A RESOLUTION CONVEYING THE SEMI-ANNUAL REPORTS OF THE
CAPITAL IMPROVEMENTS ADVISORY COMMITTEE, RELATIVE TO
THE PROGRESS OF THE CAPITAL IMPROVEMENTS PLAN AND THE
IMPOSITION OF IMPACT FEES FOR THE PERIOD OF OCTOBER 1,
2014 THROUGH MARCH 31, 2015.
WHEREAS, the City Council of the City of Euless, Texas, has adopted Water and
Wastewater Impact Fees and is operating under a Capital Improvements Plan as
required by Chapter 395 of the Texas Local Government Code for the imposition of
impact fees for water and sanitary sewer improvements; and
WHEREAS, the City Council, in compliance with Chapter 395, has appointed a Capital
Improvements Advisory Committee to monitor and evaluate implementation of the
Capital Improvements Plan; and
WHEREAS, Chapter 395 requires the Capital Improvements Advisory Committee to file
semi-annual reports to the City Council with respect to the progress of the Capital
Improvements Plan and any perceived inequities in implementing the Plan or imposing
the impact fees; and
WHEREAS, the Capital Improvements Advisory Committee has monitored and
evaluated the implementation of the Capital Improvements Plan and imposition of
impact fees;
NOW THEREFORE BE IT RESOLVED BY THE CAPITAL IMPROVEMENTS
ADVISORY COMMITTEE OF THE CITY OF EULESS, TEXAS:
SECTION 1. That adequate progress is being made to implement the Capital
Improvements Plan for providing facilities necessitated by and attributable to new
development.
SECTION 2. That the Capital Improvements Advisory Committee finds no inequities in
implementing the Capital Improvements Plan or imposing the impact fees.
SECTION 3. That the Capital Improvements Advisory Committee finds that the impact
fees are being collected and that all funds collected are maintained in accordance with
the law.
SECTION 4. That the City Council adopted Ordinance No 1992 on April 9, 2013
approving updated Land Use Assumptions, Capital Improvements Program and Impact
Fee Program in accordance with Texas Local Government Code.
SECTION 5. That the semi-annual reports, attached hereto as Exhibit A and
accompanying Tables and staff memos, are hereby conveyed to the City Council of the
City of Euless, Texas, for its information.
PASSED AND ADOPTED THIS 19th DAY OF MAY 2015.
f i -
P.2•4
Richard M9rNe se, Chairman
Resolution 15-02-CIAC, Page 2 of 2
EXHIBIT A
SEMI-ANNUAL REPORT
OCTOBER 1, 2014 THROUGH MARCH 31, 2015
BY THE
CAPITAL IMPROVEMENTS ADVISORY COMMITTEE
May 19, 2015
PURPOSE
This semi-annual report was prepared by the Capital Improvements Advisory
Committee to advise the City Council of the progress of Water and Wastewater Impact
Fees and the Capital Improvements Plan, as well as, any perceived inequities found in
implementing the Plan or imposing the impact fees. It is intended to satisfy the
requirements of Chapter 395 of the Local Government Code.
LAND USE ASSUMPTIONS
The Land Use Assumptions, adopted by City Ordinance No. 1992 on April 9, 2013
provides a description of the City’s water and wastewater service area, as well as,
projections of changes in land use densities and intensit ies, and projections of
population changes in the service area. The Land Use Assumptions have been
deemed appropriate for use as the basis for the Capital Improvements Plan (CIP).
CAPITAL IMPROVEMENTS PLAN:
WATER AND WASTEWATER
Appendices A and B of the 2013 Water and Wastewater Impact Fee Review and update
show eligible existing facility costs and eligible proposed facility costs identified in the
CIP adopted for water and wastewater. Pages 1 0-13 of the same report describe the
Living Unit Equivalency and Maximum Impact Fee calculations. The CIP is progressing
at a pace that meets the demands of the City of Euless. Additions to the water and
wastewater systems will be implemented as development occurs within those areas of
the City needing additional capacity.
IMPACT FEE CHARGES
The impact fee calculations show the actual cost of providing capital improvements
needed to maintain the current level of service were $2,955.80 per service unit for water
facilities and $1,049.40 per service unit for wastewater facilities. These figures
represent the maximum impact fee per service unit that could be charged by the City.
Impact fees set by the City Council in April of 2013 were 50% of the maximum impact
fee amount allowed. City Council Ordinance No. 1992 established impact fees per
service unit of $1,477.90 for water facilities and $524.70 for wastewater facilities. The
Fees charged for both water and wastewater facilities are based on water meter size,
with a 5/8” water meter considered one service unit. Wastewater impact fees are not
charged when water meters are installed for water that will not enter the wastewater
system, such as landscape irrigation. The Ordinance established the following impact
fees:
Meter Size
(inches) Water Sewer Total
5/8” or 3/4” $1477.90 $524.70 $2,002.60
1” $3,694.75 $1,311.75 $5,006.50
1.5” $7,389.50 $2,623.50 $10,013.00
2” $11,823.20 $4,197.60 $16,020.80
3” $35,469.60 $12,592.80 $48,062.40
4” $62,071.80 $22,037.40 $84,109.20
6” $135,966.80 $48,272.40 $184,239.20
8” $236,464.00 $83,952.00 $320,416.00
IMPACT FEE ASSESSMENT, COLLECTION, AND DISBURSEMENT
From October 1, 2014 through March 31, 2015 impact fees collected were $206.392.48
for water and $65,611.39 for wastewater. Impact fee funds disbursed from the accounts
during this time period totaled $184,518.00. The projects funded included: Water Tower
Debt Payment (Project WT0101) for $124,068.00; Reclaimed Water Line Extension
Debt Payment (Project WT1403) for $60,450.00.
CONCLUSION
The Capital Improvements Advisory Committee finds that for the time period included in
this report, no inequities were created in imposing the impact fees and the fees were
properly approved by the City Council through Ordinance No. 1992. The assessment
and collection of water and wastewater impact fees was in accordance with the
guidelines of Ordinance No. 1992, and Chapter 395 of the Texas Local Government
Code. All money collected was deposited into separate interest bearing accounts
reserved for impact fees.
M E M O R A N D U M
TO: Mike Collins, Director of Planning and Economic Development
FROM: Ross Fairclo, Accountant II
DATE: May 13, 2015
SUBJECT: Impact Fee Funds
Impact Fees are recorded into two separate funds. The amount of funds available in the Water
Impact Fee Fund as of March 31, 2015 is $1,445,841. A portion totaling $1,418,190 is invested
in interest bearing accounts with $418,190 available immediately and the remainder available
within 2 months. The amount of funds available in the Wastewater Impact Fee Fund as of
March 31, 2015 is $518,899. This is all invested in interest bearing accounts and is available
immediately.
City of Euless
Impact Fee Revenues and Expenses
October 1, 2014 - March 31, 2015
Revenues
Fund 505 - Water Impact Fees Fund 508 - Wastewater Impact Fees
Impact Fees 205,884.70$ Impact Fees 65,509.65$
Interest Income 507.78$ Interest Income 101.74$
Total Revenues 206,392.48$ Total Revenues 65,611.39$
Expenses
Project WT0101 - Water Tank Debt Payment Project WW0605 - TRA Sewer Payment
Transfer to Debt 20,678.00$ 10/1/2014 TRA Sewer Payment -$
Transfer to Debt 20,678.00$ 11/1/2014
Transfer to Debt 20,678.00$ 12/1/2014
Transfer to Debt 20,678.00$ 1/1/2015
Transfer to Debt 20,678.00$ 2/1/2015
Transfer to Debt 20,678.00$ 3/1/2015
Total 124,068.00$
Project WT1403 - Reclaimed Water Line Ext. Debt Payment
Transfer to Debt 10,075.00$ 10/1/2014
Transfer to Debt 10,075.00$ 11/1/2014
Transfer to Debt 10,075.00$ 12/1/2014
Transfer to Debt 10,075.00$ 1/1/2015
Transfer to Debt 10,075.00$ 2/1/2015
Transfer to Debt 10,075.00$ 3/1/2015
Total 60,450.00$
Total Expenses 184,518.00$ Total Expenses -$