HomeMy WebLinkAbout19-1562 12-17-2019 RESOLUTION NO. 19-1562
A RESOLUTION RECOMMENDING AWARD OF A CONTRACT FOR
COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) PROJECT NO.
B19-UC-48-0001-22-50 TO PM CONSTRUCTION & REHAB, LLC DBA
IPR SOUTH CENTRAL, PASADENA, TEXAS, IN THE AMOUNT OF
$330,605.48 FOR THE REPLACEMENT OF SANITARY SEWER MAIN
IN THE MIDWAY PARK 2ND ADDITION PHASE I.
WHEREAS, the City Council of the City of Euless, Texas, does hereby
recommend the award of contract for CDBG Project No. B19-UC-48-0001-22-50 to PM
Construction & Rehab, LLC dba IPR South Central, Pasadena, Texas, in the amount of
$330,605.48 for the replacement of the sanitary sewer main in the Midway Park 2nd
Addition Phase I; and
WHEREAS, CDBG Project No. B19-UC-48-0001-22-50 consists of the
replacement of approximately 2,409 linear feet of sanitary sewer main between
Stonewall Drive and Milam Drive and from Limestone Drive to Ector Drive, and between
Freestone Drive and Ector Drive on the southside of Milam Drive and Limestone Drive
using trenchless technology and open trench methods; and
WHEREAS, the City Council recommends including the authorization for the City
of Euless staff and Tarrant County to issue change order(s) totaling an amount not to
exceed five percent of the base contract amount ($16,530.00) without requiring formal
action by the City Council and Commissioner's Court; and
WHEREAS, the construction funds available through Tarrant County for this
project are $356,200; and
WHEREAS, City staff has reviewed the bid tabulation and based on supporting
documentation from Elliott and Hughes, Inc. (Exhibit A), recommends that Tarrant
County award the contract to the low bidder, PM Construction & Rehab, LLC dba IPR
South Central.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF EULESS, TEXAS, THAT:
SECTION 1.
The City of Euless City Council recommends award of a contract to PM
Construction & Rehab, LLC dba IPR South Central, for the replacement of the sanitary
sewer main in the Midway Park 2nd Addition Phase I in the amount of $330,605.48 of
which Tarrant County Community Development will pay the full amount.
SECTION 2.
This Resolution shall take effect immediately from and after its passage in
accordance with the Charter of the City of Euless and upon publication, and it is
accordingly so resolved.
APPROVED AND ADOPTED at a regular meeting of the Euless City Council
on December 17, 2019, by a vote of 6 ayes, 0 nays, and 0 abstentions.
APPROVED:
Z
Linda Ma in, a or
ATTEST:
or Kim tt r, TR , MC, City Secretary
Resolution No. 19-1562, Page 2 of 5
EXHIBIT A
s
November 21, 2019
City of Euless
201 North Ector Drive
Euless, Texas 76039
Attention: Mr. Allen J. Harts, P.E.
Senior Civil Engineer
Re: Sanitary Sewer Line Replacement
Midway Park 2"d Addition Phase I
City of Euless, Tarrant County, Texas.
CDBG Project No. B19-UC-48-0001-22-50
Dear Mr. Harts:
Our firm completed the civil engineering design and construction plans and prepared
contract documents for the above captioned improvements.An official "Advertisement
for Bid Notice" was published and the plans and documents were available from
Tarrant County and were on file in area plan rooms. Sealed bids for the construction
were received and publicly opened and read aloud at 10:30 AM, November 20, 2019.
A copy of the Bid Summary Sheet is attached to this correspondence for your review.
Five (5) sealed bids were submitted. They ranged from a low bid of $330,605.48
submitted by PM Construction and Rehab, LLC, of Pasadena, Texas; to a high of
$470,820.69 submitted by Joe Funk Construction of Dallas, Texas. The engineer's
estimate of cost for the construction was $340,791.50. Completion time was
established in the bid documents at 75 calendar days.
We submit that a recommendation be made to Tarrant County Commissioner's Court
to award the construction contract to PM Construction & Rehab, LLC dba IPR South
Central in the amount of their low bid of $330,605.48. Funds are available for the
construction through Tarrant County in the total amount of$356,200.00.
In any resolution on construction contract award, we recommend that the City Council
include authorization for the City of Euless Staff and Tarrant County to issue change
order(s) totaling an amount not to exceed five (5%) percent of the base contract
amount ($16,530.00) without requiring formal action by the City Council and
Commissioner's Court.
As a matter of information, PM Construction has been active in sanitary sewer facility
rehabilitation utilizing trenchless technology (pipe bursting) for 22 years. They
currently operate fourteen (14) crews consisting of 8 to 9 employees per crew. The
majority of their work has been in the greater Houston area, although they have .
recently been awarded contracts in varying cities in the north Texas area (including
Euless) and have to the best of our knowledge comlpeted same with out incident.
They successfully completed construction on the 44th Year CDBG project for the City
of Euless in Oakwood Terrace East Addition in October 2019 without issue.
1001 West Euless Blvd., Suite 212 • Euless, Texas 76040 • 817-267-1303 • Fax 817-283-5310
Resolution No. 19-1562, Page 3 of 5
Allen J. Harts, P.E.
Page 2
Representatives of PM advised us that they have reviewed the unit prices of their bid
as well as those of the other bidders and they are comfortable with their bid prices as
submitted. In addition, they advised us that their crew(s) working on this project would
be quartered in hotels/motels in this area and would rotate at 3 week intervals. This is
important since they will be available to address problems that might arise during
non-working hours.
Surety bonds (performance, payment, and maintenance bonds) are underwritten by
Arch Insurance Company of Jersey City, New Jersey.
The project is located in the west central part of the City in the Midway Park Additiion.
The area is bounded by Ector Drive on the west, the Euless Post Office on the south,
and Freestone and Limestone on the north. The project serves only residential
properties and generally includes replacement by up-sizing deteriorated 6-inch
vitrified clay tile and/or concrete pipe with 8-inch diameter high density polyethylene
pipe by traditional open-trench, and pipe bursting (trenchless technology) methods.
Reconnection of individual sewer services, replacement and/or rehabilitation of
manholes, and other incidental construction items required for a complete project are
included.
We trust the foregoing will be beneficial to you as you prepare your final
recommendations on this project. We appreciate very much the opportunity to be of
service to you and the City of Euless and respectfully invite you to contact us should
you have questions or if we may provide additional information.
Very truly yours,
ELLIOTT & HUGHES, INC.
Davi , Jr., P.E. � gr
/sd
cc file °` a li.31: 4 ;�
Enclosures 4Zes is .Q.,
C ['al 'zoVV
Resolution No. 19-1562, Page 4 of 5
RECORD OF BIDS RECEIVED
PROJECT DESCRIPTION SANITARY SEWER LINE REPLACEMENT IN MIDWAY PARK ADDI-
TION—B19-UC-48-0001-22-50—CITY OF EULESS, TARRANT COUNTY, TEXAS
BID OPENING DATE: NOVEMBER 20, 2019 TIME 10:30 AM
CONTRACTOR BID AMOUNT BID
BOND
PM CONSTRUCTION ** 5% $330,605.48
PASADENA, TX
LEETECH SOLUTIONS
5% $334,632.00
ALEDO, TX
EXEL 4 CONSTRUCTION
FORT WORTH, TX 5% $335,184.00
CIRCLE C CONSTRUCTION 50/0 $427,255.00*
FORT WORTH, TX
JOE FUNK CONSTRUCTION $470,808.65*
DALLAS, TX 5%
*, AS BID (SEE LINE ITEM BID TABULATION FOR ACTUAL AMOUNT BID)
** LOW BIDDER
COMPLETION TIME SET AT 75 CALENDAR DAYS
ELLIOTT & HUGHES, INC.
ENGINEERS/PLANNERS
1001 WEST EULESS BLVD., #212
EULESS, TEXAS 76040
(817)267-1303
Resolution No. 19-1562, Page 5 of 5