
$0
100%
Sidewalk/Curb Construction
$22,033
$22,033
$0
100%
*WTI 201 has been split into two projects - see WTI 201 and WTI 212. Future phases shown in unfunded.
FY2015 Total Project $6,650,000
Phase II (WT1212) ($3,129,300)
Budget Reduction ($281,248)
Phase I (WT1201) $3,239,452
AL PROJECT
$3,239,452 $3
279
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: April 08,2014
Submitted By: HAL CRANOR Date Completed: May 31, 2016
Project Title: VALVE REPLACEMENT -CINNAMON, ANICE, FULLER -WISER
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Proiect Code: WT1501 Priority: A
COUNCIL AUTHORIZATION:
May 26, 2015: Awarded Bid No. 004-15 for a construction contract to Atkins Bros. Equipment Co., Inc. for the FY
2015 Gate Valve Replacement Project and authorized the City Manager to enter into a contract with Atkins Bros.
Equipment Co., Inc. The estimated expenditure is $141,800.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
The water mains included in this project are part of the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project will replace three 24-inch gate valves on the 24-inch main line running between North Main Street
and Fuller -Wiser Road.
PROJECT SCHEDULE:
Begin Construction: July 2015
Construction Complete: November 2015
JUSTIFICATION:
Old and deteriorated water valves prevent water lines from being isolated in the event of a line break. Not being
able to isolate as small a segment as possible during a line break increases the labor required to isolate the line,
as well as the number of residents and fire hydrants that would be affected by a line break. Systematic annual
replacement of old deteriorated water valves will increase efficiency, reduce maintenance costs, and ensure
maximum fire protection and water service availability.
--IN
280
PROJECT TITLE: VALVE REPLACEMENT -CINNAMON, AN ICE, FULLER -WISER PROJECT CODE: M150
INET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
I Subtotal:
TOTAL ESTIMATED CAPITAL COST:
Engineering
$0 Total Estimated Ca it
Funding Source:
Transfer from:
W/WW Operating Fund
$20, 000
$160, 000
$180, 000 1
$220,
Subtotal: $0 Transfer to:
W/WW CIP Fund Balance ($40,000)
W/WW CIP Fund Balance ($48,630)
Total Estimated Annual Cost $0 Total Funding $131,370
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Engineering $20,000 $100 $19,900 1%
Construction $160,000 $131,270 $28,730 82%
$180,000 $131,370 $48,630
73%
281
City of Euless
Capital Project Request
Department: PUBLIC WORKS Date Prepared: March 11,2015
Submitted By: HAL CRANOR Date Completed: May 31, 2016
Project Title: LINE REPLACEMENT- DONLEY DRIVE/SHELMAR DRIVE
Project Type: WATER Sub -Type: MAIN REPLACEMENT
Proiect Code: WT1601 Priority: A
COUNCIL AUTHORIZATION:
April 26, 2016: Awarded a construction contract for the FY2016 Waterline Replacement Project to Murphy
Pipeline Contractors, Inc. through the Education Service Center -Region 19 Purchasing Allied States Cooperative.
The estimated expenditure $150,000.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
This water main is included in the City's Water System Master Plan.
PROJECT DESCRIPTION:
The project consists of the replacement of 1,212 feet of 6" cast iron main with an 8" PVC main along Donley
Drive from Glen Drive to Shelmar Drive and along Shelmar Drive from Donley Drive (E) to Donley Drive (W).
PROJECT SCHEDULE:
Began Construction: May 2016
Construction Complete: May 2016
JUSTIFICATION:
Old and deteriorated water mains increase the City's maintenance costs. Substandard size water mains provide
inadequate flow of water. Systematic annual replacement of old deteriorated or substandard size water mains
will reduce maintenance costs.
_ 1
282
PROJECT TITLE: LINE REPLACEMENT- DONLEY DRIVE/SHELMAR DRIVE PROJECT CODE: WT1601
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost Engineering $25,000
Personnel: Full Time Construction $187,000
Part Time $0
Total Salary $0
Purchase of Services
Materials & Supplies
Utilities
$0
Subtotal: $0 Total Estimated Capital Cost $212,000
Maintenance Costs Funding Source:
Transfer from:
W/WW Operating Fund $212,000
Subtotal:
$U
Transfer to:
W/WW CIP Fund Balance
($59,010)
Total Estimated Annual Cost
$0
Total Funding
$152,990
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET EXPENDED
BUDGET (-+)
% EXPENDED
Engineering
$25,000 $0
$25,000
0%
Construction
$187,000 $152,990
$34,010
82%
TOTAL PROJECT $212,000 $152,990 $59,010 72% I
283
w
T H E C I T Y O f
ss
284
M
CAPITAL IMPROVEMENTS PROGRAM
COMPLETED PROJECTS SUMMARY
Project
Number
Project Description
Total Project (Over) Under
Date Completed Total Budget Costs Budget
OTHER PROJECTS
AC9901
Athletic Complex Phase II
06/30/02
$ 123,654
$ 75,047
$ 48,607
ACO202
Athletic Complex Phase Ill
05/31/06
$ 1,252,221
$ 1,251,915
$ 306
AC1001
Texas Star Sports Complex Lighting Improvements
05/31/12
$ 504,200
$ 475,246
$ 28,954
ED0102
Bell Ranch Terrace
Cancelled
$ 200,000
$ -
$ 200,000
FM0209
Midway Recreation Upgrade
06/30/02
$ 557,125
$ 557,125
$ -
FM0101
Building D
09/30/02
$ 930.610
$ 930,608
$ 2
FM0308
Building A Remodel
05/31/07
$ 1,663,238
$ 1,651,325
$ 11,913
FM0309
Fire Station #3
05/31/07
$ 2,286,798
$ 2,286,229
$ 569
FM0601
Public Works Facility
05/31/08
$ 2,210,956
$ 2,213,507
$ 2,551
FMO802
Senior Citizen Center Design
cancelled
$ 250,000
$ -
$ 250,000
FM0804
Library -Shell Expansion
12/31/08
$ 307,034
$ 305,664
$ 1,370
FMO803
Midway Recreation Improvements
03/31/09
$ 293,500
$ 75,976
$ 217,524
FMO504
Building "B" Remodel
05/31/09
$ 1,322,490
$ 1,315,697
$ 6,793
FMO801
TX Star Golf Course & Conference Ctr Expand
05/31/09
$ 3,630,079
$ 3,630,079
$ -
GR1401
Golf Course Upgrades
09/30/14
$ 587,000
$ 581,296
$ 5,704
PD9901
Police and Courts Facility
05/31/15
$ 11,718,304
$ 11,718,304
$ -
PR0015
Purchase of Dallas Stars Center
05/31/00
$ 10,327,978
$ 10,327,978
$ -
PR0016
Wilshire Park Improvements
06/30/02
$ 150,000
$ 149,926
$ 74
PR0110
Sloe Protection/Screening Wall
03/31/03
$ 1,275,203
$ 1,273,923
$ 1,280
PR0409
Parking Improvements, Simmons
07/29/04
$ 6,960
$ 6,960
$ -
PR0410
Parking Improvements, Villages Bear Creek
07/29/04
$ 33,666
$ 33,666
$ -
PR0302
Bob Eden Parkin
04/30/05
$ 75,000
$ 74,854
$ 146
PR0303
Youth Ballpark
04/30/05
$ 600,000
$ 600,000
$ -
PR9901
Hike/Bike Trail
04/30/05
$ 237,714
$ 237,714
$
PR9902
Senior Citizen Remodel
04/30/05
$ 16,130
$ 16,130
$ -
PR0407
Parking Improvements, Midway
Cancelled
$ 11,000
$ -
$ 11,000
PR0408
Parking Improvements, S. Euless Park
05/31/06
$ 55,000
$ 20,991
$ 34,009
PR0411
Preserve at McCormick Park
05/31/06
$ 1,168,427
$ 1,168,427
$ -
PR0412
Splash Pool
05/31/06
$ 125,000
$ 124,477
$ 523
PR9903-
PR9918
Various EDC Park Projects
09/30/06
$ 259,566
$ 248,891
$ 10,675
PR0602
Mid Cities Landscaping
05/31/09
$ 40,000
$ 33,199
$ 6,801
PR0719
Midway Park Trail
05/31/09
$ 210,000
$ 190,473
$ 19,527
PR0601
Park Amenities Upgrade
04/17/10
$ 150,000
$ 145,316
$ 4,684
PRO901
Trail Enhancements - Bob Eden Park
04/17/10
$ 135,000
$ 101,673
$ 33,327
PRO902
Senior Citizen Center at Midway Park
05/31/11
$ 4,763 661
$ 3,888,892
$ 874,769
PR0907
Euless Family Life Center Phase 1
05/31/11
$ 2,105,000
$ 2,099,281
$ 5,719
PR9922
Teas Remodel
11/30/01
$ 430,000
$ 455885
$ 25,885
PR9927
Park Improvements - Texas Star
09/30/01
$ 1,036,500
$ 1,025 298
$ 11,202
PR1201
Euless Family Life CenterA uatics
09/30/14
$ 7,504,972
$ 7,319,299
$ 185,673
SS9901
Fire Station II
03/30/00
$ 49,688
$ 49,688
$ -
SS9919
Fire Station #3 - Structural Repairs
03/30/00
$ 30,000
$ 17,344
$ 12,656
SS9902
Library Books
08/15/00
$ 3,302
$ 3,302
$ -
SS0010
Former Fire Station #2
06/30/02
$ 599,600
$ 595,257
$ 4,343
SS0113
Park Building
06/30/02
$ 1,492,400
$ 1,492,100
$ 300
OtherPro"ects- PriorYears
$ 60,728.976
$ 58,768,962
$ 1,960,014
AC1201
ITexas Star Sports Complex Phase IV
05/31/16
$ 645,687
$ 575,653
$ 70,034
CM1508
Icar Rental contingency
05/31/16
$ 700,000
$ 700,000
$ -
Other Pro'ects- Current Year
Is 1.345.687
1 $ 1,275,653
1 $ 70,034
Total Other Projects
1 $ 62,074,663
1 $ 60,044,615
1 $ 2,030,048
285
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 01,2010
Submitted By: RAY MCDONALD Date Completed: May 31, 2016
Project Title: TEXAS STAR SPORTS COMPLEX PHASE IV
Project Type: PARK/RECREATION Sub -Type: TSSC IMPROVEMENTS
Project Code: AC1201 Priority: A
COUNCIL AUTHORIZATION:
January 24, 2012: Authorized the City Manager to negotiate and execute a Field Use and Lease Agreement with
Sting Soccer Group, LP and Texas Titans FC, LLC, (collectively "Sting") for the use of a portion of the property
located at 1501 South Pipeline Road Euless, Texas 76040 (The Parks at Texas Star Sports Complex) as a
practice and training facility for youth soccer. In consideration of its use of the property, Sting will construct
certain facility improvements on the property.
August 28, 2012: Ratified the Euless Development Corporation action taken on August 28, 2012, approving Bid
No. 015-12, to award a contract to Reliable Paving, Inc. in the amount of $494,823 for parking improvements at
the Parks at Texas Star.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
Texas Star Sports Complex Phase IV incorporates the addition of a concession and rest room facility and parking
for 200 vehicles. This addition will ensure that the Texas Star Sports Complex is positioned as a premier facility
that serves the athletic and recreational programming needs of the City.
PROJECT DESCRIPTION:
The project scope includes the design and construction of a parking lot and a concession/rest room facility at the
Texas Star Sports Complex. Related support facilities such as electrical service, lighting, fencing, etc. are also
included in the scope of the project.
PROJECT SCHEDULE:
Began Construction: September 2012
Construction Complete: December 2013
JUSTIFICATION:
Since the completion of Phase III at the Texas Star Sports Complex, the facility has been severely under served
in parking, rest room facilities, and concessions. With the completion of Phase IV, the Texas Star Sports
Complex will be positioned to serve the ever-increasing athletic needs of the community and spur economic
opportunities for the City.
W
'-,*N
286
PROJECT TITLE: TEXAS STAR SPORTS COMPLEX PHASE IV
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
PROJECT CODE: AC1201
TOTAL ESTIMATED CAPITAL COST:
Parking Lot
$0 Lights/Electrical
$0 Material storage bin
$0 Entry walk
$0 Fencing
$7,500 Concession equipment
$3,500 Retaining Wall
5% Contingency
$11,000 Total Estimated Capital Cost
Funding Source:
$0 Transfer from:
EDC CIP Fund Balance
$412,000
$90,000
$15,600
$35,000
$18,000
$16,000
$18,000
$41, 087
$645,6871
$645,6871
Subtotal:
$0
Transfer to:
EDC CIP Fund Balance
($70,034)
Total Estimated Annual Cost
$11,000
Total Funding
$575,653
CURRENT STATUS
OVER/UNDER
PHASE/FUNDING SOURCE
BUDGET
EXPENDED
BUDGET(-+)
% EXPENDED
Parking Improvements
$489,561
$489,561
$0
100%
Lighting
$33,000
$33,000
$0
100%
Remodel / Improvements
$8,030
$8,030
$0
100%
Land Betterments
$45,000
$26,717
$18,283
59%
Construction
$1,585
$1,584
$1
100%
Buildings*
$0
$0
$0
0%
Contingencies
$12,111
$0
$12,111
0%
Special Services
$56,400
$16,760
$39,640
30%
*Concession/Restroom not constructed.
*Contributed capital removed.
TOTAL PROJECT
$645,687
$575,653
$70,034
89%
287
City of Euless
Capital Project Request
Department: CITY MANAGER Date Prepared: July 22,2014
Submitted By: GARY MCKAMIE Date Completed: May 31, 2016
Project Title: CAR RENTAL CONTINGENCY
Project Type: MISCELLANEOUS Sub -Type: DEVELOPMENT
Project Code: CM1508 Priority: A
COUNCIL AUTHORIZATION:
August 25, 2015: Approved Chapter 380 agreement by and between the City of Euless and CADG 901 Airport
Freeway, LLC and authorized the City Manager to execute an agreement. The agreement provides for an
economic development grant to be paid upon demolition of all buildings and structures and clearing of debris to
prepare the site for new development.
RELATIONSHIP TO OTHER PROJECTS AND/OR MASTER PLAN:
PROJECT DESCRIPTION:
To provide funding for development opportunities that arise throughout the year.
PROJECT SCHEDULE:
JUSTIFICATION:
This project provides flexibility and enables the City to act quickly on development opportunities.
W
1W
288
PROJECT TITLE: CAR RENTAL CONTINGENCY
NET EFFECTS ON OPERATING AND
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operating Cost
Personnel: Full Time
Part Time
Total Salary
Purchase of Services
Materials & Supplies
Utilities
Subtotal:
Subtotal:
PROJECT CODE: CM1508
TOTAL ESTIMATED CAPITAL COST:
:.ontingency $700,000
$0
$0
$0
$0 Total Estimated Capital Cost $700,000
Funding Source:
Transfer from:
Car Rental Fund $700,000
$0
$0
Total Estimated Annual Cost $01 Total Funding $700,000
CURRENT STATUS
OVERIUNDER
PHASE/FUNDING SOURCE BUDGET EXPENDED BUDGET (-+) % EXPENDED
Continaencv $700,000 $700,000 $0 100%
AL PROJECT
$700,000 $700,000 $0 100%
289
I
C
Y
^t