HomeMy WebLinkAbout17-1497 01-24-2017 RESOLUTION NO. 17-1497
A RESOLUTION RECOMMENDING AWARD OF A CONTRACT FOR
COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) PROJECT NO.
B16-UC-48-0001-22-50-A TO EXCEL 4 CONSTRUCTION, LLC, FORT
WORTH, TEXAS, IN THE AMOUNT OF $191,602.00 FOR THE
REPLACEMENT OF SANITARY SEWER MAIN IN THE OAKWOOD
TERRACE EAST AND CEDAR HILL ESTATES ADDITIONS, AND
PROVIDING AN EFFECTIVE DATE.
WHEREAS, the City Council of the City of Euless, Texas does hereby
recommend the award of contract for CDBG Project No. B16-UC-48-0001-22-50-A to
Excel 4 Construction, LLC, Fort Worth, Texas, in the amount of $191,602.00 for the
replacement of the sanitary sewer main in the Oakwood Terrace East and Cedar Hill
Estates Additions; and
WHEREAS, CDBG Project No. B16-UC-48-0001-22-50-A consists of the
replacement of approximately 1,500 linear feet of sanitary sewer main along Reaves
Court using trenchless technology and open trench methods; and
WHEREAS, the City Council recommends including the authorization for the City
of Euless staff and Tarrant County to issue change order(s) totaling an amount not to
exceed five percent of the base contract amount ($9,580.00) without requiring formal
action by the City Council and Commissioner's Court; and
WHEREAS, the construction funds available through Tarrant County for this
project are $208,840.19; and
WHEREAS, staff has reviewed the bid tabulation and based on supporting
documentation from Elliott and Hughes, Inc. (Exhibit A), recommends that Tarrant
County award the contract to the low bidder, Excel 4 Construction, LLC, Fort Worth,
Texas.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF EULESS, TEXAS, THAT:
SECTION 1.
The City of Euless, Texas City Council recommends award of a contract to Excel
4 Construction, LLC, Fort Worth, Texas for the replacement of the sanitary sewer main
in the Oakwood Terrace East and Cedar Hill Estates Additions in the amount of
$191,602.00 of which Tarrant County Community Development will pay the full amount.
SECTION 2.
EFFECTIVE DATE. This resolution shall be in full force and effect from and after
its passage.
APPROVED AND ADOPTED at a regular meeting of the Euless City Council on
January 24, 2017, by a vote of ayes, 0 nays, and 0 abstentions.
APPROVED:
•
Linda Martin, Mayor
ATTEST:
9
dieu,vt„..., 4 V' ''
Kim Sutter, TRMC, City Secretary
Resolution No. 17-1497, Page 2 of 6
Elliott & Hughes, Inc.
Engineers/Planners
January 11, 2017
VIA HAND DELIVERY
City of Euless
201 North Ector Drive
Euless, Texas 76039
Attention: Mr. Allen J. Harts, P.E.
Senior Civil Engineer
Re: Sanitary Sewer Line Replacement
Oakwood Terrace East and Cedar Hill Estates Additions
CDBG Project No. B16-UC-48-0001-22-50-A
Dear Mr. Harts:
Our firm completed the civil engineering design, construction plans, and prepared
contract documents for the above captioned improvements. An official
"Advertisement for Bid Notice" was published and the plans and documents were
available from Tarrant County and were on file in area plan rooms. Sealed bids for
the construction were received in the offices of Tarrant County Community
Development, at 10:00 o'clock A.M. on Tuesday, December 28, 2016.
Two (2) sealed bids were submitted. The low bid of $191,602.00 was submitted
by Excel 4 Construction, LLC. (aka "XCEL 4") of Fort Worth, Texas. The second or
high bid of $244,380.00 was submitted by BSK USA, LLC of Benbrook, Texas. A
third bid was presented that was absent required information in the bid documents
and, in accord with the requirements of HUD and Tarrant County, the bid was
ruled non-responsive and was not read into the record. A copy of the Bid Summary
and the line item Bid Tabulation for the two (2) bids are enclosed for your
information and file. The engineer's estimate for the construction was $201,690.00.
Completion time was established in the documents at ninety (90) calendar days.
We submit that a recommendation be made to Tarrant County Commissioner's
Court to award the construction contract to Excel 4 in the amount of their low bid of
$191,602.00. Funds are available for the construction through Tarrant County in
the total amount of$208,840.19.
In any resolution on construction contract award, we recommend that the City
Council include authorization for the City of Euless Staff and Tarrant County to
issue change order(s) totaling an amount not to exceed five (5%) percent of the
base contract amount ($9,580.00) without requiring formal action by the City
Council and Commissioner's Court.
1001 West Euless Blvd., Suite 212 • Euless, Texas 76040 • 817-267-1303 • Fax 817-283-5310
Resolution No. 17-1497, Page 3 of 6
Allen J. Harts, P.E.
Page 2
As a matter of information, Excel 4 was incorporated in June, 2011, and
established their offices in Fort Worth. Prior to the new venture, all four (4)
principals were employed by Hall-Albert Construction, Inc. (H-A) a highly respected
utility contractor and pioneer in the trenchless technology methods of sanitary
sewer rehabilitation. When Hall-Albert dissolved their corporation in early 2001, the
four (4) Excel principals made arrangements to purchase equipment from H-A,
arrange to subcontract work from ARK Construction (a multi million dollar utility
contractor in Kennedale), and start to establish a project history necessary to
obtain bonding as an independent contractor. At the present time, all the principals
have at least twenty (20) years of experience in trenchless technology and open
trench construction. They have completed approximately 80 sanitary sewer
projects since they started, with construction costs ranging from $1,800.00 to
$980,000.00. They have completed sanitary sewer line rehabilitation projects in the
City of Euless as a subcontractor under ARK, and have performed construction in
most all of the cities the Metroplex.
All of their projects that we are familiar with were successfully completed in a
timely and acceptable manner. We spoke with representatives of Excel 4
regarding their unit prices and total bid, and they are comfortable with their bid as
submitted. They indicated they have enjoyed their past relationship with the City
and Tarrant County and look forward to successfully completing this project.
Surety bonds (performance, payment and maintenance bonds) are underwritten by
Washington International Insurance Company of New Hampshire. We spoke to the
surety's local representative and they told of no problems with the contractor, and
they assured us they would be issuing the necessary bonds.
We trust the foregoing will be beneficial to you as you prepare your final
recommendations on this project. We appreciate very much the opportunity to be
of service to you, the City of Euless, and Tarrant County. We respectfully invite you
to contact us should you have questions or if we may provide additional
information. , 7..
•s
Very truly yours, :• * �•
ELLIOTT & HUGHES, INC. `:
, pi) f sia:a:s o °1
` �L•'t�
rk
•avid ughes, r., P E. � �� E� �' U— - '1
/sa
cc Mr. Brad Hearne; Tarrant County Community Development
file
Enclosures
Resolution No. 17-1497, Page 4 of 6
o
CITY OF EULESS
SANITARY SEWER LINE REPLACEMENT
CDBG PROGRA 42ND YEAR
iT HUFFMAN D'
�Qq A �-
2q q o
CA
U
LJ
> ROSS AVE
H
I— )1
U G `
7 WEST ALEXANDER Ntiq
4 o EAST ALEXANDER N —
. . z
vv) ARNETT DRQ— cz
H
Q
\ LINDAL N , J
(A
4 Q
�' WEST HUITT Li I CZ D
Q o Q
/ Q I
I JEFFLYN c� 0 EAST HUITT LN
CL Y ., w W
Z z 0 QQ
I o Y Z o z QJ
cL
z o w 0 C�
i e• YLE' ; z _ W
I A ESS z JEAN LN MAIL PL
REA S Cf PROJECT cPAULINE
- ____% . , LOCATION
cct
° A.MI
J❑N ilii iii�iiii
Q d F-- D '• ili\7.,6.1111110
w (4 cL o w ED
Z a Q 3 I— - > CZ CZ V)
Q X Y (4 Q Q A
CZ X w Q
O
C.)r----1WHITI ER RD
I >-
I Q w
II 3 z w
L1 ca
Q zz `i'
<9z o z z
G�'tI �.1� > Pq 0 _
i OP "c)' SUNSET DR z TRIGG
NS
Sv o
F-
r
Q
Resolution No. 17-149 Page 5 of 6 w z
SOUTH PIPELINE RD
RECORD OF BIDS RECEIVED
PROJECT DESCRIPTION SANITARY SEWER LINE REPLACEMENT, OAKWOOD TERRACE
EAST AND CEDAR HILL ESTATES ADDITIONS. -B16-UC-48-0001-22-50-A--CITY OF EULESS,
TARRANT COUNTY, TEXAS
BID OPENING DATE: DECEMBER 28, 2016 TIME 10:00 AM
CONTRACTOR BID AMOUNT BID
BOND
EXCEL 4 CONSTRUCTION, LLC**
FORT WORTH, TEXAS 50/0 $191,602.00
BSK USA, LLC
5% $244,380.00
BENBROOK, TEXAS
ENGINEER'S OPINION OF CONSTRUCTION $201,690.00
COST
** LOW BIDDER
COMPLETION TIME SET AT 90 CALENDAR DAYS
ELLIOTT & HUGHES, INC.
ENGINEERS/PLANNERS
1001 WEST EULESS BLVD., #212
EULESS, TEXAS 76040
(817)267-1303
Resolution No. 17-1497, Page 6 of 6