HomeMy WebLinkAbout22-1618 02-22-2022RESOLUTION NO. 22-1618
A RESOLUTION RECOMMENDING AWARD OF A CONTRACT FOR
COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) PROJECT NO.
B21-UC-48-0001-22-50 TO A & B CONSTRUCTION, LLC LOCATED IN
DALLAS, TEXAS IN THE AMOUNT OF $343,865.00 FOR THE
REPLACEMENT OF SANITARY SEWER MAIN ALONG PAULA LANE,
DAVID DRIVE, SUSAN STREET, AND RAIDER COURT.
WHEREAS, the City Council of the City of Euless, Texas does hereby
recommend the award of contract for CDBG Project No. B21-UC-48-0001-22-50 to A &
B Construction, LLC located in Dallas, Texas in the amount of $343,865.00 for the
replacement of the sanitary sewer main along Paula Lane, David Drive, Susan Street,
and Raider Court; and
WHEREAS, CDBG Project No. B21-UC-48-0001-22-50 consists of the
replacement of approximately 2,558 linear feet of sanitary sewer main along Paula
Lane, David Drive, Susan Street, and Raider Court using trenchless technology and
open trench methods; and
WHEREAS, the City Council recommends including the authorization for the City
of Euless staff and Tarrant County to issue change order(s) totaling an amount not to
exceed five (5%) of the base contract amount ($17,193.25) without requiring formal
action by the City Council; and
WHEREAS, the construction funds available through Tarrant County for this
project are $327,060.04; and
WHEREAS, Staff has reviewed the bid tabulation and based on supporting
documentation from Parkhill / Schrickel Rollins (Exhibit A), recommends that Tarrant
County award the contract to the low bidder, A & B Construction, LLC located in Dallas,
Texas.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF EULESS, TEXAS, THAT:
SECTION 1.
The City of Euless, Texas City Council recommends award of a contract to A & B
Construction, LLC located in Dallas, Texas for the replacement of the sanitary sewer
main along Paula Lane, David Drive, Susan Street, and Raider Court in the amount of
$343,865.00 of which Tarrant County Community Development will pay $327,060.04.
The remaining cost will be paid for by the City of Euless.
SECTION 2.
This Resolution shall take effect immediately from and after its passage in
accordance with the Charter of the City of Euless and upon publication, and it is
accordingly so resolved.
APPROVED AND ADOPTED at a regular meeting of the Euless City Council on
February 22, 2022, by a vote of 6 ayes, 0 nays, and 0 abstentions.
APPROVED:
' ::-,z 0 !, ,4L 1
�ind-a-'M'�-rtin,•
ATTEST:
r�
!�-
1
i , Sutter. City CMC, City Secretary
Resolution No. 22-1618, Page 2 of 5
Parkhill Schrickel
Rollins
February 7, 2022
City of Euless
201 Ector Drive
Euless, Texas 76039
ATTN: Mr. Allen J. Harts, P.E.
Senior Civil Engineer
RE: Fairmont and Bell Hi Additions Sanitary Sewer Rehabilitation Project
Community Development Project No. B-21-UC-48-001-22-50
Dear Mr. Harts:
Parkhill/ Schrickel Rollins completed the engineering design and construction plans and
prepared contract documents for the above referenced project. An official "Advertisement of
Bid Notice" was published and the plans and documents were available from Tarrant County
and were on file in area plan rooms. Sealed bids for the project were received and publicly
opened and read aloud at 10:30am on February 2, 2022. A copy of the Bid Summary Sheet is
attached.
Six (6) sealed bids were submitted. They ranged from a low bid of $343,865.00 submitted by
A & B Construction, LLC of Dallas, Texas; to a high bid of $1,003,990.00 submitted by Atkins
Brothers Equipment Co. of Midlothian, Texas. The engineer's opinion of probable construction
cost was $400,165.00. Completion time was established in the bid documents at 120 calendar
days.
We submit that a recommendation be made to the Tarrant County Commissioner's Court to
award the project to A & B Construction, LLC in the amount of $343,865.00. Funds are
available for construction through Tarrant County in the amount of $327,060.04.
A & B Construction, LLC has performed satisfactorily on projects of similar size and scope for
other municipalities in the DFW area (including the City of Euless) and have to the best of our
knowledge completed same without incident. A & B Construction were sub -contractors on a
reclaimed water project for the City of Euless in 2020 and they are currently working for the
City of Euless on water line replacements along Alexander Lane and Dickey Drive.
We have verified with A & B Construction, LLC that they have reviewed the tabulation of bids
and they are comfortable with the bid they submitted.
The project is located in the Fairmont and Bell Hi Additions, generally East of Raider Drive,
North of Needles Street, West of Paula Lane and South of West Pipeline Road.
A:\2021\8589.21\04_PRCMNT\04_OPEN\Fairmont_Bell Hi SS -Letter —City Format.docm
255 North Center Street Suite 200 Arlington, Texas 76011 817.649.3216 Parkhill.com
Resolution No. 22-1618, Page 3 of 5
Allen J. Harts
February 7, 2022
Page 2
If you have any questions or comments regarding our recommendation, please contact me at
your earliest convenience.
Sincerely,
PARKHILL/ SCHRICKEL, ROLLINS
jL ///ill)
Sanford P. LaHue, Jr., P.E.
cc: Brad Hearne, Tarrant County Community Development
Resolution No. 22-1618, Page 4 of 5
RECORD OF BIDS RECEIVED
PROJECT:
FAIRMONT and BELL HI ADDITIONS SANITARY SEWER REHABILITATION PROJECT
Tarrant County CDBG (B21 -UC-001 -22-50)
City of Euless
BID OPENING:
FEBRUARY 2, 2022 10:30AM
CONTRACTOR
BID BOND
AMOUNT BID
A & B CONSTRUCTION, LLC
Dallas, TX
Yes
$343,865.00
DOUGLAS DAILEY CONSTRUCTION
Ferris, TX
Yes
$346,226.00
EXCEL 4 CONSTRUCTION, LLC
Fort Worth, TX
Yes
$468,650.00
PM CONSTRUCTION & REHAB.
Pasedena, TX
Yes
$550,309.66
HORSESHOE CONSTRUCTION
LaPorte, TX
Yes
$555,800,00
KINS BROTHERS EQUIPMENT CO.
Fd
lothian, TX
Yes
$1,003,990.00
COMPLETION TIME SET AT 120 CALENDAR DAYS
Parkhill Rollins el
Rollins
255N.CENTER STREET
SUITE 100
ARLINGTON, TEXAS 76011
Resolution No. 22-1618, Page 5 of 5